division 1: general requirements - d.n. higginsdnhiggins.com/docs/rfb 695 addendum 1 technical...

112
SECTION DESCRIPTION PAGES TOC-1 DIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and Standards 2 01020 Measurement and Payment 1 01050 Field Engineering 3 01065 Permits and Fees 1 01071 Standard References 9 01200 Project Meetings and Reports 3 01300 Submittals 8 01310 Cost Loaded Construction Schedules 8 01320 Construction Videos and Photographs 3 01410 Testing and Quality Control 4 01510 Temporary Utilities and Facilities 5 01530 Temporary Barriers and Controls 4 01531 Manatee Protection 3 01580 Project Identification and Informational Signs 2 01590 Field Offices and Sheds 3 01600 Equipment and Materials 4 01630 Product Options and Substitutions 2 01660 Equipment and System Performance and Operational Testing 4 01700 Contract Closeout 4 01730 Operation and Maintenance Information 2 DIVISION 2: SITE WORK 02100 Site Preparation 2 02110 Clearing & Land Preparation 3 02114 Tree Removal 4 02200 Earthwork 8 02211 Blasting 14 02220 Excavation and Backfilling 2 02221 Trenching, Backfilling and Compacting 3 02250 Dredging and Excavation 5 02262 Aluminum and Steel Sheet Piling 6 02370 Riprap System 6 02401 Dewatering and Cofferdam 5 02435 Turbidity Control & Monitoring 7 02436 Environmental Protection 12 02455 Round Timber Piling 4 02486 Grassing 3 02645 Corrugated Aluminum-Alloy Pipe and Riser 5 02782 Boat Barrier – Tuffboom 4 02920 Sodding 3 DIVISION 3: CONCRETE 03300 Cast-In-Place Concrete 14 03600 Grout 8 DIVISION 4: MASONRY (Not Used) DIVISION 5: METALS 05060 Welding 3 05070 Bolted Fasteners 3 05521 Handrails, Railings and Bollards 3

Upload: others

Post on 13-Mar-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

SECTION DESCRIPTION PAGES

TOC-1

DIVISION 1: GENERAL REQUIREMENTS

01010 Summary of Work 201015 Definitions and Standards 201020 Measurement and Payment 101050 Field Engineering 301065 Permits and Fees 101071 Standard References 901200 Project Meetings and Reports 301300 Submittals 801310 Cost Loaded Construction Schedules 801320 Construction Videos and Photographs 301410 Testing and Quality Control 401510 Temporary Utilities and Facilities 501530 Temporary Barriers and Controls 401531 Manatee Protection 301580 Project Identification and Informational Signs 201590 Field Offices and Sheds 301600 Equipment and Materials 401630 Product Options and Substitutions 201660 Equipment and System Performance and Operational Testing 401700 Contract Closeout 401730 Operation and Maintenance Information 2

DIVISION 2: SITE WORK

02100 Site Preparation 202110 Clearing & Land Preparation 302114 Tree Removal 402200 Earthwork 802211 Blasting 1402220 Excavation and Backfilling 202221 Trenching, Backfilling and Compacting 302250 Dredging and Excavation 502262 Aluminum and Steel Sheet Piling 602370 Riprap System 602401 Dewatering and Cofferdam 502435 Turbidity Control & Monitoring 702436 Environmental Protection 1202455 Round Timber Piling 402486 Grassing 302645 Corrugated Aluminum-Alloy Pipe and Riser 502782 Boat Barrier – Tuffboom 402920 Sodding 3

DIVISION 3: CONCRETE

03300 Cast-In-Place Concrete 1403600 Grout 8

DIVISION 4: MASONRY (Not Used)

DIVISION 5: METALS

05060 Welding 305070 Bolted Fasteners 305521 Handrails, Railings and Bollards 3

Page 2: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

SECTION DESCRIPTION PAGES

TOC-2

05550 Fabricated Metalwork and Castings 5

DIVISION 6: WOODS (Not Used)

DIVISION 7: THERMAL AND MOISTURE PROTECTION (Not Used)

DIVISION 8: DOORS AND WINDOWS (Not Used)

DIVISION 9: FINISHES

09900 Protective Coatings 14

DIVISION 10: SPECIALTIES (Not Used)

DIVISION 11: EQUIPMENT

11415 Manually Operated Aluminum Slide Gates 7

DIVISION 12: FURNISHINGS (Not Used)

DIVISION 13: BUILDING (Not Used)

DIVISION 14: CONVEYING SYSTEMS (Not Used)

DIVISION 15: MECHANICAL (Not Used)

DIVISION 16: ELECTRICAL

16050 Basic Materials and Methods 716064 Cathodic Protection for Aluminum Sheet Piling 616120 Wires and Cable 616450 Grounding 4

END OF DIRECTORY

Page 3: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01010-1 Revision: 3/3/15

SECTION 01010 SUMMARY OF WORK

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: This SECTION summarizes the WORK of the Project as covered in detail in thecomplete Contract Documents. This is a general summary and is not intended to be complete and allinclusive of the required WORK items.

1.02 SUBMITTALS:

A. Submittals shall be in accordance with SECTION 01300.

1.03 PROJECT DESCRIPTION:

A. Description of Project: The Picayune Strand Restoration Project, Manatee Mitigation Feature islocated along the westerly bank of the Faka Union Canal in Collier County, Florida. The projectgenerally consists of the following:

1. Construction of three (3) deep water refugia pools and connecting channels adjacent to and west ofthe Faka Union Canal.

2. Construction of two (2) connections to the Faka Union Canal. (One at each end of the ManateeMitigation Feature.)

3. Construction of a 48” diameter gated control structure with manatee protection grates on each endtogether with associated aluminum sheet pile endwalls.

4. It is assumed that construction will begin by June 20, 2015 so that it is within 60 days of the initialgopher tortoise relocation date, which is scheduled to be completed on April 20, 2015. TheDISTRICT will conduct a final gopher tortoise survey within the Manatee Mitigation Feature(PSRP) construction footprint. If any remaining tortoises are found, the DISTRICT will workwith the CONTRACTOR so that the CONTRACTOR on site excavates those burrows and theDISTRICT will deliver the tortoises to the recipient site. Once construction is complete, theDISTRICT will document that there are no remaining tortoises on the site. This final survey willbe used to assist the DISTRICT in closing the FWC permit.

5. Installation of Boat Barriers with boat gates at the access channels from the Faka Union Canal.

6. On site stockpile, grading and stabilization of excavated spoil materials.

7. SITE ACCESS IS BY WATER, ONLY.

1.04 RELATED CONTRACT ACTIVITIES:

A. The CONTRACTOR shall provide adequate bank protection and/or stabilization to prevent erosion.The CONTRACTOR shall revegetate embankments after grading. Revegetation shall not be greaterthan 1500 LF behind the grading. The CONTRACTOR shall submit an embankment protection planfor DISTRICT approval.

B. Maximum water surface elev. 1.69 ft NAVD (2012), minimum water surface elev. -1.42 ft NAVD(2007)

1.05 WORK PERFORMED BY OTHERS:

1.06 CONTRACTOR'S USE OF PREMISES:

A. See General Terms & Conditions Article 6.11.

B. During construction activities, the CONTRACTOR shall be responsible for maintaining the off-sitestaging of area(s) and all access roads in good condition, including grading and drainage. See Section00700 - General Terms & Conditions.

Page 4: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01010-2 Revision: 3/3/15

1.07 DISTRICT'S USE OF PREMISES:

A. Partial DISTRICT Occupancy: The DISTRICT reserves the right to occupy and to place and installequipment in areas of the Project, prior to Substantial Completion provided that such occupancy doesnot interfere with completion of the WORK. Such placing of equipment and partial occupancy shallnot constitute acceptance of the WORK.

1.08 WORK SEQUENCE, COORDINATION ACTIVITIES AND SCHEDULED DATES:

A. General: The CONTRACTOR shall coordinate its WORK with other adjacent landowners andDISTRICT activities, with specific attention to access and staging areas. Construction sequence shallbe determined by CONTRACTOR subject to the needs for continuous access and operation by others.

1.09 COPIES OF DOCUMENTS:

A. See Section 00700 - General Terms & Conditions Article 2.02.

1.10 LIST OF DRAWINGS:

A. Drawings:

1. 100397 - Picayune Strand Restoration Project – Manatee Mitigation Feature – Faka UnionCanal, Sheets 1-23, inclusive.

B. Reference Materials:

1. The following reference materials are available for inspection at the offices of the DISTRICT:These materials are for reference only, are provided as-is, are not contractual documents, and donot replace the CONTRACTOR’s due diligence in bid preparation.

a. Hydrographic and Topographic Survey – Picayune Strand Restoration Project, CollierCounty, FL prepared by CivilSurv, Inc., dated June 2014.

b. Geotechnical Engineering Services, West Indian Manatee Mitigation Feature, PicayuneStrand Restoration Project prepared by Radise dated March 21, 2014.

PART 2 - EXECUTION (Not Applicable)

END OF SECTION

Page 5: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 01050-1 Revision: 3/3/15

SECTION 01050 FIELD ENGINEERING

PART 1 - GENERAL (See General Terms & Conditions Article 4.05 "Reference Points.")

1.01 SCOPE:

A. Summary of Work:

1. The CONTRACTOR shall engage a Professional Engineer of the discipline required, registeredin the State of Florida, to perform engineering services for temporary facilities including thedesign of shoring systems, shores, earth and water retaining systems, forms, temporary erectionsupports, and similar items provided by the CONTRACTOR as part of its means and methodsof construction.

2. The CONTRACTOR shall engage a Professional Surveyor and Mapper registered in the Stateof Florida to perform the necessary layout, survey control and monumentation.

3. The CONTRACTOR shall provide two (2) sets of certified As-Built Drawings depicting allelevations referenced to the NAVD 88 (North American Vertical Datum 88). The as-builtelevations shall be italicized, bracketed, and underscored. Refer to 2.03.A.5 for datum offsetrequirements.

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 01700

3. SECTION 02200

1.02 SUBMITTALS:

A. Submit in accordance with SECTION 01300.

PART 2 - CONTRACTOR CONSTRUCTION STAKING

2.01 DESCRIPTION: In connection with this WORK, CONTRACTOR shall:

A. Perform all construction layout and reference staking necessary for the proper control and satisfactorycompletion of the WORK.

B. Run a level circuit between vertical control points indicated to check benchmarks and establish newbenchmarks where necessary.

2.02 CONSTRUCTION REQUIREMENTS:

A. The CONTRACTOR’s personnel performing the construction staking shall work under the directsupervision of a Florida registered Professional Engineer or Florida registered Professional Surveyorand Mapper. Submit name and address of firm responsible for surveying to the DISTRICT prior tostart of survey activities.

B. The CONTRACTOR shall be solely and completely responsible for the accuracy of the line and gradeof all features of the WORK. Any errors or apparent discrepancies found in previous surveys,drawings, or specifications shall be called to the attention of the DISTRICT by the CONTRACTOR forcorrection or interpretation prior to proceeding with the WORK.

C. Field notes shall be kept in standard, bound field notebooks in a clear, orderly, and neat mannerconsistent with standard engineering practices.

D. The CONTRACTOR shall be responsible for the placement and preservation of adequate ties andreference to all control points, whether established by him or found on the Project, necessary for theaccurate reestablishment of all base lines or centerlines shown on the Drawings. All land ties (i.e.control points, section corners, fractional section corners, and similar items) that may be destroyed ordisturbed during construction shall be carefully referenced and replaced by the CONTRACTOR.

Page 6: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 01050-2 Revision: 3/3/15

E. The supervision of the CONTRACTOR’s construction layout personnel shall be the responsibility ofthe CONTRACTOR; any deficient layout or construction WORK which may be the result ofinaccuracies in his staking operations or of his failure to report inaccuracies found in WORKpreviously done by the DISTRICT shall be corrected at the expense of the CONTRACTOR.

F. In order to expedite the commencement of construction operations, the staking operation maycommence prior to the issuance of the Notice to Proceed. The CONTRACTOR shall obtain writtenapproval of the DISTRICT prior to commencing staking.

2.03 SURVEYING STANDARDS for water control structures:

A. A permanent mark shall be established on the site, as shown on the drawings.

1. All vertical elevations shall commence from a minimum of two (2) National Geodetic Survey(NGS) second order or better published benchmarks.

2. All elevations shall be established to NGS third order standards and certified to those standardsby a Professional Surveyor and Mapper registered in the State of Florida.

3. All level runs shall be double run (forward and back) or looped into two (2) NGS second orderor better published benchmarks.

4. A Site benchmark shall be set if one does not exist. The benchmark shall consist of a minimumof two (2) 80-pound bags of concrete mix, a ferrous piece of material able to be located with amagnetic locator, and a survey cap (supplied by the DISTRICT) stamped with the Sitedesignation or DISTRICT approved alternative.

5. All elevations shall be established in NAVD 88 with the datum offset for conversion to NGVD29. Datum offsets shall be made using the CORPSCON 6.0.1 or the most recent version. Thedatum conversion to NGVD 29 shall be made from the closest bench mark. The NGVD 29conversions shall be accurate to 0.01 feet.

6. State Plane Coordinates (NAD 83/99) shall be established at the benchmark location with ahorizontal positional accuracy of +/- three feet.

7. A DISTRICT benchmark description sheet shall be completed for each set benchmark.

8. If there are no second order or better published benchmarks within six miles of the site, contactthe DISTRICT Surveying & Mapping Section representative at (561) 682-6688 prior tocommencement.

9. Contact the DISTRICT Survey & Mapping Section prior to commencement to check forpreviously established site benchmarks that may be suitable to use.

B. All structures shall have a permanent benchmark mounted as shown on the Drawings. The marker forthe benchmark can be obtained from the DISTRICT Survey & Mapping Section, (561) 682-6688. TheCONTRACTOR shall only stamp or engrave the benchmark identification and not the elevation.

2.04 RECORDS AND SUBMITTALS:

A. Submittal:

1. Provide DISTRICT a copy of the designs described in Paragraph 1.01 signed and sealed by theFlorida registered Professional Engineer.

2. Provide DISTRICT the data required for the firm responsible for layout and records as requiredin Paragraph 2.02 A.

3. Provide DISTRICT one (1) copy of the Preliminary Surveyor’s Report (MS Word 2007), andtwo (2) copies of the final signed, sealed and certified Surveyor’s Report to the DISTRICT.

a. At a minimum, the report shall include: an overall Project description, location sketches,field notes, equipment used, pictures and an NAD 83/99 state plane coordinate (RTK) oneach new bench mark (if applicable).

b. A CD containing: Surveyor’s firm name and logo, Surveyor’s Report, digital pictures,benchmark description sheets and any other associated data.

Page 7: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 01050-3 Revision: 3/3/15

B. Records: At the end of the Project, submit to the DISTRICT two (2) copies of a certified As-BuiltSurvey showing the location and elevations of the completed WORK. These are part of the recorddocuments required in SECTION 01700.

END OF SECTION

Page 8: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01410-1 Revision: 3/3/15

SECTION 01410 TESTING AND QUALITY CONTROL

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work:

1. The CONTRACTOR shall provide and maintain an effective Quality Control Program thatfulfills the requirements of Article 13 "Warranty and Guarantee, Tests and Inspections,Correction, Removal or Acceptance of Defective Work" of the GENERAL TERMS &CONDITIONS.

2. The CONTRACTOR shall establish and implement a Quality Control Plan to perform sufficientinspection of all items of the WORK, including that of Subcontractors, to insure conformanceto the Technical Specifications and the Drawings with respect to the materials, workmanship,construction, equipment performance, and identification.

3. The CONTRACTOR's job supervisory staff may be used for quality control, supplemented asnecessary by additional personnel for surveillance or special technicians to provide capabilityfor the controls required by the Technical Specifications. The CONTRACTOR's QualityControl Plan must clearly identify the quality control leader and personnel organizationalsystem. The leader must have the authority to direct the removal and replacement of defectivework.

4. After the Contract is awarded and before the construction begins, the CONTRACTOR shallsubmit a Contractor Quality Control (CQC) Plan: schedule, resource loaded schedule, featuresof work, submittal register, Quality Control requirements, and equipment list, and shall meetwith the DISTRICT or its representative to discuss quality control requirements. The meetingshall develop mutual understanding relative to the details of the Quality Control Plan, includingthe appropriate forms to be used for recording the quality control operations, inspections,administration of the Quality Control Plan, and the interrelationship of the CONTRACTOR andthe DISTRICT inspection.

5. The CONTRACTOR shall submit a written CQC Plan for review, describing the activities andlisting those inspection and testing activities that the CONTRACTOR will perform prior tobeginning the WORK. The CONTRACTOR’s Quality Control Plan shall describe how he willcommunicate timely notification to allow for testing and inspection activities performed by theDISTRICT, or its representatives, for on and off-site construction activities.

a. Daily CQC Reports. The CONTRACTOR shall submit a tracking sheet that records basicQuality Control data and which shall be the CONTRACTOR's official report. TheTracking Sheet shall summarize data from any supplemental reports by the Contractor.The CONTRACTOR shall electronically submit reports to the DISTRICT within 24hours after the date covered by the report, and shall provide a signed, printed copy of thedaily Quality Control report.

The CQC Plan shall cover all construction operations, both onsite and offsite, includingwork by subcontractors, designers of record, consultants, architect engineers, fabricators,suppliers, and purchasing agents:

i. Describe Quality Control Organization: Include an Organization Chart with linesof authority and reporting. CQC Staff shall include a CQC System Manager whoshall perform his duties. For CQC matters, CQC System Manager shall directlyreport to Contractor other than Project Manager/Site Superintendent.

ii. Definable Features of Work: Although each section of Specifications maygenerally be considered as a definable feature of work, there are frequently morethan one definable features under a particular section. A definable feature of worklist will be agreed upon during the Coordination Meeting.

Page 9: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01410-2 Revision: 3/3/15

iii. CONTRACTOR Quality Control Staff Qualifications: Names, qualifications (inresume format), duties, responsibilities, and authorities of each person assigned aQuality Control function

iv. Submittal Control: Procedures for scheduling, reviewing, certifying, and managingsubmittals, including submittal items from subcontractors, designers of record,consultants, architect engineers.

b. Deficiency Tracking. The tracking sheet shall include deficiencies identified by theCONTRACTOR shall be numerically tracked. The CONTRACTOR shall maintain acurrent log of its Quality Control punch list items. The DISTRICT will log thedeficiencies it has identified and inform the CONTRACTOR. The CONTRACTOR shallregularly update the correction status of both Quality Control and Quality Assurancepunch list items.

c. Quality Control Requirements. The CONTRACTOR shall develop and maintain acomplete list of Quality Control testing, and shall update all data on these Quality Controlrequirements as work progresses, and promptly provide this information to theDISTRICT.

6. All compliance inspections shall be recorded on the appropriate forms, including but not limitedto the specific items required in each SECTION of the Technical Specifications. The completedforms, including record of corrective actions taken, shall be furnished to the DISTRICT. TheDISTRICT's quality control representative will maintain a list of all deficiencies which are notcorrected the same day as they are discovered.

7. Should recurring deficiencies in an item or items indicate that the Quality Control Plan is notadequate, the CONTRACTOR shall take corrective actions as directed by the DISTRICT toupdate the Quality Control Plan, to satisfactorily address and resolve any reoccurringdeficiencies.

B. Related Work Specified Elsewhere:

1. SECTION 01300

1.02 TESTING LABORATORY SERVICES:

A. All tests which require the services of a laboratory to determine compliance with the ContractDocuments shall be performed by a USACE validated independent commercial testing laboratoryacceptable to the DISTRICT. The laboratory shall be staffed with experienced technicians, and shallbe properly equipped, ACI certified, and fully qualified to perform the tests in accordance with thespecified standards.

1.03 TESTING LABORATORY SERVICES FURNISHED BY CONTRACTOR:

A. The testing that the DISTRICT will coordinate and pay for is described in paragraph 1.04 below. Allother testing required in connection with the performance of the WORK (which are identified as theCONTRACTOR's responsibility in the Contract Documents) shall be performed and paid for by theCONTRACTOR, and a certified copy of the results will be furnished to the DISTRICT within five (5)days of the test.

B. The CONTRACTOR is also responsible for all testing and inspection services required to achieve aneffective Quality Control Program, to assure that the WORK strictly complies with the Contractrequirements. The CONTRACTOR shall pay all costs for such services. The CONTRACTOR shallalso pay for any tests performed by the DISTRICT which do not meet the requirements of theTechnical Specifications and as described below.

1.04 TESTING LABORATORY SERVICES FURNISHED BY DISTRICT:

Page 10: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01410-3 Revision: 3/3/15

A. The DISTRICT will secure the services of a materials testing company, for field and laboratory tests,for certain items of the WORK. The DISTRICT will pay all charges for services on: moisture density(Proctor) and relative density tests on embankment, fill and backfill materials, and in-place fielddensity tests on embankments and fills etc. The field sampling and testing will be performed in thegeneral manner indicated in the Technical Specifications, with minimal interference to the constructionoperations.

While the CONTRACTOR may request testing in order to proceed to a following construction stage,the DISTRICT will determine the exact time and location of the field sampling and testing, and mayrequire additional sampling and/or testing as necessary to determine that the materials and equipmentconform with the CONTRACTOR-submitted data and with the Contract Documents.

1. The DISTRICT shall be reimbursed by the CONTRACTOR for the cost of anyCONTRACTOR-requested tests or inspections, or tests on an item purported to be ready, whichfail to meet the Technical Specification requirements. The DISTRICT may withhold suchamounts from payments otherwise due to the CONTRACTOR.

B. Arrangements for the delivery of samples and test specimens to the testing laboratory under thisparagraph will be made by the DISTRICT. The testing laboratory shall perform all laboratory testswithin a reasonable time consistent with the specified standards and shall furnish a written report ofeach test.

C. The CONTRACTOR shall furnish all sample materials and cooperate in the sampling and field testingactivities, interrupting the WORK when necessary.

D. When sampling or testing activities are performed in the field by testing laboratory personnel, theCONTRACTOR shall furnish personnel and facilities to assist in the activities.

E. The Testing Laboratory contracted by the DISTRICT will not be authorized to:

1. Release, revoke, alter or enlarge on requirements of the Contract Documents.

2. Approve or accept any portion of the WORK.

3. Perform any duties of the CONTRACTOR.

4. The CONTRACTOR shall provide at least 48 hours advance notice of any work for which hemay desire required testing for compliance by the DISTRICT.

1.05 TRANSMITTAL OF TEST REPORTS:

A. Written reports of test and engineering data furnished by the CONTRACTOR shall be submitted asspecified in SECTION 01300.

1. Documentation: The CONTRACTOR shall maintain records for each construction daydocumenting quality control activities that have been performed. The records shall includetesting record, work of subcontractors and suppliers. A CONTRACTOR Quality Control reportwith supporting attachments shall be prepared daily on an acceptable form that includes thefollowing information:

a. CONTRACTOR/subcontractor and their area of responsibility.

b. Equipment with hours worked, idle, or down for repair.

c. Work performed each day, giving location, description, and by whom.

d. Testing and control activities performed with results and references to Specifications ordrawings requirements. List deficiencies noted, along with corrective action.

e. Quantity of materials received at the site with statement as to acceptability, storage, andreference to Specifications or drawings requirements.

Page 11: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 06/30/14 01410-4 Revision: 3/3/15

f. Submittals and deliverables reviewed, with Contract reference, by whom, and actiontaken.

g. Offsite surveillance activities, including actions taken.

h. Job safety evaluations stating what was checked, results, and instructions or correctiveactions.

i. Instructions given or received and conflicts in Plans or Specifications.

j. Contractor's verification statement.

The records shall describe trades working on the project; number of personnel working; weatherconditions encountered; and delays encountered. The records shall cover both conforming anddeficient work and shall include a statement that equipment and materials incorporated into workand workmanship comply with Contract. The CONTRACTOR shall furnish the original and onecopy of these records to the DISTRICT daily within 24 hours after the date covered by report. NoCONTRACTOR Quality Control daily report is required for days on which no work is performed;however, next report shall document weather during those days and note possible effects onrestarting work. The CONTRACTOR shall submit a report for a minimum every 7 days of nowork and on the last day of a no work period. All Contract calendar days shall be accounted for.The CONTRACTOR Quality Control System Manager or Alternate shall sign and date reports.The CONTRACTOR Quality Control System Manager's reports shall include copies of testreports, phase checklists, meeting minutes, inspector notes, and copies of reports prepared by otherquality control

B. Notification of Noncompliance: The DISTRICT will notify the CONTRACTOR of noncompliancewith Contract requirements. The CONTRACTOR shall take corrective action immediately after receiptof noncompliance notification. The CONTRACTOR personnel notified at work site is sufficient for thepurpose of CONTRACTOR notification. If CONTRACTOR fails to comply promptly, the DISTRICTmay issue an order stopping all or part of work until satisfactory corrective action has been taken. Suchstop orders shall not be made a basis of a CONTRACTOR's claim for time extension or other damages.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION

Page 12: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/18/13 01510-1 Revision: 3/3/15

SECTION 01510 TEMPORARY UTILITIES AND FACILITIES

PART 1 - GENERAL

1.01 SUMMARY:

A. This SECTION includes requirements of a temporary nature not normally incorporated into finalWORK. It may include, but not necessarily be limited to the following:

1. Utility services

2. Construction and support facilities

3. Construction aids

4. Fire Protection

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 01530

3. SECTION 01590

4. DIVISIONS 2 through 16

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the publications of the organizations listed below in effect at thetime of the advertisement for bids form a part of this specification to the extent referenced. See thevarious paragraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. American National Standards Association (ANSI):

a. A10 Series - Safety Requirements for Construction and Demolition

b. ANSI/ASME PTC 19.1-1998 Test Uncertainty, Instrument and Apparatus

2. National Electrical Contractors Association (NECA):

a. Electrical Design Library - Temporary Electrical Facilities

3. National Fire Protection Association (NFPA):

a. NFPA 10 - Portable Fire Extinguishers

b. NFPA 70 - National Electrical Code

c. NFPA 241 - Safeguarding Construction, Alterations, and Demolition Operations

4. National Electrical Manufacturers Association (NEMA)

5. Underwriters Laboratories (UL)

6. Florida Department of Transportation Standard Specifications for Road and BridgeConstruction

7. Florida Trench Safety Act (90-96, Laws of Florida)

1.03 SUBMITTALS:

A. Submit in accordance with SECTION 01300.

B. Site Plan: Submit to the DISTRICT a Site Plan indicating CONTRACTOR's facilities including:

Page 13: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/18/13 01510-2 Revision: 3/3/15

1. Trailers

2. Equipment Yard

3. Parking

4. Traffic Control

1.04 QUALITY ASSURANCE:

A. Regulations: Comply with industry standards and applicable laws and regulations of authoritieshaving jurisdiction, including but not limited to:

1. Building Code requirements

2. Utility company regulations

3. Police, Fire Department, and rescue squad rules

4. Environmental protection regulations

B. Standards:

1. Comply with NFPA 10 and 241, and ANSI A10 Series standards "Temporary ElectricalFacilities."

2. Comply with NEMA, NECA, and UL standards and regulations for temporary electric service.Install service in compliance with NFPA 70.

C. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utilitybefore use. Obtain required certifications and permits.

PART 2 - PRODUCTS

2.01 MATERIALS AND EQUIPMENT:

A. Provide new materials and equipment. If acceptable to the DISTRICT, undamaged previously usedmaterials and equipment in serviceable condition may be used. Provide materials and equipmentsuitable for the use intended, of capacity for required usage, and meeting applicable codes andstandards. Comply with requirements of DIVISIONS 2 through 16.

B. Water: Provide potable water approved by local health authorities.

C. Electrical Outlets: Provide properly configured, NEMA-polarized outlets to prevent insertion of 110-to 120V plugs into higher voltage outlets. Provide receptacle outlets equipped with ground-faultcircuit interrupters, reset button, and pilot light for connection of power tools and equipment.

D. Electrical Power Cords: Provide grounded extension cords. Use hard-service cords where exposed toabrasion and traffic. Provide water proof connectors to connect separate lengths of electric cords ifsingle lengths will not reach areas where construction activities are in progress. Do not exceed safelength-voltage ratio.

E. Lamps and Light Fixtures: Provide general service incandescent lamps of wattage required foradequate illumination. Provide guard cages or tempered-glass enclosures where exposed to breakage.Provide exterior fixtures where exposed to moisture.

F. Fire Extinguishers: Provide hand-carried, portable, UL-rated, Class A fire extinguishers for temporaryoffices and similar spaces. In other locations, provide hand-carried, portable, UL-rated, Class ABC,dry-chemical extinguishers or a combination of extinguishers of NFPA-recommended classes for theexposures. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and sizerequired by location and class of fire exposure.

Page 14: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/18/13 01510-3 Revision: 3/3/15

PART 3 - EXECUTION

3.01 TEMPORARY UTILITIES:

A. General:

1. Engage the appropriate local utility company to extend temporary electric and phone service tothe staging area from nearby existing utilities. Where utility company provides only part of theservice, provide the remainder with matching, compatible materials and equipment. Complywith utility company recommendations.

2. Provide adequate utility capacity at each stage of construction. Prior to availability oftemporary utilities at the Site, or in remote areas without services, provide trucked-in servicesas required for start-up and construction operations.

3. Furnish, install and maintain temporary utilities required for adequate construction, safety andsecurity. Modify, relocate and extend systems as WORK progresses. Repair damage caused byinstallation or use of temporary facilities. Grade the areas of Site affected by temporaryinstallations to required elevations and grades, and clean the area. Remove on completion ofWORK or until service or facilities are no longer needed or are replaced by authorized use ofcompleted permanent facilities.

4. The types of temporary construction utilities and facilities required may include, but are notnecessarily limited to, potable drinking water, wastewater, drainage, dewatering equipment,enclosure of WORK, ventilation, electrical power, lighting, hoisting facilities, stairs, ladders,and roads.

5. Inspect and test each service before placing temporary facilities into use. Arrange for requiredinspections and tests by governing authorities, and obtain required certifications and permits foruse.

6. Materials used for temporary facilities shall not be used in the permanent system unless sospecified or acceptable to the DISTRICT.

3.02 TEMPORARY ELECTRICITY AND LIGHTING:

A. New Service:

1. Arrange with utility company to extend existing electric service to temporary office trailers.

2. Connect temporary service in a manner directed by utility company officials. Provide separatemeter for metering of power used by all entities authorized to be at or perform WORK at theProject Site.

3. The electric service shall be of sufficient capacity and characteristics for the variousconstruction tools, machinery, lights, heating and air conditioning, pumps, and other toolsrequired by CONTRACTOR and his Subcontractors. In areas of the Project where permanentor temporary power service from the local utility is not available, the CONTRACTOR shallsupply and maintain engine-driven, power-generator sets.

4. Provide weatherproof, grounded, power distribution system sufficient to accommodateconstruction operations requiring power, use of power tools, electrical heating and lighting.Provide overload protection. Supply power for electric welding, if any, from engine-driven,power-generator sets.

5. Provide adequate artificial lighting for all areas of WORK when natural light is not adequate forWORK.

6. Sufficient light shall be provided for general construction areas, with additional sufficientlighting for specific tasks and to meet safety requirements.

