document ref: rep-pl-3br-007 - crawley borough council · ove arup & partners ltd ... 2 design...
TRANSCRIPT
Thameslink Programme Rolling Stock Project: Depots and Stabling -Three Bridges Scheme External Lighting Strategy Black
Document Ref: REP-PL-3BR-007
Thameslink Programme Rolling Stock Project: Depots and Stabling -Three Bridges Scheme External Lighting Strategy
October 2009
This report takes into account the
particular instructions and requirements
of our client.
It is not intended for and should not be
relied upon by any third party and no
responsibility is undertaken to any third
party Ove Arup & Partners Ltd
63 St Thomas Street,
Bristol BS1 6JZ
Tel +44 (0)117 976 5432 Fax +44 (0)117 976 5433 www.arup.com
Job number 207670-00
Thameslink Programme Rolling Stock Project:
Depots and Stabling - Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS
Ove Arup & Partners Ltd 21 October 2009
Contents Page
1 External Lighting Strategy 2
1.1 Introduction 2
2 Design Criteria 3
2.1 Criteria 3
3 Existing External Lighting 5
4 Proposed External Lighting 6
4.1 Authorised Walkway Lighting 7
4.2 Operational Staff Car Parking 7
4.3 General Footpaths 7
4.4 Access Roads 7
4.5 Wheel Lathe 7
4.6 Proposed Maintenance Depot 8
4.7 NR Electricity Sub-stations 8
4.8 Bridges 8
4.9 Underpass 8
4.10 Temporary Lighting 9
5 External Lighting Control 10
6 Energy Efficiency 11
6.1 Dark Skies 11
6.2 Type of Lamps 11
7 Environmental Impact Assessment 12
7.1 Sensitive Areas 12
8 Waste Electrical and Electronic Equipment Directive (WEEE Directive) 13
8.1 Disposal of Existing External Lighting 13
9 Cabling and Containment 14
9.1 Introduction 14
10 Responsibilities 15
Appendix A
Generic Luminaire Schedule
Appendix B
The Proposed Three Bridges Scheme –
Base Scheme Layout
Appendix C
The Proposed Three Bridges Scheme –
External Lighting Strategy Drawing
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 2 Ove Arup & Partners Ltd
21 October 2009
1 External Lighting Strategy
1.1 Introduction
Arup have been commissioned to produce an external lighting strategy within the Network
Rail (NR) infrastructure for the proposed Three Bridges scheme as described below:
• Proposed Three Bridges Maintenance Depot;
• Wheel Lathe;
• Controlled Emission Toilet (CET) transfer facility;
• Train washers;
• Underframe Cleaning (UFC) facility;
• Stabling sidings;
• Operational staff car parking;
• Access roads and footpaths; and
• Proposed and existing vehicular and pedestrian bridges.
The design criteria applicable for the proposed Three Bridges scheme are identified in
Section 2 of this strategy report.
In formulating this strategy, consultation has taken place with various parties during the
design stage.
A generic Luminaire Schedule is attached in Appendix A.
Drawings within Appendix B identify the base scheme layout for the proposed Three
Bridges scheme. To supplement the base scheme an external lighting strategy drawing has
been included within Appendix C.
The lighting treatment for these areas would generally utilise a combination of column and
building mounted luminaires including low level bollards specifically for access walkways.
Lamps would generally utilise metal halide lamps producing a white light source.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 3 Ove Arup & Partners Ltd
21 October 2009
2 Design Criteria
2.1 Criteria
External design criteria that will be used to determine the illuminance levels for the proposed
scheme will be designed to, but not limited to, the following Standards and Codes:
• Railway Group Standards G1/GN 7520;
• Lighting of Railway Premises G1/RT 7010;
• BS EN 13201 Part 2:2003 Road Lighting;
• BS EN 5489-1:2003 Code of Practice for the Design of Road Lighting;
• Highways Agency BD2604 Documentation;
• CIBSE Lighting Guides, particularly External Lighting Guide LG6;
• Network Rail; Junction Lighting Specification; NR/LNW/E&P/036; Issue 1; November
2007;
• Network Rail Specification, Specification of lighting for track inspection in darkness; July
2008;
• BS EN 40 Lighting Columns;
• BS EN 5649 Lighting Columns;
• BS EN 12464-2 Lighting of work places – Part 2: Outdoor work places;
• BS EN 62035 Discharge lamp (excluding fluorescent lamp) safety specifications;
• CIE 88 Guide for the lighting of Road Tunnel and Underpasses;
• Clean Neighbourhoods and Environment Act:2005;
• Campaign for Dark Skies (CFDS).
