D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Final Report
Solid Waste Management
Detail Project Report
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
2
TABLE OF CONTENTS
TABLE OF CONTENTS 2
1 PROJECT BACKGROUND 9
1.1 SOLID WASTE MANAGEMENT 9 1.2 PROBLEMS DUE TO SOLID WASTE 10 1.3 CURRENT STATUS OF SWM IN INDIA 10 1.4 INITIATIVES TO IMPROVE SWM IN INDIA 10 1.5 PROJECT BACKGROUND & OBJECTIVES 14 1.6 SCOPE OF STUDY 14 1.7 REPORT OVERVIEW 16 1.8 WORK DONE IN THIS STUDY 16 1.9 STRUCTURE OF THE REPORT 19
2 TOWN PROFILE 20
2.1 BACKGROUND & HISTORY 20 2.2 PROFILE OF THE TOWN 20 2.3 TOPOGRAPHY AND CLIMATE 21 2.4 POPULATION OF THE TOWN 22 2.5 SLUM POPULATION 24 2.6 POPULATION DENSITY 25 2.7 FLOATING POPULATION 25 2.8 MAJOR TOURIST CENTRE’S 25 2.9 KHANAPUR TOWN PANCHAYATH 26
3 PRESENT SYSTEM OF SOLID WASTE MANAGEMENT 27
3.1 THE PRESENT SCENARIO OF SWM SYSTEM IN KHANAPUR 27 3.2 POPULATION PROJECTION 28 3.3 WASTE GENERATION PROJECTION 29 3.4 WASTE COLLECTION 30 3.5 TRANSPORTATION OF WASTES 32 3.6 STREET SWEEPING 33 3.7 TOOLS USED 34 3.8 PROCESSING AND DISPOSAL OF WASTE 34 3.9 STAFF INVOLVED IN SWM 36 3.10 MUNICIPAL SOLID WASTE COMPOSITION 36 3.11 SEGREGATION OF RECYCLABLES WASTES 38 3.1 PRESENT EXPENDITURE ON SOLID WASTE MANAGEMENT 38
4 ISSUES AND GAPS IN THE PRESENT MANAGEMENT SYSTEM OF MSW 40
4.1 GAPS AND ISSUES IN KHANAPUR 40
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
3
5 POTENTIAL STRATEGIES SUGGESTED FOR MSWM 41
5.1 PROPOSED CONCEPT FOR WASTE MANAGEMENT 41 5.2 PROPOSED WASTE FLOW PROCESSES 45 5.3 STORAGE OF WASTE AT SOURCE 46 5.4 SEGREGATION OF WASTE AT SOURCE 46 5.5 DOOR TO DOOR COLLECTION AND ROUTING PLAN 47 5.6 SLAUGHTERHOUSE WASTE 50 5.7 BIOMEDICAL WASTE 51 5.8 DRY WASTE AND E WASTE COLLECTION CENTRE 51 5.9 CONSTRUCTION AND DEMOLITION WASTE 54 5.10 ZERO WASTE MANAGEMENT 54
6 PROPOSED PROCESSING FACILITY 56
6.1 TECHNOLOGY SELECTION 56 6.2 AEROBIC COMPOSTING 57 6.3 PROCESSING DECOMPOSED GARBAGE 61 6.4 PROPOSED INFRASTRUCTURE AT LANDFILL SITE 61 6.5 DESIGN OF RECOMMENDED PROCESSING AND DISPOSAL OPTIONS 64 6.6 VERMI COMPOSTING 71
7 DESIGN OF LANDFILL 72
7.1 DESIGN AND DEVELOPMENT OF SANITARY LANDFILL FACILITY 72 7.2 BIO REMEDIATION AT PREVIOUS ENGINEERING SITE 72 7.3 MATERIAL SPECIFICATIONS FOR SANITARY LANDFILL 85 7.4 OPERATION PLAN OF SANITARY LANDFILL 87
8 INSTITUTIONAL ASPECTS AND CAPACITY BUILDING 98
8.1 DECENTRALIZATION OF ADMINISTRATION 98 8.2 DELEGATION OF POWERS 99 8.3 WORK NORMS 99 8.4 INDUCTION OF ENVIRONMENTAL/PUBLIC HEALTH ENGINEERS 101 8.5 HUMAN RESOURCE DEVELOPMENT 102 8.6 THE ENTIRE ADMINISTRATION OF SWM DEPARTMENT TO BE UNDER ONE UMBRELLA 104 8.7 INTER DEPARTMENTAL CO-ORDINATION 105 8.8 ENCOURAGEMENT TO NGO’S AND WASTE COLLECTOR CO-OPERATIVES 106 8.9 PUBLIC AWARENESS AND IEC 107
9 SUMMARY OF FINANCIAL REQUIREMENTS 115
9.1 REQUIREMENT OF CAPITAL COST 115 9.2 FUNDING PATTERN 116 9.3 DETAILED BOQ AND ESTIMATES 117
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
4
9.4 REQUIREMENT OF OPERATION AND MAINTENANCE COST 176 9.5 REVENUE FROM SALE OF COMPOST AND USER CHARGES 177 9.6 REVENUE PROPOSED 179 9.7 BREAKUP OF FINANCIAL ASPECT 179
ANNEXURE 1. LEGAL ASPECTS 180
ANNEXURE 2. SOLID WASTE CHEMICAL ANALYSIS 190
ANNEXURE 3. WASTE GENERATION ESTIMATION 191
ANNEXURE 4. SURVEY ANALYSIS 193
ANNEXURE 5. EXISTING AND PROPOSED ROUTE MAP FOR COLLECTION AND TRANSPORT VEHICLES 203
ANNEXURE 6. DESIGNS FOR PROPOSED WASTE PROCESSING FACILITY 204
ANNEXURE 7. MACHINE SPECIFICATIONS AT PROCESSING FACILITY 205
ANNEXURE 8. NORMATIVE STANDARDS FOR MUNICIPAL SOLID WASTE MANAGEMENT 216
ANNEXURE 9. OFFICE MEMORANDUM FOR GOI SHARE 218
ANNEXURE 10. MINIMUM WAGES ACT GOK 2016 219
ANNEXURE 11. QUOTATION 221
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
5
LIST OF TABLES
Table 1-1: Indicative Plans for Municipal Solid Waste Management ...................................... 14
Table 1-2Consultant Team’s Field Visit Details ........................................................................ 17