B. Use of Permanent System:

Page 15: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/18/13 01510-4 Revision: 3/3/15

1. Prior to use of permanent system to be installed by the power company for constructionpurposes, obtain written permission of the DISTRICT.

2. Maintain permanent system as specified for temporary facilities.

C. Costs of Installation and Operation:

1. Pay fees and charges for permits and applications.

2. Pay costs of installation, maintenance, removal of temporary services, and restoration of anypermanent facilities used.

3. Pay costs of electrical power used (if applicable).

4. Pay costs of furnishing, operating, and maintaining engine-driven power-generator sets, whereapplicable.

3.03 TEMPORARY HEAT AND VENTILATION:

A. General:

1. Provide temporary heat, ventilation and cooling as required to maintain adequate environmentalconditions in temporary office trailers and storage sheds and to facilitate progress of theWORK, to meet specified minimum conditions for the installation of materials, and to protectmaterials and finishes from damage. Protect from adverse affects of low temperatures or highhumidity, and to prevent hazardous accumulations of dust, fumes, vapors, or gases.

2. Methods of heating and fuel shall be suitable for particular purposes. Portable heaters shall bestandard approved units with controls.

B. Costs of Installation and Operation:

1. Pay fees and charges for applications, permits, and inspections.

2. Pay costs of installation, operation, maintenance, removal of equipment, and restoration ofexisting or permanent facilities if used.

3. Pay cost of power and fuel used.

3.04 TEMPORARY TELEPHONE SERVICE:

A. General:

1. Arrange with local telephone service company to extend existing direct line telephone service tothe CONTRACTOR’s and DISTRICT's field office site for the use of the DISTRICT andconstruction personnel and employees.

2. Telephone Service: Local Provider.

3. Minimum Service Required: Direct lines for voice and data communication for theDISTRICT's field office as specified in SECTION 01590.

a. One direct line instrument in superintendent's field office.

b. Adequate number of service lines and instruments for needs of trades.

c. Other instruments and pay telephone station(s) at the option of the CONTRACTOR, or asrequired by regulations.

d. Provide a dedicated telephone line for a fax machine in the Superintendent's field office.

4. CONTRACTOR shall arrange with local cellular/mobile telephone service company to providemobile telephone service for use by CONTRACTOR and so CONTRACTOR can be reachedthroughout the entire Project area during normal working hours.

Page 16: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/18/13 01510-5 Revision: 3/3/15

B. Costs of Installation and Operation:

1. Pay all costs for installation, maintenance and removal, and service charges for local calls. Tollcharges shall be paid by the party who places the call.

3.05 TEMPORARY SANITARY FACILITIES:

A. CONTRACTOR-Furnished Facilities:

1. Furnish, install and maintain temporary sanitary facilities for use through construction period.Remove on completion of WORK.

2. Provide for all construction workers under this Contract and representatives at the Site.

3. Toilet facilities shall be of the chemical-aerated recirculation or combustion type, properlyvented and fully enclosed with a glass- fiber-reinforced polyester shell or similar nonabsorbentmaterial.

3.06 TEMPORARY CONSTRUCTION AIDS:

A. General:

1. Provide construction aids and equipment required by personnel, available for DISTRICTobservers’ use, and to facilitate the execution of the WORK; scaffolds, staging, ladders, stairs,ramps, runways, platforms, railings, hoists, cranes, chutes, and other such facilities andequipment.

2. Materials may be new or used, must be suitable for the intended purpose and meet therequirements of applicable codes, regulations and standards.

3.07 TEMPORARY BYPASS FLOW: (Not Used)

3.08 INSTALLATION AND REMOVAL:

A. Relocation: Relocate construction aids as required by progress of construction, by storage or WORKrequirements, and to accommodate requirements of DISTRICT at the Site.

B. Removal: Remove temporary materials, equipment and services when construction needs can be metand allowed by use of permanent construction, or at completion of the Project.

C. Repair: Clean and repair damage caused by installation or by use of temporary facilities.

1. Grade the areas of the Site affected by temporary installations to required elevations and cleanthe area.

END OF SECTION

Page 17: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 01531-1 Revision: 3/3/15

SECTION 01531 MANATEE PROTECTION

PART 1 - GENERAL

1.01 SCOPE: The scope of this SECTION is to instruct all personnel associated with the Project of the potentialpresence of manatees and manatee speed zones, and the need to avoid collisions with and injury to manatees.All construction personnel are responsible for observing water-related activities for the presence ofmanatee(s).

1.02 RELATED WORK SPECIFIED ELSEWHERE:

A. SECTION 01530

B. SECTION 02435

1.03 REFERENCES:

A. Marine Mammal Protection Act of 1972

B. Endangered Species Act of 1973

C. Florida Manatee Sanctuary Act of 1978

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

A. The CONTRACTOR shall advise all construction personnel that there are civil and criminal penaltiesfor harming, harassing, or killing manatees, which are protected under the Marine Mammal ProtectionAct of 1972, the Endangered Species Act of 1973, and the Florida Manatee Sanctuary Act of 1978.The CONTRACTOR may be held responsible for any manatee harmed, harassed, or killed as a resultof construction activities.

B. Siltation barriers shall be installed and shall be made of material in which manatees cannot becomeentangled, shall be properly secured, and shall be monitored regularly to avoid manatee entanglementor entrapment. Barriers shall not impede manatee movement or block manatee entry to or exit fromessential habitat.

C. All vessels associated with the project shall operate at “No Wake/Idle” speeds at all times while in theimmediate area and while in water where the draft of the vessel provides less than four feet clearancefrom the bottom. All vessels shall follow routes of deep water whenever possible.

D. If a manatee is sighted within 100 yards of the project area, all appropriate precautions shall beimplemented by the CONTRACTOR to ensure protection of the manatee. All in-water operations,including vessels, must be shutdown if a manatee(s) comes within 50 feet of the operation. Activitieswill not resume until the manatee(s) has moved beyond the 50-foot radius of the project operation, oruntil 30 minutes elapses if the manatee(s) has not reappeared within 50 feet of the operation. Animalsmust not be herded away or harassed into leaving. (Shutdown of in-water operations due to thepresence of manatee(s) shall not be considered a basis for a modification to the Contract Time orContract Price.)

E. Any collision with and/or injury to a manatee shall be reported immediately to the DISTRICT’srepresentative and to the “Florida Fish and Wildlife Conservation Commission (FWC) ManateeHotline” at 1-888-404-FWCC (1-888-404-3922). Collision and/or injury should also be reported to theU.S. Fish and Wildlife Service in Jacksonville (1-904-232-2580) for north Florida or Vero Beach (1-561-562-3909) in South Florida.

Page 18: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 01531-2 Revision: 3/3/15

F. Temporary signs concerning manatees shall be posted prior to and during all in-water project activities,including construction/dredging activities. Awareness signs that have already been approved for thisuse by the FWC must be used. Samples of manatee signage are included at the end of thisspecification. All signs shall be removed by the CONTRACTOR upon completion of the project. One(1) sign measuring at least three (3) feet by four (4) feet which reads Caution Boaters: Watch forManatees shall be posted in a location where it is prominently visible to water related constructioncrews. A second sign shall be posted if vessels are associated with the construction, and shall beplaced in a location that is prominently visible to the vessel operator. The second sign shall be at least8 ½ inches by 11 inches and read:

Caution: Manatee Habitat. Idle speed is required if operating a vessel in the construction area.All equipment must be shutdown if a manatee comes within 50 feet of the operation. A collisionwith and/or injury to a manatee shall be reported immediately to the Florida Marine Patrol at 1-888-404-FWCC (1-888-404-3922) and the U. S. Fish and Wildlife Service at (1-904-232-2580) fornorth Florida or (561-562-3909) for south Florida.

G. A permanent manatee awareness sign shall be installed and maintained at the southerly connection tothe Faka Union Canal. The sign shall be three feet by four feet, 125 gauge 61TS aluminum, coveredwith white and blue, engineer grade, reflective sheeting: black and white, painted lettering: blackscreened design: and black, engineer grade, reflective tape border. The 3 feet wide by 4 feet long signshall conform to the Florida Uniform Waterway marking System in accordance with F.S. 327.40-1.The installation of the sign shall be made in accordance with DEP Specification for such signs.

H. Verification (photos) that signs have been installed at designated locations shall be provided to theFWS and the Corps at Substantial Completion of the project.

Sign 1: Caution Manatee Area

Page 19: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 01531-3 Revision: 3/3/15

Sign 2: Idle Speed/No Wake

END OF SECTION

Page 20: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/30/13 01590-1 Revision: 3/3/15

SECTION 01590 FIELD OFFICES AND SHEDS

PART 1 - GENERAL

1.01 SCOPE:

A. Summary: This SECTION includes requirements for temporary field offices and other structures foroffice and storage space required by CONTRACTOR and the DISTRICT.

B. Related Work Specified Elsewhere:

1. SECTION 01510

2. SECTION 01600

C. Use of Existing Facilities: Existing facilities at the Site shall not be used for field offices.

D. Use of Permanent Facilities: Permanent facilities, when substantially completed, shall not be used forfield offices or for storage.

PART 2 - PRODUCTS

2.01 FIELD OFFICES:

A. General:

1. Provide trailers, mobile buildings, or buildings constructed with floors raised aboveground,with steps and landings at entrance doors.

2. Buildings shall be structurally sound, secure, and weathertight.

3. Provide four (4) appropriate portable type fire extinguishers at each office and storage area.

4. Maintain offices for duration of Contract.

5. Install office spaces ready for occupancy within thirty (30) days of the Notice to Proceed.

6. Obtain any required building permits for installation of temporary field offices and sheds.

B. CONTRACTOR’s Office:

1. Provide a field office for CONTRACTOR’s superintendent on the Site.

2. Field office shall be of size required for general use, with lights, heat and air conditioning,furnishings, telephone service, and other necessary facilities and utilities required byCONTRACTOR’s operations.

C. DISTRICT Office:

1. Provide a field office for DISTRICT use in a location near the Site with parking space for four(4) vehicles. The parking area shall have at least a shell rock surface.

2. Provide the following minimum requirements:

a. Single wide, 12-foot by 60-foot trailer

b. Secure entrance doors - three (3) sets of keys

c. Windows with operable sash and insect screens

d. Lockable storage closet, minimum area of 60 square feet

e. Resilient floor covering

f. Minimum of two (2) individual offices

g. Conference room, minimum area of 500 square feet

h. Furnishings:

i. Two (2) standard size desks with three (3) drawers, swivel desk chair with arms,and side chairs

ii. Conference table with six (6) swivel chairs

iii. Two (2) throw tables of sufficient size for full size Drawings and submittals

Page 21: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/30/13 01590-2 Revision: 3/3/15

iv. One (1) plan rack to hold a minimum of six (6) racks of drawings

v. Three 4-drawer legal-size metal filing cabinets with lock and key

vi. Two (2) sets of six (6) linear feet of bookshelves, 10 inches minimum depth

vii. Ten (10) folding chairs

viii. One (1) wastebasket per desk and table

ix. One (1) tackboard, 36 inches x 30 inches

x. Two (2) white boards 48 inches x 60 inches

xi. One (1) first aid kit and identifying sign

xii. Fire extinguishers per 2.01.A

i. Services:

i. Lighting Interior: 50 foot-candles at desktop height; Exterior lighting at entrancedoor

ii. Heating and air conditioning

iii. Electrical Service: Minimum of four circuits, 110V, 60 hertz; Minimum of (16)110V duplex convenience outlets

iv. Temporary Sanitary Facilities in accordance with SECTION 01510

v. Electric water cooler with bottled water

vi. 21 cubic foot (c.f.) refrigerator

vii. Microwave oven, one (1) cubic feet

viii. One ten (10) pot coffeemaker

ix. Multi-line phone service for each office conference room and kitchen/break room.

j. Office Equipment:

i. Required Network Configuration (for each DISTRICT furnished computer): T1connection to construction Site from 3301 Gun Club Road, West Palm Beach,Florida, to include installation, configuration, and service.

If T1 is unavailable to Site, as determined by geographical location, then provideISDN connectivity to construction Site from 3301 Gun Club Road, West PalmBeach, FL, to include installation, configuration and service.

If ISDN (Integrated Service Digital Network) is unavailable to Site, as determinedby geographical location, network service is to be provided through the modem.In this case, Dial-up access to the construction Site is required, to include onetelephone line per computer including installation, configuration and service.

ii. Two (2) additional first aid kits.

2.02 STORAGE SHEDS AND TRAILERS:

A. On-Site:

1. The CONTRACTOR shall provide temporary buildings or trailers needed for storage ofEquipment and Materials installed under this Contract (and those furnished by DISTRICT orothers under separate Contract).

2. Provide ventilation and heating as required by Equipment and Material stored or as perMANUFACTURER’s requirements.

3. The CONTRACTOR shall be solely responsible for temporary buildings and trailers located onsite.

B. Off-Site:

1. The CONTRACTOR shall advise the DISTRICT of any arrangements made for storage ofEquipment and Materials in a place other than DISTRICT’s Site. The CONTRACTOR shall

Page 22: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/30/13 01590-3 Revision: 3/3/15

furnish evidence of insurance coverage with Application for Payment in conformance with theSection 00700 - General Terms & Conditions.

PART 3 - EXECUTION

3.01 LOCATION, INSTALLATION AND MAINTENANCE:

A. General:

1. Place temporary buildings, trailers, and stored materials in locations acceptable to DISTRICT.

2. Installed field offices and sheds to resist winds and elements of the locality where installed.

3. Remove when no longer needed at the Site or when WORK is completed.

4. Keep approach walks free of leaves, mud, water, or ice.

5. At completion of WORK, remove temporary buildings and trailers, foundations (if any), utilityservices, and debris.

6. Prepare ground or paved areas as specified in applicable SECTIONs.

END OF SECTION

Page 23: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/30/06 01660-1 Revision: 3/3/15

SECTION 01660 EQUIPMENT AND SYSTEM PERFORMANCE AND OPERATIONAL TESTING

PART 1 - GENERAL

1.01 DESCRIPTION:

A. This Section contains requirements for the CONTRACTOR in documenting testing work requiredunder this contract. In addition, this Section contains requirements for the CONTRACTOR duringinstalled performance testing of all mechanical equipment and systems, including structures forwatertight construction, provided under this contract. This Section supplements but does not supersedespecific testing requirements that may be found elsewhere in the Contract Documents.

1.02 QUALITY CONTROL:

A. CONTRACTOR's Quality Control Manager: The CONTRACTOR shall appoint a Quality ControlManager to manage, coordinate, and supervise the CONTRACTOR's quality control program. TheQuality Control Manager shall have at least 5 years of total experience, or experience on at least 5separate projects, in managing similar types of projects. The quality control program may include, butnot necessarily be limited to the following:

1. A testing plan setting forth the sequence in which all testing work required under this projectmanual will be implemented

2. A documentation program to record the results of all equipment and system tests

3. An installed performance testing program for all mechanical equipment and systems installedunder this contract

4. A testing schedule conforming to the requirements specified in paragraph 01660-2.02 C

For the purposes of this Section, a system shall include all items of equipment, devices andappurtenances connected in such a fashion as their operation or function complements, protects orcontrols the operation or function of the others. The CONTRACTOR’s Quality Control Manager shallcoordinate the activities of all subcontractors and suppliers for equipment and materials supplied byboth the CONTRACTOR and the DISTRICT to implement the requirements of this Section.

1.03 CALIBRATION: (Not Used)

1.04 SUBMITTALS:

A. Submittal material, to be submitted in accordance with SECTION 01300, shall consist of thefollowing:

1. The CONTRACTOR's plan for documenting the results from the test program in conformancewith the requirements of paragraph 01660-2.02 A, including:

a. Sample forms for documenting the results of field performance and operational tests.

2. Preoperational check-out procedures, reviewed and approved by the respective equipmentmanufacturers

3. Detailed testing plans, setting forth step-by-step descriptions of the procedures proposed by theCONTRACTOR for the systematic testing of all equipment and systems installed under thiscontract

4. A schedule and subsequent updates, whenever schedule changes occur, presenting theCONTRACTOR's plan for testing the equipment and systems installed under this contract

5. A schedule establishing the expected time period (calendar dates) when the CONTRACTORplans to commence operational testing of the completed systems.

Page 24: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/30/06 01660-2 Revision: 3/3/15

6. A summary of the Quality Control Manager's qualifications, showing conformance to paragraph01660-1.02 A requirements

PART 2 - PRODUCTS

2.01 GENERAL:

A. The CONTRACTOR shall prepare test plans and documentation plans as specified in the followingparagraphs. The DISTRICT will not witness any test work for the purpose of acceptance until all testdocumentation plans and the specified system or equipment test plans have been submitted andaccepted.

2.02 DOCUMENTATION:

A. Documentation Plans: The CONTRACTOR shall develop a records keeping system to documentcompliance with the requirements of this Section.

Equipment and system documentation shall include date of test, equipment number or system name,nature of test, test objectives, test results, test instruments employed for the test and signature spacesfor the DISTRICT's witness and the CONTRACTOR's Quality Control Manager. A separate file shallbe established for each system and item of equipment. These files shall include the followinginformation as a minimum:

1. Field performance tests

2. Field operational tests

The CONTRACTOR shall develop test documentation forms specific to each item of equipment andsystem installed under this contract. Acceptable documentation forms for all systems and items ofequipment shall be produced for review by the DISTRICT.

B. Test Plans: The CONTRACTOR shall develop test plans detailing the coordinated, sequential testingof each item of equipment and system installed under this contract. Each test plan shall be specific tothe item of equipment or system to be tested. Test plans shall identify by specific equipment eachdevice to be manipulated or observed during the test procedure and the specific results to be observedor obtained. Test plans shall also be specific as to support systems required to complete the test work,temporary systems required during the test work, subcontractors' and manufacturers' representatives tobe present and expected test duration.

As a minimum, the test plans shall include the following features:

1. Performance testing of each individual item of mechanical equipment. Performance tests shallbe selected to duplicate the anticipated operating conditions.

2. System tests designed to duplicate, as closely as possible, anticipated operating conditions.

Test plans shall contain a complete description of the procedures to be employed to achieve the desiredtest environment.

The importance of the test plan submittals is represented by the requirement to provide it as amilestone on the construction progress schedule, and as a line item in the Schedule of Values. Deliveryof all test plans required for the systematic field performance and operational tests for all equipmentand systems installed under this contract shall be made at least two (2) weeks in advance of the datethe CONTRACTOR wishes to begin such testing. Once the DISTRICT has reviewed and taken noexception to the CONTRACTOR's test plans, the CONTRACTOR shall reproduce the plans insufficient number for the CONTRACTOR's purposes and an additional three (3) copies for delivery tothe DISTRICT. No test work shall begin until the CONTRACTOR has delivered the specified numberof final test plans to the DISTRICT.

Page 25: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/30/06 01660-3 Revision: 3/3/15

C. Testing Schedule: The CONTRACTOR shall produce a testing schedule setting forth the sequencecontemplated for performing the test work. The schedule shall be coordinated with theCONTRACTOR's construction schedule specified in SECTION 01310. The schedule shall show thecontemplated start date, duration of the test and completion of each test. The test schedule shall besubmitted no later than two (2) weeks in advance of the date testing is to begin. The DISTRICT willnot witness any testing work for the purpose of acceptance until the CONTRACTOR has submitted aschedule to which the DISTRICT takes no exception. The test schedule shall be updated as necessary,showing actual dates of test work, indicating systems and equipment testing completed satisfactorilyand meeting the requirements of this project manual.

2.03 SYSTEM AND EQUIPMENT PERFORMANCE TESTS:

A. Each item of mechanical equipment installed under this contract shall be tested to demonstratecompliance with the performance requirements of the Contract Documents.

2.04 OPERATIONAL TESTS:

A. Once all equipment and systems have been tested individually the CONTRACTOR shall then operateall systems simulating actual operating conditions to the greatest extent possible. During theoperational testing period, the CONTRACTOR's Quality Control Manager and testing team shallmonitor the characteristics of the equipment and report any unusual conditions to the DISTRICT.

2.05 PRODUCT DATA:

A. Records produced during the testing program shall be considered as Product Data, to be provided inaccordance with SECTION 01300.

PART 3 - EXECUTION

3.01 GENERAL:

A. The CONTRACTOR's Quality Control Manager shall organize teams made up of qualifiedrepresentatives of equipment suppliers (for both CONTRACTOR and DISTRICT supplied equipmentand materials), subcontractors, the CONTRACTOR's independent testing laboratory, and others, asappropriate, to efficiently and expeditiously test the equipment and systems installed and constructedunder this contract. The objective of the testing program shall be to demonstrate, to the DISTRICT'scomplete satisfaction, that the structures equipment constructed and installed under this contract meetall performance requirements. In addition, the testing program shall produce baseline operatingconditions for the DISTRICT to use in a preventive maintenance program.

3.02 CALIBRATION OF FIXED INSTRUMENTS: (Not Used)

3.03 PERFORMANCE TESTS:

A. General: Performance tests shall consist of the following:

1. Pressure and/or leakage tests

2. Preoperational checkout for all mechanical equipment. Preoperational check-out proceduresshall be reviewed and approved by the respective equipment manufacturers.

3. Initial operation tests of all mechanical equipment and systems to demonstrate compliance withthe performance requirements of the Contract Documents.

In general, performance tests for any individual system shall be performed in the order listed above.The order may be altered only on the specific written authorization of the DISTRICT after receipt of awritten request, complete with justification of the need for the change in sequence.

Page 26: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/30/06 01660-4 Revision: 3/3/15

B. Pressure and Leakage Tests: Pressure and leakage tests shall be conducted in accordance withapplicable portions of the Specifications. All acceptance tests shall be witnessed by the DISTRICT.Evidence of successful completion of the pressure and leakage tests shall be the DISTRICTrepresentative's signature on the test forms prepared by the CONTRACTOR.

C. Pre-Operational Tests: Preoperational tests shall include the following:

1. Pre-operation lubrication, as necessary

2. Tests per the manufacturers' recommendations for pre-operational check-out procedures

D. Functional Tests:

1. General: Once all affected equipment has been subjected to the required preoperational check-out procedures and the DISTRICT has witnessed and has not found deficiencies in that portionof the Work, individual items of equipment and systems may be operated under simulatedoperating conditions to determine as nearly as possible whether the equipment and systemsmeet the requirements of these specifications. The equipment shall be operated a sufficientperiod of time to determine operating characteristics to observe performance characteristics;and to permit initial adjustment of operating controls.

Test results shall be within the tolerances set forth in the detailed specification sections of theContract Documents. If no tolerances have been specified, test results shall conform totolerances established by recognized industry practice. Where, in the case of an otherwisesatisfactory functional test, any doubt, dispute, or difference should arise between theDISTRICT and the CONTRACTOR regarding the test results or the methods or equipment usedin the performance of such test, the DISTRICT may order the test to be repeated.

If the repeat test, using such modified methods or equipment as the DISTRICT may require,confirms the previous test, then all costs in connection with the repeat test will be paid by theDISTRICT. Otherwise, the costs shall be borne by the CONTRACTOR. Where the results ofany functional test fail to comply with the contract requirements for such test, then such repeattests as may be necessary to achieve the contract requirements shall be made by theCONTRACTOR at his expense. The CONTRACTOR shall provide, at no expense to theDISTRICT, necessary consumable item, all labor, temporary piping, and all other items andwork, required to complete the functional tests.

2. Retesting: If under test, any portion of the Work should fail to fulfill the contract requirementsand is adjusted, altered, renewed, or replaced, tests on that portion when so adjusted, altered,removed, or replaced, together with all other portions of the Work as are affected thereby, shall,unless otherwise directed by the DISTRICT, be repeated within reasonable time and inaccordance with the specified conditions. The CONTRACTOR shall pay to the DISTRICT allreasonable expenses incurred by the DISTRICT, as a result of repeating such tests.

3. Post-Test Inspection: Once functional testing has been completed, all equipment shall bechecked for loose connections, unusual movement, or other indications of improper operatingcharacteristics. Any deficiencies shall be corrected to the satisfaction of the DISTRICT.

END OF SECTION

Page 27: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02114-1 Revision: 3/3/15

SECTION 02114 TREE REMOVAL

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall furnish all labor, material, equipment and perform allwork in strict accordance with the Specifications, Contract, and applicable requirements for theremoval and disposal of trees and heavy brush.

1. SECTION 01300

2. SECTION 02110

B. The CONTRACTOR shall accomplish the complete removal of designated trees, the disposal ofresulting waste and debris, as well as any other rubbish, solid waste or debris existing and exposedduring the execution of the WORK in those areas described. The CONTRACTOR shall perform theWORK in accordance with recognized and approved principles of modern arboricultural methods. TheCONTRACTOR shall perform all WORK without damage to trees, shrubs, and/or facilities that areintended to remain in the work area.

C. The CONTRACTOR shall perform the WORK which involves the following procedures:

1. Removal of designated trees

2. Exotic vegetation removal

3. Pruning of native vegetation to facilitate removal of exotic vegetation

4. Preservation and protection of native vegetation

5. Minimizing disturbance of the canal banks and other facilities

6. Debris/rubbish/solid waste removal and disposal, site clean up, and finish grading to leave aclean and smoothly graded appearance

1.02 APPLICABLE PUBLICATIONS:

A. American National Standards Institute (ANSI)

1. (ANSI) Z133.1a: “Safety Requirements for Tree Care Operations - Pruning, Trimming,Repairing, Maintaining and Removing Trees, and for Cutting Brush”

2. (ANSI) Z133.1: “Tree Care Operations - Pruning, Trimming, Repairing, Maintaining andRemoving Trees, and for Cutting Brush”

3. (ANSI) A300: “Tree Care Operations B Tree, Shrub and Other Woody Plant Maintenance”

B. Florida Department of Agriculture & Consumer Services, Division of Forestry, “Tree ProtectionManual for Builders and Developers”

C. Florida Statute Chapter 487, “Florida Pesticide Laws”

D. Occupational Safety and Health Regulations “29 CFR 1910,” Florida Statute 442 Occupational Safetyand Health and other applicable federal, state and local regulations

E. Florida Department of Transportation (FDOT)

1. Index No. 544 – Landscape Installations

2. Manual on Uniform Traffic Control Devices for Streets and Highways

1.03 DEFINITIONS: (Not Applicable)

Page 28: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02114-2 Revision: 3/3/15

1.04 SUBMITTALS:

A. The CONTRACTOR shall submit as specified in SECTION 01300 the proposed methods andmaterials for clearing of invasive exotic plant material and trees, including a schedule indicatingspecific timeframes per sections/phases of the project and methods to protect trees to remain.

B. The CONTRACTOR shall obtain all necessary permits to accomplish all of the WORK.

C. The CONTRACTOR is responsible for performing all WORK in accordance with all applicableregulations, ordinances and code requirements from the appropriate city, county, state and/or federaljurisdiction the Project is located in.

1.05 QUALIFICATIONS: (Not Applicable)

1.06 RESPONSIBILITIES: (Not Applicable)

1.07 CERTIFICATIONS AND TESTING: (Not Applicable)

1.08 INSPECTION COORDINATION: The CONTRACTOR shall provide access to the WORK for theDISTRICT as requested for inspection. The CONTRACTOR shall provide at least 48 hours advance noticeof its intention to begin new WORK activities.

1.09 WARRANTY: (Not Applicable)

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.01 TREE REMOVAL:

A. The CONTRACTOR shall accomplish the removal of trees and or all exotic plant material in a safeand acceptable manner by means of equipment designed for this purpose in conformance with ANSIStandards, A300, Z133.1 and Z133.1a. All other debris, trees and wood growth shall be removed. TheCONTRACTOR shall accomplish the WORK of Tree Removal as outlined below.

B. Remove exotic vegetation from all areas outside of sensitive areas using mechanical equipment forclearing and grubbing. Sensitive areas are defined as areas dominated by native vegetation, canal bankslopes, canal bank areas to be preserved at existing grade and wetlands.

1. Only handwork and hand tool work will be permitted within the sensitive areas. No mechanicalequipment will be allowed within the sensitive areas. Existing native flora and fauna shall beprotected from harm during the process. Treat exotic stumps with herbicide mixture approvedby the DISTRICT. Herbicide shall be used in combination with flush cut tree stumps wherenecessary to protect native vegetation from damage by mechanical equipment.

2. Where exotic trees are removed in sensitive areas, they shall be cut as low as possible (within 4inches of surrounding natural grade).

3. In tree trimming, any cut of at least two (2) inches in diameter shall be cut flush to the mainlimb or trunk. All limbs shall be undercut to prevent bark teardown. All pruning shall be inconformance with ANSI A300 Pruning Standards.

4. In the event that the removal of exotic plant materials could damage any native trees or listedspecies, the CONTRACTOR shall notify the DISTRICT before proceeding further.

3.02 CLEARING AND BRUSH REMOVAL:

Page 29: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02114-3 Revision: 3/3/15

A. The CONTRACTOR, where necessary or required, shall implement selective clearing methodsconforming to the applicable requirements of ANSI Standards Z133.1, Z133.1a and A300.

B. The CONTRACTOR may burn combustible products of the clearing operation on the site with thewritten approved of the DISTRICT and with permission of the local authorities. The CONTRACTORshall comply with all local ordinances or regulations for burn locations and methods, includingmethods for preventing uncontrolled spread of the burn. The CONTRACTOR shall provide theDISTRICT with copies of permits prior to burning.

3.03 REMOVAL AND DISPOSAL:

A. It shall be the CONTRACTOR's responsibility to remove and dispose of (in a legal manner) all mulch,cut branches, tree trunks and any other debris or solid waste at an approved disposal site. Limbs andany other debris/solid waste shall be disposed of by the CONTRACTOR and shall not be depositedinto any trash container.

B. The CONTRACTOR shall perform all work in conformance with all applicable regulations, ordinancesand code requirements of the appropriate city, county, state and/or federal jurisdiction. Exotic/invasiveplants are defined as Brazilian Pepper, Australian Pine, Melaleuca, or as directed by the DISTRICT,and Contract Specifications.

C. The CONTRACTOR may dispose of all organic materials and residues left from burning operationson-site as directed by the DISTRICT.

3.04 TREE AND SHRUB PROTECTION:

A. The CONTRACTOR shall exercise care to protect all trees and shrubs designated to remain. TheCONTRACTOR shall install tree protection barricade in accordance with FDOT Index No. 544.Where trees and shrubs are adjacent to construction, they shall be protected - where damaged, restoredor replaced to original conditions. Trees or existing grade damaged on the construction site shall berestored to original condition. Tree limbs, which interfere with equipment operation and are approvedfor pruning, shall be neatly trimmed in accordance with NAA/ANSI standards. The CONTRACTORshall be responsible for damages, maintenance, and protection of trees and shrubs to be protected.

3.05 GRADES:

A. It shall be the responsibility of the CONTRACTOR to provide the final grading to conform tosurrounding grades and to be at the proper elevation with relation to drainage structures, berms andother site conditions, unless indicated otherwise.

3.06 HERBICIDE TREATMENT:

A. The CONTRACTOR shall provide herbicide for stump eradication as approved by the DISTRICT.Use of herbicides shall be in accordance with the MANUFACTURER’s printed label instructions andapplicable federal, state and local laws. Application of herbicides shall be by appropriately licensedpersonnel.

