Download - BTS InstallationManual
PointMAX 10000 Installation Manual Page 1
PointMAX10000 Mobile WiMAX
Base Station Installation Manual
PointMAX 10000 Installation Manual Page 2
© 2009 PointRed Telecom (P) Ltd No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, including photography, recording, or any information storage and retrieval system without written consent. Information in this manual is subject to change without notice, and does not represent a commitment on the part of PointRed. PointRed shall not be liable for incidental or consequential damages resulting from the furnishing, performance, or use of this manual. All brand names used in this manual are the registered trademarks of their respective owners. The use of trademarks or other designations in this publication is for reference purposes only and does not constitute an endorsement by the trademark holder
PointMAX 10000 Installation Manual Page 3
Table of Contents
1.0 PointMAX 10000 System Overview……………………………………………………... 04
1.1 PointMAX 10000 BTS Units…………………………………………………………….... 05
1.2 PointMAX 10000 Installation Site Requirements…………………………………….… 07
2.0 Installing the PointMAX System……………………………………………………….… 08
2.1 Packaging Content………………………………………………………………………... 08
2.2 Installation………………………………………………………………………………….. 08
2.2.1 Remote Radio Head(RRH) Installation……………………………………………….… 08
2.2.2 Remote Radio Head(RRH) Interface drawing………………………………………..… 09
2.2.3 DC Power Supply……………………………………………………………………….… 10
2.2.4 Recommended Maximum Power Supply Cable length……………………………..… 10
2.2.5 Earth Requirements……………………………………………………………………..… 11
2.2.6 Fuse…………………………………………………………………………………………. 11
2.2.7 Optical Convertor………………………………………………………………………..… 11
2.2.8 Health and Safety……………………………………………………………….………… 11
2.2.9 Remote Radio Head(RRH) Mounting…………………………………………….……... 12
2.2.10 Base Station Controller Unit(BSC) Installation..……………………………................ 13
2.2.11 Base Station Controller Unit(BSC) Interface Drawing………………………………… 14
2.2.12 LED Indication…………………………………………………………………….……….. 15
2.3 Radio Configuration……………………………………………………………………….. 15
PointMAX 10000 Installation Manual Page 4
1. PointMAX 10000 System Overview PointRed Telecom’s PointMAX10000 Mobile WiMAX Base Station operates in 2.5 GHz frequency band, and it is also QUAD PLAY enabled in compliance with WiMAX Forum. It supports 2X2 MIMO with Matrix A & B. The Base Station supports various levels of Quality of Service, allowing wireless operators to address a wide variety of user profiles to serve the retail and enterprise markets. The Base Station can be easily managed via standard interfaces, and is Software Upgradeable. Architecture is scalable to accommodate various network architecture and topology. The below figure illustrates a typical installation of PointMAX BTS radio with external antenna.
PointMAX 10000 Installation Manual Page 5
1.1 PointMAX 10000 BTS Units
PointMAX BTS comprised following Units:
1. Remote Radio Head(RRH) – ODU 2. Base Station Controller Unit(BSC) – IDU
PointMAX ODU comes with two N-Type connector (MIMO - Ant1 & Ant 2) for connecting to External Sector Antenna. Both Ant1 & Ant2 should be connected to Single Sector Antenna and weather proof fibre port-Optical 1 for connecting fibre cable to IDU (PM-18).
The ODU to be powered on separately with -48VDC using power connectors which is supplied with the unit. The ODU should be attached to a Mast/ Tower using a mounting kit, which is supplied with the unit. PointMAX IDU is chassis based unit which has following Modules, 1. Power Module(PM 14) – 2no’s
2. MCH(PM 16) – 1 no
3. Radio Card(PM 18) – 1no
4. Controller Card(PM 17) – 2no’s
5. Cooling Units(PM 14) – 2 no’s
The IDU – PM14 module to be powered on separately with -48VDC using power connectors which is supplied with the unit. In IDU – PM 18 module comes with SFP Fibre port should be connected to the ODU using Fibre Cable and PM17 module comes with Gigabit Ethernet port should be connected to Backhaul(Switch) using CAT6 cable. Note: The Modules (PM13/PM14/PM16/PM17 & PM18) has to be handled with care. Improper handling will lead to malfunction of modules.