Table 2-1: Population of Khanapur .......................................................................................... 22
Table 2-2: Ward-wise population ............................................................................................ 24
Table 2-3: Slum Settlements .................................................................................................... 24
Table 3-1: Waste Generation Estimation ................................................................................. 27
Table 3-2: Ward wise Waste Generation ................................................................................. 28
Table 3-3: Population Projections ............................................................................................ 29
Table 3-4: Estimated Solid Waste Generation in Future ......................................................... 30
Table 3-5: Existing Vehicle Details ........................................................................................... 30
Table 3-6: quantification based on no. of trips to the landfill site .......................................... 30
Table 3-7: MSW Transportation Vehicles ................................................................................ 32
Table 3-8Frequency for street sweeping ................................................................................. 33
Table 3-9 Physical composition of waste in Percentage ......................................................... 37
Table 3-10 Chemical Composition of the Waste ..................................................................... 38
Table 5-1: Details of Personal Protective Equipments ............................................................ 49
Table 5-2 Vehicles required for waste collection and transportation ..................................... 50
Table 6-1 Existing and Proposed Civil Structures..................................................................... 58
Table 6-2 Details Of Civil Structures Proposed ........................................................................ 60
Table 6-3 Material Flow ........................................................................................................... 69
Table 6-4: Arrangement and Turning of Windrows ................................................................. 71
Table 7-1: Area at Landfill Site after Bioremediation and Segregation ................................... 73
Table 7-2 Leachate generation ................................................................................................ 83
Table 7-3 Estimation of Leachate Tank .................................................................................... 83
Table 8-1: Training Requirement for Municipal Workers ...................................................... 104
Table 8-2 Activities to be practiced for participation model for implementation of Segregation ............................................................................................................................ 111
Table 8-3 Action Plan for IEC .................................................................................................. 113
Table 9-1 Estimated Capital Expenditure .............................................................................. 116
Table 9-2: Requirement of Manpower .................................................................................. 176
Table 9-3 O&M cost requirement for manpower.................................................................. 176
Table 9-4 O&M Expenditure .................................................................................................. 176
Table 9-5: Proposed user charges .......................................................................................... 177
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
6
LIST OF FIGURES
Figure 2-1 Average rainfall for Belagavi district ....................................................................... 21