B. The CONTRACTOR shall exercise extreme care to prevent damage to desirable existing growth. Ifnecessary, the CONTRACTOR shall conduct a test to establish suitability of product and applicatorthat will be used on this project prior to execution of the full application.

3.07 QUALITY ASSURANCE:

A. The WORK Site shall be clean and free of trimmings, stumps, roots, logs, or any other debris resultingfrom the WORK, and trash, litter or rubbish exposed during the CONTRACTOR’s tree removalservices. Stumps and roots may remain in sensitive areas (as referenced in 3.01.B.1 of this SECTION)in accordance with the Contract Document.

Page 30: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02114-4 Revision: 3/3/15

3.08 EQUIPMENT:

A. The CONTRACTOR shall provide equipment in good repair and operating condition at all times.Only equipment designed for performance of WORK described herein will be acceptable for operation.All equipment shall meet all safety requirements as established for this type of WORK. Equipmentshall be operated and maintained in accordance with MANUFACTURER’s recommendations.Equipment shall have the appropriate safety guards, which shall not be removed (e.g., chain saws,chippers, etc.).

B. The CONTRACTOR will be required to have available on site and in good working condition aminimum of the following:

1. Sufficient traffic control devices to safely control traffic including boat traffic around WORKareas.

2. Navigational buoys and advance warning signs, if applicable

C. It shall be the responsibility of the CONTRACTOR to verify the location of all utilities, structures,etc., by hand excavation or other appropriate measures before performing any work that could result indamage or injury to persons, utilities, structures or property. The CONTRACTOR shall make athorough search of the site for utilities, structures, etc., before work is commenced in any particularlocation.

D. The CONTRACTOR shall not purposefully disrupt or disconnect any type of utility, electric orirrigation service without first obtaining the written permission of the DISTRICT. Requests fordisconnection must be in writing and received by the DISTRICT at least seven calendar days prior tothe time of the requested interruption.

E. The CONTRACTOR shall take within two hours and complete within 48 hours the necessary steps torepair, replace, or restore all services to any utilities or other facilities, which are disrupted due to his orher operations.

F. Should utilities, structures, etc., be encountered that interfere with the work and are not shown on theDrawings; the CONTRACTOR shall notify the DISTRICT immediately.

END OF SECTION

Page 31: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-1 Revision: 3/3/15

SECTION 02200 EARTHWORK

GENERALPART 1 -

SCOPE:1.01

A. Summary of Work: The CONTRACTOR shall furnish all labor, equipment, and materials for allexcavating, trenching, filling, construction of embankment, backfilling, compacting, grading, and allrelated items of earthwork necessary to complete the WORK indicated or specified.

B. Related Work Specified Elsewhere:

The specification sections listed below may be related to the Project WORK. This list is not intendedto be all-inclusive.

1. SECTION 01300

2. SECTION 01410

3. SECTION 02110

4. SECTION 02211

5. SECTION 02220

6. SECTION 02221

7. SECTION 02401

8. SECTION 02486

9. SECTION 02920

APPLICABLE STANDARDS AND PUBLICATIONS:1.02

A. Standards or Codes: The edition of the standards of the organizations listed below in effect at the timeof the advertisement for bids form a part of this specification to the extent referenced. In the case of aconflict between the requirements of this SECTION and those of the listed document, the requirementsof this SECTION shall prevail.

1. American Society of Testing Materials (ASTM):

a. C33 - Standard Specification for Concrete Aggregates

b. D698 – Standard Test Methods for Laboratory Compaction Characteristics of Soil Usingthe Standard Effort (12,400 ft-lbf/ ft3 (600 kN-m/m3)).

c. D1557 – Standard Test Methods for Laboratory Compaction Characteristics of Soil Usingthe Modified Effort (56,000 ft-lbf/ ft3 (2,700 kN-m/m3))

d. D2487 – Standard Practice for Classification of Soils for Engineering Purposes (UnifiedSoil Classification System)

e. D3740 – Standard Practice for Minimum Requirements for Agencies Engaged in Testingand/or Inspection of Soil and Rock as Used in Engineering Design and Construction

f. D4253 – Standard Test Methods for Maximum Index Density and Unit Weight of SoilsUsing a Vibratory Table.

g. D4254 – Standard Test Methods for Minimum Index Density and Unit Weight of Soilsand Calculation of Relative Density.

h. D6938 – Standard Test Method for In-place Density and Water Content of Soil and Soil-Aggregate by Nuclear Method Shallow Depth

i. E329 – Standard Specification for Agencies Engaged in Construction Inspection and/orTesting

Page 32: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-2 Revision: 3/3/15

2. Florida Department of Transportation (FDOT):

a. Standard Specifications for Road and Bridge Construction (latest edition)

3. American Association of State Highway Transportation Officials (AASHTO):

a. T 27 – Sieve Analysis of Fine and Course Aggregates

b. T 99 - Standard Method of Test for Moisture-Density Relations of Soils Using a 2.5-kg(5.5-lb) Rammer and a 305-mm (12-in.) Drop

c. T 180 – Standard Method for Moisture-Density Relations of Soils using a 10 lb (4.54 kg)Rammer and 18 in (457 mm) Drop

B. Florida Method (FM) of Test:

1. FM T-1 011 – Florida Method of Test for Sampling Aggregates

C. Miscellaneous Project Data:

1. Subsurface soil data logs are provided for the CONTRACTOR’s reference

a. Geotechnical Engineering Services, West Indian Manatee Mitigation Feature, PicayuneStrand Restoration Project Prepared By: Radise International (dated March 21, 2014) For:URS Corporation

DEFINITIONS:1.03

A. Select Fill:

1. Select Fill shall be clean, well-graded material free from debris, peat, roots, seeds of nuisanceor exotic species, organic material, clods, and stones with a diameter greater than three (3)inches (76 mm) in any direction. Select Fill shall have an average organic content of not morethan 2% or have an individual test value of not more than 4%. Select Fill shall be placedwhere indicated on the Drawings. Select Fill is required where higher control of materials andplacement is needed such as water retaining embankment cores, roadway embankments, andadjacent to structures.

2. Select Fill shall be material excavated for the WORK (native). The CONTRACTOR mayblend native materials to achieve a material that meets the requirements for Select Fill.

3. Select Fill shall meet the following Unified Soil Classification System (ASTM D2487)designations: SW, SM or SP-SM. Materials classified as SP may be used only where theexisting excavated and surrounding materials are confirmed by laboratory testing to be SP.

4. The following table displays Select Fill maximum lift thickness and maximum particle size.

SELECT FILL

STRUCTURE TYPEMAXIMUM

PARTICLE SIZEMAXIMUM LOOSELIFT THICKNESS

Water Bearing Levee 3 inches 8 inches

Non-Water Bearing Levee 3 inches 12 inches

Embankment 3 inches 12 inches

5. Select Fill shall meet the ASTM D2487 gradation limits with the largest particle diameter notexceeding the following:

Page 33: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-3 Revision: 3/3/15

SELECT FILL LARGEST PARTICLE LIMITS

SIEVE SIZE PERCENT PASSING (%)

3 inches [90 mm] 100

B. Random Fill:

1. Random Fill shall be clean, well-graded material, meeting one of the following Unified SoilClassification System (ASTM D2487) designations: SW, SP, SM, SC, SW-SM, SW-SC, SP-SM, and SP-SC, that is thoroughly mixed and free from debris, clods, seeds of nuisance orexotic species, and stones with a diameter in any direction greater than those specified in thebelow table. Random Fill shall have an organic content of less than 5% by weight. Tighterrestrictions on stone size are considered in the top layer of fill, as per subsection 3.05 FinalDressing of Slopes, if the area is to be seeded, sodded, or landscaped. Random Fill shall beplaced where indicated on the Drawings. Random Fill is required where stable backfill isneeded to maintain slopes and grades, but shall not retain water or be adjacent to structures.

2. Random Fill shall be material excavated for the WORK (native). The CONTRACTOR mayblend native materials to achieve a material that meets the requirements for Random Fill.

3. Random Fill shall meet the ASTM D2487 requirements with the largest particle diameter notexceed the following:

C. Unified Soil Classification System (USCS): USCS is a two-letter classification system used todescribe the texture and grain size of a soil. In the USCS system, letters are representative as follows:G stands for gravel, S stands for sand, M stands for silt, C stands for clay, O stands for organic, Pstands for poorly graded, W stands for well graded, H stands for high plasticity, and L stands for lowplasticity.

D. Excavation: Excavation shall be the removal of all materials within the defined configuration to thelimits of excavation shown on the Drawings, excluding stripping material.

E. Unsuitable Fill: Soil that does not meet the requirements for fill (or backfill) addressed thus far in thisSECTION shall be considered Unsuitable Fill soil.

F. Unclassified Fill: Unclassified Fill may be material used to bring areas to grade where there is nopotential for slope erosion and the fill will not support a structure of critical function. Unclassifiedbackfill shall be placed where neither select backfill nor random backfill are shown on the Drawing.Unclassified Backfill shall be free from seeds of nuisance or exotic species, and will be composed ofmaterial excavated for the WORK or imported material that can be compacted to the required density.

G. Cohesionless materials: These materials include gravels, gravel-sand mixtures, sands, and gravellysands and are generally exclusive of clayey and silty materials.

H. Cohesive materials: These materials include silts and clays and are generally exclusive of sands andgravel.

I. Silica Filter Sand: Silica Filter Sand shall be in accordance with the General Characteristics for ASTMC-33 and the size gradation tabulated below.

RANDOM FILL

MAXIMUMPARTICLE SIZE

SURFACEDEPTH

MAXIMUM COMPACTEDLIFT THICKNESS

8 inches < 12 inches 12 inches

Page 34: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-4 Revision: 3/3/15

SILICA FILTER SAND GRADATION LIMITS

SIEVE SIZE PERCENT PASSING (%)

3/8” [9.5 mm] 100

No. 4 [4.75 mm] 95-100

No. 8 [2.36 mm] 80-100

No. 16 [1.18 mm] 50-96

No. 30 [0.60 mm] 25-60

No. 50 [0.30 mm] 5-30

No. 100 [0.15 mm] 0-10

No. 200 [0.075 mm] 0-2

The size gradation when tested at the supplier shall have a maximum fines (<#200 mesh) content ofnot more than 2%. The in-place compacted filter sand shall have a maximum fines content of not morethan 5%. Testing of in-place filter sand may be required if there is reason to believe that the particlegradation was altered or contaminated during handling or placement.

SUBMITTALS:1.04

A. Submittals shall be in accordance with SECTION 01300.

B. The CONTRACTOR shall submit laboratory test results on the materials proposed to be used (whethernative or imported) as Select Fill, Random Fill and Silica Filter Sand. At a minimum the laboratorytesting shall include sieve analysis, organic content, USCS classification and modified proctor perASTM D1557, as applicable. Prior to construction, the CONTRACTOR shall provide the source ofeach material proposed to be used.

C. The CONTRACTOR shall submit two (2) copies of field measured cross-sections at each design cross-section for record purposes for excavations and embankments as described in this SECTION. Thesubmittal of the field measured cross-sections shall be signed and sealed by a Professional Surveyorand Mapper licensed in the State of Florida.

QUALIFICATIONS:1.05

A. Geotechnical Testing Agency Qualifications: The CONTRACTOR shall engage and pay for anindependent testing agency qualified according to ASTM E329 to perform Quality Control. ThisQuality Control involves conducting soil materials and rock-definition testing during earthworkoperations, as documented according to ASTM D 3740.

B. Earthwork Contractor Qualifications: The CONTRACTOR shall use an adequate number of skilledlaborers and installers who are thoroughly trained and have a minimum of five (5) years of successfulexperience in the necessary crafts and are completely familiar with the code requirements, the contractprovisions, and the methods needed for the proper performance of the WORK of this SECTION. TheCONTRACTOR shall employ the adequate resources and equipment necessary to successfully performthe WORK of this SECTION on schedule.

RESPONSIBILITIES:1.06

A. The CONTRACTOR shall excavate any material encountered to the depth and grades required, shallbackfill such excavations as required, and shall dispose of excess or unsuitable materials from

Page 35: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-5 Revision: 3/3/15

excavation as approved by the DISTRICT. The CONTRACTOR shall provide and place necessaryborrow material to properly backfill excavations as indicated on the Drawings, specified herein, or asdirected by the DISTRICT.

B. Excavation, dewatering, sheeting, and bracing required shall be carried out so as to prevent anypossibility of undermining or disturbing the foundations of any existing structure or WORK, and sothat all WORK may be accomplished and inspected in the dry, except as directed by the DISTRICT.Aqueous construction may be performed only with prior written approval of the DISTRICT.Excavation and backfilling shall be in accordance with SECTION 02220.

C. The CONTRACTOR shall furnish, at his expense, the services of a Professional Surveyor and Mapperlicensed in the State of Florida for the field layout of all WORK indicated or specified in thisSECTION. The CONTRACTOR’s licensed surveyor shall perform all initial Site layout and shallprovide follow-up verification of all WORK underway as necessary.

CERTIFICATIONS AND TESTING:1.07

A. The responsibility to retain the services of an independent testing laboratory shall be as defined inSECTION 01410.

B. The CONTRACTOR shall furnish, at his own expense, all field density testing required to establishand maintain his Quality Control (QC) processes required or specified in this SECTION. Field densitytests shall be in accordance with all applicable ASTM Standards appropriate to each type of materialused in the earthwork. Failure to meet the specified density will require the CONTRACTOR torecompact and retest, at his own expense, those areas directed by the DISTRICT.

INSPECTION COORDINATION:1.08

A. The CONTRACTOR shall provide access to the WORK for the DISTRICT as requested forinspection. The CONTRACTOR shall provide at least 48 hours advanced notice of its his intention tobegin new WORK activities.

WARRANTY:1.09

A. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PRODUCTSPART 2 -

MATERIALS ENCOUNTERED:2.01

A. The CONTRACTOR shall excavate all materials encountered which may include, but not necessarilybe limited to:

1. Material referenced in the Radise/URS Geotechnical Report for the Project

B. The CONTRACTOR shall consider all materials encountered in excavations as suitable for use inRandom Fill, provided that they consist of two (2) or more well-graded (per ASTM D2487) soils andachieve the required compaction as specified in this SECTION.

C. The CONTRACTOR shall consider all materials encountered, regardless of type, character,composition and condition thereof unclassified other than as indicated in Article 1.03 Definitions. TheCONTRACTOR shall estimate the quantity of various materials included prior to submitting the BidForm. Rock encountered shall be handled by the CONTRACTOR at no additional cost to theDISTRICT.

Page 36: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-6 Revision: 3/3/15

EXECUTION:PART 3 -

SITE PREPARATION:3.01

A. Clearing and Demolition: The CONTRACTOR shall perform clearing and demolition as specified inSECTIONS 02110 and 02050.

DISPOSAL OF SURPLUS AND UNSUITABLE MATERIAL: The CONTRACTOR shall dispose of all3.02excess or unsuitable material on-site in areas shown on the Drawings or in areas otherwise approved by theDISTRICT.

STOCKPILE OF EXCAVATED MATERIAL: The CONTRACTOR shall stockpile excavated materials in3.03areas shown on the Drawings or in areas otherwise approved by the DISTRICT.

EXCAVATION AND TRENCHING:3.04

A. Trenching for Pipes: The CONTRACTOR shall perform trenching for pipes as shown on theDrawings, required, and specified in accordance with SECTION 02221.

B. Sheeting and Bracing: The CONTRACTOR shall provide sheeting and bracing shown on theDrawings or as required in accordance with the following provisions.

1. Use when required by the specifications or Drawings and where resulting slopes fromexcavation or trenching might endanger the structural integrity of in-place or proposedstructures.

2. Provide materials on-site prior to start of excavation. Adjust spacing and arrangement asrequired by conditions encountered.

3. Remove sheeting and bracing as backfill progresses. Fill voids left after withdrawal with sandor other DISTRICT approved material.

4. In-place structures damaged by sheeting and bracing activities shall be repaired by theCONTRACTOR at no additional cost to the DISTRICT.

5. Comply with all applicable Sections of OSHA.

6. Comply with all requirements of the Florida Trench Safety Law as specified in the GeneralTerms and Conditions.

C. Blasting: If required and approved by the DISTRICT, the CONTRACTOR shall perform blasting inaccordance with the SECTION 02211.

D. Excavation for Structures: The CONTRACTOR shall perform excavation for structures as shown,required and specified below:

1. Excavate area adequate to permit efficient construction.

2. Excavate by hand in areas where confined space and access restricts the use of machines.

3. Notify the DISTRICT immediately when excavation has reached the depth indicated on plans.

4. Restore bottom of excavation to proper elevation with concrete in areas that are overexcavated.

5. Conform to the requirements of SECTION 02221.

E. Canal/Channel Excavation: The CONTRACTOR shall perform canal/channel excavation by anymethod meeting the requirements of these specifications and the Drawings. Transitions in bottomwidth and elevation shall be uniform. The excavated slopes and bottom of the canals/channels shall beleft as smooth as skilled use of the excavating equipment will permit.

Page 37: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-7 Revision: 3/3/15

1. A construction tolerance of 0.25 foot above or below the lines and grades indicated shall bepermitted; however, the canal cross sectional area shall not be less than designed.

a. The CONTRACTOR shall provide field measured cross-sections of the “As-Built”conditions to the DISTRICT, plotted at the same stations as the detailed cross-sectionsshown on the Drawings to show the above specified tolerance has been met.

2. Where Select Fill is specified, the CONTRACTOR shall exercise care in excavation to avoid,to the maximum practicable extent, mixing of peat with materials suitable for use in SelectFill.

F. Demucking: The CONTRACTOR shall remove all organic soils from areas below structures, piping,and road subgrades to the lines and grades as shown in the Drawings. Materials excavated shall not beused for backfill of structures or pipes and shall be placed in Random Fill zones only. Organic soils(including peat) shall be used in Random Fill in the top layer of the final dressing of the levee.

G. Cross-Sections: For pay quantities and record purposes, the CONTRACTOR shall submit fieldmeasured cross-sections as required by the DISTRICT.

EMBANKMENT:3.05

A. Berm Embankment: The CONTRACTOR shall construct embankments for berms in accordance withthe requirements of Section 120 of the latest edition of the FDOT Standard Specifications for Road andBridge Construction.

B. Final Dressing of Slopes: Following the completion of embankment placement and compaction, theCONTRACTOR shall grade embankment slopes and adjacent transition areas so that they arereasonably smooth and free from irregular surface changes. The CONTRACTOR shall comply withthe following:

1. In areas where the embankment is to have grass, sod, or landscaping, the material within thetop one (1) foot of the levee, shall be free of any rocks greater than two (2) inches (51 mm) indiameter.

2. The degree of finish shall be that ordinarily obtained from blade grader or similar operations.

3. Provide roundings at bottom of slopes and other breaks in grade.

C. Cross-Sections: Provide the DISTRICT with two (2) certified copies of field measured cross-sectionsof the final embankments, prepared by a Professional Surveyor and Mapper licensed in the State ofFlorida for payment and record purposes, measured at the same stations as the detailed cross-sectionsshown on the Drawings.

BACKFILLING:3.06

A. Pipe Backfill: The CONTRACTOR shall perform pipe backfill as required, shown, and specified inaccordance with SECTION 02221.

B. Structure Backfill: The CONTRACTOR shall place structural backfill in accordance with the lines,grades, and cross-sections shown in the Drawings or as ordered by the DISTRICT. TheCONTRACTOR shall backfill using Random Fill. Stones or rocks greater than two (2) inches (51mm) in any dimension shall not be placed within twelve (12) inches of the structure. Lifts shall notexceed twelve (12) inches. The following procedures shall be adhered to:

1. Structure backfill shall be compacted to not less than 95% maximum dry density as measuredby ASTM D1557.

2. Backfill shall not be placed against fresh concrete without the approval of the DISTRICT.Once approved, backfill only after concrete has attained at least 70% design strength. Backfilladjacent to structures only after a sufficient portion of the structure has been built to resist theimposed load.

Page 38: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 10/30/13 02200-8 Revision: 3/3/15

3. Remove all debris from excavation prior to placement of material.

4. Place backfill in level layers of thickness within the compacting ability of equipment used.

5. Perform backfilling simultaneously on all sides of structures. For walls, backfill shall bebrought up evenly on each side of the wall and sloped to drain away from the wall.

C. Unclassified Backfill: The CONTRACTOR shall ensure that unclassified backfill be placed in twelve(12) inch loose lifts to the lines and grades shown on the Drawings or as approved by the DISTRICT.The CONTRACTOR shall compact unclassified backfill to a density approximating the density ofsurrounding native material and in a manner that will prevent settlement of the completed area.

SILICA FILTER SAND:3.07

A. The CONTRACTOR shall place and compact silica filter sand to the limits shown on the Drawings.The silica filter sand shall be placed in 1-foot loose lifts and compacted to not less than 95% ofmaximum dry density per ASTM D698.

GRADING: The CONTRACTOR shall perform grading as shown on the Drawings, required, and provided3.08for below:

A. Grade and compact all areas within the project area, including excavated and filled sections andadjacent transition areas, reasonably smooth, and free from irregular surface changes.

B. Degree of finish shall be that ordinarily obtained from blade grader or scraper operations except asotherwise specified.

C. Finished rough grades shall generally be not more than one quarter foot above or below those indicatedwith due allowances for topsoil.

D. Provide roundings at top and bottom of banks and at other breaks in grade.

MAINTENANCE:3.09

A. The CONTRACTOR shall protect newly graded areas from actions of the elements.

B. The CONTRACTOR shall fill, repair, and re-establish grades to the required elevations and slopes forany area that shows settling or erosion occurring prior to seeding.

C. The CONTRACTOR shall maintain grassed and sodded areas in accordance with SECTIONS 02486and 02920, respectively.

END OF SECTION

Page 39: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-1 Revision: 3/3/15

SECTION 02211 BLASTING

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall furnish all labor, equipment, and materials for theexplosives in drill and blast operations as required to complete the Work indicated or specified.

B. Related work Specified Elsewhere:

1. SECTION 02110

2. SECTION 02200

3. SECTION 02221

4. SECTION 02401

5. SECTION 02370

6. SECTION 02435

1.02 APPLICABLE PUBLICATIONS:

A. All applicable local (City, County, Village, Town, Tribe, etc.), State of Florida (Division of State FireMarshal, Florida Department of Transportation, etc.) and Federal (Occupational Safety & HealthAdministration, or OSHA, The Bureau of Alcohol, Tobacco and Firearms, or BATF, U.S. Departmentof Transportation, Federal Highway Administration, Research and Special Programs Administration,Commerce Department, Environmental Protection Agency, and any other federal entity that regulatesthis industry) laws, ordinances, codes, standards, regulations, licenses, medical and other certificates,and registration requirements pertain to this contract.

B. The CONTRACTOR shall abide with the following federal and state legislations

1. The Endangered Species Act

2. The Marine Mammal Protection Act

3. The Florida Manatee Sanctuary Act

4. The Marine Turtle Protection Act

C. The CONTRACTOR shall submit a complete listing of all applicable rules and regulations with whichthey must comply.

1.03 DEFINITIONS: (Not Applicable)

1.04 SUBMITTALS: The Following Compliance Submittals are required:

A. Proposed Blasting Plan: The CONTRACTOR shall provide a blasting plan that will be reviewed bythe DISTRICT, appropriate state and federal regulatory agencies (i.e., U.S. Fish and Wildlife Service,National Marine Fisheries Service, U.S. Coast Guard, and U.S. Army Corps of Engineers) as well asthe Florida Fish and Wildlife Conservation Commission (FWC), and any required third-party reviews,for compliance with the requirements specified herein. The CONTRACTOR is responsible for planimplementation and effectiveness. Review and acceptance of the CONTRACTOR’S blasting planshall not relieve CONTRACTOR from executing work activities in accordance with this or other partsof the Contract Documents, and any required federal, state, and local regulations and/or acceptableexcavation practices. Blasting shall not commence until the Blasting Plan is accepted by theDISTRICT and any third party stakeholders, and all permits have been acquired and submitted asspecified. The Blasting Plan shall include as a minimum:

Page 40: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-2 Revision: 3/3/15

1. Type of explosives; whether wet, dry or packed.

2. Procedures to be implemented in inclement weather.

3. Ignition plans, including initiation system, detonation devices and appurtenances.

4. Timing and duration of underwater blasting, the limitation to daylight shooting, and any tidaland/or seasonal restrictions.

5. A sample blast pattern, including Spacing and Burden, and dimensions to benches or free faces,if any. Blast pattern and geometry of the individual shots for a small project or of a general blastproduction for a large blasting program. Test program to develop from small charges to themaximum charge weight per delay interval necessary for production. The expected productioncharge weight per delay, spacing and burden between borings, placement of explosives withinborings, stemming type and minimum length of stemming placement within the structure, andthe location of the initiator within the boring.

6. A sample of a shot plan including number and orientation of holes, and how the hole locationswill be directly related to project survey monumentation or survey stationing. Include (vertical)topographic information related directly to the project survey datum.

7. Detailed description of the material to be blasted (i.e., substrata characteristics, description ofconcrete and reinforcement, etc.) and surrounding geology (water depth, water width, sedimentthickness, rock or structure being removed, etc.)

8. A discussion of how the CONTRACTOR will relate the required inverts that the excavation isto achieve, with instructions to the driller, and how adjustments are to be made.

9. In the event of overblast, indicate procedures for adjusting the blasts and for disposal ofoverblast materials.

10. Shot charges, and overall quantity of explosives. Expected type and weight of explosives to beused per shot for production shots and the maximum charge weight per interval of 25milliseconds (preferred). Sequentially list every charges’ total delay time in increasing timeorder. Any charge weights with less than 9-milliseconds interval are summed to find themaximum charge weight per delay.

11. Description of millisecond-delays that will be used if multiple charges are required.

12. Tube diameter, tube depth, and collars.

13. Procedures and coordination for adjustment of the blast with the hole driller’s observations, toaccount for geologic anomalies, such as changing strata and cavities.

14. Stemming: Stemming will apply to this project. On this subject, the CONTRACTOR is toinclude identifying the type and quantity of inert incombustible materials or devices it will use,and provide the backup calculations to establish the confinement depth. Stemming will be usedto control flyrock and produce proper fragmentation of the blasted material. Standing watershall not be used alone as a stemming agent unless specifically approved by the DISTRICT.Should water be used as a component of stemming, provide plans for management and positivecontainment of the water pre and post-blast. Should commercial crushed stone be utilized,provide a gradation specification. Should drill cuttings be utilized, provide details on screeningequipment and acceptable gradation. Identify the type and arrangement of blast mats, if any, tocontrol flyrock. Obtain regulatory approvals, if any. Note: Stemming is required in areasidentified in Part 3 of this specification.

15. Storage jobsite conditions WILL NOT allow for on-site storage of explosives.

16. Regarding fragmentation requirements, correlation of activities is required with other TechnicalSections or Plan Sheets of the Contract Documents, if any. CONTRACTOR’S plan shallinclude correction procedures in the event of improper fragmentation, for future blasts, and alsoshall include remedial measures such as reblasting, or mechanical fracturing to achieve proper

Page 41: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-3 Revision: 3/3/15

gradation. Disposal and replacement of incorrectly fragmented (unsuitable) material shall beaddressed.

17. Safety plan; including at a minimum, a code of blasting signals, signboards, maps showing thelocation of access routes (including the Faka Union Canal), methods for controlling access anda proposed system of notification. The signboards shall clearly describe the audible signalsystem for warning of impending blasts and shall be clearly visible from points of access. Allregulatory safety requirements shall be met. List the name and phone number of the State FireMarshal in whose jurisdiction the project lies.

18. Qualified Manatee Observers along the Faka Union Canal, both pre-blast and post-blast. TheQualified Manatee Observer shall have a commensurate experience in blasting and/or dredgingprojects observing animals and with the protocol in similar level of threat or environments asthe proposed project.

19. Refer to applicable regulations for transportation, handling, placement, and usage of explosives.

20. List post-blast inspections and procedures, including establishment of an all-clear signal, thatindicates that misfires and hazardous gases are either safely isolated or under control. Listprovisions for inspecting for damage and producing damage investigation survey reports.

21. Describe vehicular traffic (including vessels) control and maintenance.

22. Security Plan, including proposed security procedures in the event of having to leave loadedshot holes overnight. How many and what type of security personnel, along with any localgovernment requirements and timeframes for acquisition of staff.

23. Impact Assessment. The CONTRACTOR shall provide a “detailed” Environmental ImpactAssessment of the proposed blasting project. At a minimum, the following information must beincluded:

a. The likelihood of sea turtles and marine mammals being in the blasting area. TheCONTRACTOR shall consult existing scientific literature and the FWC and/or otherresource agencies. Pre-blast marine mammal/sea turtle surveys may be required, at thediscretion of the FWC, USFWS, NMFS, or other reviewing/permitting agencies.

b. A description of the marine mammal/sea turtle “exclusion zone” that will be developedand used for underwater blasting programs to provide species’ protection. The preferredminimum exclusion zone radius or range from which to protect marine mammal/seaturtles is 500 linear feet beyond the perimeter of placed blasting agents for a shot. Thepreferred maximum exclusion zone is a 2,000-foot radius beyond the blast perimeter for asubmerged shot. An additional 500 feet should be added to the calculated radius orexclusion zone in order to adequately control animals being precluded from this area.When underwater blasting will be conducted in a very controlled manner for a protractedperiod of months and has acceptable project monitoring, the CONTRACTOR may applyto the FWC and other appropriate permitting agencies for a special review of exclusionzone criteria.

Underwater explosions can be broadly categorized as either “confined” or “open-water.”Confined shots produce much less environmental damage for the same charge weightwhen compared to open-water shots. For confined shots, the pressure waves aredominantly radiated into a stiff medium (such as rock or a massive structure founded onrock) and remain in that medium. Confined shots have vertical heights of the stiffmedium exposed to water (or loose sediment below water) of less than half the smallerareal (horizontal) dimension of removal. Blasting in the water column, not connected to astructure, has a high transmission of pressure waves through the water column. Blastremoval of some stiff-medium structures below the water surface (e.g., columns, piers, orpilings) releases its energy directly to the surrounding water column or loose sediment,which has a high transmission of pressure waves through the water column. Underwater

Page 42: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-4 Revision: 3/3/15

blasting with high transmission to the water column and, thus potentially high organismimpact, shall be termed open-water blasting.

The “exclusion zone”, also referred to as the “watch zone” shall be calculated using thefollowing methods, appropriate to the type of blasting:

Open Water Blasting

The exclusion zone for open-water blasting shall be determined from the open-watershot’s maximum charge weight per delay, with an additional buffer of 500 feet. For anopen-water shot’s maximum charge weight per delay of less than 0.19 pound, theexclusion-zone radius of 300 linear feet applies. The maximum charge weight per delayof a confined shot shall not exceed 57 pounds for the exclusion-zone criterion beneath thewaters of the State of Florida, because the exclusion-zone radius would be greater than2,000 linear feet. The equation for the open-water blasting exclusion-zone radius, EZOW,for maximum charge weights per delay between 0.19 to 57 pounds is:

EZOW (feet) = (520 w1/3)(2) + 500 feet,

where w is the maximum charge weight (in pounds) per delay of an individual openwatershot.

