DIRAC Phase 1 Reporting, Dec. 1 st , 2005 Reporting to the Commission • Periodic Reports • Interim Activity Reports • Project Deliverables • Final Reports

Upload: hugh-black

Post on 19-Jan-2016

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Reporting to the Commission

• Periodic Reports

• Interim Activity Reports

• Project Deliverables

• Final Reports

Page 2: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Reporting to the Commission

• Periodic Reports

• Interim Activity Reports

• Project Deliverables

• Final Reports

Page 3: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic reportsPeriodic Activity Report:

(one per project year)

What is this ? Description of the work performed and comparison with the original plan (=text of the contract).

Who has to do it ? a) Task leadersb) Project managementc) Few information from each partner

When is it due ?In Brussels: 45 days after the end of the rep. period=> We need all input 30 days earlier, i.e. Oct. 15th !

Page 4: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Activity Report

What do we need from you ?

For each task:

a) Objectives and starting point for the work at the beginning of the reporting period

b) Sub-tasks worked on and achievements made

c) Deviations from scheduled plan, reasons for this,corrective actions taken

d) List of deliverables, due date and actual/planned submission date

e) List of milestones, due date and actual/planned submission date

Page 5: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Activity Report: Annex

Plan for using and disseminating the knowledge1) Exploitable knowledge and its Use2) Dissemination of knowledge 3) Publishable results

Who has to do this ? Each partner, or if the partners agree within a task, the task leader.

Relevant for us: Patents (=exploitable results), conferences and publications

Page 6: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic reports

Periodic Management Report:

What is this ? What have we done with the money ?

Who has to do it ? a) Task leadersb) Project managementc) Each partner, together with their administration

When is it due ?In Brussels: 45 days after the end of the rep. period=> We need all input 30 days earlier, at Oct. 15th !!!

Page 7: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management Report

What do we need from you (= each contractor) ? (I)

a) Brief description of work performed for each task you are involved in.

b) Explanatory note on any major cost item, justifying their necessity to the project, e.g.:

Costs for Kicker Magnet: 500 000 Euro. The Magnet is required for the extraction line upgrade, task 17.

Page 8: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (II)

FC contractors: ->

Tabular overview of budgeted and actual costs, per contractor and major cost item

AC contractors

Tabular overview of all resources employed and global estimate of all costs.

This includes personnel !!!

Page 9: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (III)

All: Tabular overview of budgeted and actual person-months, per contractor and task

AC contractors:

In addition, estimate of the number of person-months of permanent staff (unfunded) working on the project.

Page 10: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (IV)

Contractors or task leaders: Short explanation of the impact of deviations from the work plan (see activity report) on the cost budget and person-month budget:

If something does not work out as planned,

– how does it affect costs and person-months?

– how does one want to resolve the situation (e.g. delay of sub-task, additional manpower, etc...)?

Page 11: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management Report

Cost statement

This form will be provided to each contractor !

Page 12: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportCost statement

Page 13: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (V)

Cost statement ("Form C Financial statement per activity for the contractual reporting period"):

Page 14: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management Report

Specific Support Action

means:• There are only two types of activities:

– "Management"– "other"

• All task-related costs are "Other activities"

• Don't mix this with other EU projects !

Page 15: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (still V)

Page 16: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (even still V)

Page 17: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management ReportWhat do we need from you (= each contractor) ? (last of V)

Page 18: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Management Report

Cost summary statement (Summary financial report)

Contains the summary information of the Cost statement

Page 19: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Other Reports Required1. Interim Science and Society reporting questionnaire,

to be completed by the project management (=GSI)

2. Interim socio-economic reporting questionnaire,to be completed by each contractor (=you), VERY easy.

3. Of course, any deliverable ! Cf. Annex 1 of the contract, which task has to deliver what !

Page 20: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Sheets and detailed instructionsare available by two sources:

• at http://www.cordis.lu/fp6/find-doc-management.htm#reporting

• from the project management. [email protected] or [email protected]

• To these two, also all questions regarding management and

reporting should be addressed !

They will provide you with all required electronic forms in due time before the end of the first reporting period.

Thank you for cooperation !

Page 21: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Page 22: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Activity Report: Annex

• 1 Exploitable knowledge and its use

Page 23: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Activity Report: Annex

• 2 Dissemination of knowledge

Page 24: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005

Periodic Activity Report: Annex

• 3 Publishable results

a) Results descriptionb) Possible market applications or how they might be used in further researchc) Stage of developmentd) Collaboration sought of offerede) Collaborator details (which kind of partner is required ?)f) Intellectual property rights granted or publishedg) Contact address

Page 25: DIRAC Phase 1 Reporting, Dec. 1 st, 2005 Reporting to the Commission Periodic Reports Interim Activity Reports Project Deliverables Final Reports

DIRAC Phase 1

Reporting, Dec. 1st, 2005