dose rate reduction experiences of piping …2005/02/03  · unit 4 • high dose rate at rhr-4,...

13
Dose Rate Reduction Experiences of Piping Replacement at Fukushima Daiichi Unit 4 and 5 Atsutoshi Makihira ALALA Mini-Workshop Nov.9, 2005 Hamaoka NPS

Upload: others

Post on 18-Jun-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

Dose Rate Reduction Experiences of Piping Replacement at

Fukushima Daiichi Unit 4 and 5

Atsutoshi MakihiraALALA Mini-Workshop

Nov.9, 2005 Hamaoka NPS

Page 2: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

Removal Work Scope of Equipment and Floor Drain Piping

4(BWR4)

Schedule

Unit

Work

Nov.22, 2002 ~ May 21,2003

Removal:415mInstallation:556m

Reactor Building Suppression Pool Area

West East

Reactor Building Suppression Pool Area

West East

5(BWR4)Jan.20, 2003 ~ Sep.26, 2003

:: Drain PipingDrain Piping::Working AreaWorking Area

Removal:446mInstallation:446m

Page 3: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

Dose Rate at Piping Before Replacement Work

Unit 4Unit 4

West 東側

Contact (max)Contact (max)3.503.50mSv/hmSv/hField (max)Field (max)1.301.30mSv/hmSv/h

RHR pipingRHR piping

Work areaWork area

East East

ContactContact((projectionprojection))6.006.00mSv/hmSv/h

FiledFiled((projectionprojection))2.402.40mSv/hmSv/h

Unit 5Unit 5

Page 4: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

RHR and Drain Piping at West Part of Suppression Pool Area

Unit 4Unit 4

West East

RHR PipingRHR Piping

Drain PipingDrain Piping

Page 5: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

(1)Filed Dose Rate and Estimated Working Time per Person-Day

(2) Estimated Working Time per Person with Annual Dose Limit <20mSv

Unit 4Unit 4

Exposure Doseat 2002

Remaining Dose at 2002

Filed Dose Rate(Geometric Ave.)

Estimated Working Hours

Estimated Working Days(4 hours/day)

Max:8.64mSv 11.36mSv

Min:0.00mSv 20.00mSv

0.151mSv/h

7575

133133

1919

約33日約33日

Unit 4Unit 4 1.30mSv/h 0.9mSv/person-day 41分41分

Field Dose Rate Planned Exposure Estimated Time

41min.

33

Unit 5Unit 5 2.40mSv/h 0.9mSv/person-day

Unit 5Unit 5Max:8.64mSv 10.36 mSv

Min:0.00mSv 20.00mSv

0.300mSv/h

3434

6666

88

約16日約16日16

22分22分22min.

Estimated Working Time for the Task

Page 6: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

1. Work Schedule Conditioning

Proposals for Improvement

Unit 4• Increase of field dose rate (~1.3mSv/h) at west

area because RHR is used for intermediate shutdown

• Shortage of temporary shielding materials for other high radiation work– Start working at east area– Work at west area after installing temporary shielding

Unit 5• Installing scaffold and temporary shielding for the

task during operation when RHR dose rate is low

Page 7: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

Proposals for Improvement

2. FlushingUnit 4• High dose rate at RHR-4, RHR-41, RHR-23

because of RHR operation in shutdown– Flushing RHR-4, RHR-41 by using RHR(C) pump which

circulates water in suppression pool– Flushing RHR-23 by opening MO-23 valve when RHR(C)

pump runningUnit 5• High dose rate at RHR-3, RHR-7, RHR-27 because

of RHR operation in shutdown– Flushing by using RHR pumps which circulates water in

suppression pool

Page 8: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

RHR-Hx(B)