Confined Blasting

The exclusion zone for confined blasting shall be determined from the confined shot’smaximum charge weight per delay, with an additional buffer of 500 feet. For a confinedshot’s maximum charge weight per delay of less than 1.5 pound, the “exclusion zone”radius of 500 linear feet applies. The maximum charge weight per delay of an open-watershot shall not exceed 450 pounds for the exclusion-zone criterion beneath the waters ofthe State of Florida, because the exclusion zone radius would be greater than 2,000 linearfeet. The equation for the confined blasting exclusion zone radius, EZC, for maximumcharge weights per delay between 1.5 to 450 pounds is:

EZOW (feet) = (520 w1/3) + 500 feet

Where w is the maximum charge weight (in pounds) per delay of an individual confinedshot.

c. A record of the type of underwater blasting (open-water or confined), procedures toreduce impacts, calculations of blast parameters, actual placement of explosive agents,organism exclusion zone distance calculations, and plans for observation shall be filedon-site before every shot is fired. Records for each shot of the blasting program shall beretained by the CONTRACTOR for the duration of project and made available to theFWC, USFWS, and NMFS immediately onsite or within two business days to thespecified mailing address, as requested.

The following records shall be kept for each placement position or boring: (1) - the upperand lower bounds of cemented or consolidated material to be removed or blasted; (2) -the weight of blasting agents and explosives, and their upper and lower bounds; (3) -stemming material appropriate for the size of the borehole; and (4) - upper and lowerbounds of the stemming placement within the cemented or consolidated material (usuallyrock or concrete). The record shall include the sequence of delays from the shortest tolongest individual delay time with the total weight of blasting agent at that delay time.The record keeping shall provide enough detail to allow interpretation of the quality ofshooting and level of compliance with the Blasting Plan.

d. A description of the monitoring program shall be implemented to record particlevelocities when a blasting position is within 1,000 feet of a land-based location. Particlevelocity monitoring independently confirms proper shot performance without the costand difficulty of either pressure-wave recording or organism testing. Reports of particlevelocity monitoring should be available to the FWC, USFWS, and NMFS, if requested,on the third business day following the shot.

Page 43: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-5 Revision: 3/3/15

Quantitative evaluation of potential marine mammal/sea turtle (i.e., manatee feedingareas, etc.) habitat that will be destroyed by the blasting project.

24. Mitigation Plan. The CONTRACTOR shall prepare a Mitigation Plan that shall include adetailed discussion of the measures employed to avoid or minimize the adverse impacts ofblasting. The following measures shall be included in the Mitigation Plan:

a. Blasting shall be conducted during the time when manatees, other marine mammals, andsea turtles are least likely to be in the blasting area. CONTRACTORs should consult withthe FWC, USFWS, and NMFS to determine the appropriate timing.

b. In tidal areas, the blasting CONTRACTOR shall conduct blasting during therecommended tidal phase deemed appropriate for the area (i.e., slack or low-tideconditions).

c. The volume and length of all blasting agents, detonation cord, and explosives will belimited to the minimum necessary to conduct the work in a manner that is efficient, safefor workers, and protective of aquatic and marine organisms. Initiation of explosivecharges should be conducted with the minimum length of detonation cord possible orshould utilize alternative initiation systems. Detonation cord has its own impact radius(injury/kill zone) along the entire length of submerged detonation cord.

d. All shock-tubes and detonation cord or electric wires will be recovered and removed aftereach blast.

e. After loading a charge in a hole, the hole will be back-filled (stemmed) with angularstemming material. The stemming material shall be uniform, crushed, angular stone. Thestemming material shall be within the range of 1/20 to 1/8 of the borehole diameter beingconfined. The stemming shall not be acceptable if it contains more than 10% fines(smaller than 1/20 of the hole diameter). Stemming material shall be placed a minimumvertical length of three borehole diameters above the placed charge within sound rock orconcrete. A standard procedure of logging the hole and placing the explosives shall beestablished to resolve and verify the proper placement of stemming material.

f. If multiple charges are required, time-delays should be used to reduce the overalldetonation pressures to a series of smaller explosions. Delays shall be used to effectivelydevelop the removal while lowering the maximum charge weight per delay to as low asreasonably achievable. Delays of less than a 9-millisecond interval shall not be countedas delays. All charges within any 9-millisecond interval shall be summed to resolve themaximum charge weight per delay for a given shot.

g. In addition to these measures, the CONTRACTOR should consider additional mitigationmeasures including, but not limited to the following: Deployment of barriers or cofferdams in shallow water.

25. Endangered Species Watch Plan. The CONTRACTOR shall prepare a Watch Plan using theguidance below to ensure that marine mammals and sea turtles are not in the exclusion zoneduring blasting events.

a. A formal Watch Plan Coordination Meeting shall be held at least one (1) week prior tothe first blasting event to review the Watch Plan, to discuss the responsibilities of allparties, and to review and approve the schedule of events. Personnel invited to the WatchPlan Coordination Meeting shall be contacted at least two (2) weeks prior to the firstdetonation event. Contacted invitees shall include the Explosives Engineer, theobservation team, FWC, USFWS, NMFS, U.S. Coast Guard, U.S. Army Corps ofEngineers, and other interested parties. The agenda shall be coordinated with the FWC,USFWS, and NMFS prior to the meeting. The meeting shall include the latestinformation concerning the possible presence of manatee, other marine mammals, andsea turtles during blasting, the logistics of the detonation schedule, details of the aerialsurvey, the communications plan, and the responsibilities of all parties involved.

Page 44: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-6 Revision: 3/3/15

b. The Watch Plan shall include time tables for the endangered species observation periods(e.g., start times for aerial surveys, boat surveys, and land-based surveys), observerpositions, and a copy of the Watch Plan log sheet and map to record manatee and/or seaturtle sightings.

c. The Watch Plan shall include a list of names and qualifications of the observers. Approvalof the observers is at the discretion of the FWC, USFWS, and NMFS and will be madeprior to the blasting event.

d. The watch crew shall consist of a minimum of a Watch Plan Coordinator, four land orboat-based observers, and one aerial observer. All observers shall have had previousexperiences in observing/spotting marine mammals and sea turtles or be approved by theFWC, USFWS, and NMFS. The aerial observer shall have a minimum of 30 aerial hoursof experience observing sea turtles and marine mammals, a large number of which wasflying aerial surveys as a secondary observer during blasting events.

e. Observers shall follow the protocol established for the Watch Plan and shall conduct thewatch in good faith and to the best of their ability.

f. Each observer shall be equipped with a two-way radio that will be dedicated exclusivelyto the watch. Observers will be equipped with a cell phone as a backup verbalcommunications system. Observers shall also be equipped with polarized sunglasses,binoculars, a red flag for backup visual communication, and a sighting log with a map torecord sightings.

g. All blasting events shall be weather dependent. Climatic conditions must be suitable foroptimal viewing. Slack water, low tide provides optimal viewing conditions. Blasting isprohibited if wind speeds are in excess of 10 knots, during periods of fog and heavy rain.The Watch Plan Coordinator shall determine if optimal observation conditions occur priorto initiation of the survey for each blast event.

h. All blasting events shall occur during daylight hours to ensure that optimal observationconditions occur.

i. A continuous aerial survey shall be conducted by helicopter or airplane, beginning onehour prior to the start of blasting. The survey route shall be designed in conjunction withthe FWC, USFWS, and NMFS. After detonation, the aerial survey crew will make acomplete survey of the blast area. The aerial survey crew shall continue surveillance ofthe survey areas for 30 minutes post-blast in case there is a need of aerial tracking of aninjured sea turtle or marine mammal.

j. The additional observers shall be located at predetermined positions around the blast site.These positions will be situated to provide maximum visibility of the exclusion zone andwill be approved by the FWC, USFWS, and NMFS. The observers shall begin surveyingthe area one hour prior to the blast event and continue observing for one half hour afterthe blasting event.

k. The perimeter of the exclusion zone shall be marked with brightly colored buoys and anadded 300-foot radius perimeter around the exclusion zone shall be marked with whitebuoys for aerial reference.

l. All of the observers shall be in close communication with the blaster in order to halt theblast event, if the need arises. The event shall be halted (delayed), if a marine mammal orsea turtle is spotted within 300 feet of the perimeter of the exclusion zone. If a marinemammal or sea turtle is observed swimming in the direction of the blast zone and theirarrival time is projected to coincide with the blast, the blasting event shall be halted. Theblasting event shall be halted immediately upon the request of any observer. The blastshall not take place until the animal(s) move out of the area under its own volition.Animals shall not be herded away or harassed into leaving. If the animal(s) is not sighteda second time, the blasting shall not resume until 30 minutes after the initial sighting.

Page 45: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-7 Revision: 3/3/15

m. If an injured or dead marine mammal or sea turtle is sighted after the blasting event, theWatch Plan Coordinator shall contact the FWC through their Hotline at 1-888-404-FWCC, the NOAA Fisheries Service’s Southeast Regional Hotline at 305-862-2850.Notification shall also be given to the FWC Imperiled Species Management Section at850-922-4330, and the USFWS at the Jacksonville Ecological Services Office at 904-232-2580 (if the project is located in north Florida), or the Vero Beach Field Office at772-562-3909 (if in south Florida).

n. If there are any problems encountered during blasting, the problems shall be evaluated bythe observers and explosives engineer. Logistical solutions will be presented to the FWC,USFWS, and NMFS for their approval. Corrections to the Watch Plan shall be made priorto the next blasting event.

o. Within two (2) weeks after completion of all the blasting events, the Watch PlanCoordinator will submit a summary report to the FWC, USFWS, and NMFS. The reportshall include the observer logs, provide the names of the observers and their positionsduring the event, the number and location of manatee, other marine mammals, and seaturtles sighted and the actions that were taken when the animals were observed. Thereport shall reference the appropriate permit or other authorization numbers.

B. Individual Shot Plans. The CONTRACTOR shall provide plans for each individual shot to theDISTRICT. The CONTRACTOR is responsible for plan implementation and effectiveness. At least48 hours in advance of the blast, the CONTRACTOR shall submit its details for the shot. Followingthe blast, the Individual Shot Plan will be supplemented with a post blast report.

1. Proposed details for the individual shot plan, shall include spacing, burden, dimensions tobenches or free faces, horizontal and vertical ties to project monuments and/or stationing, theinvert to be achieved, shot charges, drillers log, and proposed stemming and supportingcomputations. Specific surface or ground water management activities shall be described.These details, and any other change from the Blast Plan, shall be submitted at least 48 hours inadvance of the blast.

2. A Post Blast Report shall be prepared and submitted as a supplement to the Individual ShotPlan. This report shall include quantity of explosive actually used, final number of holes,pounds of explosive per hole, a narrative of any problems encountered (such as misfires andflyrock) and a discussion of proposed corrective actions. Seismograph and airblastoverpressure records, certified as accurate by the CONTRACTOR, shall be submitted. ThePost-Blast Report shall be submitted with 48 hours of the blast.

C. The CONTRACTOR shall provide insurance certificates indicating a blasting endorsement on publicliability and property damage insurance policy in keeping with the Contract Documents.

D. Blast Monitoring Records:

1. The CONTRACTOR shall submit a Pre-Blast survey no later than 14 days prior to commencingblasting operations.

a. Pre-blast survey document

i. The CONTRACTOR shall schedule and conduct a pre-blast survey. TheCONTRACTOR shall provide one person from its organization and its specialiston vibration control to organize and lead a team, with the DISTRICT and therepresentative of the property, utility, facility, canal bank or structure, in making apre-blast survey. As a minimum, any property, structure, canal bank, facility orutility (within or adjacent to the site) that could receive seismic motion greaterthan one-half inch per /second (or more stringent velocity required by a permit oragency) or an airblast overpressure greater than 0.013 psi (133 dBL) shall beinspected and their condition documented.

ii. The Pre-blast survey document shall include as a minimum:

Page 46: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-8 Revision: 3/3/15

a) A map of the project site with areas of concern highlighted.

b) Videotaped or photographically documented existing conditions, andinstances of pre-existing cracks or other defects. The documentation shallclearly identify each item. Documentation shall describe the location, thedirection from which the photo was taken, and dates. Documentation shallinclude a narrative of each issue. CONTRACTOR shall note the conditionof the existing canal banks and shall locate and identify any areas wherebulging, sloughing, cracking, or existing damage is observed.

c) Actual measured horizontal dimensions (not estimated dimensions) fromthe nearest blast hole to surveyed properties, structures, levees, utilities orfacilities. Measured ties to the project vertical datum. The CONTRACTORis required to have a Professional Surveyor and Mapper registered in theState of Florida supervise the acquisition and recording of this information.

d) Pertinent diaries or logs of conversations with owners related to the pre-blast condition of the inspected structures, levees, utilities or facilities.

iii. CONTRACTOR shall clearly document existing conditions.

E. The CONTRACTOR shall provide pattern and shot charge plans prior to individual blast events.

F. The CONTRACTOR shall provide seismic monitoring records, including instrument identification,locations, dates, times, with tabulated and summarized results. The records shall be clearly tied tospecific blast events.

G. The CONTRACTOR shall submit a Damage Investigation survey document:

1. Within 7 calendar days of any event causing damage to any property. Such survey shall includeas a minimum:

a. Detailed description of the damage. Include Videotape or photographic documentation.

b. Name, address and telephone number of the Owner of the damaged property, structures,levees, utilities or facilities. The DISTRICT will supply a master list of adjacent propertyowner information.

c. Evaluation of the cause of the damage and measures taken or to be taken to preventrecurrence.

2. The CONTRACTOR shall supplement this report on a bi-weekly basis (or other time period asdetermined by the DISTRICT) until the damage is repaired or otherwise made whole.

3. The CONTRACTOR shall submit an overview of the damage survey results including thestatus of any damage events, within 60 calendar days of the completion of all blasting.

H. The CONTRACTOR shall submit a copy of each permit, license, certificate, and other qualifications asrequired in SECTION 1.02 to perform the blasting.

I. The CONTRACTOR shall provide a Transmittal of Compliance Submittals for this section, and submitthe quality and quantity indicated in SECTION 01300, except where the CONTRACTOR revises itsBlast Plan (revised either at its own convenience or due to unacceptable blasts) or for the componentsof Individual Shot Plans, or when it supplements a Damage Investigation Survey Report. In theseinstances:

1. The Blast Plans, Individual Shot Plans and Damage Survey Reports shall be submitted in 3-ringbinder format, indexed and divided according to subject.

2. Resubmit only the portions of the Blast Plan, Individual Shot Plans and its supplements, andDamage Survey Reports that are affected. Mark and track the submittals with a logicalnumbering system and dated revision numbers. Resubmissions shall be 3-hole punched andorganized for insertion into the revised documents.

Page 47: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-9 Revision: 3/3/15

1.05 QUALIFICATIONS:

A. The CONTRACTOR shall submit qualifications of proposed master blaster and experience statementof the blasting contract firm to demonstrate competency in the use of explosives for rock excavationand verification of Florida State Explosive Blasters Permit and State Explosive License, plus anyrequired licensure by applicable agencies.

1. Minimum qualifications and experience: Provide documentation of 15 years minimumexperience in rock excavation projects in addition to the any licensure and/or certificationrequired by the state, county, city and local agencies.

B. Blasting Consultant: The CONTRACTOR shall provide the name and experience statement of theBlasting consultant permitted and licensed in the State of Florida, to be used in the event ofunacceptable blasts as defined herein.

C. Vibration Control specialist. The CONTRACTOR shall provide the name and experience statement ofthe consultant permitted and licensed in the State of Florida.

1.06 RESPONSIBILITIES:

A. The CONTRACTOR shall include in its bid consideration in its progress schedule for time it takes toobtain permits, permit revisions and inspections from the issuing entities.

B. The CONTRACTOR shall maintain proper shipping documentation; provide legal markings, labels,placards, and packaging. The CONTRACTOR shall keep accurate records of explosives, blastingagents, and blasting supplies transported, used, stored, and produce them upon request.

C. The CONTRACTOR’S Blasters are required to be experts in this field as demonstrated by applicableexperience and all required licensure. Blasters are required to know about and comply with the latestversion of all regulations. When the regulations of one agency are more stringent on a specific issuethan those of another, the CONTRACTOR shall comply with the more stringent regulation.

D. The CONTRACTOR shall obtain copies of all applicable codes, regulations, laws and ordinances andkeep them in its on-site project file.

E. The CONTRACTOR shall obtain all applicable permits from all pertinent state, county and localagencies. Contractor shall coordinate with the Florida Fish and Wildlife Conservation Commission(FWC) when preparing the blasting plan. The blasting plan shall follow all regulatory conditions fromthe FWC. FWC approval of the blasting plan should be obtained before submittal for permits.

1.07 CERTIFICATIONS AND TESTING: (Not Applicable)

1.08 INSPECTION COORDINATION: (Not Applicable)

PART 2 - PRODUCTS

2.01 MATERIALS ENCOUNTERED:

A. Materials to be excavated include geologic formations for which the CONTRACTOR has determinedthat explosive blasting is more appropriate for achieving required grades, loosening material, andfragmenting according to gradation requirements, than by alternate means. The CONTRACTOR shallensure that it has considered all the potential expenses related to blasting required to comply with theindustry regulations and with requirements of the plans and specifications, in its bid.

B. The CONTRACTOR shall ensure that all blasted materials must either meet, or be made to meet,contract gradation requirements or it shall be stockpiled on the site at a location designated by theDISTRICT, at no additional expense.

Page 48: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-10 Revision: 3/3/15

PART 3 - EXECUTION

3.01 GENERAL:

A. The CONTRACTOR shall be responsible for any damage to existing properties, utilities, structures,facilities, canal banks or access roads due to blasting excavation activities. CONTRACTOR shallexpediently repair (within 30 days or as directed by the DISTRICT) at no additional expense. Uponthe circumstance of damage:

1. The CONTRACTOR shall stop blasting.

2. Notify the DISTRICT by phone and follow-up in writing.

3. The CONTRACTOR shall provide the required damage survey.

4. The CONTRACTOR shall undertake to rectify the damage.

5. The CONTRACTOR shall revise, resubmit, and obtain the DISTRICT’S acceptance, and anyrequired third-party acceptance, on the appropriate SECTIONS of his Blasting Plan before anyfurther blasts are undertaken. The CONTRACTOR shall obtain the services of a BlastingConsultant permitted and licensed in the State of Florida to advise the CONTRACTORregarding changes to be made to the blasting procedures necessary to meet the requirementsspecified herein. The CONTRACTOR is responsible for plan implementation andeffectiveness. The DISTRICT is to be provided a review period of 7 calendar days, and anythird party requirements must be met. As many 100-foot long Test Blasts shall be made as areneeded until it is verified that the changes were effective.

B. The CONTRACTOR shall have the sole responsibility for the safety of all work activities includinglabor, materials handling, shipment, storage, and equipment.

C. The CONTRACTOR shall revise its Blast Plan and Individual Shot Plans and prove that the revisedplans are acceptable. The DISTRICT will not pay for unacceptable blasts (invert not achieved,fragmentation not according to specifications, flyrock uncontrolled, etc.) until they have beencompletely rectified. In addition, any corrections or repairs resulting from an unacceptable blast willbe corrected and approved prior to requesting payment.

D. No time extensions will be made, nor will additional compensation be made for delays or othercircumstances related to unacceptable blasts.

E. The DISTRICT will allow two changes to the blast plan, for which the DISTRICT will bear the cost ofreview. The DISTRICT’S costs, including consultants, for subsequent reviews will be at theCONTRACTOR’s expense.

F. The CONTRACTOR shall be responsible for obtaining proper fragmentation and achieving therequired depth of excavation within specified tolerances.

G. The CONTRACTOR shall take in consideration the resulting size of the fragments material whenpreparing the Blast Plan. The resulting size shall conform to the Type B Rip-Rap gradation specified inSECTION 02370.

3.02 COORDINATION WITH THIRD PARTIES WITH RESPECT TO BLASTING:

A. Critical properties, public utilities, canal banks, structures or facilities may lie close to constructionareas associated with this project. During project development agreements may have been madebetween the DISTRICT and relevant third parties. Some of the agreements will guide, restrict andaffect the CONTRACTOR’S activities. The CONTRACTOR shall be responsible for planimplementation and effectiveness while accommodating such agreements. The following list includesthe affected parties, and conditions, restrictions, timeframes, issues and consequences that theCONTRACTOR must consider in his bid for both costs and scheduling. There will be no extracompensation for activities the CONTRACTOR must pursue to satisfy these conditions.

Page 49: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-11 Revision: 3/3/15

1. The Contractor shall coordinate and request any third party agreements obtained by the Districtbefore beginning of construction.

3.03 BLAST NOTICE REQUIREMENTS:

A. The CONTRACTOR shall submit required documents and notify the DISTRICT in writing at least 48hours prior to a blast. If the blast is scheduled with less than 72-hour notification, the blast shall bedelayed until the DISTRICT indicates that all parties have been duly notified. Such delays are theCONTRACTOR’S responsibility and no extra compensation will be paid.

3.04 TURBIDITY AND EROSION CONTROL:

A. The CONTRACTOR shall install turbidity and erosion control devices as indicated and as specifiedherein prior to initiation of blasting operations

3.05 SITE PREPARATION:

A. The CONTRACTOR shall clear the site in accordance with SECTION 02110.

B. The CONTRACTOR shall strip the site in accordance SECTION 02200.

C. Vibration Control: The CONTRACTOR shall provide a minimum of (3) three seismographs sufficientto measure and record ground movements caused by each blast detonated under the contract. Theseismographs shall be placed at locations to include, but not limited to, the nearest properties,buildings, structures, levees, or utilities, and such locations are to be approved by the DISTRICT:

1. Seismograph operators shall be qualified personnel capable of setting up instruments atdesignated locations and efficiently recording the blast. Blasting shall be controlled in such amanner that the maximum ground vibration level at any structure which is vulnerable todamage shall not exceed a resultant peak particle velocity of 0.5 inches per second whenmeasured on the ground at the nearest building or structure finished or under construction orany more stringent requirement required by a permit or regulatory agency.

The maximum allowable airblast, measured at the nearest building or structure or whenmeasured at a distance of 5,280 feet from the blast shall not exceed 129 decibels whenmeasured by an instrument having a flat frequency response over a range of at least 6 to 200hertz. If the airblast is measured with an instrument having a flat frequency measure over arange of at least 2 to 200 hertz, the corresponding limit is 133 decibels.

2. The instrumentation shall record three (3) orthogonal components (vertical, radial, andtransverse with respect to the location of the blast) of particle velocity direct (or shall havesufficient resolution of acceleration or displacement such that particle velocity can be readilyand accurately determined from the records). The instantaneous vector sum of the three (3)directional components of vibration will be used to compute the maximum vibration level. Therecord for each blast shall consist of seismograph records identified by instrument number,location of instruments positively identified, date and time and location of blast, amount ofexplosives used, peak particle velocity, and all other data necessary to adequately controlblasting operations. A written memorandum of vibration intensity shall be submitted within 24hours when specifically requested by the DISTRICT, or without request when such intensityexceeds a resultant peak particle velocity of 0.5 inches per second. The CONTRACTOR shallsubmit a copy of the record in tabular form for each blast on a semi-monthly basis.

3.06 EXCAVATION AND TRENCHING:

A. The CONTRACTOR shall furnish and install Sheeting and Bracing as follows:

1. Use where resulting slopes from blasting, excavation or trenching might endanger existingcanal banks or proposed structures or personnel working below adjacent grades.

Page 50: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-12 Revision: 3/3/15

2. Provide materials on site prior to start of excavation. Adjust spacing and arrangement ofsheeting and bracing as required by conditions encountered.

3. Remove sheeting and bracing as conditions allow and construction progresses.

4. Comply with all requirements of the Florida Trench Safety Law as specified in the GENERALTERMS & CONDITIONS.

B. The CONTRACTOR shall conduct Blasting as follows:

1. General:

a. Comply with all laws, ordinances, applicable safety code requirements, and regulationsconcerning the transportation, handling, storage, loading, preparation and usage ofexplosives and blasting agents, relative to the protection of life and property.

b. In keeping with the overall blasting plan, provide individual blast pattern and shot chargeplans to ensure against blasting which may result in damage or loss of life.

c. It is the DISTRICT’S objective to manage the requirements of this Section to prevent orminimize fly rock from impacting outside of the construction limits.

d. Overnight storage of explosives and any associated blasting components thereof WILLNOT be allowed on the project site. Safe storage and handling is the CONTRACTOR’Sresponsibility. Loaded shot holes shall not be left unguarded overnight. Shouldunavoidable circumstances delay a blast or cause loaded shot holes to remain overnight,the CONTRACTOR shall immediately provide adequate full time security on-site at noextra cost to the DISTRICT. Following such an occurrence, the Blasting Plan will bereviewed and may be required to be revised to prevent similar occurrences, such asreducing the blast limits. Changes made to the blast plan to comply with this section areto be considered part of the original project scope and shall be completed at no additionalcost.

e. Drill and blast in a manner that prevent disturbance to adjacent properties, utilities, canalbanks or structures, including damage from flyrock and vibration. Drill and blast in amanner that results in fragmentation conforming to the rock gradation required in theplans and specifications, and that also reduces overbreak.

f. Stemming: Stemming is required in the following locations for positive control offlyrock. The CONTRACTOR is to specify the means and methods.

i. The contractor shall advise the District of any concern areas where stemmingmight be appropriate.

g. Blasting shall only be performed by persons who are qualified, competent, andthoroughly experienced in the use of explosives for rock excavation and shall besupervised by a person licensed in the State of Florida.

h. Locate charge holes properly and drill to correct depth for charges used.

i. Limit charges in size to minimum required for correct breakage and appropriate removalof material by excavating equipment.

j. Determine spacing of drill holes, size of explosive charges, time delays and blastingtechniques, including pre-splitting and confined blasting procedures, to avoid overbreak.

k. The CONTRACTOR shall assume full liability for any damage to existing properties,levees, structures, utilities or new construction caused by blasting operations, and anydamage shall be repaired at no additional cost.

l. Before delivery of any explosives at jobsite, The CONTRACTOR must have obtained ablasting endorsement on its public liability and property damage insurance policy, andhave included Additional Insured as required. A copy of such insurance certificate shallbe provided to the DISTRICT.

Page 51: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-13 Revision: 3/3/15

m. Remove overblasted rock materials to competent rock within 30 days, unless anothertime period is accepted in writing by the DISTRICT, following blasting. Dispose ofoverbreak according to the Blast Plan.

n. Flyrock: The CONTRACTOR shall strive to contain flyrock from blasting within theconstruction limits indicated on the plans. Should the CONTRACTOR fail to achievethis requirement, the following procedures will apply, without further compensation intime or money:

i. The CONTRACTOR shall stop blasting.

ii. The CONTRACTOR shall clean up flyrock.

iii. The CONTRACTOR shall revise, resubmit and get the DISTRICT’S acceptance,and any required third-party acceptance, on the appropriate sections of its BlastingPlan before any further blasts are undertaken. The CONTRACTOR shall obtainthe services of a Blasting Consultant permitted and licensed in the State of Floridato advise the CONTRACTOR regarding changes to be made to the blastingprocedures necessary to meet the requirements specified herein. TheCONTRACTOR is responsible for plan implementation and effectiveness. TheDISTRICT is to be provided a review period of seven calendar days and any thirdparty requirements must be met.

iv. As many 100-foot long Test Blasts shall be made as are needed until it is verifiedthat the changes were effective.

C. Maximum length of a linear blasting section shall be limited to one quarter mile, and blasting shall notbe more than one quarter mile ahead of excavation activities, unless otherwise agreed to in writing bythe DISTRICT.

D. The CONTRACTOR shall provide test digs to the full excavation cross section every 300 feet to verifythat the correct invert is being achieved and that the fragmentation is according to specifications.Should the inverts or gradation of fragments be incorrect, the CONTRACTOR shall, without furthercompensation in time or money:

1. Stop blasting.

2. Revise, resubmit and get the DISTRICT’S acceptance and any required third-party acceptance,on the appropriate sections of his Blasting Plan before any further blasts are undertaken. TheDISTRICT is to be provided a review period of seven calendar days.

3. As many 100-foot long Test Blasts shall be made as are needed until it is verified that thechanges were effective. The CONTRACTOR shall obtain the services of a Blasting Consultantpermitted and licensed in the State of Florida to advise the CONTRACTOR regarding changesto be made to the blasting procedures necessary to meet the requirements specified herein.CONTRACTOR is responsible for plan implementation and effectiveness.

E. Drilling in preparation for setting charges shall be no more than one deep water pool area in advance ofexcavation activities to allow blasting plan modifications based on results of previous blasts, withoutfurther compensation in time or money, unless changed by the DISTRICT in writing.

F. Blasting shall be prohibited in the following areas. Where blasting is prohibited, the CONTRACTORshall break rock for excavating, to the lines and grades indicated on Drawings, using mechanicalmeans.

1. Any locations beyond the 100’ diameter deep pools as shown in the contract drawings.

G. Pre-Blast Surveys shall be made and submitted in keeping with the Blast Plan. Specific locationswhere surveys are required are listed herein.

H. Damage Inspection Survey:

Page 52: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/21/06 02211-14 Revision: 3/3/15

1. The CONTRACTOR shall perform Damage Inspection surveys in keeping with the Blast Planto detect any effects resulting from blasting operations

2. The CONTRACTOR shall submit Damage Inspection survey, photographs, and other finalizeddata to the DISTRICT.

3. The DISTRICT shall inspect the properties, canal banks, structures, facilities and utilities afterreceipt of the report to verify the accuracy of the survey. FDOT, FPL or other property or utilityowners may inspect their structures, facilities, canal banks or utilities. Any damaged areas,which were not specifically identified in the pre-blasting survey narrative and photographs,shall be deemed to have been caused by the blasting operations. The CONTRACTOR shall beresponsible for required repairs at no additional cost to the DISTRICT.

I. The CONTRACTOR shall repair damage caused by blasting within 30 days unless the DISTRICTspecifies a different time frame in writing.

J. The CONTRACTOR shall take precautions to preserve the materials outside the lines of excavation inan undisturbed condition. Careful blasting control will be necessary to obtain desirable breakage andproper side slopes to achieve mandatory excavation cross sectional area.

K. The CONTRACTOR shall dewater in accordance with SECTION 02401.

L. The CONTRACTOR shall perform excavation and embankment operations in accordance with theplans and in accordance with SECTION 02200 and SECTION 02220.

END OF SECTION

Page 53: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/27/06 02250-1 Revision: 3/3/15

SECTION 02250 DREDGING

PART 1 - GENERAL

1.01 SCOPE:

A. The WORK of this Section consists of furnishing all labor, equipment plant, supplies, and materialsnecessary for the proper dredging, excavating and placement of dredging material required by theContract Documents.

1. SECTION 01530

2. SECTION 01531

3. SECTION 02110

4. SECTION 02200

5. SECTION 02211

6. SECTION 02435

1.02 SUBMITTALS:

A. Qualified Manatee Observers along the Faka Union Canal, both pre-blast and post-blast anddredging/excavation. The Qualified Manatee Observer shall have a commensurate experience inblasting and/or dredging projects observing animals and with the protocol in similar level of threat orenvironments as the proposed project.