New lighting columns will be manufactured in compliance with BS EN40 and Highways
Agency BD2604 documentation. Columns would generally be constructed of tubular steel
with a galvanised finish and be of a type that will include a low level hinge facility for ease of
maintenance and preventing disruption to the operation of the proposed scheme. Columns
would include a manual or hydraulic wind down facility to carry out routine maintenance and
re-lamping.
The external lighting for the access road and footpaths will be designed to NR standards
G1/GN 7520 section 2.12 and 2.13 specifically referring to authorised walking routes,
sidings and stabling areas plus class S3 (Table 3 – BS 13201-2:2003(E)).
The table overleaf indicates the targeted illuminance for the maintained average illuminance
(Eav), minimum illuminance (Emin) and uniformity (Emin/Eav) for the various areas noted.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 4 Ove Arup & Partners Ltd
21 October 2009
TARGETED ILLUMINANCE LEVELS (BS EN 13201-2:2003 and BS EN 5489-1:2003)
Eav (lux) Emin (lux) Min Uniformity
Main Car Park 10 2.5 * 0.25
Footpaths 7.5 - 11.25 1.5 0.13 - 0.2 *
Access Roads 7.5 - 11.25 1.5 0.13 – 0.2 *
TARGETED ILLUMINANCE LEVELS (G1/GN 7520)
Eav (lux) Emin (lux) Min Uniformity
Stabling Sidings 10 2 0.25
Authorised Walking Routes 10 5 0.3
Tunnel/Underpass 10 5 0.5
* Note: The value indicated is a calculated value and not explicitly specified in the standard.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 5 Ove Arup & Partners Ltd
21 October 2009
3 Existing External Lighting
Generally the existing external lighting at the Three Bridges depot consists of a diverse
range of external lighting.
Lighting within existing stabling sidings consists of high mast, standard type columns and
structural lattice towers with luminaires affixed at high level for the provision of illuminating
large tracked areas.
Building mounted flood lighting also provides illumination around the perimeter areas of the
existing Three Bridges depot and remote buildings.
Low level hinged standard column mounted luminaires provide illumination to operational
staff car parking and access roads.
All existing external lighting identified above will generally be removed with the exception of
lighting affixed to existing buildings that will be retained under this scheme.
Existing lighting being retained will be tested and inspected and consideration of
replacement will be identified during the next design stage.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 6 Ove Arup & Partners Ltd
21 October 2009
4 Proposed External Lighting
The proposed scheme has a single site as indicated on drawing 3BR-GX-201 (refer to
Appendix B). The proposed Three Bridges scheme would straddle the main line. On the
west side of the site, adjacent to the Up Side (carrying trains toward London), it is proposed
to locate the following facilities:
• The maintenance depot, including warehousing and administration facilities;
• A wheel lathe;
• A train washer;
• Stabling to accommodate 8 x 12-car units;
• A Network Rail electricity substation;
• Ancillary plant and equipment, CET plant room, train washer plant room, and a waste
storage/compactor compound.
On the east side of the site, adjacent to the Down Side (carrying trains towards Brighton),
the following facilities are proposed:
• Additional (but operationally separate) stabling for 4 x 12-car units;
• An Underframe Cleaning (UFC) facility;
• A train washer;
• An additional accommodation building; and
• Ancillary plant and equipment including CET plant room, UFC plant room, train washer
plant room, and a waste storage/compactor compound.
The two sides of the site will be linked by an operational staff footbridge to allow service and
maintenance staff to attend units in both the maintenance depot area and the stabling and
UFC area.
The proposed external lighting strategy has endeavoured to integrate new and existing
lighting fixtures within and around the proposed scheme.
A combination of wall and column mounted luminaires will be provided throughout the
proposed scheme. Column heights will range between 8m and 12m, however within areas
where these column heights are not practical columns of 4m may be utilised. Generally,
lighting to existing sidings and vehicular highways within the boundary of the proposed
scheme will be replaced with a luminaire type approved by the Local Planning Authority
(LPA). Wall mounted lighting has generally been considered within the development
particularly where new buildings include adjacent authorised footways and access roads,
these would however be supplemented with columns if required.
Luminaires would generally include full cut-off / asymmetric reflectors to prevent light
spillage to adjacent areas, dwellings and the main line as required.
The final lighting strategy will be fully coordinated with third party installations such as, but
not limited to, the following:
• Third Rail;
• Rail Road Junctions; and
• Existing Industrial and Domestic properties.
In Appendix A typical examples of proposed luminaire types have been indicated.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 7 Ove Arup & Partners Ltd
21 October 2009
Lighting calculations will be submitted during the next design stage and will demonstrate the
average illuminance levels to various locations/areas as identified in Section 2. Final
calculations for these areas will be submitted by the successful Train Operating Company
(TOC) as part of their design responsibility during the Technical Approval process.
