dewatering methods for foundations

17
Dewatering Methods for FOUNDATIONS Presented By: Ali Javed (2012-MS-CES-01) Mehboob Rasul (2012-MS-CES-06) D E W A T E R I N G M E T H O D S

Upload: umer-farooq

Post on 02-Jan-2016

397 views

Category:

Documents


10 download

DESCRIPTION

Dewatering Methods for FOUNDATIONS By Ali Javed (2012-MS-CES-01)Mehboob Rasul (2012-MS-CES-06)

TRANSCRIPT

Page 1: Dewatering Methods for FOUNDATIONS

Dewatering Methods for

FOUNDATIONS

Presented By:Ali Javed (2012-MS-CES-01)Mehboob Rasul (2012-MS-CES-06)

DEWATERING METHODS

Page 2: Dewatering Methods for FOUNDATIONS

Introduction:

Construction of Footings of buildings, powerhouses, multistory buildings and many other structures requires excavation below the water table into water-bearing soils. Such excavations require lowering the water table below the slopes and bottom of the excavation to prevent raveling or sloughing of the slope and to ensure dry, firm working conditions for construction operations so for this purpose Dewatering is carried out.

DEWATERING METHODS

Page 3: Dewatering Methods for FOUNDATIONS

Purpose of Dewatering:

Construction sites are dewatered for the following purposes: To provide suitable working surface at the

bottom of the excavation. To stabilize the banks of the excavation thus

avoiding the hazards of slides and sloughing. To prevent disturbance of the soil at the

bottom of excavation caused by boils or piping. Such disturbances may reduce the bearing power of the soil.

DEWATERING METHODS

Page 4: Dewatering Methods for FOUNDATIONS

Methods of Dewatering:

Following methods are used for Dewatering:

Sump pumping

Well point systems with suction pumps

Shallow wells with pumps

Deep wells with pumps

Eductor system

Drainage galleries

Electro-osmosis

Other methods

DEWATERING METHODS

Page 5: Dewatering Methods for FOUNDATIONS

1) Sumps & Sump Pumping:

A sump is merely a hole in the ground from which water is being pumped for the purpose of removing water from the adjoining area. They are used up to 8m with ditches leading to them in large excavations.For prolonged pumping the sump should be prepared by first driving sheeting around the sump area and installing a cage inside the sump made of wire mesh with internal strutting or a perforating pipe filling the filter material in the space outside the cage and at the bottom of the cage and withdrawing the sheeting.

DEWATERING METHODS

Page 6: Dewatering Methods for FOUNDATIONS

1) Sumps & Sump Pumping: (Continue) DEWATERING METHODS

Pumping from Sump

Small Sump

Page 7: Dewatering Methods for FOUNDATIONS

2) Well Point Systems: DEWATERING METHODS

A well point is 5.0-7.5 cm diameter metal or plastic pipe 60 cm – 120 cm long which is perforated and covered with a screen. The lower end of the pipe has a driving head with water holes for jetting. Well points are connected to 5.0-7.5 cm diameter pipes known as riser pipes and are inserted into the ground by driving or jetting. The upper ends of the riser pipes lead to a header pipe which, in turn, connected to a pump. The ground water is drawn by the pump into the well points through the header pipe and then discharged.

Page 8: Dewatering Methods for FOUNDATIONS

2) Well Point Systems: (Continue) DEWATERING METHODS

This type of dewatering system is effective in soils constituted primarily of sand fraction.

Well Point Dewatering System

Page 9: Dewatering Methods for FOUNDATIONS

2) Well Point Systems: (Continue) DEWATERING METHODS

The well points can lower a water level to a maximum of 5.5 m below the centerline of the header pipe. In silty fine sands this limit is 3-4 m. Multiple stage system of well points are used for lowering water level to a greater depth. A single well point handles between 4 and 0.6 m3/hr dependingon soil type.

Multi StageWell Points

System

Page 10: Dewatering Methods for FOUNDATIONS

3) Shallow Wells: DEWATERING METHODS

Shallow wells comprise surface pumps which draw water through suction pipes installed in bored wells drilled by the most appropriate well drilling and or bored piling equipment. Its limit is 8 m because these are pre bored. These wells are used in very permeable soils when well pointing would be expensive and often at inconveniently close centers. These can extract large quantities of water.

Page 11: Dewatering Methods for FOUNDATIONS

4) Deep Wells: DEWATERING METHODS

When water has to be extracted from depths greater than 8 m and it is not feasible to lower the type of pump and suction piping used in shallow wells to gain a few extra meters of depth the deep wells are such and submersible pumps installed within them. A cased borehole can be sunk using well drilling or bored piling rigs to a depth lower than the required dewatered level. The diameter will be 150 – 200 mm larger then the well inner casing. These systems are used in gravels to silty fine sands and in water bearing rocks.

Page 12: Dewatering Methods for FOUNDATIONS

4) Deep Wells: (Continue) DEWATERING METHODSTypical Deep Well

Page 13: Dewatering Methods for FOUNDATIONS

5) Eductor System: (Jet Eductor System) DEWATERING METHODS

It is similar to well point system. Instead of employing a vacuum to draw water to the well points, it uses high pressure water, each about 30-40 mm in diameter. A high pressure is supplied through a venturi tube creating a reduction in pressure which draws water through the large diameter pipe. The high pressure main feeds off the return water. Its advantage is that in operating many well points from a single pump station, the water table can be lowered in one stage from depths of 10-45 m. This method becomes economically competitive at depth in soils of low permeability.

Page 14: Dewatering Methods for FOUNDATIONS

6) Drainage Galleries: DEWATERING METHODS

Drainage galleries are used for the removal of large quantities of water for dam abutments, cut-offs, etc. Large quantities of water can be drained into gallery (small diameter tunnel) and disposed of by conventional large – scale pumps

7) Electro Osmosis:

It is used in low permeability soils (silts, silty clays, etc) when no other method is suitable. In this method direct current electricity is applied from anodes (steel rods) to cathodes (well-points, i.e. small diameter filter wells)

Page 15: Dewatering Methods for FOUNDATIONS

8) Other Methods: DEWATERING METHODS

Ground freezing with ammonium brine or liquid nitrogen. It is used for all types of saturated soils.

Slurry trench cut-off walls with bentonite or native clay. It is used for all types of soils.

Impervious soil barrier. Used for all soils. Relatively shallow applications (5-6m max.)

Sheet piling. It is used for all soils except soils with large boulders.

Compressed air. It is used for all types of saturated soils and rock. Its applications is in tunnels, shafts and caissons.

Page 16: Dewatering Methods for FOUNDATIONS

THANK YOU

DEWATERING METHODS

Page 17: Dewatering Methods for FOUNDATIONS

DEWATERING METHODS

References: Quinion, D.W. and Quinion, G.R.(1987), Control of

Groundwater, ICE Works Construction Guides, Thomas Telford Pub.Co., London.

Somerville, S.H.(1986), Control of Groundwater for Temporary Works, CIRIA (Construction Industry Research and Information Association) Report No.113.

Mansur, C.I. and Kaufman, R.I. (1962) Dewatering, in Foundation Engineering Ed.by G.A. Leonards pp.241-350, Mc Graw-Hill Book Co.

Powers, J.P. (1992), Construction Dewatering, 492p., 2nd ed. John Wiley and Sons Inc.

Teng, V.C.(1962) Foundation Design, 466 p., Ch.5, Prentice-Hall, IAC.,Englewood Cliffs, N.J.