1.03 MATERIAL TO BE REMOVED:

A. The material to be removed consists of fine sand fill (SP), organic peats and marls (PT/OL/ML),slightly fie sand (SP), silty to slightly clayey fine sand (SC) and porous sandy limestone (LS). Refer tothe Radise report “Geotechnical Engineering Services, West Indian Manatee Mitigation Feature,Picayune Strand Restoration Project (100397)”, March 21, 2014, for details.

B. Hard Material is defined as material requiring the use of special equipment for economical removal,and includes boulders or fragments too large to be removed in one piece by the dredge.

1.04 ARTIFICIAL OBSTRUCTIONS:

A. Except as indicated, the DISTRICT has no knowledge of cables, pipes, or other artificial obstructionsor of any wrecks, wreckage, trees, or other material that would require the use of explosives or theemployment of additional equipment for economical removal. Contractor shall arrange for mark outprior to dredging. If actual conditions differ from those stated or shown, or both, an adjustment incontract price or time for completion, or both, may be made. The DISTRICT has no knowledge ofsunken trees or other vegetative debris. The CONTRACTOR shall remove any such debris from thewater and properly dispose off site.

1.05 QUANTITY OF MATERIAL:

A. The CONTRACTOR shall independently estimate the quantities necessary to be removed based on thedrawings provided.

1.06 SIDE SLOPES:

A. Dredging on side slopes shall follow, as closely as practicable, the lines indicated or specified. Anallowance may be made for dredging beyond the lines indicated or specified for side slopes. Theallowance will be determined by projecting a line upwards, paralleling the project design side slopes,

Page 54: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/27/06 02250-2 Revision: 3/3/15

from the intersection of the overdepth dredging limit (at a point located vertically below the limit ofdredging at the top of slope). The amount of material excavated from side slopes may be determinedby cross-sections, computer, or both.

1.07 PERMIT:

A. The CONTRACTOR shall comply with conditions and requirements of State or Federal permits.

1.08 CHARGES: (Not Applicable)

1.09 ENVIRONMENTAL PROTECTION REQUIREMENTS:

A. The CONTRACTOR shall provide and maintain during the life of the contract, all necessaryenvironmental protective measures. Additionally, the CONTRACTOR shall provide environmentalprotective measures required to correct conditions, such as oil spills or debris that occur during thedredging operations. Comply with Federal, State, and local regulations pertaining to water, air, andnoise pollution.

B. The following conditions must be followed to protect manatees and marine turtles during all in-waterdredging activities:

1. All personnel associated with the project shall be instructed about the presence of marineturtles, manatees and manatee speed zones, and the need to avoid collisions with (and injury to)these protected marine species. The permittee shall advise all construction personnel that thereare civil and criminal penalties for harming, harassing, or killing manatees which are protectedunder the Marine Mammal Protection Act, the Endangered Species Act, and the FloridaManatee Sanctuary Act.

2. All vessels associated with the construction project shall operate at "Idle Speed/No Wake” at alltimes while in the immediate area and while in water where the draft of the vessel provides lessthan a four-foot clearance from the bottom. All vessels will follow routes of deep waterwhenever possible.

3. Siltation or turbidity barriers shall be made of material in which manatees and marine turtlescannot become entangled, shall be properly secured, and shall be regularly monitored to avoidmanatee entanglement or entrapment. Barriers must not impede manatee or marine turtlemovement.

4. All on-site project personnel are responsible for observing water-related activities for thepresence of marine turtles and manatee(s). All in-water operations, including vessels, must beshutdown if a marine turtle or manatee comes within 50 feet of the operation. Activities willnot resume until the animal(s) has moved beyond the 50-foot radius of the project operation, oruntil 30 minutes elapses if the animal(s) has not reappeared within 50 feet of the operation.Animals must not be herded away or harassed into leaving.

5. Any collision with or injury to a marine turtle or manatee shall be reported immediately to theFlorida Fish and Wildlife Conservation Commission (FWC) Hotline at 1-888-404-3922, and toFWC at [email protected]. Collision and/or injury should also be reported tothe U.S. Fish and Wildlife Service (for north Florida, Jacksonville 1-904-731-3336 or for southFlorida Vero Beach 1-772-562-3909). Care should be taken in handling sick or injured marineturtle specimens to ensure effective treatment and care and in handling dead marine turtlespecimens to preserve biological materials in the best possible state for later analysis of cause ofdeath. In conjunction with the care of sick or injured endangered or threatened species orpreservation of biological materials from a dead animal, the finder has the responsibility toensure that evidence intrinsic to the specimen is not unnecessarily disturbed.

6. Temporary signs concerning manatees shall be posted prior to and during all in-water projectactivities. All signs are to be removed by the permittee upon completion of the project.Temporary signs that have already been approved for this use by the FWC must be used. One

Page 55: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/27/06 02250-3 Revision: 3/3/15

sign which reads Caution: Boaters must be posted. A second sign measuring at least 8 ½” by11" explaining the requirements for “Idle Speed/No Wake” and the shut-down of in-wateroperations must be posted in a location prominently visible to all personnel engaged in water-related activities. These signs can be viewed at MyFWC.com/manatee. Questions concerningthese signs can be sent to the email address listed above.

7. Dedicated observers shall be designated when in-water work is being performed on a dredge,other than a cutterhead dredge, and shall perform no other duties that may interfere with theirability to observe for protected marine species (such as manatees, marine turtles, dolphins, etc.)during dredging activities. That person shall have significant prior on the job experienceobserving for protected marine species (including manatees) during previous dredging eventswhere the activities were similar in nature to this project. Observers shall be equipped withpolarized sunglasses to aid in observation during the daytime. A dedicated observer must be onsite during dredging activities, other than cutterhead dredge activities, and will advise personnelto cease operation upon sighting a protected marine species within 50 feet of any in-waterconstruction activity.

8. A list of the observers, their contact information and their qualifications, must be included in theEnvironmental Protection Plan. Copies of this Plan shall be provided to the Florida Fish andWildlife Conservation Commission (FWC) at [email protected] for review atleast 30 days prior to the proposed date of the dredging(s) as a matter of comity. Any furthermodifications to this Plan related to observers shall be coordinated with these entities prior toimplementation. These entities shall also be notified at the initiation and completion of dredgingevents.

9. A log detailing work activities, sightings, collisions, or injuries to protected marine speciesduring the contract period shall be maintained. Observer logs and a report summarizingincidents and sightings shall be submitted to the Florida Fish and Wildlife ConservationCommission, Imperiled Species Management Section at: [email protected]. Logsand a report shall be submitted within 30 days following each event, which is defined as thetime period between when mobilization of equipment begins and when demobilization ofequipment ends, or submitted on an annual basis, for multi-year projects.

10. During construction, project lighting shall be limited to the immediate area of activeconstruction only and shall be the minimal lighting required to comply with U.S. Coast Guardand/or OSHA requirements. Stationary lighting and all lighting on equipment shall beminimized through reduction, shielding, lowering, to the maximum extent practicable whilecomplying with COE EM 385-1-1 (2003) U.S. Army Corps of Engineers Safety and HealthRequirements Manual and applicable OSHA/USGC regulations - Specifically - 07.A.04 Marinelighting shall be in accordance with American National Standards Institute/ IlluminatingEngineering Society of North America (ANSI/IESNA) RP-12, and appropriate placement oflights to minimize illumination of marine turtle nesting beaches.

11. When clamshell dredges are used, the bucket shall be released at the water surface during anynighttime dredging (gravity release method).

1.10 BASIS FOR BIDS:

A. The CONTRACTOR shall base his bid on the quantity of dredging estimated from the drawings andthe dredging conditions specified and indicated which are known

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.01 INSPECTION:

Page 56: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/27/06 02250-4 Revision: 3/3/15

A. The CONTRACTOR shall inspect the WORK, keep records of WORK performed, and ensure thatgages, targets, ranges, and other markers are in place and usable for the intended purpose. Furnish, atthe request of the Contracting Officer, boats, boatmen, laborers, and materials necessary for inspecting,supervising, and surveying the WORK. When required, the CONTRACTOR shall providetransportation for the DISTRICT and inspectors to and from the disposal area and between thedredging plant and adjacent points on shore.

3.02 CONDUCT OF DREDGING WORK:

A. Order of Work

1. The CONTRACTOR will direct the sequence of the WORK except as specified as shown onthe drawings or Section 01010. The DISTRICT reserves the right to change the order ofWORK at any time.

B. Lights

1. If work is continued when dark, the working conditions shall meet OSHA or other applicableState/Federal requirements for providing adequate lighting for a safe working condition.

C. Ranges, Gages, and Lines

1. The CONTRACTOR shall furnish, set, and maintain ranges, buoys, and markers needed todefine the WORK and to facilitate inspection. Establish and maintain gages in locationsobservable from each part of the WORK so that the depth may be determined. Suspenddredging when the gages or ranges cannot be seen or followed.

D. Plant

1. The CONTRACTOR shall maintain the plant, scows, coamings, barges, pipelines, andassociated equipment to meet the requirements of the WORK. Promptly repair leaks or breaksalong pipelines. Remove dredged material due to leaks and breaks.

E. Disposal of Excavated Material

1. The CONTRACTOR shall provide for safe transportation and disposal of dredged materials.Transport and dispose of dredged material in the spoil area designated for disposal of dredgedmaterial. The deposit of dredged materials in unauthorized places is forbidden. Spoil materialinadvertently spilled on roads, public rights of way and private property shall be promptlyremoved and the area restored by the CONTRACTOR in accordance with the GENERALTERMS & CONDITIONS. Comply with rules and regulations of the DISTRICT.

2. The CONTRACTOR may deposit dredged material by hydraulic or mechanical processes.Except where authorized in the plans and specifications, dredge pipelines or open ditches shallnot block roads or public rights of way or otherwise interfere with access unless approved.

F. Salvaged Material

1. Large items recovered from dredging such as automobiles and refrigerators shall be disposed ina proper manner. The CONTRACTOR shall notify proper law enforcement agencies asappropriate.

G. Navigation Warnings

1. The CONTRACTOR shall provide and maintain appropriate signage notifying boaters of theclosure, closure date(s) and the local telephone number of the CONTRACTOR. Signage shallconform to industry standards or Coast Guard recommendations as appropriate. TheCONTRACTOR shall completely remove and properly dispose of signage upon completion ofthe project.

H. Method of Communication

Page 57: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 11/27/06 02250-5 Revision: 3/3/15

1. The CONTRACTOR shall provide a system of communication between the dredge crew andthe crew at the disposal area. A portable two-way radio is acceptable.

I. Safety of Structures

1. The prosecution of the WORK shall ensure the stability of bridges, piers, docks mooring piles,bulkheads, seawalls retaining walls, pile supported or subaqueous utility crossings, buriedutilities, parallel runs, utility poles, guys and anchors, culverts, pipes and other structures ortrees and vegetation or existing slope protection lying on or adjacent to the site of the WORK,insofar as structures may be jeopardized by dredging operations. The CONTRACTOR shall beresponsible for repair of damage resulting from dredging operations, insofar as such damagemay be caused by variation in locations or depth of dredging, or both, from that indicated orpermitted under the contract.

J. Plant Removal

1. Upon completion of the WORK, promptly remove plant, including ranges, buoys, piles, siltscreens or silt barriers, rope, line, cable and artificial anchors, signage and other markers orobstructions and return the site to its original condition.

3.03 MEASUREMENT:

A. The CONTRACTOR shall take soundings before and after dredging or excavation.

B. Method of Measurement

1. The drawings represent existing conditions based on current available information, but will beverified and corrected, if necessary, by soundings taken before dredging in each locality.Soundings will be taken by lead line or 200 kHz sonic methods, or both, as determined by theDISTRICT; results of soundings by either or both methods will be the basis for payment. Areassounded more than 30 days prior to dredging will be re-sounded when requested by theCONTRACTOR. The CONTRACTOR has the option of being present when such soundingsare made.

C. Surveys during Progress of Work

1. Contract depth will be determined by soundings or sweepings taken behind the dredge as theWORK progresses. The CONTRACTOR shall take progress soundings or sweepings to verifycompliance with contract requirements.

D. Monthly Estimates

1. Monthly estimates of WORK completed will be based on the result of soundings taken duringthe progress of the WORK. Deductions will be made for dredging and disposal not inaccordance with the specifications.

3.04 FINAL EXAMINATION AND ACCEPTANCE:

A. On completion of dredging or excavation of a section or an area, the CONTRACTOR shall engage alicensed surveyor to provide as-built cross sections to provide certified drawings of the section. Crosssections shall be taken at the same locations used for the contract unless specified otherwise. TheDISTRICT may take additional cross sections and soundings if necessary. The CONTRACTOR shallprovide to the DISTRICT signed and sealed certified as-built drawings indicating the existing crosssection superimposed on the dredged cross sections as the final submittal. The CONTRACTOR shallremove intermediate (between the cross sections) shoals. Final estimates will be subject to deductionsor correction of deductions previously made because of excessive overdepth, dredging outside ofauthorized areas, or disposal of material in an unauthorized manner.

END OF SECTION

Page 58: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-1 Revision: 3/3/15

SECTION 02262 ALUMINUM AND STEEL SHEET PILING

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall furnish all labor, materials, and equipment necessary toinstall all temporary and permanent sheet piling, including wales, tie rods, and bolts, for the structureas indicated on the Drawings and specified herein.

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 09900

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the publications of the organizations listed below in effect at thetime of the advertisement for bids form a part of this specification to the extent referenced. See thevarious paragraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. American Society for Testing and Materials (ASTM):

a. A36 - Standard Specification for Carbon Structural Steel

b. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and SteelProducts

c. A153 - Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

d. A325 - Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi (kipsper square inch) Minimum Tensile Strength

e. A328 - Standard Specification for Steel Sheet Piling

f. A563 - Standard Specification for Carbon and Alloy Steel Nuts [Metric]

g. A572 - Standard Specification for High-Strength Low-Alloy Columbium-VanadiumStructural Steel

h. A668 - Standard Specification for Steel Forgings, Carbon and Alloy, for GeneralIndustrial Use

i. A780 - Standard Practice for Repair of Damaged and Uncoated Areas of Hot-DipGalvanized Coatings

j. B209 Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

k. B221 Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods,Wire, Profiles, and Tubes

l. B308/B308M Standard Specification for Aluminum-Alloy 6061-T6 Standard StructuralProfiles

m. F436 – Standard Specification for Hardened Steel Washers

n. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs

o. F594 - Standard Specification for Stainless Steel Nuts

2. American Welding Society (AWS):

a. AWS D1.1 - Structural Welding Code - Steel

Page 59: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-2 Revision: 3/3/15

1.03 DEFINITIONS: (Not Applicable)

1.04 SUBMITTALS:

A. The CONTRACTOR shall make submittals for permanent aluminum and temporary steel sheet pilingin accordance with SECTION 01300 and the following provisions. The CONTRACTOR shall beresponsible for coordination of materials, equipment, and installation regardless if the submittals aremade together or separately.

1. For Temporary Sheet Piles:

a. The CONTRACTOR shall submit the temporary steel sheet pile design signed and sealedby a Professional Engineer registered in the State of Florida.

b. Submit fabrication and erection drawings for temporary piling, wales, tie rods, andaccessories prior to installation signed and sealed by a Professional Engineer registered inthe State of Florida.

2. For Permanent Aluminum Sheet Piles:

a. Metal sheet piling shall be extruded aluminum sections fabricated from aluminumconforming to ASTM B221, ASTM B308/B308M, Alloy 6061, Temper T6.

b. Materials submission as identified in Part 2 of this SECTION.

c. Pile driving installation plan.

d. Submit certification that surface preparation and protective coatings have been applied inconformance with specifications.

3. For Temporary and Permanent Sheet Piles:

a. Make and model of pile-driving hammer.

b. Weight of capblock assembly, cushion dimensions, type of cushion material, and cushionstiffness.

B. During pile driving, the CONTRACTOR shall submit records to the DISTRICT each day including thefollowing for each temporary and permanent sheet pile:

1. Name of structure and pile number

2. Driven pile length

3. Pile length after cut off

4. Pile cut off and tip elevations

5. Ground surface elevation during driving

6. Final driving resistance and pressure gauge readings or hammer stroke

7. Date and time of day pile is driven

8. Heaving or redriving data

9. Remarks concerning pile-driving operations

1.05 QUALIFICATIONS:

A. Experience Requirement:

1. The CONTRACTOR shall have a minimum of five (5)-year experience installing aluminumand steel sheet piles.

1.06 RESPONSIBILITIES:

Page 60: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-3 Revision: 3/3/15

A. The CONTRACTOR shall be responsible for layout of the piles to the location shown on theDrawings. The CONTRACTOR shall establish monitoring devices and benchmarks as required tocomplete the WORK. The DISTRICT shall provide elevation reference for the CONTRACTOR tomark each pile along its entire length at one (1) foot intervals and along at least the last foot of drivingat one (1) inch increments, so as to permit determination of the pile tip elevation and correspondingdriving resistances during driving.

1.07 CERTIFICATIONS AND TESTING: (Not Used)

1.08 INSPECTION COORDINATION:

A. The CONTRACTOR shall provide access to the WORK for the DISTRICT as requested forinspection. The CONTRACTOR shall provide at least 48-hour advance notice of its intention to beginnew WORK activities.

1.09 WARRANTY:

A. The MANUFACTURER shall warrant the EQUIPMENT, MATERIALS and PRODUCTS specified inthis SECTION against defective materials and workmanship with the MANUFACTURER’s standardwarranty, but for no less than one (1) year from the date of Substantial Completion, and as described inArticle 13 of Section 00700 - General Terms and Conditions.

B. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - PRODUCTS

2.01 DRIVEN SHEET PILES:

A. The CONTRACTOR shall provide Sheet Pile in accordance with the following:

1. Sheet piles shall be the size and make as shown on Drawings or approved equal.

2. Permanent sheet piles shall be extruded aluminum sections fabricated from aluminumconforming to ASTM B221, ASTM B308/B308M, Alloy 6061, Temper T6. Use of cold-rolledand/or cold-formed permanent sheet piles is not permitted.

3. Sheet piles shall not have a camber or sweep in excess of the permitted mill tolerance.

4. Store on platforms, skids or other supports at the Site and support to prevent excessivedeflection.

5. Sheet pile points shall be reinforced with protector as manufactured by Associated Pile andFitting Corporation or DISTRICT approved equal. Points shall be welded to the piles inaccordance with the MANUFACTURER’s recommendations and conforming to ASW D1.1.

B. The CONTRACTOR shall drive sheet piles to the specified elevation.

C. The CONTRACTOR shall provide equipment for driving sheet piles as required to complete theWORK and as specified below:

1. The sheet piles shall be driven with an approved single, partial double-acting or double-actingsteam, air, diesel or vibratory hammer.

2. The pile driving hammer shall be operated at all times at the speeds and conditionsrecommended by the hammer MANUFACTURER.

3. The boiler or compressor capacities for the steam or air-operated hammers shall be sufficient tooperate the hammer continuously at the full rated speed and energy.

Page 61: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-4 Revision: 3/3/15

4. For the steam- or air-operated hammer drivers, the CONTRACTOR shall provide a pressuregauge to be located on the hammer steam or airline in a position such that it can be clearly readby the pile driver operator.

5. For the double-acting diesel hammers, the CONTRACTOR shall provide a pressure gauge to belocated in a position such that it can be clearly read by the pile driver operator.

6. For a single-acting diesel hammer, the CONTRACTOR shall mark the ram as approved by theDISTRICT to permit determination of the stroke.

D. Capblock and Cushion:

1. The CONTRACTOR shall submit to the DISTRICT details concerning the stiffness of thecapblock and cushion assembly and the coefficient of restitution and weight of the capblock andcushion assembly two (2) weeks prior to driving.

E. The CONTRACTOR shall provide 6061-T6 marine grade aluminum Wales, Plate and Washersconforming to ASTM B209 and B221.

F. The CONTRACTOR shall provide 6061-T6 marine grade aluminum tie rods conforming to ASTMB221.

G. The CONTRACTOR shall provide aluminum 7075-T73 bolts and nuts.

H. The CONTRACTOR shall provide 6061-T6 marine grade aluminum couplers.

PART 3 - EXECUTION

3.01 DRIVEN SHEET PILES: The CONTRACTOR shall provide pile driving equipment and drive sheet piles inaccordance with the following:

A. Templates: A template shall be provided for each location and be constructed to locate the relativeposition of the proposed piling layout.

B. Equipment for Driving Sheet Piles:

1. All pile-driving equipment shall be subject to the DISTRICT's approval after inspection at thejob Site.

2. At any time during the progress of the WORK, equipment, which in the DISTRICT's opinion, isin poor operating condition will not be approved for pile installation.

C. Driving Procedure:

1. Sheet piles shall not be driven until inspected and approved for driving.

2. No piles shall be driven within 100 feet of concrete less than seven (7) days old, unlessauthorized by the DISTRICT.

3. Drive piles in contact with surrounding soil and leave all permanent piles in place.

4. Do not drive coated piling until coating has cured a minimum of one (1) week (7 days).

5. Prior to driving pilings in water, a horizontal line shall be painted on both sides of each piling ata fixed distance from the bottom so that it is visible above the water line after installation. Thisline shall indicate the profile of the bottom elevation of installed pilings so potential problemareas can be identified by abrupt changes in elevation.

6. Pilings shall be driven with the proper size hammer and by approved methods to ensure nodamage to the piles and proper interlocking over their entire lengths. Driving hammers shall bemaintained in proper alignment during driving operations by the use of leads or guides attachedto the hammer. Caution shall be taken in the sustained use of vibratory hammers when a harddriving condition is encountered to avoid interlock melt or other damage. The use of vibratory

Page 62: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-5 Revision: 3/3/15

hammers should be discontinued and impact hammers employed whenever the penetration ratedue to vibratory loading is one (1) foot or less per minute.

7. A protective cap shall be employed during driving when using impact hammers to preventdamage to the tops of the pilings. Pilings damaged during driving or those driven out ofinterlock shall be removed and replaced at the CONTRACTOR’s expense.

8. Pilings shall be driven without the aid of a water jet, unless authorized by the DISTRICT.Authorized jetting shall be performed on both sides of the pilings simultaneously and must bediscontinued at least 5 feet before final seating of pilings. Adequate precautions shall be takento ensure that pilings are driven plumb. If the forward or leading edge of the piling wall isfound to be out of plumb, the piling being driven shall be driven to the required depth andtapered pilings shall be driven to interlock with the out-of-plumb leading edge. If approved,other corrective measures may be employed to ensure that succeeding pilings are plumb. Themaximum permissible taper for any tapered piling shall be 1/8 inch per foot of length.

9. Pilings in each run or continuous length of piling wall shall be driven alternately, in incrementsof depth, to the required elevation. No piling shall be driven to a lower elevation than thosebehind it in the same run, except when the pilings behind it cannot be driven deeper. If thepiling next to the one being driven tends to follow below final elevation, it may be pinned to thenext adjacent piling. If obstructions restrict driving a piling to the specified elevation, theobstructions shall be removed or penetrated with a chisel beam. If the CONTRACTORdemonstrates that removal or penetration is impractical, the CONTRACTOR shall makechanges in the design alignment of the piling structure as directed to ensure the adequacy andstability of the structure. Pilings shall be driven to the depths shown and shall extend up to theelevation indicated for the tops of the piles.

D. Tip Elevation:

1. The sheet piles shall be driven to the tip elevation(s) indicated on the Drawings.

E. Cutoff:

1. Piles shall be cut off perpendicular to the vertical axis of the pile and to within one half inch ofthe cutoff elevation indicated.

2. Remove the portion of the pile cut off from the Site.

3. If excavation is required to achieve pile cutoff, remove the excess excavated materials asdirected by the DISTRICT.

4. Splicing shall not be permitted without approval of the DISTRICT.

F. Installation Tolerance:

1. Tolerances in Driving: All piles shall be driven with a variation of not more than one quarterinch per foot of pile length from the vertical for plumb piles. Top of pile shall be within three(3) inches of the location indicated. Manipulation of piles to force them into position will notbe permitted. All piles will be checked for heave. Piles found to have heaved shall be redrivento the required point elevation.

G. Predrilling and Jetting:

1. Predrilling or jetting will not be permitted without written approval from the DISTRICT.

H. Rejected Piles:

1. The DISTRICT will determine the acceptability of all piles driven and may reject those pilesthat do not conform to the specifications.

2. Perform one of the following, as directed by the DISTRICT, for those piles that have beenrejected.

Page 63: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 02262-6 Revision: 3/3/15

a. Leave the piles in place, cut off as directed and drive one or more new piles in locationsdesignated by the DISTRICT.

b. Withdraw the pile and drive a new pile.

I. Sheet Pile Bracing: Install permanent wales, tie rods and accessories as indicated.

J. Provide temporary bracing as required prior to installation of permanent bracing.

END OF SECTION

Page 64: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-1 Revision: 3/3/15

SECTION 02370 RIPRAP SYSTEM

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall furnish all labor, equipment and materials necessary forthe proper placement of stone riprap, bedding stone and filter fabric where indicated as required by theContract Documents.

B. Related Work Specified Elsewhere:

1. SECTION 01300

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the standards of the organizations listed below in effect at the timeof the advertisement for bids form a part of this specification to the extent referenced. In the case of aconflict between the requirements of this SECTION and those of the listed document, the requirementsof this SECTION shall prevail.

1. American Society for Testing and Materials (ASTM):

a. C88 - Standard Test Method for Soundness of Aggregate by use of Sodium Sulfate orMagnesium Sulfate.

b. C127 - Standard Test Method for Density, Relative Density (Specific Gravity) andAbsorption of Course Aggregate

c. C535 - Standard Test Method for Resistance to Degradation of Large Size CoarseAggregate by Abrasion and Impact in the Los Angeles Machine

2. American Association of State Highway and Transportation Officials (AASHTO)

a. T 85 Standard Method of Test for Specific Gravity and Absorption of Coarse Aggregate

b. T 120 Method of Test for Aggregate Durability Index

3. Florida Department of Transportation (FDOT)

a. Standard Specifications for Road and Bridge Construction, latest edition

i. 514 – Standard Specification for Plastic Filter Fabric (Geotextile)

ii. 901 – Standard Specifications for Coarse Aggregate

b. Florida Methods

i. 3-C-535 - Resistance to Degradation of Large-Size Coarse Aggregates by Abrasionand Impact in the Los Angles Machine

ii. 5-538 – Sampling and Testing Rip-Rap Material

1.03 DEFINITIONS: (Not Used)

1.04 SUBMITTALS:

A. Submittals shall be in accordance with SECTION 01300.

B. The CONTRACTOR shall furnish to the DISTRICT, testing certificates from a qualified independenttesting laboratory prior to acceptance of the rock source to verify the conformity to the requirements ofthe Contract Documents.

Page 65: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-2 Revision: 3/3/15

1.05 QUALIFICATIONS: (Not Used)

1.06 RESPONSIBILITIES: (Not Used)

1.07 CERTIFICATIONS:

A. Test Reports: The CONTRACTOR’s riprap supplier shall submit certified test reports prepared by aqualified independent testing laboratory selected and compensated by CONTRACTOR for the testsrequired in Article 2.01 B of this SECTION. The table shown below specifies the minimum number oftests for each Project to establish quality control during the processing of a single 2,500-ton stockpile.

Test Required Number of Tests Test Method

Specific Gravity 2 ASTM C127

Absorption 2 ASTM C127, AASHTO T 85

Soundness 2 ASTM C88

Durability Index 2 AASHTO T 210

L.A. Abrasion 2 FM 3-C 535

Gradation 1 FM 5-538

B. Filter Fabric: The CONTRACTOR shall submit MANUFACTURER’s data for filter fabricdemonstrating compliance with specified material properties, and including MANUFACTURER’srecommendations for storage, handling, installation, and anchoring fabric.

1.08 INSPECTION COORDINATION:

A. The CONTRACTOR shall provide access to the WORK for the DISTRICT as requested forinspection. The CONTRACTOR shall provide the DISTRICT at least 48 hours advance notice of itsintention to begin new WORK activities.

1.09 WARRANTY:

A. The MANUFACTURER shall warrant the MATERIALS and PRODUCTS specified in this SECTIONagainst defective materials and workmanship with the MANUFACTURER’s standard warranty, but forno less than one (1) year from the date of Substantial Completion, and as described in Article 13 ofSection 00700 - General Terms and Conditions.

B. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - MATERIALS

2.01 RIPRAP: The CONTRACTOR shall furnish stone for riprap that is sound, durable and angular in shape. Nomore than 10% of the stone for any gradation shall have an elongation (ratio of greatest dimension to leastdimension) greater than 3:1, and no stone shall have an elongation greater than 4:1. The riprap material shallbe provided by a Florida Department of Transportation (FDOT) certified pit or from onsite excavations andconform to the following additional requirements.

A. Material shall be free from cracks, seams, non- mineralized or other defects that would tend to increaseits deterioration from natural causes. Riprap shall consist of dense, natural rock fragments. Stonesshall be resistant to weathering and to water action; free from overburden, spoil, shale and organicmaterial; and shall meet the gradation requirements below. Shale and stones with shale seams are notacceptable.

Page 66: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-3 Revision: 3/3/15

B. Stone for riprap shall have the following properties:

1. Bulk specific gravity (saturated surface-dry basis) not less than 2.38 when tested by ASTMC127 for gradations A, B, and C, and D.

2. The minimum apparent specific gravity of the stones shall be 2.5 as determined by AASHTOT 85.

3. Absorption of not more than 5.0% when tested by ASTM C127.

4. Soundness: Soundness of stone shall be determined in accordance with ASTM C88, modifiedas specified herein. Weight loss in five (5) cycles shall be not more than 10% when sodiumsulfate is used or 15% when magnesium sulfate is used.

5. Stones shall consist of durable, sound, hard, angular rock meeting the following requirementsfor durability absorption ratio, soundness test, and abrasion test:

Durability Absorption Ratio Acceptability

Greater than 23 Passes

10 to 23 Passes only if Durability Index is 52 or greater

Less than 10 Fails

Durability Index (Coarse)Durability Absorption Ratio = % absorption + 1

6. The durability index and percent absorption shall be determined by AASHTO T 210 andAASHTO T 85, respectively. The minimum apparent specific gravity of the stones shall be 2.5as determined by AASHTO T 85.

7. Stones shall have less than ten (10) percent loss of weight after five (5) cycles, when tested perASTM C88.

8. Stones shall have a wear not greater than 40 percent, when tested per ASTM C535.

9. Stone gradation based on a representative sample of not less than 2.0 cubic yards. Each stone inthe sample shall be individually weighed, and a cumulative plot of percent lighter (by weight)versus stone weight in pounds shall be submitted.

C. The riprap shall be graded as follows:

Type B (12-inch Average Size)

Sieve Size Percent Passingby WeightMaximum Minimum

21” 15” 10014” 12” 5011” 8” 15

D. Control of gradation shall be by visual inspection. The CONTRACTOR shall furnish a sample of theproposed gradation of at least five (5) tons or ten (10) percent of the total riprap weight, whichever isless. If approved, the sample may be incorporated into the finished riprap at a location where it can beused as a frequent reference for judging the gradation of the remainder of riprap. Any difference ofopinion between the DISTRICT and the CONTRACTOR shall be resolved by dumping and checkingthe gradation of two (2) random truckloads of stones. Arranging for and the costs of mechanicalequipment, a sorting site, and labor needed in checking gradation shall be the CONTRACTOR’sresponsibility.

