District 3 ITS/Operational Improvement Plan

SACOG Regional Planning Partnership

May 22, 2013

ITS/Operational Improvement Plan

Why is this Plan Needed?

1. Develop consistent process for continuous effectiveness

– Investment strategy and portfolio instead of a list

– Produce complementary and collective projects

– Understand and convey value of the projects for prioritization

– More systematic/transparent and less random process

– Whole team knowing the game plan and end game

2. Achieve measurable desired outcomes for mutual benefits

– Achieve benefits every year progressively and accumulatively

2

System Optimization (Game Plan)

• Develop Concept of Operations ConOps will provide a unified direction

for TMS development and operational

improvement program based on

Department’s goals and addressing

regional transportation needs.

Project Overview

3

Project Overview

ITS and Operational Improvement Plan

1. Maintain inventory of ITS/operational improvement projects

2. Concept of Operations congruency

3. Prioritization of the projects

4. Selection recommendation for funding

4

Project Overview

Coordination & CollaborationPlanning

Public Works/

Engineering

PlanningEngineering/

Operations

5

Benefits of ITS & Operational Improvements

Key Classes of Benefits (End Game)

� Increased Safety (preventing accidents)

� Improved Operational Performance (maximizing capacity by improving throughput)

� Enhanced Mobility and Convenience (reducing congestion)

� Improved Environmental Outcomes (reducing fuel consumption and emissions)

� Boosted Productivity and Economic Growth (reducing travel times and fuel costs)

6

Benefits of ITS & Operational Improvements

Make California’s Transportation System More Intelligent (End Game)

� Travelers and Goods Get Where They Need To Go Safely, On Time

� Provide Choice and Control to Travelers

� Provide Necessary Integrated Systems & Tools for System Managers

� Make Best Use of Limited Funds

7

Benefits of ITS & Operational Improvements

Caltrans Vision

(Game Plan)

MTC Director:

“Rather than asphalt lanes that are left

to function on their own, a modern

freeway is one in which performance is

monitored continuously, operation is

adjusted minute by minute, incidents

are cleared quickly, and motorists are

provided up-to-date information before

and during their trips.”

8

Local Jurisdiction 1 – Traffic Signal System

AVL system–Transit Agency

Regional Rail Agency Train Management System–

– Freeway Management SystemCaltrans –

Benefits of ITS & Operational Improvements

Optimization (Game Plan)

• Build Project Inventory (in layers)

PParking Management

–Local Jurisdiction 2 Traffic Signal System– Fu

ture

Fu

lly I

nte

gra

ted

Sys

tem

9

Benefits of ITS & Operational Improvements

Optimization (Game Plan)

• Build Project Inventory (in layers – future focus)

MTC Director:

“Operating the entire transportation

network as a whole, rather than each

system in isolation as is done now, is

the next leap forward in achieving

efficient use and management of our

constrained infrastructure.”

Here now Near future

10

Corridor Example

Optimization (US50 Example)

• Build Inventory from Concept of Operations

• Build Inventory Addressing Issues

Mobility – Safety – Incidents – Traveler Information – Goods Movement

AM Peak Congestion PM Peak Congestion

11

Corridor Example

AM Peak (8AM) Congestion PM Peak (5PM) Congestion

May 2, 2013

May 9, 2013

May 16, 2013

May 2, 2013

May 9, 2013

May 16, 2013

12

Total Cost County Type Project Description

$1,400,000 SAC ITS / IM Fiber Optic - 50 In Sacramento County on Route 50 from PM 0 to PM 5.1

$1,000,000 SAC ITS / IM Upgrade Video Wall at RTMC

$2,500,000 SAC Ops - Auxiliary LaneExtend aux lane on WB Rt-50 from Stockton Blvd off-ramp to the Rt-51 connector on-

ramp. Realign Stockton Blvd on-ramp to WB Rt-50 and add accel taper.

$5,000,000 SAC Ops - Auxiliary Lane Auxiliary Lane: EB and WB, from Sunrise Blvd. to Zinfandel Dr.

$3,000,000 SAC Ops - Transition Lane Transition Lane: NB, Howe Ave. on-ramp to SB Howe Ave. on-ramp.

$3,000,000 SAC Ops - Transition Lane Transition Lane: WB, from Sunrise Blvd. slip off-ramp to Sunrise Blvd. slip on-ramp.

$8,000,000 SAC Ramp Metering Ramp meter improvements on both directions on US 50 from Folsom to Stockton Blvd.

$8,000,000 SAC Ramp MeteringFolsom Blvd bridge widening to two lanes. Loop onramp improvements including ramp

metering.

$1,000,000 ED Arterial ManagementTraffic signal modification - dual left turn from Pioneer Trail and two WB lanes on the

highway, through intersection, then merging prior to Santa Fe Trail/ Apache intersection

$1,000,000 ED Arterial Management Controlled intersection at SR89

$1,000,000 ED Arterial ManagementInstall Adaptive Traffic Signal Control at 19 locations in El Dorado County along US 50

from Pioneer Trail to Stateline Avenue.

$2,784,600 EDTraveler Information (TI)

Incident Management (IM)

El Dorado ITS - Install IM System and TI System including CCTV, BTR, TMS, HAR, TTS, and

RWIS at various locations, and one RMS at Cambridge Rd.

$2,488,200 EDTraveler Information (TI)

Incident Management (IM)

Sierra 50 ITS - Install Incident Management System including TMS, BTR, RWIS, HAR, CMS,

and CCTV at various locations.