External luminaires will be manufactured to a minimum Ingress Protection (IP) rating of
IP65.
An emergency lighting strategy for external areas will also require approval with LPA and
Building Control.
The following sections identify external lighting proposals to specific areas of the scheme.
4.1 Authorised Walkway Lighting
Authorised walkway lighting, such as those within the proposed stabling sidings, would
generally consist of column mounted and low level bollard lighting. Particular areas such as
raised CET facility platforms will utilise low level hinged columns with suitable luminaires
and outreach arm brackets. Low level walkways between rolling stock will utilise low level
bollards positioned at strategic locations to allow safe passage of personnel.
An illuminance level in this area will be based on an average 10lux (Eav) with a uniformity of
0.3 (Emin/Eav).
Drawing 3BR-BE-101 (refer to Appendix C) provides guidance on the lighting strategy. The
Yellow shaded area indicates the lighting assessment for authorised walkway routes.
4.2 Operational Staff Car Parking
Operational staff car parking facilities associated with the proposed scheme would generally
be illuminated by using column mounted luminaires mounted on adjacent footpaths. To
compliment the columns building and wall mounted luminaires as necessary to achieve the
required illumination levels.
An illuminance level in this area will be based on an average of 10lux (Eav) with a uniformity
of 0.25 (Emin/Eav). The grey shaded area shown in drawing 3BR-BE-101 (refer to
Appendix C) indicates the lighting assessment for the car parking facilities.
4.3 General Footpaths
The general footpaths within the proposed scheme would generally utilise building and
column mounted luminaires. An average illuminance level to these areas will be based on
7.5 – 11.25lux (Eav) and a minimum uniformity of 0.13 – 0.2 (Emin/Eav).
The grey and green shaded area shown in drawing 3BR-BE-101 (refer to Appendix C)
indicates the lighting strategy for footpath areas.
4.4 Access Roads
The access road would generally utilise column mounted luminaires. An average
illuminance level to these areas will be based on 7.5 – 11.25lux (Eav) and a minimum
uniformity of 0.13 – 0.2 (Emin/Eav).
The grey shaded area shown in drawing 3BR-BE-101 (refer to Appendix C) indicates the
lighting strategy for access road area.
4.5 Wheel Lathe
The external elevation of the proposed Wheel Lathe located adjacent to the proposed
maintenance depot will be illuminated using building mounted luminaires. Generally,
lighting would illuminate the perimeter and specifically access routes and entrance and exits
to and from the building.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 8 Ove Arup & Partners Ltd
21 October 2009
An illuminance level in this area will be based on an average of 10lux (Eav) with a uniformity
of 0.3 (Emin/Eav).
The green shaded area shown in drawing 3BR-BE-101 (refer to Appendix C) indicates the
lighting assessment for the proposed Wheel Lathe building.
4.6 Proposed Maintenance Depot
The proposed maintenance depot includes a three road maintenance area, stores facility
and office accommodation. The external elevations of the proposed maintenance depot will
be illuminated using building mounted luminaires. Generally, lighting would illuminate the
perimeter and specifically access routes and entrance and exits to and from the building.
The entrance to the three road maintenance area within the maintenance depot will be
illuminated by high level building mounted floodlights producing a higher level of average
illuminance. The luminaires will be angled and suitable luminaire baffles will be installed to
prevent glare to adjoining areas of the scheme where applicable.
Adjacent to the main entrance of the office accommodation, recessed architectural in-
ground mounted LED uplighters will be installed using coloured LEDs to illuminate the
underside of proposed roof overhangs. Narrow and wide beam in-ground uplighters will be
used. Care will also be taken to ensure the glass surface temperature will be below 70°C.
Anti-glare baffles will be used to reduce glare as required.
Special consideration will be taken in order to limit glare to train drivers.
An illuminance level in this area will be based on an average 7.5 – 11.25lux (Eav) with a
uniformity of 0.13 – 0.2 (Emin/Eav). Adjacent to the rolling stock entrance of the proposed
maintenance depot an illuminance level will be enhanced.
The green shaded area shown in drawing 3BR-BE-101 (refer to Appendix C) indicates the
lighting assessment for the proposed depot building.
4.7 NR Electricity Sub-stations
The proposed external lighting of the NR sub-station buildings will be undertaken directly by
Network Rail (NR). We envisage external lighting would generally be illuminated using
building mounted luminaires. External lighting would illuminate the perimeter and
specifically external equipment, authorised access routes and entrance and exits to the
building.
The green shaded areas shown in drawing 3BR-BE-101 (refer to Appendix C) indicate the
lighting assessment for the proposed NR sub-station buildings.
4.8 Bridges
Lighting for the bridges will generally consist of column mounted luminaires affixed to the
bridge structure in a way to prevent disruption to vehicular and pedestrian routes.