E. The acceptability of the stones will be determined by the DISTRICT prior to placement.

Page 67: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-4 Revision: 3/3/15

2.02 GRANULAR BEDDING: The CONTRACTOR shall place a layer of bedding material beneath the riprapmaterials to the lines and grades shown on the Drawings. Stone for use in granular bedding shall weigh notless than 135 lbs/cf (saturated surface dry – pounds/cubic foot). The material shall be composed of tough,durable particles, shall be reasonably free from thin, flat and elongated pieces, and shall contain neitherorganic matter nor soft, friable particles in quantities considered objectionable by the DISTRICT. Beddingstone shall be placed within the limits shown on the Drawings and shall be reasonably well graded inaccordance with FDOT Section 901. The bedding stone for each type of riprap shall be as follows:

Type of Riprap Bedding Stone

Type B ASTM C33 Size No. 357

2.03 FILTER FABRIC: The CONTRACTOR shall provide a twelve (12) ounce per square yard, non-woven,needle-punched geotextile (filter) fabric conforming to the following properties:

Criteria Minimum Average Roll Value

Permittivity (sec-1)0.7 (<15% passing 200 Seive)

0.2 (>15% to <50% passing 200 Seive)

Minimum Grab Tensile Strength 1.1 kN

Minimum Sewn Strength 0.99 kN

Minimum Puncture Strength 0.4 kN

Minimum Trapezoidal Tear 0.25 kN

UV Resistance 50% in 500 hours

2.04 TEMPORARY RIPRAP: (Not Used)

PART 3 - PERFORMANCE

3.01 FIELD QUALITY CONTROL:

A. The CONTRACTOR shall recombine the riprap stone sample used for gradation analysis, transport tothe Project Site, and place in a location acceptable to the DISTRICT. Field control of riprap gradationwill be by visual comparison of the representative sample to arriving loads. Arriving loads not bearingreasonable similarity to the sample will be rejected.

1. The CONTRACTOR may, at his option, arrange for gradation analysis of rejected loads at theProject Site. Should the analysis indicate the rejected stone meets the requirements of thisSECTION; all reasonable costs for such analysis will be reimbursed to the CONTRACTOR. Inno instance will stone of a coloration or appearance dissimilar to that in the sample be accepted.

3.02 SUBGRADE PREPARATION:

A. Dry Installation: The CONTRACTOR shall prepare the subgrade to the lines, slopes and elevationsindicated on the Drawing. The CONTRACTOR shall clear the subgrade of sticks, stones, debris andother materials that could puncture the overlying filter fabric. The finished subgrade shall not varyfrom design grade by more than two (2) inches at any location.

Page 68: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-5 Revision: 3/3/15

B. Subaqueous Installation: The CONTRACTOR shall excavate the subgrade to the lines and gradesshown on the Drawing. Tolerance shall be plus 0.0 feet to minus 0.5 feet in the Canal invert, and plusor minus 0.5 feet on the Canal banks.

3.03 FILTER FABRIC:

A. . Filter fabric shall be placed only on subgrade approved by the DISTRICT.

B. Overlap adjacent strips of fabric a minimum of twelve (12) inches, and anchor them with securing pinsinserted through both strips of fabric along a line through the midpoint of overlap and to the extentnecessary to prevent displacement of the fabric. Securing pins shall be as per the MANUFACTURER’srecommendations. The CONTRACTOR may opt for a six (6) inch stitched overlap.

C. Place the fabric so that the upstream strip of fabric overlaps the downstram strip.

D. The fabric shall be placed on the entire slope, continuous from top to bottom, without any joints orsplices.

E. Do not drop bedding stone or riprap from heights greater than three (3) feet onto the fabric.

3.04 GRANULAR BEDDING: The CONTRACTOR shall place bedding material beneath the riprap, to a nominaldepth of six (6) inches.

A. Bedding material shall be spread uniformly over filter fabric material. Placement shall not commenceuntil the DISTRICT has approved subgrade preparation and filter fabric installation.

B. Placement methods, which segregate the bedding particles, will not be permitted.

C. Compaction of the bedding material will not be required, but material shall be finished to a reasonablyeven surface.

D. Tolerance shall be + three-tenths foot provided this tolerance is not continuous over an area greaterthan 200 square feet when placed in the dry, or greater than 400 square feet when placed subaqueous.

E. The CONTRACTOR shall maintain the bedding material until the riprap is in place.

3.05 RIPRAP: The CONTRACTOR shall proceed placing the riprap upon completion of filter fabric and beddingmaterial (where required) and after receiving approval of the DISTRICT to proceed. The CONTRACTORshall place riprap in accordance with the following.

A. Stone shall be placed in such a manner as to produce a reasonably well-graded mass with the minimumpracticable percentage of voids.

1. Place to full course thickness in one operation in a manner to avoid displacing or puncturingfilter fabric.

a. Stone shall not be dropped from a height greater than three (3) feet above the fabric.

2. Finished riprap shall be free from objectionable pockets of small stones and clusters of largerstones. Hand place or adjust if necessary to secure the desired results, to the satisfaction of theDISTRICT.

B. Surface Tolerances:

1. Dry Installation: The finished stone surface shall not vary from design grade by more thanthree (3) inches at any location, except that any extreme of the tolerance shall not be continuousover an area greater than 100 square feet.

2. Subaqueous Installation: The finished stone surface shall not vary from design grade by morethan plus one foot, minus one-half feet at any location; either extreme of the tolerance shall notbe continuous over an area greater than 225 square feet.

Page 69: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02370-6 Revision: 3/3/15

3.06 MAINTENANCE:

A. The CONTRACTOR shall maintain the riprap until accepted by the DISTRICT. The CONTRACTORshall replace riprap displaced by any cause prior to acceptance.

END OF SECTION

Page 70: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 02401-1 Revision: 3/3/15

SECTION 02401 DEWATERING AND COFFERDAM

PART 1 - GENERAL

1.01 SCOPE:

A. Summary or Work: The CONTRACTOR shall furnish all labor, material and equipment necessary forthe removal of all surface and subsurface waters from excavation areas. The CONTRACTOR mayexcavate the deep pools and channels in the wet. Construction of the culvert structure shall be in thedry. This SECTION includes the construction of a wellpoint system used in conjunction with an openexcavation or cofferdam, temporary cofferdams with steel sheet piling and bracing, or other systems asproposed by the CONTRACTOR. The WORK includes the removal of temporary sheet piling andother temporary features at the completion of the WORK.

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 01530

3. SECTION 02435

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the standards of the organizations listed below in effect at the timeof the advertisement for bids form a part of this specification to the extent referenced. See the variousparagraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. American Society for Testing and Materials (ASTM):

a. A36 - Standard Specification for Carbon Structural Steel

b. A328 - Standard Specification for Steel Sheet Piling

2. Geotechnical Engineering Services, West Indian Manatee Mitigation Feature, Picayune StrandRestoration Project prepared by URS Corporation Southern dated May 2, 2014.

1.03 DEFINITIONS: (Not Used)

1.04 SUBMITTALS: The CONTRACTOR shall make submittals in accordance with SECTION 01300 and thefollowing:

A. The CONTRACTOR shall submit to the DISTRICT a site-specific dewatering plan for regulatoryapproval, which includes qualifications of the design professional(s), the dewatering system andtemporary cofferdam design, dewatering equipment, safety procedures, sequence of construction, andre-watering procedures, prior to the start of any such operations. The dewatering plans shall alsoinclude the items specified in Article 1.06 of this SECTION.

B. Submit certification from a Professional Engineer registered in the State of Florida that the temporarycofferdam has been designed to meet the criteria specified herein.

C. Two (2) sets of signed and sealed prints of the temporary cofferdam system shall be submitted to theDISTRICT.

D. Acquire all permits required to discharge water and protect waterways from turbidity during thedewatering operation.

1.05 QUALIFICATIONS:

A. The CONTRACTOR shall demonstrate a minimum of ten (10) years experience in the construction ofdewatering systems including, but not necessarily limited to, sheet pile, pumping and cofferdams.

B. Qualifications of the dewatering system design engineer must demonstrate a minimum of ten (10)years experience doing similar work as approved by the DISTRICT and be a Professional Engineerregistered in the State of Florida.

Page 71: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 02401-2 Revision: 3/3/15

1.06 RESPONSIBILITIES:

A. This is a performance specification. Except as otherwise specified or indicated, selection ofequipment, materials, and methods shall be CONTRACTOR's responsibility. The dewatering of anyexcavation areas and disposal of all water handled shall be in strict accordance with all local and stategovernment rules and regulations.

B. The CONTRACTOR shall be responsible for the design of the dewatering system including, but notnecessarily limited to, the temporary cofferdam, required pump equipment, temporary shoring, as wellas any miscellaneous temporary structures required.

C. The dewatering plan shall include at a minimum:

1. A site plan of the Project indicating the location of the proposed discharge point(s) with theassociated water quality monitoring locations including background and compliance turbiditymonitoring locations, the location and type of erosion and turbidity control devices, and themethods necessary to ensure that the state water quality standards are met.

2. Calculations for estimating the area of influence of dewatering, depth of dewatering, pumpingrates, duration and volumes, and the proposed method of dewatering must be submitted forreview.

3. A water quality monitoring plan. Based on the Site specific conditions, daily monitoring forother parameters may be required in addition to the daily monitoring for turbidity.

D. Unless otherwise specified, the dewatering systems shall lower the groundwater table to a minimum oftwo (2) feet below the excavation. The dewatering plan shall include installation of a minimum of two(2) groundwater monitoring wells located on opposite sides of the excavation.

E. Volume of water discharged must be reported at each Site. The CONTRACTOR shall submit,calibration data, operating ranges of the pumping equipment, and instrumentation to be used todetermine flows and daily volumes pumped.

F. If it is anticipated that offsite discharges will occur due to construction dewatering activities, theCONTRACTOR must also include documentation that the dewatering activities will meet the criteriacontained in the “Basis of Review for Water Use Permit Applications within the South Florida WaterManagement District” - latest edition, with emphasis on the reasonable assurances requirements for on-site retention of dewatering water in Section 2.5.2.

The CONTRACTOR shall comply with the following conditions of the National Pollutant DischargeEliminating System (NPDES) Generic Permit for the Discharge of Produced Ground Water from anyNon-Contaminated Site Activity.

1. The facility is authorized to discharge produced ground water from any non-contaminated siteactivity which discharges by a point source to surface waters of the State, as defined in Chapter62-620, Florida Administrative Code (F.A.C.), ONLY if the reported values for the parameterslisted in Table 1 do not exceed any of the listed screening values. Before discharge of producedground water can occur from such sites, analytical tests on samples of the proposed untreateddischarge water shall be performed to determine if contamination exists.

2. Minimum reporting requirements for all produced ground water dischargers: The effluent shallbe sampled before the commencement of discharge, again within 30 days after commencementof discharge, and then once every six (6) months for the life of the Project to maintaincontinued coverage under this generic permit. Samples taken in compliance with the provisionsof this generic permit shall be taken prior to actual discharge or mixing with the receivingwaters. The effluent shall be sampled for the parameters listed in Table 1. In addition,equipment and trip blanks will be required and monitoring using an autosampler may berequired.

Page 72: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 02401-3 Revision: 3/3/15

Table 1

Screening Values for Discharges into:Parameter Fresh Waters Coastal WatersTotal Organic Carbon (TOC) 10.0 mg/l 10.0 mg/lpH, standard units 6.0-8.5 6.5-8.5Total Recoverable Mercury 0.012 µg/l 0.025 µg/lTotal Recoverable Cadmium 9.3 µg/l 9.3 µg/lTotal Recoverable Copper 2.9 µg/l 2.9 µg/lTotal Recoverable Lead 0.03 mg/l 5.6 µg/lTotal Recoverable Zinc 86.0 µg/l 86.0 µg/lTotal Recoverable Chromium (Hex.) 11.0 µg/l 50.0 µg/lBenzene 1.0 µg/l 1.0 µg/lNaphthalene 100.0 µg/l 100.0 µg/l

All chemical analyses that are necessary to comply with the monitoring requirements in all applicable permitsmust be performed by a commercial laboratory that is certified to perform the required analyses according tothe approved methods and procedures by the National Environmental Laboratory Accreditation Conference(NELAC). Use of FDEP sampling standard protocols is required, when appropriate.

1.07 CERTIFICATIONS AND TESTING:

A. A Professional Engineer registered in the State of Florida hired by the CONTRACTOR shall inspect,accept, and certify the temporary sheet piling used for dewatering purposes.

1.08 INSPECTION COORDINATION:

A. The CONTRACTOR shall provide access to the WORK for the DISTRICT as requested forinspection. The Contractor shall provide at least 48 hours advance notice of its intention to begin newWORK activities.

1.09 WARRANTY: (Not Used)

PART 2 - PRODUCTS

2.01 PRODUCT REQUIREMENTS:

A. All materials used in the construction of the dewatering facilities shall be selected, furnished andinstalled by the CONTRACTOR in accordance with the design as submitted to the DISTRICT.

2.02 SHEET PILE:

A. The CONTRACTOR shall provide new or used temporary sheet piling for use in the cofferdamconforming to the requirements of ASTM A328.

2.03 STRUCTURAL STEEL:

A. The CONTRACTOR shall provide structural steel for use in the cofferdam conforming to therequirements of ASTM A36.

PART 3 - EXECUTION

3.01 PERFORMANCE: The CONTRACTOR shall furnish and install sheet pile cofferdams in accordance withthe following.

A. The CONTRACTOR shall retain the services of a Professional Engineer registered in the State ofFlorida for the design of the cofferdam system. The walls and bracing shall be designed to withstand,

Page 73: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 02401-4 Revision: 3/3/15

without damage, the maximum water elevations indicated in the Regulation Schedule below(Paragraph 3.05). Bracing will not be allowed to impart loads to the permanent structure. Temporaryconstruction loads to the permanent structure in excess of those imparted during in-situ operatingconditions will not be allowed. It should be noted that the sheet pile wing walls are supported byanchor rods connected to anchor walls, concrete deadmen, pilings, etc., so installation of a cofferdamshall be phased to avoid interfering with these elements or otherwise reducing their load-carryingcapacity.

B. Approximate locations of cofferdam, structural characteristics and embedment depths shall bedetermined by the engineer designing the cofferdam. It should be noted that steel sheet pile cutoffwalls and wing walls are a part of the permanent features to be constructed both within and outside thedewatered areas. If a sheet pile cofferdam is proposed, the CONTRACTOR shall provide a sequenceof construction that complies with the requirement of SECTION 02262 and does not affect theintegrity of the permanent components.

C. The layout and design of the interior and exterior bracing system for the cofferdam shall fullyaccommodate with appropriate factors of safety, all applied loading indicated. Those loadings may beincreased if considered appropriate by the engineer designing the cofferdam.

3.02 DEWATERING:

A. The CONTRACTOR shall provide adequate equipment for removal of storm, subsurface or cofferdamleakage waters, which may accumulate in the cofferdam interior.

B. The CONTRACTOR shall perform all WORK for the water control structure in the cofferdam interiorfree from water. The CONTRACTOR shall furnish, install, maintain, and operate all necessarypumping and other equipment necessary for dewatering the WORK area.

1. All dewatering equipment shall be in first-class condition and shall at all times be maintainedand operated at the efficiency and capacity necessary for maintaining the cofferdam interior freefrom standing water or wet conditions that may prevent proper construction.

C. The CONTRACTOR shall comply with all local, state and federal regulations when disposing of watergenerated by dewatering operations.

3.03 TURBIDITY BARRIER:

A. The CONTRACTOR shall install and maintain suitable turbidity barriers as described in SECTIONs01530 and 02435.

3.04 REMOVAL OF DEWATERING SYSTEM AND COFFERDAMS:

A. The CONTRACTOR shall remove the dewatering system in such a manner as to allow groundwaterand surface water elevations to slowly return to natural elevations without causing erosion or damageto the structure or foundation.

B. The CONTRACTOR shall slowly flood the dewatered area to establish water surface elevationsupstream of water control structure and equal to tailwater downstream of water control structure priorto removal of temporary cofferdams.

C. If a portion of the cofferdam is incorporated into the structure, the CONTRACTOR shall review theDrawings to determine what portion of the sheet pile of the cofferdam that shall be removed.

3.05 REGULATION SCHEDULE:

A. Canal Water Levels:

1. The DISTRICT operates the existing structure to maintain, in as much as practical the followingcanal elevations:

Location Normal Operating Elevation Maximum Operating ElevationFaka Union Canal -0.30 NAVD 2.14 NAVD

Page 74: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 02401-5 Revision: 3/3/15

B. Noise Abatement: The CONTRACTOR shall furnish, install, and maintain throughout the course ofthe WORK, mufflers, noise-control enclosures, or other noise control methods, measures, and featureson and around all dewatering pumps and their drive units such that steady noise emanating from thisequipment does not exceed the permissible sound levels defined in the local County ordinances.

END OF SECTION

Page 75: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02486-1 Revision: 3/3/15

SECTION 02486 GRASSING

PART 1 - GENERAL

1.01 SUMMARY:

A. The WORK covered by this SECTION consists of furnishing all the necessary equipment, materialsand labor associated with the establishment and maintenance of grass in all areas as specified hereinand in the drawings. These include, but are not limited to seeding, mulching and fertilizing newlygrassed areas and maintenance.

1.02 SUBMITTALS:

A. Certificates:

1. Seed and fertilizer shall be certified that they meet requirements of these specifications, statingbotanical name, percentage by weight, percentage of purity, germination, and weed seed foreach grass seed species.

1.03 WARRANTY:

A. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - MATERIALS:

2.01 GRASS SEED:

A. Provide fresh, clean, new crop seed complying with tolerance for purity and germination establishedby Official Seed Analysts of North America and as required below.

B. Seed shall be labeled according to the U.S. Department of Agriculture Federal Seed Act and shall befurnished in containers with tags showing seed mixture, purity, germination, weed content, name ofseller, and date on which seed was tested.

1. Seed Mixtures: Meet the following minimum weight of pure live seed per acre:

Seed Name Pounds Pure Live SeedCoastal Bermuda 41

NOTE: Pure live seed (PLS) is determined by multiplying the % pure seed by the % germination.Therefore, if the pure seed is 80% and the germination is 70% the PLS is .80 X .70 or 56%. At56% it would take 53.5 pounds to equal 30 pounds of PLS.

2. Moldy seed or seed that has been damaged in storage will not be accepted.

3. When seasonal conditions mandate, substitute a winter grass such as rye grass for the brown topmillet.

2.02 FERTILIZER:

A. Commercial fertilizer shall be Ammonium Sulfate (21-0-0-24S) containing 21 percent nitrogen and 24percent sulfur. Fertilizer containing phosphorus is not acceptable.

B. Deliver to site in unopened, labeled bags or containers.

2.03 MULCH:

Page 76: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02486-2 Revision: 3/3/15

A. Vegetative Anti-Erosion Mulch: Seed free, salt hay, rye or oats, or of pangola, peanut, coastalBermuda.

B. Only undeteriorated mulch that can readily be cut into the soil shall be used.

C. Green mulch will not be accepted.

PART 3 - EXECUTION

3.01 SOIL PREPARATION:

A. Any growth, rocks, or other obstructions which might interfere with tilling, seeding, or latermaintenance operations shall be removed and disposed of properly. Remove stones over two (2)inches in any dimension and sticks, roots, rubbish and other extraneous matter.

B. Areas to be seeded are to be graded to a smooth, even surface with loose, uniformly fine texture. Rolland rake, remove ridges and fill depressions, to meet finish grades. Limit fine grading to areas whichcan be planted within immediate future.

C. Moisten prepared areas before planting if soil is dry. Water thoroughly and allow surface to dry beforeplanting.

D. If prepared areas are eroded or otherwise disturbed after fine grading and prior to planting they shall berestored to specified condition prior to planting.

E. Immediately upon completion of construction, grass shall be planted in all disturbed areas and asdesignated in the drawings. Method of planting shall be either hydroseeding or dry seeding.

3.02 FERTILIZING:

A. Apply fertilizer in accordance with MANUFACTURER’s recommendations.

B. Incorporate fertilizer into the soil to a depth of at least two (2) inches by discing, harrowing or raking,except on slopes steeper than two (2) horizontal to one (1) vertical.

3.03 SEEDING:

A. Do not use wet seed or seed that is moldy or otherwise damaged in transit or storage.

B. Do not seed when wind velocity exceeds five (5) miles per hour. Distribute seed evenly over entirearea by sowing equal quantity in two directions at right angles to each other.

C. Sow not less than a rate of 76 pounds of pure live seed per acre.

D. Rake seed lightly into top 1/8-inch of soil, roll lightly, and water with fine spray.

E. Methods of Application:

1. Dry Seeding: Spreader or seeding machine.

3.04 MULCHING:

A. Apply a mulch covering to all seeded areas.

B. Apply vegetative mulch to loose depth of two (2) inches, by means of a mechanical spreader or otherapproved methods.

C. Mulch material shall be cut into the soil so as to produce a loose-mulched thickness of three to fourinches. The use of harrows will not be permitted.

Page 77: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/31/12 02486-3 Revision: 3/3/15

D. Immediately following the application of the mulch, water the seeded area in one watering, insufficient amount to penetrate the seedbed to a minimum depth of two (2) inches. Perform so as not tocause erosion or damage to the seeded surface.

E. Protect seeded areas against hot, dry weather or drying winds by applying mulch not more than 24hours after completion of seeding operations.

3.05 MAINTENANCE:

A. Perform maintenance until eight (8) weeks after all areas have been seeded.

B. Requirements:

1. The CONTRACTOR shall water all newly grassed areas a minimum of once a week untilsatisfactory grass growth is attained.

2. Repair any portion of the seeded surface which becomes gullied or otherwise damaged, or theseeding becomes damaged or destroyed.

3. Replace mulch when washed or blown away.

C. If, at the end of the 8-week maintenance period, a satisfactory stand of grass has not been produced,renovate and reseed the grass or unsatisfactory portions thereof immediately.

3.06 ACCEPTANCE OF GRASSING:

A. When grassing work is substantially completed, including maintenance, the DISTRICT will, uponrequest, make an inspection to determine acceptability.

1. Seeded areas may be inspected for acceptance in parts agreeable to the DISTRICT, providedWORK offered for inspection is complete, including maintenance.

B. Replant rejected WORK and continue specified maintenance until reinspected by the DISTRICT andfound to be acceptable.

1. A satisfactory stand is defined as a grass or section of grass that has:

a. No bare spots larger than three (3) square feet.

b. Not more than five (5) percent of total area with bare spots larger than six (6) inches.

c. Not more than ten (10) percent of total area with bare spots larger than two (2) inchessquare.

2. If the grassing is still unsatisfactory upon inspection of replanted area, the CONTRACTORshall sod those areas that are unacceptable. Acceptance of the sodded areas is dependent uponsatisfactory coverage criteria established in 3.06.B.1 above.

END OF SECTION

Page 78: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02920-1 Revision: 3/3/15

SECTION 02920 SODDING

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall provide all labor, equipment and materials necessary toestablish a stand of grass within the specified areas by furnishing and placing sod, and rolling,fertilizing, watering and maintaining the sodded areas to ensure a healthy stand of grass.

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 01600

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the standards of the organizations listed below in effect at the timeof the advertisement for bids form a part of this specification to the extent referenced. In the case of aconflict between the requirements of this SECTION and those of the listed document, the requirementsof this SECTION shall prevail.

1. Florida Department of Transportation (FDOT)

a. Standard Specifications for Road and Bridge

1.03 SUBMITTALS:

A. Submittals shall be in accordance with SECTION 01300 and the General Terms and Conditions of theContract.

B. Sod certification for grass species and location of sod source.

1.04 QUALITY ASSURANCE:

A. Sod Producer: Company specializing in sod production and harvesting with minimum five (5) years’experience, and certified by the State of Florida.

B. Installer: Company approved by the sod producer.

C. Sod: Minimum age of eighteen (18) months, with root development that will support its own weight,without tearing, when suspended vertically by holding the upper two corners.

D. The DISTRICT reserves the right to test, reject or approve all materials before application.

1.05 REGULATORY REQUIREMENTS:

A. Comply with regulatory agencies for fertilizer.

1.06 DELIVERY, STORAGE, AND HANDLING:

A. Deliver products to Site in accordance with the provisions of SECTION 01600.

B. Store and protect products in accordance with the provisions of SECTION 01600.

C. Deliver sod on pallets. Protect exposed roots from dehydration.

D. Do not deliver more sod than can be laid within 48 hours.

Page 79: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02920-2 Revision: 3/3/15

E. Deliver fertilizer in water proof bags showing weight, chemical analysis, and name ofMANUFACTURER.

F. The CONTRACTOR shall furnish the DISTRICT with the MANUFACTURER’sapplication/installation instruction for all materials received in order that the minimum application rateof materials may be determined.

1.07 MAINTENANCE SERVICE:

A. Maintain sodded areas immediately after placement until grass is well established and exhibits avigorous growing condition.

1.08 WARRANTY:

A. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - PRODUCTS

2.01 MATERIALS:

A. Sod:

1. The sod shall be Coastal Bermuda, to closely match existing as directed, with well mattedroots.

2. The sod shall be commercial size rectangular measuring twelve (12) inches by 24 inches orlarger.

3. The sod shall be sufficiently thick to secure a dense stand of live grass, with a minimumthickness of two (2) inches.

4. The sod shall be live, fresh and uninjured at the time of planting.

5. The sod shall have a soil matt of sufficient thickness adhering firmly to the roots to withstandall necessary handling and be reasonably free of weeds and other grasses.

6. The sod shall be planted as soon as possible after being harvested, and shall be shaded andkept moist from the time of harvesting until it is planted.

7. The source of the sod may be inspected for approval by the DISTRICT prior to construction.

B. Topsoil:

1. Excavated from Site and free of weeds.

C. Fertilizer:

1. Commercial fertilizer shall be Ammonium Sulfate (21-0-0-24S) containing 21 percent nitrogenand 24 percent sulfur.

a. Fertilizer containing phosphorus is not acceptable.

D. Water:

1. Clean, fresh, and free of substances or matter which could inhibit vigorous growth of grass.

Page 80: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 12/03/13 02920-3 Revision: 3/3/15

PART 3 - EXECUTION

3.01 SOIL PREPARATION:

A. Any growth, rocks, or other obstructions which might interfere with maintenance operations shall beremoved and disposed of properly. Remove stones over two (2) inches in any dimension and sticks,roots, rubbish and other extraneous matter.

B. Areas to be sodded are to be graded to a smooth, even surface with loose, uniformly fine texture. Rolland rake, remove ridges and fill depressions, to meet finish grades. Limit fine grading to areas whichcan be planted within immediate future.

C. Moisten prepared areas before planting if soil is dry. Water thoroughly and allow surface to dry beforeplanting.

D. If prepared areas are eroded or otherwise disturbed after fine grading and prior to planting they shall berestored to specified condition prior to planting.

E. Immediately upon completion of construction, sod shall be planted in all disturbed areas and asdesignated in the Drawings.

3.02 FERTILIZING:

A. Apply fertilizer in accordance with MANUFACTURER’s instructions.

B. Apply after smooth raking of topsoil and prior to installation of sod.

C. Apply fertilizer no more than 48 hours before laying sod.

D. Mix thoroughly into upper two (2) inches of topsoil.

E. Lightly water to aid the dissipation of fertilizer.

3.03 LAYING SOD:

A. Moisten prepared surface immediately prior to laying sod.

B. Lay sod tight with no open joints visible. Do not overlap. Stagger end joints twelve (12) inchesminimum. Do not stretch or overlap sod pieces.

C. Do not use sod which has been cut for more than 48 hours

D. Peg sod at locations where sod may slide, as directed by the DISTRICT.

E. Roll sod using a lightweight turf roller to provide and true and even surface.

3.04 MAINTENANCE:

A. Water all newly grassed areas at least once a week, at a rate equivalent to ½” to ¾” per week, toprevent grass and soil from drying out.

B. Immediately replace sod in areas which show deterioration or bare spots.

C. The CONTRACTOR shall include in pricing, water and equipment to insure adequate survival of thesod and such maintenance as filling, leveling and repairing of any washed or eroded areas as may benecessary, for one (1) year after Substantial Completion.

END OF SECTION

Page 81: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/22/12 05060-1 Revision: 3/3/15

SECTION 05060 WELDING

PART 1 - GENERAL

1.01 SCOPE: The CONTRACTOR shall provide all labor, equipment, and materials for all shop and field weldingas required by the Drawings and/or Specifications.

1. SECTION 05070

1.02 SHOP DRAWINGS AND ERECTION PROCEDURES:

A. Drawing shall include all shop and erection details, including welds. All welds, both shop and field,shall be indicated by standard welding symbols as noted by American Welding Society (AWS) A2.0.Drawings shall show the size, length and type of each weld.

1.03 STANDARD REFERENCES: The following standard specifications shall apply to the WORK of thisSECTION as indicated:

A. American Welding Society, Structural Welding Code, (AWS)

B. American Institute of Steel Construction Manual for Steel Construction, 9th Edition, (AISC)

C. American Society for Testing and Materials (ASTM)

D. American Welding Society:

1. D1.1 - Code for Welding in Building Construction

2. D1.2 - Structural Welding Code— Aluminum

E. Welding shall be in accordance with American Welding Society Standard Code D1.1 and D1.2.

1.04 WELDERS QUALIFICATIONS: All welders, including tack welders, shall be qualified in accordance withSection 5, Part C of AWS D1.1 and D1.2. The CONTRACTOR shall certify by name, to the DISTRICT, thewelders so qualified including the code and procedures under which the individual qualified.

A. Welders and Welding Operators, shop and field, shall be qualified by an independent laboratory usingtest procedures covered by an independent laboratory using test procedures covered in AWS D1.1 andD1.2, and shall have been employed as a welder using the positions for which he is qualified during theprevious 90 days. The CONTRACTOR shall provide the DISTRICT and the laboratory inspector withthe names of welders to be employed in the shop and field on the WORK, certification of the position,date of the last qualification test and the name of the qualifying laboratory.

1. All welders employed in the shop on the fabrication of the steel work shall be qualified for themost difficult welding position during shop fabrication.

2. All welders employed in the field on the erection of the steel work shall be qualified for themost difficult welding position during field erection.

3. The CONTRACTOR shall require any welder to retake the test, when, in the opinion of theDISTRICT, the WORK of the welder creates a reasonable doubt as to the proficiency of thewelder. Recertification of the welder shall be made to the DISTRICT only after the welder hastaken and passed the specified test. The DISTRICT may require radiographic or ultrasonictesting or may require coupons to be cut from any location in any joint for testing.

4. Should any two radiographic or ultrasonic tests or coupons cut from the work of any weldershow strengths, under tests, less than that of the base metal, it will be considered evidence ofnegligence or incompetence and such welder shall be removed from the WORK.

Page 82: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/22/12 05060-2 Revision: 3/3/15

5. When coupons are removed from any part of a structure, the members cut shall be repaired, atno additional cost to the DISTRICT, in a neat and workmanlike manner with joints of type todevelop the full strength of the members and joints cut, with peening to relieve residual stress.All SECTIONS of welds found defective shall be chipped or cut out to base metal and reweldedbefore proceeding with the WORK.