PointMAX 10000 Installation Manual Page 6
PointMAX 10000 BASE STATION
Base Station Controller Unit (BSC) - IDU
Remote Radio Head Unit (RRH) – ODU
PointMAX 10000 Installation Manual Page 7
1.2 PointMAX10000 Installation Site Power Requirements
This section is intended to illustrate the power supply requirements for the PointMAX 10000 system installation location
To Alarms Panel Recommended
To Alarms Panel Recommend
PointMAX 10000
RRH
PointMAX 10000
RRH
PointMAX 10000
RRH
Electrical meter and service disconnect at fence or property
line
Main Service Disconnect
Circuit Breaker
Surge Suppressor
Main Panel board with a main Breaker
Automatic Transfer Switch
Surge Suppressor
Utility Panel Board
To Alarms Panel Exchange
DC Power Bank (‐48DC)
Meter
Utility Feed AC 1 or 3Phase
Step Down or
Isolation Transformer
Generator PointMAX10000 BSC
PointMAX10000 Base Station Power Consumption
Qty
Max
Typical
Total
BSC 1 380W
365W 380W
RRH 3 200W
190W 600W
PointMAX 10000 Installation Manual Page 8
2. Installing the PointMAX System 2.1. Package Contents The PointMAX BTS packages include,
1. Remote Radio Head(RRH) – ODU : 3 no’s
2. Base Controller Unit(BSC) – IDU : 1 no
3. GPS Antenna : 1no
4. 120 degree Sector Antenna : 3 no’s
5. 2mtr Pigtail Cable : 6 no’s
6. Fibre Cable : 3 no’s
7. RRH(ODU) Power Connector : 1 no
8. BSC(IDU) Power Cable with Connector : 2 no’s
Component Inspection: • Carefully unpack the PointMAX package and inspect the unit for physical damage. • Verify that all the components are present against the shipping information or purchase order. Immediately contact PointRed Telecom (P) ltd., if any portion of the system is missing or damaged. 2.2. Installation Physical installation of the PointMAX system installation includes two steps as follows:
• RRH – ODU installation. • BSC – IDU installation.
2.2.1 Remote Radio Head (ODU) installation:
• RRH has to be installed on the tower/mast using appropriate clamps. • 3 RRH installed on the tower represent each per Sector. • Connect Pigtail(2 per RRH) from each RRH to Antenna • Install and Connect Fibre cable from each RRH to IDU in appropriate module(PM 18) • Install the Power cable using power connector provided to each RRH. • Install GPS Antenna with cables using appropriate clamps provided & connect to BSC
unit (PM 18 module). • Install Grounding cable to each RRH using proper lugs and connect to Earth Point.
PointMAX 10000 Installation Manual Page 9
2.2.2 RRH Interface Drawing
Antenna Port DC Power Port Fuse Fibre PortEarth Point
PointMAX 10000 Installation Manual Page 10
2.2.3 DC Power Supply The power connector is of AMP Tyco CPC series 5 type. The cable connector is shown in below Figure.
The connector is wired as follows:
Pin 1
Negative Supply
Pin 2
Positive Return
Pin 3
On the mating (RRH) connector this pin is
connected to chassis Earth
Cable crimp pins are available in two sizes. One to fir cable gauge AWG 8-10 and one to fit AWG 12-14. Either can be fitted although the cable gauge determines the maximum length of power cable that can be supported. 2.2.4 Recommended Maximum Power Supply Cable Length The power cable should be AWG12 minimum gauge, specified to NEC/ CEC.ANSI/NFPA 70. The cable length should be sufficient to make sure that the cable voltage drop under highest current load does not increase the input voltage at the RRH above -36V the maximum allowable cable length can be calculated using the following equation:
PointMAX 10000 Installation Manual Page 11
Maximum cable length (m) = 1000 X (VPSU – 36) / (IMAX X 2 X CableRES) Where the maximum current IMAX is typically 5.5A, the source voltage VPSU is -48V and the cable RES is the cable resistance expressed as ohm/Km. This value will depend upon the manufacturer and gauge of cable. For AWG12 cable with a resistance of 5.2 ohm/Km this would give a maximum cable length of 209m. However, if back up battery power is used with a voltage of 40V the maximum cable length is reduced to 70m.
2.2.5 Earth Requirements The RRH must be connected to the local earth bonding point and has a connection for this purpose. This is two M6X6mm deep holes on a 15.5mm pitch. The earth strap should be AWG10 minimum diameter. The inputs to the RRH power supply are isolated from chassis ground. However the positive terminal can be connected to local (chassis) earth external to the RRH as required (access via pin 3 of chassis socket). 2.2.6 Fuse The RRH is fitted with a 5A anti‐surge fuse fitted to the supply line (‐48V nominal). 2.2.7 Optical Connector The optical input carries the digital IQ data and unit control data. The standard optical wavelength is 850nm. The fibre fitted is a multi‐mode fibre. The connectors are ODC2 Flange mount. In the case that 2 optical connectors are fitted the left hand optical 1 is the primary connector. 2.2.8 Health and Safety The unit weighs approximately 12Kg; so it is recommended that care should be exercised when lifting the product. Appropriate safety gear should be used at all times. If using a hoist to lift the unit up a mast, attach the rope to the carrying handle at the top of the unit.