4.9 Underpass
It is proposed that luminaires within the pedestrian underpasses will consist of vandal
resistant material and to be rated IP65. Luminaires will be linear enclosed fluorescent
luminaires complete with attachments for the provision of producing a direct downlight
component.
An illuminance level in this area will be based on 10lux average (Eav) and with a uniformity
of 0.5.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 9 Ove Arup & Partners Ltd
21 October 2009
4.10 Temporary Lighting
The temporary lighting that will be installed during the construction period will be the
responsibility of the successful bidder’s contractor. The bidder’s contractor will undertake
the required design calculations and submit these directly to the LPA for Technical Approval
prior to construction commencing on site.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 10 Ove Arup & Partners Ltd
21 October 2009
5 External Lighting Control
External lighting will generally be controlled in various zones relating to the activity taking
place:
• Zone 1: Authorised Walkways;
• Zone 2: Car parking, Access roads and general Footpaths.
Each external lighting zone will be controlled from a number of external feeder pillars (final
locations to be agreed) strategically located throughout the proposed scheme. Each feeder
pillar will be controlled via a photocell, contactor and solar time switch arrangement. An
override switch would also be located within the main reception area of the proposed
maintenance depot.
Time switches will be of the 7-day multi-programmable digital type allowing a minimum of
three ‘On’ and three ‘Off’ positions.
Electrical supplies to the feeder pillars will emanate from the main electrical distribution
within the proposed Depot building.
Luminaires within the pedestrian underpass will utilise automatic presence detection as the
control medium.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 11 Ove Arup & Partners Ltd
21 October 2009
6 Energy Efficiency
6.1 Dark Skies
With the exception of some architectural lighting all other lighting will minimise any stray
light within the recommended limits and to the satisfaction of the “Campaign for Dark Skies”
and the guide for Obtrusive Lighting published by the Institution of Lighting Engineers.
Where in-ground uplighting will be provided it will generally be installed below the building
overhang however stray light will be minimised and calculated within recommended limits.
6.2 Type of Lamps
The external lighting scheme will be carefully designed to minimise the cost in operation by
choosing the most efficient light sources appropriate to the task it is fulfilling.
Typically Metal Halide light sources will be used where applicable with the appropriate
colour rendering properties. Generally, this type of lamp source will produce a better visual
environment for each area.
The illuminance output level from luminaires would vary to suit the external ambient
conditions installed therein.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 12 Ove Arup & Partners Ltd
21 October 2009
7 Environmental Impact Assessment
7.1 Sensitive Areas
The Environmental Impact Assessment has identified areas adjacent to the site that are
particularly sensitive to the effects of light spillage. All external light sources would include
full cut-off / asymmetric reflectors where applicable to prevent light spillage to these
areas. Environmentally sensitive areas, marked on the External Lighting Strategy Drawing
(see Appendix C), are as follows:
Visually sensitive areas:
• Domestic properties to the east along Stainer Close, Craven Road, Wheeler Road and
Fenchurch Road; and
• Domestic properties to the west along Marion Road.
Ecologically sensitive areas:
• Bat and bird habitat along Gatwick stream and the rail side vegetation; and
• Tilgate Forest Park.
In addition to these environmentally sensitive areas, light spillage to the following receptors
will be minimised:
• The operational railway line; and
• Skies.
Lighting within pedestrian underpasses will include linear fluorescent luminaires complete
with attachments for the provision of producing a direct downlight component. The aim will
be to minimise light pollution at high level where existing animal activity takes place.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 13 Ove Arup & Partners Ltd
21 October 2009
8 Waste Electrical and Electronic Equipment Directive
(WEEE Directive)
8.1 Disposal of Existing External Lighting
All electrical equipment being removed and provided as part of the proposed Three Bridges
scheme will be compliant with the Waste Electrical and Electronic Equipment Directive
(WEEE Directive). The WEEE Directive has been applicable since its launch in January
2007.
The main aims of the WEEE Directive are detailed below:
• To reduce the amount of electrical and electronic equipment being produced;
• Re-use it;
• Recycle it; and
• Recover it.
Manufacturers of external lighting equipment will also comply with the WEEE Directive. The
aim is to improve the supply, use, recycling and recovery of electrical and electronic
equipment from inception to completion of the scheme.
Disposal of existing lamps will need to be waste managed carefully as some may contain
harmful chemicals such as mercury.
Reference: Environment Agency Website www.environment-agency.gov.uk ; sub-heading -
WEEE - 19 June 2009
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 14 Ove Arup & Partners Ltd
21 October 2009
9 Cabling and Containment
9.1 Introduction
A rewireable containment system will be provided to allow installation and removal of
cabling at any time. Cabling will be run within a ducted infrastructure complete with cable
chambers located at strategic locations of the scheme.