Corridor Example

Optimization (US50 Example)

• Build Project InventoryCapital Improvements

ITS/Operational Improvements

Total Cost County Type Project Description

$75,000,000 SAC Widening and HOV Construct HOV lanes and widen freeway - various segments.

$100,000,000+ SACFreeway to Freeway

Interchange Modification

Multiple phase project to reconstruct 1) the Oak Park IC, 2) the W-X portion of Rt-50 and

3) the River Front IC in City of Sacramento. This project would reconstruct freeway-to-

freeway direct connectors and add HOV direct connectors to the Oak Park Interchange.

13

Corridor Example

Optimization (US50 Example)

• Determine Prioritization (and Sequencing)

– Qualitative Assessment

� Congruent with Concept of Operations

� Address issues (high-medium-low)

� Expected desired outcome (high-medium-low)

– Quantitative Assessment

� Valuation (benefit-cost analysis)

– Sequencing

� Address downstream bottlenecks/congestion first

� High benefit versus low cost

14

Selection Priority Benefit-Cost Total Cost County Type Project Description

1 3.5 $8,000,000 SAC Ramp Metering Ramp meter improvements on both directions on US 50 from Folsom to Stockton Blvd.

2 3.4 $2,500,000 SAC Ops - Auxiliary LaneExtend aux lane on WB Rt-50 from Stockton Blvd off-ramp to the Rt-51 connector on-

ramp. Realign Stockton Blvd on-ramp to WB Rt-50 and add accel taper.

3 < 2.0 $8,000,000 SAC Ramp MeteringFolsom Blvd bridge widening to two lanes. Loop onramp improvements including ramp

metering.

4 1.0 $3,000,000 SAC Ops - Transition Lane Transition Lane: NB, Howe Ave. on-ramp to SB Howe Ave. on-ramp.

5 2.0 typical $1,000,000 ED Arterial ManagementTraffic signal modification - dual left turn from Pioneer Trail and two WB lanes on the

highway, through intersection, then merging prior to Santa Fe Trail/ Apache intersection

6 2.0 typical $1,000,000 ED Arterial Management Controlled intersection at SR89

75.0 (TI)

3.0 typ (IM)$2,784,600 ED

Traveler Information (TI)

Incident Management (IM)

El Dorado ITS - Install IM System and TI System including CCTV, BTR, TMS, HAR, TTS, and

RWIS at various locations, and one RMS at Cambridge Rd.

8 1.7 $5,000,000 SAC Ops - Auxiliary Lane Auxiliary Lane: EB and WB, from Sunrise Blvd. to Zinfandel Dr.

9 1.5 $3,000,000 SAC Ops - Transition Lane Transition Lane: WB, from Sunrise Blvd. slip off-ramp to Sunrise Blvd. slip on-ramp.

104.4 (TI)

3.0 typ (IM)$2,488,200 ED

Traveler Information (TI)

Incident Management (IM)

Sierra 50 ITS - Install Incident Management System including TMS, BTR, RWIS, HAR, CMS,

and CCTV at various locations.

11 4.5 typical $1,000,000 ED Arterial ManagementInstall Adaptive Traffic Signal Control at 19 locations in El Dorado County along US 50

from Pioneer Trail to Stateline Avenue.

12 < 1.0 $1,400,000 SAC ITS / IM Fiber Optic - 50 In Sacramento County on Route 50 from PM 0 to PM 5.1

13 < 1.0 $1,000,000 SAC ITS / IM Upgrade Video Wall at RTMC

Corridor Example

Optimization (US50 Example)

• Determine Prioritization (and Sequencing)

Capital Improvements

ITS/Operational Improvements

Selection Priority Benefit-Cost Total Cost County Type Project Description

- < 2.0 $75,000,000 SAC Widening and HOV Construct HOV lanes and widen freeway - various segments.

- < 1.0 $100,000,000+ SACFreeway to Freeway

Interchange Modification

Multiple phase project to reconstruct 1) the Oak Park IC, 2) the W-X portion of Rt-50 and

3) the River Front IC in City of Sacramento. This project would reconstruct freeway-to-

freeway direct connectors and add HOV direct connectors to the Oak Park Interchange.

15

Corridor Example

AM Peak Congestion PM Peak Congestion

5

3

2

5

3

2

Optimization (US50 Example)� Capital Improvements - HOV & ML widening at various segments; Oak Park IC

� ITS/Operational Improvements

1. SAC – Ramp metering from Folsom Blvd to Stockton Blvd

2. SAC – Auxiliary lane from Stockton Blvd to SR51

3. SAC – WB transition lane at Howe Ave IC

4. ED – Controlled SR89 I/S and Pioneer Trail I/S modification

5. SAC – EB/WB auxiliary lane and transition lane between Zinfandel Dr to Sunrise Blvd

6. SAC/ED – traveler information and incident management

16

Project Overview

Why is Project Needed

1. Develop consistent process for continuous effectiveness

– Investment strategy and portfolio instead of a list

– Produce complementary and collective projects

– Understand and convey value of the projects for prioritization

– More systematic/transparent and less random process (cradle to grave)

– Whole team knowing the game plan and end game

2. Achieve measurable desired outcomes for mutual benefits

– Achieve benefits every year progressively and accumulatively

17

Contact

Rupinder JawandaCaltrans Project ManagerCaltrans District 3 Transportation Planning703 B StreetMarysville, CA 95901Office (530) 740-4989Email [email protected]