dose rate reduction experiences of piping …2005/02/03 · unit 4 • high dose rate at rhr-4,...
TRANSCRIPT
Dose Rate Reduction Experiences of Piping Replacement at
Fukushima Daiichi Unit 4 and 5
Atsutoshi MakihiraALALA Mini-Workshop
Nov.9, 2005 Hamaoka NPS
Removal Work Scope of Equipment and Floor Drain Piping
4(BWR4)
Schedule
Unit
Work
Nov.22, 2002 ~ May 21,2003
Removal:415mInstallation:556m
Reactor Building Suppression Pool Area
West East
Reactor Building Suppression Pool Area
West East
5(BWR4)Jan.20, 2003 ~ Sep.26, 2003
:: Drain PipingDrain Piping::Working AreaWorking Area
Removal:446mInstallation:446m
Dose Rate at Piping Before Replacement Work
Unit 4Unit 4
West 東側
Contact (max)Contact (max)3.503.50mSv/hmSv/hField (max)Field (max)1.301.30mSv/hmSv/h
RHR pipingRHR piping
Work areaWork area
East East
ContactContact((projectionprojection))6.006.00mSv/hmSv/h
FiledFiled((projectionprojection))2.402.40mSv/hmSv/h
Unit 5Unit 5
RHR and Drain Piping at West Part of Suppression Pool Area
Unit 4Unit 4
West East
RHR PipingRHR Piping
Drain PipingDrain Piping
(1)Filed Dose Rate and Estimated Working Time per Person-Day
(2) Estimated Working Time per Person with Annual Dose Limit <20mSv
Unit 4Unit 4
Exposure Doseat 2002
Remaining Dose at 2002
Filed Dose Rate(Geometric Ave.)
Estimated Working Hours
Estimated Working Days(4 hours/day)
Max:8.64mSv 11.36mSv
Min:0.00mSv 20.00mSv
0.151mSv/h
7575
133133
1919
約33日約33日
Unit 4Unit 4 1.30mSv/h 0.9mSv/person-day 41分41分
Field Dose Rate Planned Exposure Estimated Time
41min.
33
Unit 5Unit 5 2.40mSv/h 0.9mSv/person-day
Unit 5Unit 5Max:8.64mSv 10.36 mSv
Min:0.00mSv 20.00mSv
0.300mSv/h
3434
6666
88
約16日約16日16
22分22分22min.
Estimated Working Time for the Task
1. Work Schedule Conditioning
Proposals for Improvement
Unit 4• Increase of field dose rate (~1.3mSv/h) at west
area because RHR is used for intermediate shutdown
• Shortage of temporary shielding materials for other high radiation work– Start working at east area– Work at west area after installing temporary shielding
Unit 5• Installing scaffold and temporary shielding for the
task during operation when RHR dose rate is low
Proposals for Improvement
2. FlushingUnit 4• High dose rate at RHR-4, RHR-41, RHR-23
because of RHR operation in shutdown– Flushing RHR-4, RHR-41 by using RHR(C) pump which
circulates water in suppression pool– Flushing RHR-23 by opening MO-23 valve when RHR(C)
pump runningUnit 5• High dose rate at RHR-3, RHR-7, RHR-27 because
of RHR operation in shutdown– Flushing by using RHR pumps which circulates water in
suppression pool
RHR-Hx(B)
DA B
B A
PLRポンプ PLRポンプ
PLR-5 PLR-2
RHRー23 RHRー3
MO15C
MO15A
MO13A
MO65B
MO15B
MO15D
MO39A
MO34A
RHR-22 RHR-21RHR-1
MO13B
MO13D
RHR-2
MO25A
MO27A
MO20
MO27B
MO66B
RHRRHR--4141
MO12B
RHR-3
RHR-3
RHR-55RHR-53
RHR-55
RHR-1RHR-21
RHR-7
PLR-1PLR-4RHR-23
RHR-41
RHR-27
RHR-23
RHRRHR--2323
RHR-53
MO38A
MO39B
MO38B
RH
R-2
3R
HR
-26
RH
R-2
4
RH
R-3
RH
R-4
RH
R-6
RH
R-3
RHR-53 RH
R-3
RHR-7RHR-8
RHR-27
RHR-28
MO67MO57RHR-52
RH
R-4
4
RHR-44
RHR-47 RHR-51
RWへ
RHRRHR--33
C
MO13C
MO65A
MO12A
MO34B
:Flushing line
:High Dose Pipng
RPV
MO66A
S/C
MO25B
RHR-Hx(A)
C
非常時熱負荷運転により、非常時熱負荷運転により、線量当量率上昇!!線量当量率上昇!!
残留熱除去運転により、残留熱除去運転により、線量当量率上昇!!線量当量率上昇!!Flushing by use of RHR(C)
pumps which circulate system water
Open VMO-20 valve when circulate system water
2.Flushing(example)
Proposals for Improvement
Unit 4Unit 4
3.Temporary Shielding
•Installing temporary shielding at high radiation piping after RHR flushing
[Unit 5]
[Unit 4]
•Installing temporary shielding at projected high radiation piping during operation•Installing temporary shielding at high radiation piping after RHR flushing
RW-1C(Lead covered with SS)
Equipment Drain( Lead covered with
SS )
RW-209( lead blanket )
[Installing during operation]RHR-27( lead blanket )
[Installing after flushing]RHR-23(lead blanket)
Proposals for Improvement
• Reactor water drained because of RRS replacement work
• High dose rate was projected at RHR-Hx, RHR pumps, suppression pool area
Proposals for Improvement4.Blow Down Water Treatment at Unit 4
R/B B floor suppression pool area R/B B floor suppression pool area R/B 1R/B 1stst floorfloor RHRRHR--HxHx roomroom R/B B floorR/B B floor RHR pump areaRHR pump area
• Planned reactor water blow down twice• First blow down water drained to
suppression pool so as to second blow down which contains higher activity can be transferred to radwaste (because of capacity)
• Removing crud deposited on RPV bottom by temporary pump and filters
• Fill up RHR-44 with water before blow down for preventing crud deposition
4.Blow Down Water Treatment at Unit 4
Proposals for Improvement
5.Remote Monitoring
2 0.57
1 0.57
Dose indicator
Wireless APDWireless APD
Remote monitoring of individual dose
TransmittanceTransmittance
Anorak
Protective cloths
Under wear
worker
A
P
D
Worker
Data transmittance
APDIAPDI
。
Dose indicator
Individual dose can bemonitored even on cloths
[Unit 5] [Unit 4 &5]
APDIAPDI
Proposals for Improvement
RHR-27
N
EW
S
CUW-19CUW-19
RW-1CRW-1C
Equipment Drain(vertical)
Equipment Drain
(horizontal)
Vertical Piping
Horizontal Piping
•CUW-19 Contact dose rate: 36.0%
•RW-1C Contact dose rate: 44.4%
•Field dose rate:20.0%
Results for Improvement
•Equipment drain piping
•Contact:66.7%
•Field:88.7%
Dose Rate Reduction Effectiveness after Installing Temporary Shielding
•RW-209 pipings
•Contact:66.7%
•Field:86.7%
Unit 4Unit 4