directional drilling - case history - perco · pdf filedirectional drilling - case history new...

1
DIRECTIONAL DRILLING - CASE HISTORY New Electric Cable Ducts from Perco Perco Engineering Services Ltd The Old Nurseries, Nottingham Road, Radcliffe-on-Trent, Nottingham, NG12 2DU Tel: 0115 933 5000 Fax: 0115 933 4692 Email: [email protected] Web: www.perco.co.uk Perco were contacted to supply, weld & install an overhead and underground cable upgrade and a system reinforcement of an existing supply line in Wrexham, North Wales. The scheme involved: Drilling from within Legacy substation to an adjacent field under a large earth bund that surrounded the substation. Crossing the A5 to North Oswestry. Crossing under Whittington Lane and three 1200mm water supply lines. Each crossing would have three 225mm SDR11 and two 125mm SDR11 ducts installed. Upon a site visit, Perco decided that the best method of installation would be via Horizontal Directional Drilling using their Vermeer D36x50 drill rig as it was compact in size, but still powerful enough to drill through the hard ground conditions. During, the works around the substation, extreme caution had to be taken as it was still live. The rig and the support lorry were kept as far away from the site as possible and a safety watcher was on duty at all times. The ground consisted of soft clay with the occasional boulder being encountered. Roughly 80mtrs of duct was installed during the first crossing which took 3 days with great care being taken to ensure a clean bore. The second crossing provided sandy ground conditions and although the road was on a small embankment, Perco’s settlement calculations showed that one of the bundles of ducts had to be installed at too great a depth. The client agreed that three 225mm and two 125mm would be installed instead. The final crossing proved to be more difficult due to the ground conditions being very hard ground. The ducts had to be installed individually. For more information please contact Chris Brodie on 0115 9335000 or 07866 043382. Scope: Horizontal Directional Drilling Project: Oswestry Substation, Wrexham Sub-Contractor: Perco Engineering Services

Upload: phunganh

Post on 15-Mar-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

DIRECTIONAL DRILLING - CASE HISTORY

New Electric Cable Ducts from Perco

Perco Engineering Services Ltd

The Old Nurseries, Nottingham Road, Radcliffe-on-Trent, Nottingham, NG12 2DU Tel: 0115 933 5000 Fax: 0115 933 4692

Email: [email protected] Web: www.perco.co.uk

Perco were contacted to supply, weld & install an overhead and underground

cable upgrade and a system reinforcement of an existing supply line

in Wrexham, North Wales.

The scheme involved:

Drilling from within Legacy substation

to an adjacent field under a large earth bund that surrounded the

substation.

Crossing the A5 to North Oswestry.

Crossing under Whittington Lane and

three 1200mm water supply lines.

Each crossing would have three 225mm SDR11 and two 125mm SDR11

ducts installed. Upon a site visit, Perco

decided that the best method of installation would be via Horizontal

Directional Drilling using their Vermeer D36x50 drill rig as it was compact in

size, but still powerful enough to drill

through the hard ground conditions.

During, the works around the substation, extreme caution had to be

taken as it was still live. The rig and the support lorry were kept as far away

from the site as possible and a safety

watcher was on duty at all times. The ground consisted of soft clay with the

occasional boulder being encountered. Roughly 80mtrs of duct was installed

during the first crossing which took 3

days with great care being taken to

ensure a clean bore.

The second crossing provided sandy ground conditions and although the

road was on a small embankment,

Perco’s settlement calculations showed that one of the bundles of ducts had to

be installed at too great a depth. The client agreed that three 225mm and

two 125mm would be installed instead.

The final crossing proved to be more

difficult due to the ground conditions being very hard ground. The ducts had

to be installed individually. For more information please contact

Chris Brodie on 0115 9335000 or

07866 043382.

Scope: Horizontal Directional Drilling Project: Oswestry Substation, Wrexham Sub-Contractor: Perco Engineering Services