Suitable cable ducts will be installed emanating from the proposed maintenance depot
buildings to feeder pillars and then terminating in the structural base of each lighting column
or bollard.
Feeder pillars will be located at strategic locations from which column and bollard wiring will
emanate. Column and bollard external luminaires will be wired using XLPE/SWA/LSF
The proposed external lighting scheme will require careful coordination with the following:
• NR facilities;
• Third Rail infrastructures;
• Industrial properties;
• Domestic properties; and
• NR main line.
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page 15 Ove Arup & Partners Ltd
21 October 2009
10 Responsibilities
The successful Main Contractor will undertake the complete lighting design, installation and
testing and commissioning including all necessary duct infrastructures and costs associated
with the external lighting installation.
The Main Contractor will also be responsible for the co-ordination of the lighting installation
including all interfaces and connections to third parties associated with the lighting
installations described within this strategy report.
Lighting calculations and final selection of luminaires will be submitted during the next
design stage for approval
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page A1 Ove Arup & Partners Ltd
21 October 2009
Graphic Description Area of use Lamp Type Generic
Manufacture Accessories
A
IP65 An oval extruded aluminium
body,
Authorised walkways
Metal Halide
3000K
Holophane
Lighting
Denver
Range
B1
IP67 The optical assembly has a
specular aluminium reflector and
aluminium body.
Stores delivery area
Elevation of
Warehousing and new
Depot building
Elevation of Wheel
Lathe building
Metal Halide
3000K
Holophane
Lighting
Seattle
Range
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page A2 Ove Arup & Partners Ltd
21 October 2009
B2
IP65 The latest in control gear and
lamp technology, coupled with a
precisely engineered refractive lens
and pre-anodised reflector assembly,
to achieve maximum performance
combined with high efficiency.
Stores delivery area
Elevation of
Warehousing and new
Depot building
Elevation of Wheel
Lathe building
Metal Halide
3000K
Holophane
Lighting
Denver
Range
C
IP67 column luminaire. Optical and
gear compartment, Aluminium body,
flat glass enclosure.
Sidings
Car parking
Access Roads
Footpaths
CET/UFC
Bridges
Metal Halide
3000K
Holophane
Lighting
Seattle Street
Range
D
IP65 linear fluorescent luminaire.
Underpass
Flour.
4000K
Thorn
Lighting
Thameslink Programme Thameslink Programme Rolling Stock Project
- The Proposed Three Bridges Scheme
External Lighting Strategy
J:\207XXX\207670-00\4.01_ISSUES\2009-10-21 3BR EXTERNAL LIGHTING STRATEGY UPDATED TO SUIT COMMENTS Page A3 Ove Arup & Partners Ltd
21 October 2009
E
In ground LED uplighters
Entrance to proposed
maintenance depot
-
Thorn
Lighting
Generally 4m – 12m high columns
complete with low level hinge to
