MARUBENI CORPORATION DOCUMENT TRANSMITTAL SLIP Ref. N HPII-MCT-HPJ-0001 Date: ### Project Name: Hai Phong II (2x300MW) Thermal Power Project. Contract No.: HP.2999 From Consortium of Dongfang Electric Corporation and Marubeni Corporation Yi Jiangwen, Consortium Project Director To: Hai Phong Thermal Power Join Stock Company 04 Origin (Fax: + 84-31-775.162) Institute of Energy: (Fax: + 84-4-852-3311 & +84-4-852-9602) 01 Origin TPPMU1: (Fax: +84-4-641-8780) Covering Copy: DEC Site Office in Hai Phong 1 orig DEC Project Office in Cheng Du 1 copy by MC Project Office, Tokyo 1 copy by Sub: Document Submission We are please to submit the following documents for your approval. No. Document No. Rev. Issue Code Title 1 MC-HP2-G-001 00 FA Master Time Schedule - Level FA= For Approval , FI = For Information Kindly acknowledge receipt by signing below in a copy of this transmittal and r Submitted by DEC/MC Consortium Acknowledgement of Receipt _________________________ Ren Yu Name: Vice Consortium Project Director Date: Mr. Tran Huu Ham, Director

Upload: roland-nicolas

Post on 01-Dec-2015

15 views

Category:

Documents


1 download

DESCRIPTION

Sample of document transmittal format

TRANSCRIPT

Page 1: Document Transmittal Slip

MARUBENI CORPORATION

DOCUMENT TRANSMITTAL SLIP

Ref. No. HPII-MCT-HPJ-0001Date: 10-Sep-07

Project Name: Hai Phong II (2x300MW) Thermal Power Project.Contract No.: HP.2999

FromConsortium of Dongfang Electric Corporation and Marubeni CorporationYi Jiangwen, Consortium Project Director

To:Hai Phong Thermal Power Join Stock Company 04 Originals

(Fax: + 84-31-775.162)

Institute of Energy: (Fax: + 84-4-852-3311 & +84-4-852-9602) 01 Original

TPPMU1: (Fax: +84-4-641-8780) Covering Only

Copy:DEC Site Office in Hai Phong 1 originalDEC Project Office in Cheng Du 1 copy by e mailMC Project Office, Tokyo 1 copy by e mail

Sub: Document Submission

We are please to submit the following documents for your approval.

No. Document No. Rev. Issue Code Title

1 MC-HP2-G-001 00 FA Master Time Schedule - Level 2

FA= For Approval , FI = For Information

Kindly acknowledge receipt by signing below in a copy of this transmittal and return to the Contractor.

Submitted byDEC/MC Consortium Acknowledgement of Receipt

_________________________

Ren Yu Name:

Vice Consortium Project Director Date:

Mr. Tran Huu Ham, Director