distributed software development
DESCRIPTION
Distributed Software Development. Customers : Damir Isovic (MDH) and Klas Eriksson (OneDial AB). Alpha prototype: Live TV. What we’ll speak about ?. 1. Project status 2. Project statistics 2. Experiences 3. Alpha Prototype. 1. Project status. 1. Project status. - PowerPoint PPT PresentationTRANSCRIPT
123-04-20
Distributed Software Development
223-04-20
Alpha prototype: Live TV
Customers : Damir Isovic (MDH) and Klas Eriksson (OneDial AB)
323-04-20
What we’ll speak about ?
• 1. Project status
• 2. Project statistics
• 2. Experiences
• 3. Alpha Prototype
1. Project status
423-04-20
1. Project status
523-04-20
• The project status is « almost » on track
• Research done
• Architecture validate by the team– Some modification will appear
2. Project statistics
623-04-20
2. Project statistics - General
723-04-20
2. Project statistics – Working hours
823-04-20
Member W40 W41 W42 W43 Total
Dalibor 12 11 6 11 40
Clément 8 6 3 12 29
Amer 8 5 13 10 36
Nima 1 10 8 9.5 28.5
Neven 8 7 5 4 24
Darko 10.5 12 6 7 35.5
Željko 8 7 5 8 28
Total 55.5 58 46 61.5 221
923-04-20
2. Project statistics - Working hours
• 221 hours on the project
• Almost 8 hours per week per person– Have to grow to 10
• Difference of 60% of work between members– Due to different tasks, different level of
knowledge
1023-04-20
2. Project statistics - Cost
• Base on 40€ per hour
• Difference due to the change of the average per week per person : from 7 to 10
Current Planned Cost 8320 €
Current Actual Cost 8840 €
Planned Project Cost 11200 €
Forecasted Project Cost 11520 €
3. Experiences
1123-04-20
3. Experiences• Underestimate the research part• Not take enough time to estimate properly• Many difficulties to find a solution for the
recording part• Only one project leader now and one
integrator• Good communication• Really good motivation• Good allocation of tasks
1223-04-20
4. Alpha prototype : LiveTv