allow ease of maintenance and lamp
replacement.
Galvanised finish
Refer to Type C
luminaire above.
-
Abacus
Phosco
Hydraulic or
manual
raise/lower
device.
Bristol BS1 6JZ
Tel +44(0)117 976 5432 Fax +44(0)117 976 5433
www.arup.com
63 St Thomas Street
J:\207xxx\2
07670-0
0\4.3
0_
Drgs\0
_Live_
Dra
win
gs\3
BR-G
X-2
01.d
gn
Depots and Stabling
Rolling Stock Project:
Thameslink Programme Three Bridges Site Plan
For Planning1:1000
207670-00 3BR-GX-201
Key Plan
Thameslink Programme
/ /070709 CO RS NDF
Issued for planning
01
02Infrastructure
(A1)
/ /170709 CO RS NDF
02
Car Parking Amended- Issued For Planning
Legend
Track Works
Proposed Buildings & Structures
Access Routes and Walkways
Redline Boundary
Vegetated Areas
Path (um)
Path
ETL
Path
49 to 57 31 to 3940 to 48
22 to 30
El
Sub
Sta
75.3
m
18 13
19
ETL
ETL
Drain
Drain
75.6
m
Maidenbower Lane
21
22
24
71.6
m
37 to 40
18to21
46 4322 15
12
9
SLs
16
18 22
13
MARION ROAD
35 39
ETL
28
80.9
m
Sub
Sta
El
49
3132WHE
ELER R
OAD
ED & Ward Bdy
66
MARIO
N ROAD
57 to 65 48 to 56
47
45
WHE
ELER R
OAD
24
42
41
23 27
25 26
30
29 28
FENCHURCH ROAD
13 to 21
MAID
ENBO
WER LANE
Oriel
Hig
h
Sc
ho
ol
MP 30
58
60 7
ED & Ward Bdy
NORWICH ROAD
Furnace
Green
Pla
yin
g
Field
El
Sub
Sta
IPN
NIP
NIP
WILLIAMS WAY
Three
Bridges Sta
196
HASLETT AVENUE EAST
ETL
Car
Par
k
WILLIAMS
WAY
Plant Room
A
A
MP 29.5ED & Ward Bdy
Adventure
Pla
yground
SL
22
Und
BILLIN
TON DRI
VEGatwick Stream
ED &
Ward B
dy
CR
ED & Ward Bdy
MP 29.7
5
Gatwick
Stream
Ward B
dy
Def
82
8684
80
92
NOR
WIC
H ROAD
15
23to26
18to21
16 12to
8 4 to 7
34to3730to33
78
El
Sub
Sta
Three
Brid
ges
Junctio
n
N
N
For c
ontin
uatio
n see b
elo
w
For c
ontin
uatio
n see in
sert
Retaining wall between
main line and stabling
For c
ontin
uatio
n see a
bove
Insert
Main Depot Building
Down Side
Footprint for
substation
Waste storage/compactor
NR Storage area
Site access off Billinton Drive
UFC plant roomRetaining wall Under frame cleaning facility (UFC)
Waste storage/compactor
Wheel lathe building
Retaining Walls
Up Side
Office/Warehouse Building
Existing up side site access road
Existing site access off Williams Way
Retaining wall to
support cutting
New pedestrian
footbridge
(Bridge 3BR-03)
Bridge wideningBridge (3BR-02)
Bridge widening(Bridge 3BR-01)
Up Side wash plant room
Up Side train wash buildingDown Side train wash building
Down Side wash plant roomDown Side CET plant roomDown Side accomodation building
Up Side CET
plant room
8788
89
90 91 92 93
1 2 3 4 5 6 7 89 10 11 12
1314
1516
1718
1920
21
2223
24
25
26
27
28
VV
29
32 3334
3536
37
38
39
40
4142
4344
4546
4748
4950
5152
5354
5556
5758
5960
6162
63
6465
6667
6869
7071
7273
7475
76
7980
8182
8384
8586
V V
30
31
7778
A1 A
9
B C D E F G H I J K L M N O P
Job No
Drawing Status
Discipline
Scale at A1
Drawing No Issue
Drawing Title
Issue Date By Chkd Appd
Job TitleClient
10
8
7
6
5
4
2
1
3
Do not scale ' Arup
Tank
Tank
SL
SL
S
Gantry
SL El
Sub
Sta
MP 29.5
80
76
78
74
31
30