Figure 2-2 Average Temperature for Belagavi ......................................................................... 21
Figure 2-3 Population Growth Rate of the Town ..................................................................... 22
Figure 2-4 Ward Wise Map of the Town .................................................................................. 23
Figure 2-5 Organization Structure of the ULB ......................................................................... 26
Figure 3-1 population projection for the ulb ........................................................................... 29
Figure 3-2 Contour Map for SWM site Khanapur .................................................................... 35
Figure 5-1: Two (2) -bin system for dry and wet waste ........................................................... 42
Figure 5-2: Storage of municipal solid waste in public places/parks ....................................... 42
Figure 5-3Proposed Waste flowchart for Khanapur ................................................................ 45
Figure 6-1 Layout Plan for SWM site Khanapur ....................................................................... 59
Table 6-2: Details of Common Facilities proposed at site ....................................................... 60
Figure 6-3 Details of Different Layers in Recharge Pit ............................................................. 63
Figure 6-4: Squeeze test to estimate moisture content .......................................................... 66
Figure 6-5 : SWM Waste Process flow Chart ........................................................................... 70
Figure 7-1: Options for Treatment of Existing MSW Dump on the Site .................................. 73
Figure 7-2: Line Placement at edges of Landfill ....................................................................... 75
Figure 7-3: Line Placement at edges of Landfill ....................................................................... 75
Figure 7-4: Placement of the HDPE Liner over the Clay liner .................................................. 76
Figure 7-5: Placement of the Gravel Drainage Layer and Geotextile over the Clay liner ........ 76
Figure 7-6: Leachate Collection Pipes are to be connected to a sump, through the liner ...... 76
Figure 7-7: Welding of HDPE Geomembrane .......................................................................... 77
Figure 7-8: Welding of Leachate Pipes .................................................................................... 79
Figure 7-9: Support of Leachate Pipes ..................................................................................... 80
Figure 7-10 Phytorid Treatment .............................................................................................. 84
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
7
ABBREVIATIONS ADB Asian Development Bank M Municipality ADP Annual Development Plan M & E Monitoring & Evaluation
AIILSG All India Institute of Local Self Government
M3 Cubic Meter
APL Above Poverty Line MIC Mayor in Council ASI Archaeological Survey of India MIS Municipal Information System ATR Action taken Report MLD Million Liters per Day BOT Built Operate Transfer LCA Lake Conservation Authority BPL Below Poverty Line LIC Life Insurance Corporation CAA Constitutional Amendment Act LPCD Liters per capita per day CBO Community Based Organizations WRD Water Resource Department (GoMP) CDP City Development Plan KSPCB Karnataka State Pollution Control Board CDS Community Development Society MSW Municipal solid Waste CII Confederation of Indian Industries NGO Non Government Organization CMO Chief Municipal Officer NH National Highway
CPHEEO Central Public Health and Environment Engineering Organization
NP Nagar Palika
DCHB District Census Handbook NSDP National Slum Development Policy DDP Draft Development Plan O & M Operation & Maintenance