DA B

B A

PLRポンプ PLRポンプ

PLR-5 PLR-2

RHRー23 RHRー3

MO15C

MO15A

MO13A

MO65B

MO15B

MO15D

MO39A

MO34A

RHR-22 RHR-21RHR-1

MO13B

MO13D

RHR-2

MO25A

MO27A

MO20

MO27B

MO66B

RHRRHR--4141

MO12B

RHR-3

RHR-3

RHR-55RHR-53

RHR-55

RHR-1RHR-21

RHR-7

PLR-1PLR-4RHR-23

RHR-41

RHR-27

RHR-23

RHRRHR--2323

RHR-53

MO38A

MO39B

MO38B

RH

R-2

3R

HR

-26

RH

R-2

4

RH

R-3

RH

R-4

RH

R-6

RH

R-3

RHR-53 RH

R-3

RHR-7RHR-8

RHR-27

RHR-28

MO67MO57RHR-52

RH

R-4

4

RHR-44

RHR-47 RHR-51

RWへ

RHRRHR--33

MO13C

MO65A

MO12A

MO34B

:Flushing line

:High Dose Pipng

RPV

MO66A

S/C

MO25B

RHR-Hx(A)

非常時熱負荷運転により、非常時熱負荷運転により、線量当量率上昇!!線量当量率上昇!!

残留熱除去運転により、残留熱除去運転により、線量当量率上昇!!線量当量率上昇!!Flushing by use of RHR(C)

pumps which circulate system water

Open VMO-20 valve when circulate system water

2.Flushing(example)

Proposals for Improvement

Unit 4Unit 4

Page 9: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

3.Temporary Shielding

•Installing temporary shielding at high radiation piping after RHR flushing

[Unit 5]

[Unit 4]

•Installing temporary shielding at projected high radiation piping during operation•Installing temporary shielding at high radiation piping after RHR flushing

RW-1C(Lead covered with SS)

Equipment Drain( Lead covered with

SS )

RW-209( lead blanket )

[Installing during operation]RHR-27( lead blanket )

[Installing after flushing]RHR-23(lead blanket)

Proposals for Improvement

Page 10: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

• Reactor water drained because of RRS replacement work

• High dose rate was projected at RHR-Hx, RHR pumps, suppression pool area

Proposals for Improvement4.Blow Down Water Treatment at Unit 4

R/B B floor suppression pool area R/B B floor suppression pool area R/B 1R/B 1stst floorfloor RHRRHR--HxHx roomroom R/B B floorR/B B floor RHR pump areaRHR pump area

Page 11: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

• Planned reactor water blow down twice• First blow down water drained to

suppression pool so as to second blow down which contains higher activity can be transferred to radwaste (because of capacity)

• Removing crud deposited on RPV bottom by temporary pump and filters

• Fill up RHR-44 with water before blow down for preventing crud deposition

4.Blow Down Water Treatment at Unit 4

Proposals for Improvement

Page 12: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

5.Remote Monitoring

2 0.57

1 0.57

Dose indicator

Wireless APDWireless APD

Remote monitoring of individual dose

TransmittanceTransmittance

Anorak

Protective cloths

Under wear

worker

Worker

Data transmittance

APDIAPDI

Dose indicator

Individual dose can bemonitored even on cloths

[Unit 5] [Unit 4 &5]

APDIAPDI

Proposals for Improvement

Page 13: Dose Rate Reduction Experiences of Piping …2005/02/03  · Unit 4 • High dose rate at RHR-4, RHR-41, RHR-23 because of RHR operation in shutdown – Flushing RHR-4, RHR-41 by using

RHR-27

N

EW

S

CUW-19CUW-19

RW-1CRW-1C

Equipment Drain(vertical)

Equipment Drain

(horizontal)

Vertical Piping

Horizontal Piping

•CUW-19 Contact dose rate: 36.0%

•RW-1C Contact dose rate: 44.4%

•Field dose rate:20.0%

Results for Improvement

•Equipment drain piping

•Contact:66.7%

•Field:88.7%

Dose Rate Reduction Effectiveness after Installing Temporary Shielding

•RW-209 pipings

•Contact:66.7%

•Field:86.7%

Unit 4Unit 4