76.5
7m
93
BM 85
105
95
Depot
ED & Ward Bdy
Sig
nal
Box
CR
Und
Three
Brid
ges
Junctio
n
ED & Ward Bdy
ETL
73.3
m
Tank
ETL
Tanks
Adventure
Pla
yground
Path (u
m)
88
84
82
86
Sluic
e
70.7
3m
BM
Path (um)
Path
SL
SL
22
ETL
113
Scout
Hall
Und
BILLIN
TON DRI
VEGatwick Stream
Gatwick Stream
ED &
Ward B
dy
CR
ED & Ward Bdy
BILLINTON DRIVE
MP 29.7
5
Path
Three Bridges Station
Cycle Track
SM
Depot
STATION HILL
WILLIAMS WAY
Sub
way
1
2
2
El
Su
b
Sta
Co
ver
Ho
use
Gatwick Stream
He
ns
on
Ho
use
FB
AVENUE
ETL
HENSON ROAD
(PH)
The
Sn
oot
y
Fo
x
Three
Bridges Sta
196
LB
200
10
Su
b
Sta
El
Su
b
Sta
El
Ta
nks
STEP
HENS
ON P
LACE
El
Su
b
Sta
Convey
or
Co
ncrete
Batc
hin
g
ETL
Ho
ppers
Pla
nt Drain
Ocea
n
Ho
use
68.5
m
39
Instit
ute
The
Mont
efior
e
16
6
19
69.0
m
1 249
S Gantry
S Gantry
Ba
nk
196
TCB
68.6
m
237
Trainin
g
Ce
ntre
El
Su
b
Sta
HASLETT AVENUE EAST
El
Su
b
Sta
FB
Car
Par
k
ETL
Gatwick
Stream
FB
ETL
HASLETT AVENUE
EAST
1L
B
5
3
11
El
Sub Sta
Estate
In
dustrial
Riv
ersid
e
House
13
El
Su
b
Sta
STEP
HENS
ON WAY
Ho
use
Sa
xo
n
In
dustrial
Post
Estate
Ta
nk
El
Su
b
Sta
ETL
Maide
nbowe
r La
ne
17
16
7
11
3
30
27
8
20
17
21
El
Su
b
Sta
24
28
30
WATER LEA
13
60
626458
68
66
121
72
70
Drain
SP
13
15
21
17
2225
23
22
10
8
12
76.2
m
83
5
17
9
2
CHIDDINGLY CLOSE
11
4
6 3
3330
28
32
3129
79
62
3
10
4
53
34
1
34
76.5
m
36
GREENACRES
38 to 47
32
7 to 161 to 6
23 to 37
17 to 22
25
22
17
51
1
4
14
2
El
Su
b
Sta
1a1
Christ
Ch
urc
h
ALICIA AV
ENUE
109
107111113
2
73.9
m
44
18
Ward B
dy
Def
64
73.0
m
82
8684
8076
PEARSON ROAD
54 123
FF
129
119121
52 117
115
92
13
18
73.8
m
74.9
m
28
101
99
40
6
105
103
1
97
Drain
Po
un
d
Hill
So
ut
h
Pla
yin
g
Field
Path (um)
Path (um)
Po
un
d
Hill
So
ut
h
Pla
yin
g
Field
35
32
23
13
1
16
2
133
1b
10
South
Lodge
1 to 18 St Ives
70.4
m
TC
B
Ma
nse
13
70.5
m
Def
10
2122
25
73
71
26
22
24
20
87
49
69
75
Pla
ygr
ou
nd
7
10
Play
grou
nd
13
12
6
11
17
6
TC
B
1
30
29
40
77.1
m
42
40
Drain
Pla
y
Ce
ntre
52
7
27
39
16
Car
Par
k
Pavilion
10
1
13BANK
S RO
AD
54
El
Su
b
Sta
64
80.9
m
18
82.7
m
30
13
15
21
31
35
33
28
40
CLOSE
PEVENSEY
43
13
86.0
m
45
49 to 57 31 to 3940 to 48
22 to 30
El
Su
b
Sta
75.3
m
18 13
Path
19
8
13
15
7
5
11
9
21
3
17
5
2624
30
2319 20
2527
44
SHEFFIE
LD CL
10
2
73.0
m
60
3945
8462 37
31
Posts
74.5
m
33
Sta
Su
b
El
54
62 96 9094
8892
84
8680
74
WARNHAM ROAD
7882
76 72
62
ETL
ETL
Drain
Drain
75.6
m
Maidenbower Lane
21
71.3
m
NOR
WIC
H ROAD
15
Posts
13
16
15
Lowestoft
Walk
12
7
1 Hawkhurst
Walk
9
7
13 1
ASHBURNHA
M ROAD
52
22
18
1612
52
STRUDGATE CLOSE
1
14
10
Path (u
m)
13
17
19
Posts
Posts
16
14
13
Barton
Walk
4
3
3
1
2
2
Posts1
4
1
2
El Sub S
ta
Posts
22
24
33
1
4 11
Posts
2
2
Posts
2
23
Car
Par
k
7
11
66 100
Pa
vilio
n
25
66
70
68
64
13
Oulton
Walk
12
Hicklin
g
Walk
15
13
14
11
16
22
24
12
10
Breydon
Walk
71.
6m
57
11
14to17
55
58
66
60
3
3
5
1
37 to 40
WALKER ROAD
4
23to26
18to21
46 4322 15
12
15
721
23
6
RAWORTH CLOSE
15to19
21
9
3
74.8
m
El
Su
b
Sta
911 1
20
NOR
MANDY
2
8
12
2
64