DFID Department of International Development
OG Outer Growth
DLB Directorate of Local Bodies OHT Over Head Tank DM District Magistrate OSD Open Sewerage Disposal DoE Department of Environment PHED Public health Engineering Department
DoHFW Department of Health and Family Welfare
PPH Persons per Hectare
EPCO Environmental Planning and Coordination Organization
PPP Public Private Partnership
EWS Economically Weaker Sections PRA Participatory Rapid Assessment
GIS Geographical Information System
Planning & Resources on Urban Development Affairs
GoI Government of India PWD Public Work Department GoK Government of Karnataka SADA Special Area Development Authority GSR Ground Structure Reservoir SC Scheduled Caste H&ED Housing and Environment Department SH State Highway
HUDCO Housing and Urban Development Corporation Ltd
ST Scheduled Tribe
INTACH Indian National Trust for Art and Cultural Heritage
SWM Solid Waste Management
JNNURM Jawaharlal Nehru National Urban Renewal Mission
ULB Urban Local Body
KL Kilo liter TCPO Town and Country Planning Organization
KM Kilo Meter UADD Urban Administration and Development Department
LS Lump Sum
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
8
AIILSG TEAM Name Degree / Experience Position Held in AIILSG
Mr. Ashish Deosthali B.E Civil, M.E in Environment Engineer Director General
Dr. Abhijeet Khandage Ph.D. Geology GIS Consultant
Mr. Sushil Sapakale DCE GIS Consultant
Mr. Nikhil Vaiude B.Arch, M.Plan (Environmental Planning) Associate Project Director
Mr. Gajanan Deshpande B.A.M.S, M.Sc. (Habitat Policy and Practice)
Programme Officer
CA Tushar Shah Chartered Accountant Municipal Finance Specialist
Mr. Aniruddha Padale Master of Social Work (MSW), Social Development Expert
Mr. Mandar Antrolikar B.Sc, Diploma in GIS Assistant Director
Mrs. Priya Kapole M.sc Environmental Science Programme Officer
Ms. Sayali B Ghogare B Arch, M-Tech (Town Planning) Programme Officer
Mrs. Monali Kachale B.E Civil Programme Officer
Ms. Anuradha Ambekar B. Sc. Microbiology, PG Diploma in Urban Planning and Development (pursuing)
Programme Officer
Ms. Ranjana Shedage M.A. Geography,
M.Sc.Geoinformatics Programme Officer, GIS
Mr. Gaurav Pawar M.Tech Civil Environment Programme Officer
Mr. Onkar Patil B.E. Environment Programme Officer
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
9
1 Project Background Waste disposal is one of the major problems being faced over the world and India is no
exception. Management of Solid Waste, though an essential service, is given low priority.
This, coupled with lack of financial resources, institutional weaknesses, improper choice of
technology & rapid urbanization, whose ramifications are more pronounced with
uncontrolled growth rate of population, has made this service far from satisfactory, thus
creating serious environmental and health problems.
1.1 Solid Waste Management
Solid Waste Management (SWM) is an organized process of storage, collection,
transportation, processing, and disposal of solid refuse residuals in an engineered sanitary
landfill. It is an integrated process comprising several collection methods, varied
transportation equipment, storage, recovery mechanisms for recyclable material, reduction
of waste volume, and quantity by methods such as composting; refuse derived fuel (RDF),
waste-to-energy, and disposal in a designated engineered sanitary landfill.
The selection of a suitable SWM process is driven by the source and quality of waste
produced. Solid waste is generated from a number of sources which include households
(kitchen and yard), commercial areas (shops, hotels and restaurants), industries (raw
material and packaging), institutions (schools, hospitals and offices), construction and
demolition sites, wild and domesticated animals (carcasses of dead animals, manure), parks
(fallen branches, leaves from trees), and streets (sand, silt, clay, concrete, bricks, asphalt,
residues from air deposition, and dust).
