Avance de obra al 15-03-2010

Torre 7

Torre 8

Torre 9 - 10

ACTIVIDADES DE CONTROL E10 E9 E8 E7

ARMADO, VACIADO PILOTES. EDIF. 100% 100% 100% 100%

ARMADO , VACIADO Y RELLENO DE VIGAS EDIF. 100% 100% 100% 100%

CONCRETO VACIADO PLACAS, MUROS 100% 100% 100% 2%

VACIADO MUROS INTERNOS 100% 88% 0% 0%

VACIADO ANTEPECHOS Y BALCONES 100% 100% 4% 0%

CENTRAL VACIADO ESCALERAS 100% 64% 0% 0%

INST. ELECTRICAS 50% 0% 0% 0%

INST. SANITARIAS 92% 42% 0% 0%

INST. ELECTROMECÁNICAS (ASCENSOR) 0% 0% 0% 0%

INST. GAS (65% APTO+35% MONT) 65% 50% 0% 0%

MARCOS INTERNOS APTOS. 42% 0% 0% 0%

BLOQUE APTO. 89% 8% 0% 0%

BLOQUE DE VENTILACIÓN APTO 72% 0% 0% 0%

FRISO APTO. 28% 0% 0% 0%

ACABADOS RESANEO DE MUROS INTERIORES 53% 0% 0% 0%

TABLILLA FACHADA 63% 0% 0% 0%

IMPERMEABILIZACION DE TECHOS 0% 0% 0% 0%

MODULO BLOQUE MOD.ASCENSOR 50% 0% 0% 0%

BLOQUE. VENTILAC. MOD.ESC. 92% 0% 0% 0%

BAJANTES DE BASURA 83% 0% 0% 0%CENTRAL

EXTERNOS

ALBAÑILERÍA

INSTALACIONES

ESTRUCT.

INFRAESTRUCT

Page 2: Avances De Obra Las  Haciendas

Avance de obra al 15-03-2010

Torre 11

Torre 12

ACTIVIDADES DE CONTROL E12 E11

ARMADO, VACIADO PILOTES. EDIF. 100% 100%

ARMADO , VACIADO Y RELLENO DE VIGAS EDIF. 100% 100%

CONCRETO VACIADO PLACAS, MUROS 100% 100%

INST. ELECTRICAS, SANITARIAS 100% 100%

INST. ELECTROMECÁNICAS (ASCENSOR) 100% 50%

INST. GAS (65% APTO+35% MONT) 100% 83%

MARCOS INTERNOS APTOS. 100% 95%

BLOQUE APTO. Y DE VENTILACIÓN, FRISO APTO 100% 100%

PUERTA PRINCIPAL , CERRADURA 100% 99%

NIVEL I ENCAMISADO , PORCELANA , CERÁMICA APTO 100% 95%

ALAMBRADO+ CABLEADO APTO. 100% 92%

PIEZAS SANITARIAS, ELECTRICAS, BATEA 92% 50%

PINTURA MARCOS INTERNOS + PTA PPAL 99% 89%

ALUMINIO Y VIDRIO 70% 33%

IMPERMEABILIZACION DE TECHOS, TABLILLA FACHADA 100% 50%

FRISO Y ENCAMISADO EN PASILLOS 100% 100%

CERÁMICA EN MÓDULO CENTRAL 100% 83%

BARANDAS ESCALERAS Y BLACONES 100% 100%

BAJANTES DE BASURA 100% 83%

CENTRAL LAMINAS EN TECHOS (carbolux) , EXTRACTORES 100% 100%

ACABADOS

ALBAÑILERÍA

INSTALACIONES

INFRAESTRUCT