PointMAX 10000 Installation Manual Page 12
2.2.9 RRH Mounting Fit the mounting brackets to the unit as described in below diagram of the mounting Instructions,
Fig 1 Fig 2 Fig 3
• Attach studs supplied to the outer pair of the holes on a mounting bracket as shown Figure 3.
• Tighten the pair of nuts against the brackets to a torque of 15Nm.
• Thread a nut and washer onto the free end of each stud as shown in Figure 4.
• Position the upper pair of pole mounting brackets in the required position for the unit to
be mounted on the pole. Secure the brackets in position using a washer and nut to a torque of 15Nm, as shown in fig 4. Once tight the nut should then be locked by tightening the opposing against the other side of the pole mounting bracket, ensuring that it does not move. Note: For the upper bracket the hooks should point upwards.
• Repeat steps i to iv for the lower bracket, positioning the pair of brackets approximately
350mm lower on the pole, with the hooks facing downwards and the brackets only tightened loosely against the pole.
• Hook the slot in the unit mounting brackets onto the hook on the upper pole mounting
bracket, see Figure 5.
PointMAX 10000 Installation Manual Page 13
• Slide the lower pair of mounting brackets down the pole until the hooks locate into the slots on the lower unit mounting bracket, as shown in Figure 5.
• Secure the lower pair of pole mounting brackets firmly in position against the pole and
lock the nuts against each other.
• Secure the unit to the pole mounting brackets using the M8 screws, washers, spring washers and nuts provided, using a torque of 15Nm, as shown in Figure 5.
Ensure all nuts are tightened to a torque of 15Nm
Fig 4 Fig 5
2.2.10 Base Station Controller Unit (IDU) installation
• BSC unit is Horizontal-mounted six (6) slots, 2U 19”inch rack-mounted enclosure. • BSC unit has to be installed on the Rack using appropriate check nets. • Check in the BSC unit, 8 modules are inserted properly as shown in the diagram. • Install the power Cable with power Connector provided to BSC unit. (PM 14
Module). • BSC unit has two power modules (PM 14) which supports power redundancy, so
install power cables for both modules for redundancy. • Install CAT6 cable from BSC unit (PM 17 module) to backhaul provided. Eg: switch.
The backhaul cable has to be connected to “Ethernet port ETH 1” in PM 17 module of BSC unit.
• BSC unit has two Controller Cards (PM 17) to support 1+1 functionality, so install backhaul cable for both modules to support redundancy.
PointMAX 10000 Installation Manual Page 14
• Connect the fibre cable which is laid from RRH to BSC unit (PM 18 Module) using STP fibre module.
• Connect the GPS cable which is laid from GPS to BSC unit (PM 18 Module) in “GPS port”.
• BSC unit has two hot swappable & manageable cooling units (Fan). • Install Grounding cable to BSC unit using proper lugs and connect to Earth Point. • Power on the BTS, check for “READY LED”. RDY LED’s in respective modules
has to turn “Green” (LED in Top Left most end in the each module) in order to know all modules are activated. Fibre Port & GPS Port LED’s should also turn “GREEN”, in order to know that respective device is active. If LED indication is “Orange”, it shows device is inactive. Note: All modules have to be handled carefully. Refer to Module Handling document.
2.2.11 Base Station Controller Unit (IDU) Interface Drawing
Fig 1
Note: All modules have to be inserted in respective slots, as shown in the above diagram. The module has to be inserted properly in the respective slot using Hot swap lever (Black Nob) & Nob has to pressed fully for the module to become Active. While removing the module, initially the Nob has to be pull back wait for 10 sec till the LED’s turns blue then remove from the slot.
Power Module 1
Power Module 2
MCH
Radio Card (With 3 Sector Fibre port)
Controller Card 1(ETH 1 Back Haul)
Controller Card 2(ETH 1 Back Haul)
Cooling Units
GPS port (To connect GPS Antenna Cable)
PointMAX 10000 Installation Manual Page 15
2.2.12 LED Indication’s
• HS – Hot Swap (BLUE LED) Off - Module is activated and should not be removed. On - Module is deactivated and may be removed. Blink - Module is being activated or deactivated.
• OSS - Out of Service (ORANGE LED)
Off - Module is not out of service and can supply power. On - Module is out-of-service and cannot supply power.
• RDY- Ready(In Service: GREEN LED)
Off - Module is not providing power to any channel. On - Module is active.
2.3. Radio Configuration
After installing the unit, refer to configuration manual for PointMAX 10000 BTS configuration.