6
12
21
PENFOLD ROAD
29
16
ED &
Ward Bdy
CR
6
Pond
Lowestoft
Walk
All
ot
me
nt
Gar
de
ns
Path
520
16
FF
7
12
22
20
FF
17
3
1
BLACKETT ROAD
31
12
8
20
33
12
16 12
15
t0
11
25
to
28
3to6
10
CRAVEN ROAD
ST
RO
UD
LE
Y
CL
OS
E
1
7
7to10
13
3t
o6
18
22
26
29
25
HA
WORTH ROAD
10
ANGELL CLOSE
23
20
to2
4
16
19
4
26a
Path5
HODGKIN CLOSE
29
26
1
69
4
1
7
Iron
Works
(sit
e
of)
21
18
Maiden
bower La
ne
25
FBs
Ward Bdy
37
265
17
13
15
14
31
GOLDIN
G CL
OSE
29
32
26c
Po
nd
Path (
um)
72.9
m
12
Path
10
1BILLIN
TON DRIV
E
74.7
m
MARI
ON R
OAD
2
44
FB
SLs
MP
30.2
5
SLs
16
18 22
13
MARION ROAD
Path (u
m)
35 39
ETL
Drain
Drain
Path (um)
Po
nd
Drain
Track
28
80.9
m
Su
b
Sta
El
49 ETL
27
26
22
24
25
23
21
7
10
16
14 18
19
20
HOLD
ER R
OAD
21
8
22
29
10
11
33
ELLSON CL
7
5
1
3
38
BILLINTON DRIVE
1
13
9
3132
4
ELLIOT C
L
1
2
32
34
36
30
10
28 40
12
2
70
1
7
15
4
CLOSE
9
STIR
LING
5
22
28
16
21
26
61
10
12
8
WALKER ROAD
ELLIOT CLOSE
5
26
86
97
6
8
7
3MAYE
S CL
OSE
MAID
ENBO
WER LANE
Oriel
Hig
h
Sc
ho
ol
8
42
14
44
15
27
19
21 20
15
4
WANTAGE CLOSE
1
8
17
32
21
WHE
ELER R
OAD
18
CLOSE
12
STEPNEY CLOSE
655
FENCHURCH ROAD
5
11
4
43
86
1918
67
1
21
1
2
7
SINCLAIR CLOSE
3
10
GODD
ARD
CLOS
E
77
80
83
10
76
5
6
8
11
12
7
25
2324
27
MATTHEWS DRIVE
26
33
19
21
31
WATSON CLOSE
17
1
9
2
WA
TS
ON
CL
OS
E
7
35
Su
b
Sta
El
6
28
10
Sta
nf
or
d
Br
oo
k
5
72
2 4
73
69
59
15
16
MAUNSELL PARK
AV
ENUE
ALICIA
23
41 t
o
48
13 to 2
1
22 t
o 40
Jaco
bs C
ourt
1 to 12
Co
bur
n
Ho
use
1 t
o
35
El
Su
b
Sta
HAZELWICK
ED & Ward Bdy
MP
30.5
Po
nd
BENN
ETT
CLOS
E
Pat
h (u
m)
79
75
71
72
66
85
1
5
Drain
66
7071
MATTHEWS DRIVE
RU
ST
ON
CL
OS
E
l
61
74
3
2
54
55
56
57
50
52
51
53
14
42 15 16
17 18
434445
41
46
48
47
6
8
49
Drain
60
62
64 65
MARIO
N ROAD
29to34 28
13 14
11 12
26
25
SLs
1
Path
35to40
7
37
57 to 65 48 to 56
47
44
9
40
45
71.6
m
WORTH PARK AV
ENUE
Ward Bdy
Access House
CHID
DIN
GLY CLOSE
STEP
HENS
ON WAY
WALESBEECH
29 6
Lamberhurst
Walk
4
GOSDEN CL
70
CLOSE
GOSDEN
14
1Wroxham
Walk
Bala
ncin
g
Po
nd
Track
5
8
Po
nd
KNEPP CLOSE
1210
HASTINGS
2
ROAD
4
Worth Way
WHE
ELER R
OAD
24
4241
23
27
25 26
3029 28
FENCHURCH ROAD
13 to 21
MAID
ENBO
WER LANE
Oriel
Hig
h
Sc
ho
ol
MP 30
36
58
60
STIRLING
CL
Path
4
1
8 4 to 7
STANIER C
LOSE
34to37
1
39
3
41
30to33
29
7
33
1
2
54
WHE
ELER RO
AD
BAXTER C
LOSE
6
HA
WORTH ROAD
Path
ED & Ward Bdy
NORWICH ROAD
CR
ED & Ward Bdy
48 to 62
78
Wort
h Wa
y
Pound
Hill
South
Pla
yin
g
Field
STATION HILL
1 t
o
37
SAUNDERS CLOSE
SAUNDERS CLOSE
Ree
ves
Ho
use
63 to 74
Ramp
1 t
o
21
TRAFALGAR GARDENS
Mor
ga
n
Ho
use
Da
niels
Ho
use
TRAFALGAR GARDENS
Mor
ga
n
Ho
use
1 t
o
31
1 t
o
31
Posts
Fur
nace
Gree
n
Pla
yin
g
Field
4
72.7
m
28
BELLOC CLOSE
PEARSON ROAD
2
BAXTER C
LOSE
20
Car
Par
k
WILLIAMS
WAY
TH
RE
E
BRID
GE
S
RO
AD
6
NORMANDY CL
OSE
El
Su
b
Sta
LUCAS CLOSE
LUCA
S CL
OSE
77
Path (u
m)
89
86
GODD
ARD
CLOS
E
Path (um)
28 to 36
19 to 27
1
24
HASTIN
GS R
OAD
THE PASTURE
7
27
14
74.9
m
35
115
4442
1
2
Cotta
ge
The
Bower
Bla
ck
water