6. Costs of all qualifications, tests and retests shall be borne by the CONTRACTOR.

1.05 INSPECTION AND TESTING:

A. Shop inspections and tests shall include fit-up, preparation of surfaces and welding.

B. Field inspections and tests shall include fit-up, preparation of surface and welding.

1.06 WARRANTY:

A. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - MATERIALS

2.01 WELD METAL: The chemical and mechanical properties of all deposited weld metal shall be compatible tothe base metal and conform to AWS specifications for electrodes.

2.02 BASE METAL: The parent structural steel shall be a weldable grade with the chemical and mechanicalproperties to produce a sound and serviceable welded joint.

2.03 FABRICATION:

A. Surfaces of joints for welded and bolted connections shall be clean, bright metal.

1. Welded connections will be permitted only where indicated on the drawings. Weldedconstruction shall conform to the AISC and AWS Specifications.

PART 3 - EXECUTION

3.01 WELDING METHODS: Unless otherwise approved by the DISTRICT, welding of steel shall be by anelectric arc welding process and shall conform to AWS, Structural Welding Code, and the applicable sectionsof the AISC.

3.02 WELDING EQUIPMENT: Welding equipment shall be capable of providing the welding required by theDrawings or Specifications herein in accordance with the requirements of joint qualifications in AWS D1.1and D1.2.

3.03 WELDING ELECTRODES:

A. Electrodes and flux used for submerged arc welding shall be of the same manufacture. The flux shallbe free of contamination from dirt, mill scale and foreign material. Fused flux used in welding shallnot be reused. Bare electrodes and flux used in combination shall conform to the requirements of AWSD1.1 and D1.2.

B. Electrodes for manual shielded metal-arc welding shall conform to AWS D1.1 and D1.2.

3.04 QUALIFIED WELDS: Only qualified welded joints shall be permitted in accordance with AWS, StructuralWelding Code, and applicable sections of AISC.

Page 83: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/22/12 05060-3 Revision: 3/3/15

3.05 PAINTING: (Not Used)

END OF SECTION

Page 84: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05521-1 Revision: 3/3/15

SECTION 05521 HANDRAILS, RAILINGS, GRATES AND BOLLARDS

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The WORK of this SECTION shall consist of furnishing all labor, material, andequipment necessary for the installation of handrails, railings, and bollards as shown on the Drawingsand specified herein.

B. Related Work Specified Elsewhere:

1. SECTION 03600

2. SECTION 05060

3. SECTION 05070

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the publications of the organizations listed below in effect at thetime of the advertisement for bids form a part of this specification to the extent referenced. See thevarious paragraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. American Society for Testing and Materials (ASTM)

a. B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

b. B210 - Specification for Aluminum and Aluminum-Alloy Drawn Seamless Tubes

c. B211 - Standard Specification for Aluminum and Aluminum-Alloy Bar, Rod, and Wire

d. B308 - Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural Profiles

e. F593 - Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs

f. F594 - Standard Specification for Stainless Steel Nuts

2. American Welding Society (AWS)

a. D1.1 – Structural Welding Code – Steel

b. D1.2 - Structural Welding Code— Aluminum

3. Florida Fire Prevention Code

1.03 SUBMITTALS:

A. Submit Shop Drawings, signed and sealed by a Professional Engineer registered and active in the Stateof Florida, for all handrails and railings showing materials, configurations, dimensions, accessories,anchorage, etc.

1.04 WARRANTY:

A. The MANUFACTURER shall warrant the EQUIPMENT, MATERIALS and PRODUCTS specified inthis SECTION against defective materials and workmanship with the MANUFACTURER’s standardwarranty, but for no less than one (1) year from the date of Substantial Completion, and as described inArticle 13 of Section 00700 - General Terms and Conditions.

B. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

Page 85: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05521-2 Revision: 3/3/15

PART 2 - PRODUCTS

2.01 MATERIALS: Comply with the requirements of the indicated specification.

A. Aluminum Sheets and Plates: ASTM B209

B. Aluminum and Aluminum-Alloy Bar, Rod: ASTM B211

C. Aluminum and Aluminum-Alloy Drawn Seamless Tubes: ASTM B210, and B241

D. All bolts, nuts and washers shall be Type 304 stainless steel.

E. All stainless steel bolts, nuts and washers shall comply with ASTM F436, and F593. Install nylonsleeves and washers when used in aluminum structures.

F. All aluminum bolts, nuts and washers shall comply with ASTM F467 and F468.

G. Non-shrink, Nonferrous Grout: SECTION 03600

2.02 FABRICATION:

A. General:

1. Form exposed work true to line and level with accurate angles and surfaces and straight sharpedges. Ease exposed edges to a radius of approximately 1/32 inch, unless otherwise shown.

2. Form bent-metal corners to the smallest radius possible without causing grain separation orotherwise impairing the WORK.

B. Non-welded Connections: When acceptable to the DISTRICT, intermediate post-to-rail connectionsmay be made using internal pipe sleeve locks and Allen screw fasteners. Locking devices that do notproduce flush, smooth, rigid, hairline joints will not be acceptable. Weld other connections.

C. Welded Connections: Cope intersections of rails and posts, weld joints and grind smooth. Butt weldend-to-end joints of railings or use welding connectors, at fabricator's option.

1. At connections to steel supports, weld post directly to steel supports, unless otherwise indicated.

2. Other methods of welding may be used when acceptable to the DISTRICT.

3. Weld corners and seams continuously and in accordance with the recommendations ofAmerican Welding Society (AWS). Grind exposed welds smooth and flush, to match and blendwith adjoining surfaces. Discoloration of finished surfaces will not be acceptable.

4. Form exposed connections with flush, smooth, hairline joints, using concealed fastenerswherever possible. Use exposed fasteners of the type shown, or if not shown, use PhillipsFlathead (countersunk) screws or bolts.

5. Provide for anchorage of the type shown, coordinated with the supporting structure. Fabricateand space anchoring devices as shown and as required to provide adequate support.

D. Brackets, Flanges, and Anchors:

1. Furnish cast metal brackets, flanges, and exposed anchors of the same material and finish assupported rails, unless otherwise indicated.

2. Furnish all fastenings as required for anchorage of railings and grates to metal concrete ormasonry work.

PART 3 - EXECUTION

3.01 INSTALLATION:

Page 86: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05521-3 Revision: 3/3/15

A. Fastening to In-Place Construction: Provide anchorage devices and fasteners where necessary forsecuring handrails and railing items to in-place construction; including, threaded fasteners for metal,concrete and masonry inserts, toggle bolts, through bolts, lag bolts and other connectors as required.Use railing manufacturer's standard method of installation when acceptable to the DISTRICT.

B. Cutting, Fitting and Placement: Perform cutting, drilling and fitting required for installation. Set thework accurately in location, alignment and elevation, plumb, level, true and free of rack, measuredfrom established lines and levels. Fit exposed connections accurately together to form tight hairlinejoints. Weld connections that are not to be left as exposed joints, but cannot be shop-welded becauseof shipping size limitations. Grind joints smooth. Do not weld, cut or abrade the surfaces of units thathave been coated or finished after fabrication, and are intended for field connections. Adjust railingsprior to securing in place to ensure proper matching at butting joints and correct alignment throughouttheir length. Space posts not more than five (5) feet on centers, unless otherwise shown on theDrawings. Plumb posts in each direction.

C. Secure handrails to walls with wall brackets and end fittings. Drill plate portion of the bracket toreceive one bolt, unless otherwise indicated for concealed anchorage. Locate brackets as indicated or,if not indicated, at not more than five (5) feet on center.

D. Bollards:

1. Refer to the Drawings for pipe diameters.

2. Erect bollards plumb and aligned and located as shown on civil drawings, footings as shown onthe Drawings. Fill steel pipes with 3,500 pounds per square inch (psi) concrete and finish topsmooth and convex. Paint and finish as required by the DISTRICT.

END OF SECTION

Page 87: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05550-1 Revision: 3/3/15

SECTION 05550 FABRICATED METALWORK AND CASTINGS

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work:

1. The WORK of this SECTION shall consist of furnishing all labor, materials, and equipmentnecessary for the installation of fabricated metalwork and castings as shown on the Drawingsand specified herein.

B. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 05070

3. SECTION 09900

1.02 GENERAL:

A. Like items of material provided hereunder shall be the end products of one manufacturer in order toachieve standardization for appearance, maintenance, and replacement.

B. See Conditions of the Contract and DIVISION 1, General Requirements, which contain informationand requirements that apply to the WORK specified herein and are mandatory for this Project.

C. Provide the material types where specified on the Drawings.

1.03 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the publications of the organizations listed below in effect at thetime of the advertisement for bids form a part of this specification to the extent referenced. See thevarious paragraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. Aluminum Association – Construction Manual Series

2. American National Standard Institute (ANSI)

a. B1.1 Unified Inch Screw Threads, UN and UNR Thread Form

3. American Society for Testing and Materials (ASTM)

a. A36 – Standard Specification for Carbon Structural Steel

b. A53 - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated,Welded and Seamless

c. A123 - Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and SteelProducts

d. A153 – Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

e. A167 - Standard Specification for Stainless and Heat-Resisting Chromium-Nickel SteelPlate, Sheet, and Strip

f. A276 - Standard Specification for Stainless Steel Bars and Shapes

g. A500 - Standard Specification for Cold-Formed Welded and Seamless Carbon SteelStructural Tubing in Rounds and Shapes

h. A554 - Standard Specification for Welded Stainless Steel Mechanical Tubing

Page 88: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05550-2 Revision: 3/3/15

i. A572 - Standard Specification for High-Strength Low-Alloy Columbium-VanadiumStructural Steel

j. A653 - Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-IronAlloy-Coated (Galvannealed) by the Hot-Dip Process

k. A992 – Standard Specification for Structural Steel Shapes

l. A1011 - Standard Specification for Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural,High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, andUltra-High Strength

m. B210 - Specification for Aluminum and Aluminum-Alloy Drawn Seamless Tubes

n. B211 - Specification for Aluminum and Aluminum-Alloy Bar, Rod, and Wire

o. B241/B241M - Specification for Aluminum and Aluminum-Alloy Seamless Pipe andSeamless Extruded Tube

p. B308 – Standard Specification for Aluminum Alloy 6061 T6 Standard Structural Profile

q. B429/B429M - Specification for Aluminum-Alloy Extruded Structural Pipe and Tub

r. F467 - Nonferrous Nuts for General Use

s. F468 - Nonferrous Bolts, Hex Cap Screws, and Studs for General Use

4. American Institute of Steel Construction (AISC)

a. Steel Construction Manual

5. American Welding Society (AWS)

a. D1.1 - Structural Welding Code - Steel

b. D1.2 – Structural Welding Code – Aluminum

c. D1.6 Structural Welding Code – Stainless Steel

6. Florida Building Code

7. International Code Council (ICC)

8. National Association of Architectural Metal Manufacturers (NAAMM)

1.04 SUBMITTALS: Submittals shall be made in accordance with SECTION 01300, and General Terms &Conditions. In addition, the following specific information shall be provided:

A. Shop Drawings, including calculations where required

B. Test pieces and samples

C. Certificates, test reports, etc.

1.05 WARRANTY:

A. The MANUFACTURER shall warrant the EQUIPMENT, MATERIALS and PRODUCTS specified inthis SECTION against defective materials and workmanship with the MANUFACTURER’s standardwarranty, but for no less than one (1) year from the date of Substantial Completion, and as described inArticle 13 of Section 00700 - General Terms and Conditions.

B. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

Page 89: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05550-3 Revision: 3/3/15

PART 2 - PRODUCTS

2.01 GENERAL:

A. The use of MANUFACTURER’s name and model or catalog number is for the purpose of establishingthe standard of quality and general configuration desired only. Products of other MANUFACTURERswill be considered in accordance with the General Terms & Conditions.

B. Unless otherwise indicated, all materials shall conform to the latest issue of the following ASTMSpecifications:

Item ASTM Specification

Aluminum, Structural Alloy 6061-T6; conform to

Shapes & Plates referenced specifications and ASTMSections found in the AluminumAssociation current ConstructionManual Series

Connection Bolts for Aluminum Use Aluminum 7075-T73 Type 516;

Stainless Steel shall have nylon sleeves and

washers

C. The miscellaneous metalwork and castings indicated on the Drawings, or required to secure the variousparts together and provide a complete installation, shall be included under this SECTION.

2.02 GRATING:

A. Gratings shall be provided with all frames, seat angles, fasteners, and other appropriate accessories asrequired.

B. Fasteners for anchoring grating to beam and channel flanges shall be Universal clip type with 1/4 inchbolts and nuts. Furnish a minimum of four (4) fasteners for each panel, or as required, for propersupport to each panel, unless otherwise noted on the Drawings.

C. Standard installation clearances and tolerances shall conform to the requirements of the current MetalBar Grating Manual published by the National Association of Architectural Metal Manufacturers.

D. Width of any single grating section shall not exceed four (4) feet, unless specified otherwise on theDrawings.

E. Grating shall be of the minimum thickness indicated on the Drawings for the various spans and shallbe designed using a uniform live load of 100 pounds per square foot, unless otherwise noted on theDrawings.

F. Provide angle supports as indicated. Size support angles to provide a minimum of one (1) inch supportfor all main-bearing bars.

G. Main bearing bars shall be serrated, of 3/16 inch thickness unless otherwise specified on the Drawingsand 1-3/16 inch center-to-center, with depth designated as grating thickness on the Drawings. Providewelded 3/16 inch banding for all openings and grating ends. Cross bar spacing shall be a maximum offour (4) inches center-to-center, unless otherwise specified on the Drawings.

2.03 SHOP FABRICATED ITEMS:

A. Fabricated Metalwork:

1. Fabricate true to shape, size and tolerances as indicated and specified on the Drawings.

Page 90: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05550-4 Revision: 3/3/15

2. Dress expose edges and ends of metal smooth, with no sharp edges and with corners slightlyrounded.

3. Provide sufficient quantity and size of anchors for the proper fastening of the WORK.

4. Fabricate details and connection assemblies in accordance with the Drawings, with projectingcorners clipped and filler pieces welded flush.

5. Provide clips, lugs, brackets, straps, plates, bolts, nuts, washers, and similar items, as requiredfor fabrication and erection.

6. Use connections of type and design required by forces to be resisted, and to provide securefastening.

7. Fit work together in fabrication shop and deliver complete, on in parts, ready to be set in place.

8. Provide holes required for the connection of adjacent or adjoining work wherever noted on theDrawings. Locate holes for bolting to supports to a tolerance of +1/16 inch of exact dimensionsindicated on the Drawings.

2.04 LIFTING LUGS:

A. Individual equipment and/or each field disassembling part over 100 pounds in weight shall be providedwith proper lifting lugs for easy handling.

PART 3 - EXECUTION

3.01 GENERAL:

A. Workmanship and finish of all metalwork specified under this SECTION shall be of the highest gradeand equal to the best practice of modern shops for the respective WORK. Exposed surfaces shall havesmooth finish and sharp, well-defined lines. Provide all necessary rabbets, lugs, and brackets so thatthe WORK can be assembled in a neat, substantial manner. Conceal fastenings where practical. Drillmetalwork and countersink holes as required for attaching hardware or other materials. Fabricatemetals as specified. Weld connections, except where bolting is directed. Items requiring specialfabrication methods are mentioned herein. Fabrication of all other items shall be of equal quality.Methods of fabrication not otherwise specified or shown shall be adequate for the stresses and asdirected by the DISTRICT.

B. Grind all exposed edges of welds smooth on walkways, guardrails, handrails, stairways, channel doorframes, steel column bases, and where indicated on the Drawings. All sharp edges shall be rounded toa 1/8 inch minimum radius; all burrs, jagged edges, and surface defects shall be ground smooth.

C. Welds and adjacent areas shall be prepared such that there is (1) no undercutting or reverse ridges onthe weld bead, (2) no weld spatter on or adjacent to the weld or any other area to be painted, and (3) nosharp peaks or ridges along the weld bead. All embedded pieces of electrode or wire shall be groundflush with the adjacent surface of the weld bead.

3.02 WELDING:

A. The technique of welding employed, appearance, quality of welds made, and the methods of correctingdefective WORK shall conform to codes for Arc and Gas Welding in Building Construction of theAWS and AISC. Surfaces to be welded shall be free from loose scale, rust, grease, paint, and otherforeign materials, except that mill scale that will withstand vigorous brushing may remain. A light filmof linseed oil may likewise be disregarded. No welding shall be done when the temperature of the basemetal is lower than 0 degrees Fahrenheit. Finished members shall be true to line and free from twists.

B. All welding operators shall be qualified in accordance with the requirements of current AWS StandardQualification Procedure, and welders of structural and reinforcing steel shall be certified for all

Page 91: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 05/23/13 05550-5 Revision: 3/3/15

positions of welding in accordance with such procedure. A recognized testing laboratory shall runqualification tests at the CONTRACTOR's expense.

C. All welding operators shall be subject to examination for requalification using the equipment,materials, and electrodes employed in the execution of the Contract WORK. Such requalification, ifordered by the DISTRICT, shall be done at the expense of the CONTRACTOR.

3.03 INSTALLATION OF FABRICATED METALWORK:

A. Install in accordance with the Shop Drawings, the Drawings, and these specifications. Perform fieldwelding and erection WORK by skilled mechanics. Install fabricated metalwork plumb or level asapplicable. The complete installations shall, in all cases, be rigid, substantial, and neat in appearance.Erect structural steel in accordance with the applicable portions of AISC Code of Standard Practice,except as modified. Install commercially manufactured products in accordance withMANUFACTURER’s recommendations as approved.

1. Aluminum: Erection of aluminum shall be in accordance with the Aluminum Association. Millmarking shall not be removed from concealed surfaces. Exposed surfaces not otherwise coatedshall have the inked or painted identification marks removed after the material has beeninspected and approved by the DISTRICT.

3.04 ELECTROLYTIC PROTECTION:

A. Where aluminum is in contact with dissimilar metals, or to be embedded in masonry and concrete,protect surfaces in accordance with SECTION 09900 (A-1). Allow paint to dry before installation ofthe materials. Protect painted surfaces during installation; should coating become marred, prepare andtouch up surface per paint MANUFACTURER’s instructions.

3.05 PAINTING:

A. Thoroughly clean all ferrous metal items not galvanized and give a shop coating of metal primer.Preparation of surfaces and application of primer shall be in accordance with the paintMANUFACTURER’s printed directions and recommendations as approved; and in accordance withSECTION 09900, utilizing the appropriate painting system.

3.06 PREPARATION FOR SHIPMENT:

A. Items provided in this SECTION shall be factory assembled to the greatest extent possible. The partsand assemblies that are of necessity shipped unassembled, shall be packaged and clearly tagged in amanner that will protect the materials from damage, and facilitate the identification and final assemblyin the field.

END OF SECTION

Page 92: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-1 Revision: 3/3/15

SECTION 09900 PROTECTIVE COATINGS

PART 1 - GENERAL

1.01 SCOPE:

A. Summary of Work: The CONTRACTOR shall provide coating on exterior and interior surfacesthroughout the Project and which are listed in PART 2, with systems specified on "coating system"sheets at the end of this SECTION.

B. Regulatory Requirements: In addition to requirements specified elsewhere for environmentalprotection, provide coating materials that conform to the restrictions of the local and regionaljurisdiction. Notify the DISTRICT of any coating specified herein that fails to conform to therequirements for the location of the Project or location of application.

1. Lead Content: Use only coatings that are totally lead free.

2. Chromate Content: Do not use coatings containing zinc-chromate or strontium chromate.

3. Asbestos Content: Materials shall not contain asbestos.

4. Mercury Content: Materials shall not contain mercury or mercury compounds.

5. The specified maximum volatile organic compounds (VOC) content shall apply to theunthinned product.

C. Related Work Specified Elsewhere:

1. SECTION 01300

1.02 APPLICABLE STANDARDS AND PUBLICATIONS:

A. Standards or Codes: The edition of the publications of the organizations listed below in effect at thetime of the advertisement for bids form a part of this specification to the extent referenced. See thevarious paragraphs for the specified standard. In the case of a conflict between the requirements of thisSECTION and those of the listed document, the requirements of this SECTION shall prevail.

1. American National Standards Institute (ANSI):

a. A13.1 - Scheme for the Identification of Piping Systems

b. Z535.1 - Safety Colors

2. American Society for Testing and Materials (ASTM):

a. C267 - Standard Test Methods for Chemical Resistance of Mortars, Grouts, andMonolithic Surfacings and Polymer Concretes

b. D3960 - Standard Practice for Determining Volatile Organic Compound (VOC) Contentof Paints and Related Coatings

c. D4258 - Standard Practice for Surface Cleaning Concrete for Coating

d. D4259 - Standard Practice for Abrading Concrete

e. D4260 - Standard Practice for Acid Etching Concrete

f. D4261 - Standard Practice for Surface Cleaning Concrete Unit Masonry for Coating

g. D5201 - Standard Practice for Calculating Formulation Physical Constants of Paints andCoatings

h. E84 - Standard Test Method for Surface Burning Characteristics of Building Materials

3. Society for Protective Coatings (SSPC) Surface Preparation Specifications:

Page 93: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-2 Revision: 3/3/15

a. SP1 - Solvent Cleaning: Removes oil, grease, soil, drawing and cutting compounds, andother soluble contaminants.

b. SP2 - Hand Tool Cleaning: Removes loose mill scale, loose rust, loose paint and otherloose foreign matter.

c. SP3 - Power Tool Cleaning: Removes loose material. Not intended to remove all scaleor rust.

d. SP5 - White Metal Blast Cleaning: Removes all scale, rust, foreign matter. Leavessurface gray-white uniform metallic color.

e. SP6 - Commercial Blast Cleaning: Two-thirds of each square inch free of all visibleresidues; remainder only light discoloration.

f. SP7 - Brush-Off Blast Cleaning: Removes only loose material, remaining surface tightand abraded to give anchor pattern.

g. SP10 - Near-White Blast Cleaning: At least 95% of each square inch shall be free of allvisible residues.

h. SP11 - Power Tool Cleaning to Bare Metal

4. International Concrete Repair Institute (ICRI)

a. Guideline #03732: Surface preparation should comply with ICRI technical guidelinenumber 03732 (selecting and specifying concrete surface preparation for sealers, coatingsand polymer overlays).

5. United States Army Corps of Engineers (USACE)

a. CRD-C 48 - Standard Test Method for Water Permeability of Concrete

1.03 DEFINITIONS:

A. Coating systems include surface preparation, prime coat (first coat), finish coats (second and thirdcoats), inspection, cleaning, and touch-up of surfaces and equipment. Shop preparation, prime coat,and finish coats to be shop-applied may be specified elsewhere or referenced to this SECTION so thata complete system is specified and coordinated.

1. Where surface preparation and first (prime) coat are specified in other SECTIONs to be shop-applied, such as for structural steel, hollow metal doors or equipment, only the touch-up andfinish coats are a part of field painting. Surface preparation is the required degree ofpreparation prior to application of first (prime) coat regardless if done in shop or field.

2. If materials are provided without shop primer such as miscellaneous steel or sheet metal, thensurface preparation, first, second, and third coats are a part of field painting.

3. Concealed surfaces are generally not required to have finish-coats unless otherwise specified,but prime coat should be applied and touched up prior to concealment.

4. Where equipment and materials are provided with shop-applied finished coating system, onlytouch-up is a part of field painting.

5. Refer to applicable SECTIONs to determine whether surface preparation and first coat, orcomplete coating system, is to be shop-applied.

6. The term "DFT" means minimum dry film thickness, with no tolerance for thinner films.

1.04 SUBMITTALS:

A. Submit as specified in SECTION 01300.

B. Submittals include, but are not limited to, the following:

Page 94: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-3 Revision: 3/3/15

1. Schedule of products and paint systems to be used. Schedule shall include the followinginformation:

a. Surfaces for system to be applied

b. Surface preparation method and degree of cleanliness

c. Product MANUFACTURER, name, and number

d. Method of application

e. Dry film thickness per coat of coating to be applied

2. Color charts for selection and acceptance

3. Product information

a. MANUFACTURER's data sheet for each product proposed

b. Technical and performance information that demonstrates compliance with the systemperformance and material requirements

c. MANUFACTURER's instructions and recommendations on surface preparation andapplication

d. Compatibility of shop and field applied coatings (where applicable)

e. Material Safety Data Sheet (MSDS) filled out completely according to the Florida Right-to-Know Law, Chapter 442, Florida Statutes, clearly identifying each product used.

4. Certification signed by coating MANUFACTURERs stating that each coating is suitable forservice intended as stated on each coating system sheet, and that the materials to be installedcomply in all respects with the requirements of this SECTION.

5. The CONTRACTOR shall certify in writing to the DISTRICT that applicators have previouslyapplied all the systems in this SECTION and have the ability and equipment to prepare thesurfaces and apply the coatings correctly.

6. Samples

a. Sample of each paint, finish, and other coating material on 8-1/2 inch by 11-inch sheetmetal. Each sheet shall be completely coated over its entire surface with one coatingmaterial, type, or color.

b. Two (2) sets of color samples that match each color selected by the DISTRICT from theMANUFACTURER's color charts. The color designation shall be shown on the back ofthe color sample.

7. Lead-based paint abatement plan.

1.05 QUALITY ASSURANCE:

A. Applicator Qualifications:

1. Coating WORK shall be performed by an SSPC certified CONTRACTOR having a minimumof Category QP 1 certification for WORK without hazardous paint removal, and Category QP 2certification for WORK involving hazardous paint removal. The certified CONTRACTORshall maintain in effect all required certifications for the duration of the Project. Any requestfor Project delay due to an expired certification will not be considered.

2. The applicator shall be certified in application of specified products and systems on projects ofsimilar size and scope, as demonstrated by previous successful installations, and shall beapproved by the MANUFACTURER in writing.

B. Manufacturer:

Page 95: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-4 Revision: 3/3/15

1. Provide products of MANUFACTURER with no less than ten (10) years experience inmanufacturing the materials for the required WORK.

1.06 RESPONSIBILITIES: (Not Used)

1.07 INSPECTION COORDINATION:

A. Pre-painting Conference:

1. Before field painting starts, representatives for the DISTRICT, CONTRACTOR, coatingapplicator, and coating MANUFACTURER's technical representative shall meet with theDISTRICT's personnel.

2. Agenda for the meeting will include details of surface preparations and coating systems toensure understanding and agreement by all parties for compliance.

B. In the event a problem occurs with coating system, surface preparation, or application, coatingapplicator and coating MANUFACTURER’s technical representative shall promptly investigate theproblem and submit results to the DISTRICT.

C. Whenever water tightness in a water-retaining structure is dependent upon WORK in other sections,the CONTRACTOR shall assume full responsibility for water tightness of the integrated assembly.Prior to starting WORK, CONTRACTOR shall meet with installers involved and withMANUFACTURERs of all materials involved to review Drawings and Specifications to insure thatmaterials are being used properly and details are correct. A written report of this meeting shall besubmitted to the DISTRICT. The report shall contain at least:

1. Meeting date and names and affiliations of those present and written statements from eachinstaller and MANUFACTURER of their acceptance of Drawings, Specifications andconditions, and of proposed use of their materials as proper for purposes shown.

1.08 WARRANTY:

A. The MANUFACTURER shall warrant the EQUIPMENT, MATERIALS, and PRODUCTS specified inthis SECTION against defective materials and workmanship with the MANUFACTURER’s standardwarranty, but for no less than five (5) years from the date of Substantial Completion, and as describedin Article 13 of Section 00700 - General Terms and Conditions. If the MANUFACTURER’s standardwarranty is less than the stipulated period, the MANUFACTURER shall provide a specialMANUFACTURER’s extended warranty for the stipulated period, or a Maintenance Bond, to extendthe MANUFACTURER’s warranty period for the stipulated period.

B. The CONTRACTOR shall warranty the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS:

A. Proprietary names and product numbers are specified in most systems for material identification fromthese MANUFACTURERs.

1. PPG (Pittsburg Plate Glass Co.)2. Carboline Company, Inc.3. BASF Building Systems4. ICI Devoe Coating Company5. The Euclid Chemical Company6. Tnemec Company, Inc.7. Xypex Chemical, Ltd.

Page 96: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-5 Revision: 3/3/15

8. Kryton International9. Sika Corporation10. GML Coatings, LLC11. Wasser Corporation12. Xymax Coatings, Inc.13. Benjamin Moore & Company14. Sherwin-Williams15. PPC Coatings16. International Fire Resistant Systems, Inc.17. Penetron18. Belzona, Inc.19. Alocit & Enviropeel USA

2.02 GENERAL:

A. Materials furnished for each coating system must be compatible with the substrate.

B. Single Manufacturer: All materials in each coating system shall be by the same coatingMANUFACTURER to assure compatibility of coatings.

C. Compatibility: When shop-painted surfaces are to be field coated, the CONTRACTOR shall ascertainwhether finish materials will be compatible with shop coating. Coatings of uncertain compositionshall be removed completely before applying new coatings.

D. Colors:

1. Color of finish coatings shall match accepted color samples.

2. When second and finish coats of a system are of same type, CONTRACTOR shall tint or use aneasy distinguishable alternate color on second coat to enable visual coverage inspection of thethird coat. When first and second coats only are specified and are of same or different types,tint or use an easy distinguishable alternate color on first coat to enable visual coverageinspection of the second coat.

E. Include on label of material containers:

1. MANUFACTURER’s name, product name, and number

2. Type of paint and generic name

3. Color name and number

4. Storage and temperature limits

5. Mixing and application instructions, including requirements for precautions which must betaken

6. Drying, recoat, or curing time

2.03 COATING SYSTEMS: Specified on the "Coating System" sheets at the end of this SECTION.

2.04 SURFACES TO BE COATED:

A. Exterior Surfaces: All exterior surfaces extending one (1) foot above the maximum surface water leveland those that are submerged in fresh water or brackish water shall be provided with the followingadditional protective measures:

Page 97: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-6 Revision: 3/3/15

Generic Description Specific Surfaces System

Steel equipment, prime coated, severeexposure, non-immersion, interior andexterior

1. Carbon steel in fabricated equipment for gatehoists and machinery

S-3

Steel, severe Exposure, Non-Immersion.Exterior or Interior. DTM Acrylic. SafetyYellow.

1. Bollards, guard posts S-7

Exterior wood 1. Sign posts W-2

Aluminum in contact with concrete or anyother metal except galvanized steel

1. Conduits, pipes, and plates A-1

2.05 SURFACES NOT TO BE COATED:

A. Factory finished equipment, except for touch-up or noted otherwise

B. Metal surfaces of stainless steel, bronze, aluminum, and fiberglass, unless otherwise specified.

C. Concrete, unless listed on specific surfaces above

D. Machined surfaces

E. Grease fittings

F. Glass

G. Equipment nameplates

H. Platform gratings, stair treads, door thresholds, and other walking surfaces unless listed on specificsurfaces above

I. Concrete Floors unless listed above

PART 3 - EXECUTION

3.01 DELIVERY, STORAGE, AND HANDLING:

A. Manufacturer Recommendations: Unless this specification requires otherwise, CONTRACTOR shallstrictly follow the MANUFACTURER’s printed recommendations and instructions for storing andhandling coating system materials.

