documentation report 31.01.2015

2
Documentation of joint Inspection PP-WRK Area : all area Time : Saturday, 31 st January 2015 04:30 pm Flushing LFO & HFO system Block 1 Control Valve already install final welding done (area pipe bridge to TB) Final welding on heat tracing system done (area FTH to pipe bridge) Need final welding on heat tracing system (area FTH to pipe bridge) Installation Heat Recovery Container’s Chimney Erection Exhaust gas duct steel structure (block 3)

Upload: danang-rahadian

Post on 29-Sep-2015

8 views

Category:

Documents


1 download

DESCRIPTION

documentation report

TRANSCRIPT

  • Documentation of joint Inspection PP-WRK

    Area : all area

    Time : Saturday, 31st January 2015 04:30 pm

    Flushing LFO & HFO system Block 1 Control Valve already install final welding done

    (area pipe bridge to TB)

    Final welding on heat tracing system done

    (area FTH to pipe bridge)

    Need final welding on heat tracing system

    (area FTH to pipe bridge)

    Installation Heat Recovery Containers Chimney Erection Exhaust gas duct steel structure (block 3)

  • Oily water Treatment unit in position (area

    Treatment Building) Hot oil piping line no yet install (Area

    Treatment Building)

    Insulation of HFO piping ongoing (area

    Outdoor auxiliary)

    Remaining final welding Hot oil piping (Heat

    recovery area)

    Remaining install instrument on instrument air

    piping (boiler 1 area) Insulation HFO & Sludge Piping Area TB to EH