B. Delivery of Materials:

1. Deliver in sealed containers with labels and information legible and intact. Containers shallalso have correct labels with required information.

2. CONTRACTOR shall allow sufficient time for testing, if required.

C. Storage of Materials: CONTRACTOR shall store under conditions recommended by the MaterialSafety Data Sheets:

1. All protective coating materials shall be used within the MANUFACTURER’s recommendedshelf life.

2. Store only acceptable materials on Project Site.

Page 98: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-7 Revision: 3/3/15

3. Store tightly sealed materials off ground and away from moisture, direct sunlight, extreme heat,and freezing temperatures. Provide separate area and suitable containers for storage of coatingsand related coating equipment.

4. Dispose of used or leftover containers, thinners, rags, brushes, and rollers in accordance withapplicable regulations.

3.02 PREPARATION FOR COATING:

A. General: All surfaces to receive protective coatings shall be clean prior to application of coatings. TheCONTRACTOR shall examine all surfaces to be coated, and shall correct all surface defects beforeapplication of any coating material. All marred or abraded spots on shop-primed and on factory-finished surfaces shall receive touch-up restoration prior to any coating application. Surfaces to becoated shall be dry and free of visible dust.

B. Protection of surfaces not to be coated: Surfaces that are not to receive protective coatings shall beprotected during surface preparation, cleaning, and coating operations.

C. Hardware, lighting fixtures, switch plates, machined surfaces, couplings, shafts, bearings, nameplateson machinery, and other surfaces not to be painted shall be removed, masked, or otherwise protected.Drop cloths shall be provided to prevent coating materials from falling on or marring adjacent surfaces.The working parts of mechanical and electrical equipment shall be protected from damage duringsurface preparation and coating operations. Openings in motors shall be masked to prevent entry ofcoating or other materials.

D. Care shall be exercised not to damage adjacent work during blast cleaning operations. Spray paintingshall be conducted under carefully controlled conditions. The CONTRACTOR shall be fullyresponsible for and shall promptly repair any and all damage to adjacent work or adjoining propertyoccurring from blast cleaning or coating operations.

E. Protection of painted surfaces: Cleaning and coating shall be coordinated so that dust and othercontaminants from the cleaning process will not fall on wet, newly coated surfaces.

3.03 SURFACE PREPARATION:

A. General

1. Prepare surfaces for each coating system conforming to SSPC or ASTM surface preparationspecifications listed.

a. If grease or oils are present, SSPC-SP1 must precede any other method specified.

b. Remove surface irregularities such as weld spatter, burrs, or sharp edges, prior tospecified surface preparation.

2. Depth of profile shall be as specified for each system, but in no instance shall it exceed one-third of the total dry-film thickness of complete system.

3. Prepare only those areas which will receive the first coat of the system on the same day.

B. Metals

1. The minimum abrasive blasting surface preparation shall be as indicated in the coating systemsheets included at the end of this Section. Where there is a conflict between these specificationsand the coating MANUFACTURER’s printed recommendations for the intended service, thehigher degree of cleaning shall apply.

2. All sharp edges shall be rounded or chamfered, and all burrs, surface defects, and weld splattershall be ground smooth prior to blast cleaning.

3. The type and size of abrasive shall be selected to produce a surface profile that meets thesystem sheet requirements for the particular coating and service conditions. Abrasives for

Page 99: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-8 Revision: 3/3/15

submerged and severe service coating systems shall be clean, hard, sharp cutting crushed slag.Automated blasting systems shall not be used for surfaces that will be in submerged service.Metal shot or grit shall not be used for surfaces that will be in submerged service, even ifsubsequent abrasive blasting is planned to be one with hard, sharp cutting crushed slag.

4. Abrasive shall not be reused unless an automated blasting system is used for surfaces that willbe in non-submerged service. For automated blasting systems, clean oil-free abrasives shall bemaintained. The abrasive mix shall include at least 50 percent grit.

5. The CONTRACTOR shall comply with the applicable federal, state, and local air pollutioncontrol regulations for blast cleaning.

6. Compressed air for air blast cleaning shall be supplied at adequate pressure from wellmaintained compressors equipped with oil and moisture separators that remove at least 95percent of the contaminants.

7. Surfaces shall be cleaned of all dust and residual particles of the cleaning operation by dry airblast cleaning, vacuuming, or another method prior to painting.

8. Enclosed areas and other areas where dust settling is a problem shall be vacuum cleaned andwiped with a tack cloth.

9. Damaged or defective coating shall be removed by the blast cleaning to meet the clean surfacerequirements before recoating.

10. If the required abrasive blast cleaning will damage adjacent work, the area to be cleaned is lessthan 100 square feet, and the coated surface will not be submerged in service, then SSPC SP2 orSSPC SP3 may be used.

11. Shop applied coatings of unknown composition shall be completely removed before theindicated coatings are applied. Valves, castings, ductile iron pipe, and fabricated pipe orequipment shall be examined for the presence of shop-applied temporary coatings. Temporarycoatings shall be completely removed by solvent cleaning per SSPC SP1 before the abrasiveblast cleaning work is started.

12. Shop primed equipment shall be solvent cleaned in the field before finish coats are applied.

3.04 APPLICATION:

A. CONTRACTOR shall apply coatings in accordance with coating MANUFACTURER’srecommendations. Materials shall be thoroughly stirred, strained, and kept at uniform consistencyduring application. Coatings from different MANUFACTURERs shall not be mixed together.

B. Use properly designed brushes, rollers, and spray equipment for all applications.

C. On unprimed surfaces apply first coat of the system the same day as surface preparation.

D. Cleaned surfaces and all coats shall be inspected prior to each succeeding coat. The CONTRACTORshall schedule such inspection with the DISTRICT in advance.

E. Blast cleaned ferrous metal surfaces shall be painted before any rusting or other deterioration of thesurface occurs. Blast cleaning shall be limited to only those surfaces that can be coated in the sameworking day.

F. Special attention shall be given to edges, angles, weld seams, flanges, nuts and bolts, and other placeswhere insufficient film thicknesses are likely to be present. Use stripe painting for these areas.

G. Dry-film thickness of each system shall be at least as thick as the minimum specified. Maximum dry-film thickness shall not exceed the minimum more than 20% or coating MANUFACTURER’srequirements, whichever is less. Where a dry-film thickness range is specified, the thickness shall notbe shall not be outside the range.

Page 100: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-9 Revision: 3/3/15

H. Shop and field painting shall not be applied within three (3) inches of unprepared surface of anysubstrate such as areas to be welded or bolted.

I. Environmental Conditions:

1. Atmospheric temperature must be 50 degrees Fahrenheit or higher during application, unlessapproved in writing by coating MANUFACTURER. Do not apply coatings when inclementweather or freezing temperature may occur during the curing time interval.

2. Wind velocities for exterior applications shall be at a minimum to prevent overspray or falloutand not greater than coating MANUFACTURER’s limits.

3. Relative humidity must be less than 85% and the temperature of the surface to be painted mustbe at least five (5) degrees above the dew point.

4. Provide adequate ventilation in all areas of application to ensure that at no time does the contentof air exceed the Threshold Limit Value given on the MANUFACTURER’s Material SafetyData Sheets for the specific coatings being applied.

J. Recoat Time: In the event a coating, such as an epoxy, has exceeded its recoat time limit, prepare thepreviously applied coating in accordance with MANUFACTURER’s recommendations.

K. Protection:

1. Cover or otherwise protect surfaces not to be painted. Remove protective materials whenappropriate.

2. Mask, remove, or otherwise protect finish hardware, machined surfaces, grilles, lightingfixtures, and prefinished units as necessary.

3. Provide cover or shields to prevent surface preparation media and coatings from enteringorifices in electrical or mechanical equipment. Where ventilation systems must be kept inoperation at time of surface preparation, take precautions to shield intakes and exhausts toprevent the materials from entering system or being dispersed.

4. Provide signs to indicate fresh paint areas.

5. Provide daily cleanup of both storage and working areas and removal of all paint refuse, trash,rags, and thinners. Dispose of leftover containers, thinners, rags, brushes, and rollers thatcannot be reused in accordance with applicable regulations.

6. Do not remove or paint over equipment data plates, code stamps on piping, or UL fire-ratinglabels.

3.05 INSPECTION:

A. CONTRACTOR shall provide and use a wet-film gauge to check each application approximately everyfifteen (15) minutes in order to immediately correct film thickness under or over that specified.

B. On ferrous surfaces, measurements shall be made with one of the thickness gauges listed below. Thegauge shall be calibrated on metal practically identical in composition and surface preparation to thatbeing coated and be of substantially the same thickness, except that for measurements on metal thickerthan 1/4 inch, the instrument may be calibrated on metal with a minimum thickness of 1/4 inch. Whencalibrating any of the gauges for making film measurements of over three (3) mils, the calibratingthickness standards (shims) shall be of non-metallic composition. Where only one thickness criterionis specified, the calibrating shim thickness shall closely approximate the specified thickness, but whereboth thicknesses are specified, the shim's thickness shall closely approximate an average of the two.Calibrating instructions, thickness standards and, in the case of the Mikrotest gauge, a calibrating tool,should obtained from the MANUFACTURER or supplier of the gauge. Authorized thickness gaugesare:

1. General Electric, Type B, General Electric Company

Page 101: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-10 Revision: 3/3/15

2. Mikrotest, Elektrophysik - Koln

3. Elcometer, Elcometer Instruments, Ltd.

4. Inspector Gage, Elcometer Instruments, Ltd.

5. Minitector, Elcometer Instruments, Ltd.

C. Use holiday or pinhole detector on systems over metal substrates to detect and correct voids whenindicated on system sheet.

D. Furnish a sling psychrometer and perform periodic checks on both relative humidity and temperaturelimits.

E. Check temperature of the substrate at regular intervals to be certain surface is five (5) degreesFahrenheit or more above the dew point.

3.06 CLEANING AND REPAIRS:

A. Remove spilled, dripped, or splattered paint from surfaces.

B. Touch up and restore damaged finishes to original condition. This includes surface preparation andapplication of coatings specified.

END OF SECTION

Page 102: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-11 Revision: 3/3/15

South Florida Water Management District3301 Gun Club Road

West Palm Beach, Florida 33406

PROTECTIVE COATING SYSTEM

System S-3

SERVICE: Equipment, Factory Coated, Severe Exposure, Non-Immersion,Exterior or Interior

Surface Preparation: Field or Shop (if applicable) First Coat: SSPC-SP1 and SP6. Cleanand dry.

First Coat: (Field) Modified vinyl-alkyd or epoxy-mastic, compatible with existing andnew finish. Apply at 1.5 to 2.0 mils dry film thickness.

Second Coat Interior: High build polyamide epoxy with minimum 50% solids by volume.Apply at 5.0 mils dry film thickness.

Second Coat Exterior: High solids aliphatic or acrylic polyurethane gloss enamel withminimum 52% solids by volume. Apply at 2.0 mils dry filmthickness.

System Total: Interior: 6.5 mils dry film thickness in addition to existing coating.Exterior: 3.5 mils dry film thickness in addition to existing coating.Check for voids with holiday or pinhole detector.

Volatile Organic Content: Maximum 3.5 lbs/gal (425 g/l).

COATINGMANUFACTURER

PRODUCT DESIGNATION

PPGCarbolineICI DevoeTnemecSherwin-Williams

FIRST COAT SECOND COAT (INT) SECOND COAT (EXT)Amercoat 385 or 2/400 Same as first coat Amercoat 450HCarbomastic 15 Carboguard 890 Carboline 134 HGBar-Rust 231 Devran 224 HS Devthane 379HOmnithane 1 Hi-Build Epoxoline II N69 Endura-Shield 1074Kem Kromlik Primer Macropoxy 646C Acrolon 218 HS Polyurethane

Page 103: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-12 Revision: 3/3/15

South Florida Water Management District3301 Gun Club Road

West Palm Beach, Florida 33406

PROTECTIVE COATING SYSTEM

System S-7

SERVICE: Steel; Severe Exposure, Non-Immersion. Exterior or Interior. DTMAcrylic. Safety Yellow.

Surface Preparation: SSPC-SP1 and SP6. Clean and dry.

First Coat: Direct to Metal Acrylic Safety Yellow. Apply a minimum of 2.5 milsdry film thickness, or greater as required by MANUFACTURER.

Second Coat: Same as first coat.

Third Coat: Not required.

System Total: 5.0 mils dry film thickness.

Volatile Organic Content: Maximum 2.08 lb per gal (< 250 g/L)

COATING MANUFACTURER PRODUCT DESIGNATION

Benjamin Moore & Co.Sherwin-Williams

FIRST COAT SECOND COATDTM Acrylic Gloss Enamel P28-15 Same as 1st coatB66Y37 DTM Acrylic Gloss Same as 1st coat

Page 104: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-13 Revision: 3/3/15

South Florida Water Management District3301 Gun Club Road

West Palm Beach, Florida 33406

PROTECTIVE COATING SYSTEM

System W-2

SERVICE: Exterior Wood

Surface Preparation: Clean surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits,and sandpaper, as required. Sand surfaces exposed to view smooth and dust off.

a. Scrape and clean small, dry, seasoned knots, and apply a thin coat of white shellacor other recommended knot sealer before applying primer. After priming, fillholes and imperfections in finish surfaces with putty or plastic wood filler. Sandsmooth when dried.

b. Prime, stain, or seal wood to be painted immediately on delivery. Prime edges,ends, faces, undersides, and back sides of wood, including cabinets, counters, andcasework.

c. If transparent finish is required, back-prime with non-yellowing varnish.d. Back-prime paneling on interior partitions where masonry, plaster, or other wet

wall construction occurs on backside.e. Seal tops, bottoms, and cutouts of unprimed wood doors with a heavy coat of

varnish or sealer immediately on delivery.f. Surface must be prepared per paint MANUFACTURER’s recommendations.

First Coat: Exterior Wood Primer: Factory-formulated alkyd wood primer for exterior application:1. Applied at a dry film thickness of not less than 1.3 mils per coat.

Second Coat: Exterior Finish Coats:

1. Exterior Low-Luster Acrylic Paint: Factory-formulated low-sheen (eggshell)acrylic-latex paint for exterior application. (2.3 mils per coat min)

Third Coat: Same as Second Coat.

System Total: 3.6 to 5.0 mils minimum, depending on primer and number of paint coats.

Volatile Organic Content: Maximum 2.72 lbs/gal (326 g/l).

COATINGMANUFACTURER

PRODUCT DESIGNATION

Sherwin-WilliamsFIRST COAT SECOND COATWood Primer: A-100 Exterior Oil, A-100 Exterior Latex Satin,Stain Blocking Primer (Y24W20). (A82 Series)

Page 105: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 07/25/13 09900-14 Revision: 1/23/15

South Florida Water Management District3301 Gun Club Road

West Palm Beach, Florida 33406

PROTECTIVE COATING SYSTEM

System A-1

SERVICE: Aluminum in contact with concrete or any other metal exceptgalvanized steel

Surface Preparation: Field: SSPC-SP1. Clean and dry

First Coat: High solids polyamine or polyamide epoxy with minimum 67 % solidsby volume. Brush apply to surfaces to be in contact at 4.0 mils DFT

Second Coat: Same as first coat

Third Coat: Not required

System Total: Minimum 8 mils DFT

Volatile Organic Content: Maximum 3.5 lbs/gal (425 g/l)

COATINGMANUFACTURER

PRODUCT DESIGNATION

PPGCarbolineICI DevoeTnemecSherwin-WilliamsWasser Corporation

FIRST COAT SECOND COATAmerlock 2/400 Same as first coatCarboguard 890 Same as first coatDevran 224HS Same as first coatHi-Build Epoxoline II N69 Same as first coatMacropoxy 646 FC Expoxy Same as first coatMC-Prepbond 100 Same as first coat

Page 106: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-1 Revision: 3/3/15

SECTION 11415 MANUALLY OPERATED ALUMINUM SLIDE GATES

PART 1 - GENERAL

1.01 SCOPE: This Section includes furnishing and installing self-contained, vertically mounted, manuallyoperated slide gate and accessories. Each gate shall be furnished and installed complete with wall thimble,guide frame and yoke, operating stem and stem nut, floor stand, actuator, and appurtenances as specified orneeded to make a complete and operable installation.

A. Related Work Specified Elsewhere:

1. SECTION 01300

2. SECTION 01600

3. SECTION 05550

4. SECTION 09900

1.02 REFERENCES:

A. Applicable Standards:

1. American Water Works Association (AWWA).

a. C513 - Standard for Open-Channel, Fabricated-Metal Slide Gates and Open-Channel,Fabricated-Metal Weir Gates

b. C540 - Standard for Power-Actuating Devices for Valves and Slide Gates

c. C560-00 – Cast Iron Slide Gates

d. C561-04 – Fabricated Stainless Steel Slide Gates

2. American Society for Testing and Materials:

a. A126 - Gray Iron Castings for Valves, Flanges, and Fittings.

b. A276 Standard Specification for Stainless Steel Bars and Shapes

c. A240 Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate,Sheet, and Strip for Pressure Vessels and for General Applications

d. A582 - Standard Specification for Free-Machining, Stainless and Heat-Resisting SteelBars, Hot-Rolled or Cold-Rolled Finished.

e. A707 - Standard Specification for Forged Carbon and Alloy Steel Flanges for Low-Temperature Service

f. B21 - Standard Specification for Naval Brass Rod, Bar, and Shapes.

g. B209 - Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

h. B211 - Standard Specification for Aluminum and Aluminum-Alloy Bar, Rod, and Wire

i. B308 - Standard Specification for Aluminum-Alloy 6061-T6 Standard Structural Profiles

j. B584 - Standard Specification for Copper Alloys and Castings for General Applications.

k. D707 - Standard Classification System and Basis for Specification for Cellulose AcetateButyrate Molding and Extrusion Compounds

l. D395 Standard Test Methods for Rubber Property—Compression Set

m. D412 Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers—Tension

Page 107: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-2 Revision: 3/3/15

n. D2240 Standard Test Method for Rubber Property—Durometer Hardness

o. D2000 - Standard Classification System for Rubber Products in Automotive Applications

p. D3935 - Standard Specification for Polycarbonate (PC) Unfilled and Reinforced Material

q. D4020 - Standard Specification for Ultra-High-Molecular-Weight Polyethylene Moldingand Extrusion Materials

r. D2000 Standard Classification System for Rubber Products in Automotive Applications

3. Steel Structures Painting Council (SSPC) Surface Preparation Specifications:

a. SP5 - White Metal Blast Cleaning.

1.03 SUBMITTALS:

A. Submit as specified in SECTION 01300.

B. Include, but not limited to, the following:

1. Catalog data and illustrations showing principal parts and materials

2. Spare parts list

3. Assembly, disassembly and repair instructions and procedures

4. Detailed layout dimensions

5. Protective coating system for non stainless steel components

6. Leakage testing procedures

7. Installation, operation, and maintenance manuals

8. Engineering calculations demonstrating compliance with the mechanical and structural criteriaspecified

9. Certification that materials and products furnished comply with the requirements of thisSpecification.

1.04 QUALITY ASSURANCE:

A. MANUFACTURERs shall be experienced in the design and manufacture of equipment and accessoriesfor a minimum period of five (5) years.

1.05 DELIVERY, STORAGE, AND HANDLING:

A. As specified in SECTION 01600, and in accordance with manufacturer's recommendations.

B. Portable operator shall be delivered to the BCB Field Station.

C. Shipment Preparation: Prepare equipment and materials for shipment in a manner to facilitateunloading and handling, and to protect against damage or unnecessary exposure in transit and storage.Include:

1. Crates or other suitable packaging materials

2. Covers and other means to prevent corrosion, moisture damage, mechanical injury andaccumulation of dirt in motors, electrical equipment and machinery

3. Suitable rust-preventive compound on exposed machined surfaces and unpainted iron and steel

4. Grease packing or oil lubrication in all bearings and similar items

D. Marking:

Page 108: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-3 Revision: 3/3/15

1. Tag or mark each item of equipment or material as identified in the delivery schedule or onSubmittals and include complete packing lists and bills of material with each shipment. Eachpiece of every item need not be marked separately provided that all pieces of each item arepacked or bundled together and the packages or bundles are properly tagged and marked.

2. Mark partial deliveries of component parts of equipment to identify the equipment, to permiteasy accumulation of parts, and to facilitate assembly.

1.06 WARRANTY:

A. The MANUFACTURER shall warrant the EQUIPMENT, MATERIALS and PRODUCTS specified inthis SECTION against defective materials and workmanship with the MANUFACTURER’s standardwarranty, but for no less than one (1) year from the date of Substantial Completion, and as described inArticle 13 of Section 00700 - General Terms and Conditions.

B. The CONTRACTOR shall warrant the WORK against defects for one (1) year from the date ofSubstantial Completion and as described in Article 13 of Section 00700 - General Terms andConditions.

PART 2 - PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS:

A. Slide Gates:

1. Fontaine

2. Golden Harvest

3. Hydro Gate

4. Rodney Hunt

5. Whipps, Inc.

6. DISTRICT approved equal

2.02 SLIDE GATES:

A. Design Requirements:

1. Gate size, mounting type, seating and unseating heads, bottom seal elevations, pedestal or yokeelevations, and operator types shall be in accordance with Table 1:

Table 1 – Slide Gates

Design Heads Elevation, (ft. NAVD88)Opening

Size(WxH)

MountingType

Seating(ft)

Unseating(ft)

Bottom seal(Gate Invert)

PedestalFloor

Top of Frame OperatorType

5 x 7

Flat backw/

embeddedbottom seal

5.0 - -6.0 +4.0 +7.5 Manual

The top of yoke elevation shall be determined by the gate manufacturer to allow the operatingnut to be 42 inches above the operating floor for compatibility with a portable operator.

2. Suitable for operation after periods of inactivity of a year or more.

B. Gates will be manually operated. Furnish a removable crank conforming to Section AWWA C501Section 3.14 for each gate. The minimum gate speed shall be 6 inches/minute at 250 rpms.

Page 109: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-4 Revision: 3/3/15

C. Frames:

1. Frames shall be extruded aluminum weighing not less than 4-14 pounds per foot. The frameconfiguration shall be of the flush-bottom type and shall allow the replacement of the top andside seals with removing the gate from the wall. Frames shall be self-contained with yokemounted gate operators as indicated on the Contract Drawings.

a. For yoke mounted gate operators, the structural members shall be designed to provide therequired structural support for the gate operator and the loads produced from the gateoperation under worse case design head conditions (for example: design seating head oneside of gate with no water on unseating side). The structural members or formed plates ofthe yoke shall be sized to limit deflections to 1/300 of its span and resist the followingloads imposed on the yoke, both in raising and lowering the gate, by the gate operator:

i. Two (2) times the rated output thrust of a manual crank type gate actuator with 40-lb effort.

ii. One-and-a-quarter (1.25) times the output thrust of an electric-motor-drivenactuator in the stalled condition.

b. The yoke shall have bolted connections to the frame.

2. Frames shall be furnished with gate stops to limit the opening of the gate. The gate stops shallbe bolted to the frames to allow removal. Stops shall be located to allow the bottom of the gateto clear the top seal opening plus six (6) inches.

3. Furnish a horizontal framing member at top of gate opening. Frame member shall be attached,welded or bolted connection, to the gate frame for mounting of a top seal.

4. Gasket material shall be furnished to seal between the frame and concrete mounting surfaceswhere applicable. For example, flat back or flanged type frames.

D. Slide:

1. Flat structural plate (minimum ¼” thick), reinforced with structural members or formed platesas required to limit its deflection to 1/300 of the gate’s span under the design head conditions.

2. Slide shall be designed to drain when opened above the water level and not trap debris, soil, etc.

E. Seals:

1. Side Seals: Seals shall extend from the bottom seal to the top seal and be retained with backingplates and fasteners, as required. Slide gate MANUFACTURER may incorporate the side sealswith the slide guides. If combined into a single assembly the seal/guide shall meet therequirements of 2.02.E.4 and 2.02.F

2. Bottom seal: Seal shall be incorporated into a structural member or formed plate. Bottom sealarrangement shall be coordinated with frame configuration and type of frame mounting,reference 2.02.C of this SECTION.

3. Top Seal: The top seal shall be attached to the horizontal framing member as described in2.02.C.3. The top seal shall be retained with backing plates and fasteners as required.

4. Seals shall meet specified maximum leakage rates at the design head conditions in both theseating and unseating conditions. Leakage rates shall be field verified by the DISTRICT afterinstallation of the gate/frame assembly under design head conditions.

a. Specified seating head leakage rate: 0.1 gallons per minute (GPM) per linear foot of seal

b. Specified unseating head leakage rate: 0.2 GPM per linear foot of seal

F. Slide Guides:

1. Guides shall run the full length of the frame and prevent metal to metal contact between theslide and the frame.

Page 110: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-5 Revision: 3/3/15

2. The guides shall be designed to accommodate the total thrust produced by water pressure at thedesign head conditions.

3. The guides shall be mechanically interlocked or attached to the frame.

G. Stem, Stem Couplings, and Stem Guides:

1. Stems:

a. The L/r ratio (i.e. Slenderness Ratio) of an unsupported stem shall be less than 200.Furnish stem guides where required to limit the unsupported stem length. Depending onoperator type the stem shall be designed to:

i. Transmit in compression a minimum of two (2) times the rated output thrust of amanual crank type gate actuator with 40-lb effort.

ii. Transmit in compression a minimum of 1.25 times the output thrust of an electricmotor driven actuator in the stalled condition.

b. Stem threads shall be machine cut Acme type. The number of threads per inch andnumber of starts shall be selected by the gate MANUFACTURER to work mostefficiently with the lift mechanism used and the gate speed specified.

c. A stop nut shall be furnished on the stem to limit the downward travel of the gate. Thestop nut shall be fabricated from a single piece matching the stem material, tapped tomatch the stem, and drilled and tapped for a minimum of two 3/8 set screws.

2. The stem shall be connected to the top of the gate with a bolted connection designed towithstand the maximum design forces imposed by the operator under design head conditions.Connection shall be designed with a minimum safety factor of two (2).

3. Stem guides where required to limit stem deflection shall be bronze or polymer bushed. Stemguides shall be factory aligned in self-contained gate frame applications and adjustable in thehorizontal direction for non-self-contained gate frame applications.

4. Furnish a bellows type stem protection boot for the entire length of the exposed stem from thetop of the gate to the underside of the yoke or pedestal as applicable. The stem boot shall bereinforced to minimize contact between the boot and stem. The boot shall be furnished withnon-metallic zipper running the full length of the boot to allow removal without disassembly ofthe gate/stem assembly.

5. Furnish a rigid protective cover for the stem section above the operator.

a. The cover shall be made of clear polycarbonate that will not discolor or become opaquefor at least five (5) years after installation.

b. The cover shall be of sufficient diameter and length to permit full travel of the threadedstem without obstruction.

c. The top of the stem cover shall be closed and vented. The bottom end of the stem covershall be vented, drained, and mounted in a housing or adapter plate for easy field-mounting installation.

d. The stem cover shall have graduations every 100th of a foot with numerical marks everyfoot. It shall be calibrated to read the top of stem at “zero” when gate is closed.

H. Anchor Bolts or Studs:

1. Gate MANUFACTURER shall furnish all anchor bolts and fasteners for the installation of thegate, frame, and operator assembly including but not limited to the following:

a. Gate frames

b. Stem guides

Page 111: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-6 Revision: 3/3/15

c. Operator pedestals

I. Materials:

1. Gate frame, yoke, slide, stem extension: Aluminum 6061-T-6 ASTM B-209, ASTM B-211, orB308

2. Threaded stem, Stem guides, Hard crank: ASTM A276 and A240, Type 304 Stainless Steel

3. Seal backing bars: ASTM A276, Type 304 Stainless Steel

4. Stem: ASTM A276, Type 304

5. Stem Block (stem to gate connection): Bronze, ASTM B584

6. Fasteners and anchor bolts: ASTM F593 and F594 Type 316 Stainless Steel

7. Stem Boot: Nylon reinforced Goretex

8. Gasket material: EDPM

9. Slide Guides: Ultra high molecular weight polyethylene (UHMWPE) meeting the requirementsof ASTM D4020

10. Bottom Seal Material: Resilient neoprene meeting the requirements of ASTM D-2000 grade 2BC-510

11. Seals: Resilient neoprene J-type meeting the requirements of ASTM D2000 grade 2 BC 615 orfabricated from ultra high molecular weight polyethylene (UHMWPE) meeting therequirements of ASTM D4020

12. Stem Cover: Clear polycarbonate meeting the requirements of ASTM D707 and D3935

13. Lift and stop nut: Manganeze bronze , ASTM B584, UNS-C86500

2.03 GATE OPERATORS: Furnish a gate operator as specified below.

A. Manual Operators:

1. Basic Operator:

a. Furnish mounted to the yoke as applicable. The mechanism shall be geared so as topermit slide operation with an effort of not more than 40 lb on the crank handle after theslide is unseated, based on the design head conditions. Gear ratio shall theMANUFACTURER’s minimum available ratio to maximize gate speed while notexceeding the 40 lb maximum force on the crank handle. The crank shall be removableand fitted with a corrosion-resistant rotating handle. The maximum crank radius shall be15 in. A bronze lift nut tapped to fit the stem shall be furnished. Ball or roller bearingsshall be provided above and below the flange on the lift nut to take the thrust developedin opening and closing the gate. Gears shall be machined accurately with cut teeth toprovide smooth, proper operation for the lifting mechanism. Suitable shafts shall beinstalled with sleeve, ball, or roller bearings of appropriate size. Pinion shafts shall bestainless steel. All gears and bearings shall be enclosed in a weatherproof cast ironhousing.. Fittings shall be furnished so that all gears and bearings can be lubricatedperiodically. All geared lifts shall be suitable for operation by use of a portable-motorapparatus. The lift shall be self-locking at any position of the stem travel. The gate speedshall be 6 inches/minute. The piggy back input shall be 250 rpm.

b. Opening direction: The direction of wheel rotation to open the gate shall be indicated onthe lift mechanism.

c. Lubrication: Provide totally enclosed gearing with lubrication fittings and all necessarymechanical seals.

d. Gear Housing: Tenzaloy aluminum alloy.

Page 112: DIVISION 1: GENERAL REQUIREMENTS - D.N. Higginsdnhiggins.com/docs/RFB 695 Addendum 1 Technical Specs.pdfDIVISION 1: GENERAL REQUIREMENTS 01010 Summary of Work 2 01015 Definitions and

Spec. Standard: 08/31/07 11415-7 Revision: 3/3/15

e. Exposed and enclosed machined or gearing surfaces: Coat with water-resistant grease orrust-preventive compound standard of the MANUFACTURER.

f. Coating System: Surfaces shall be factory painted with protective coating System S-3 asspecified in SECTION 09900.

PART 3 - EXECUTION

3.01 SLIDE GATE INSTALLATION: Install slide gates in strict accordance with manufacturer'srecommendations.

3.02 FIELD TOUCH-UP: Field touch-up all coated surfaces to repair damage resulting from shipment andinstallation. Use materials as specified for shop coating.

3.03 TESTING: Operate each gate through one complete open and close cycle, both in the dry and subsequent toflooding of the gate structure interior.

END OF SECTION