Collection
Transportation
Recovery
Recycling / Disposal
Analysis
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
10
1.2 Problems Due To Solid Waste
Accumulation of solid waste in open areas is an eyesore, diminishing real estate and
property value, a breeding ground for insects, and other vectors (rats and mice, wild and
domesticated animals). It also causes odour nuisance, reflects the unorganized nature of the
community, and creates a poor environment for growing children.
Improper and unorganized disposal of Municipal Solid Waste (MSW) in open areas and
landfills have a negative impact on the living conditions of human beings as well as the
overall environment. It results in spread of communicable and non-communicable diseases
among human beings and animals, thus affecting the welfare, livelihood, and economic
productivity. In addition, it causes contamination of soil, surface water, ground water and
generation of toxic and greenhouse gases. However, using adequate information, resources,
and efficient management practices, one can turn solid waste into a useful resource.
1.3 Current Status of SWM in India
Management of Solid Wastes is of growing concern to the general public at large, local
authorities and business communities in cities and towns across India. The problem is
exacerbating in urban areas due to rapid strides in population growth, coupled with an
economic boom that encourages the consumption of goods and, hence, wastes generation.
As per Census 2011, the urban population accounts for 31.16 percent of the total Indian
population.
The Local Governing Bodies (LGBs), viz. municipalities and municipal corporations, are
responsible for providing SWM services in the urban areas. In most of the urban areas,
insufficient funds, use of obsolete/ inefficient technologies, lack of public
awareness/training, and improper infrastructure have resulted in a state of poor SWM.
1.4 Initiatives to Improve SWM in India
In recent years, the Government of India has taken several initiatives to improve existing
SWM practices in the country. Some of the key initiatives and recommendations are
discussed below:
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
11
1.4.1 Municipal Solid Waste Management Rules
The Ministry of Environment and Forests (MoEF), Government of India, published
“Municipal Solid Waste (Management and Handling) Rules 2016” (MSW Rules 2016). These
rules were developed in conformance with Sections 3, 6 and 25 of the Environment
Protection Act, 1986 and aim at standardization and enforcement of SWM practices in the
urban sector. They dictate that, “Every municipal authority shall, within the territorial area
of the municipality, be responsible for the implementation of the provisions of these rules
and infrastructure development for collection, storage segregation, transportation,
processing and disposal of municipal solid wastes”. In addition, “the CPCB shall coordinate
with State Pollution Control Boards (SPCBs) and Pollution Control Committees (PCCs) in the
matters of MSW disposal and its management and handling”.
1.4.2 Jawaharlal Nehru National Urban Renewal Mission
The Jawaharlal Nehru National Urban Renewal Mission (JNNURM) is a notable initiative
undertaken by Government of India. JNNURM provides funding for urban infrastructure
development in 67 cities and towns of the country. This mission was initiated in 2006 and is
slated to continue until 2011.
1.4.3 Urban Infrastructure Development Scheme for Small and Medium
Towns
The primary objective of this scheme is to improve the urban infrastructure in towns and
cities in a planned manner and to promote public–private partnership (PPP) in infrastructure
development. This scheme was introduced in the year 2005-06 and will continue for seven
years. This scheme is applicable to all cities/towns as per 2001 census, except the
cities/towns covered under the JNNURM. One of the components of this scheme is to renew
the old sewerage and solid waste disposal systems in inner (old) areas.
1.4.4 Swachh Bharat Mission
Swachh Bharat Mission (SBM) was launched on 2nd of October, 2014 with a vision to
achieve a clean India as a tribute to the father of the nation, Mahatma Gandhi, on his 150th
birth anniversary, in 2019. SBM is being implemented by the Ministry of Urban
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
12
Development (M/o UD) and by the Ministry of Drinking Water and Sanitation (M/o DWS) for
urban and rural areas with a given set of guidelines for improved sanitary services and
capacity building initiatives.
Municipal Solid Waste Management (MSWM) a major component of the SBM (urban)-
“refers to a systematic process that comprises of waste segregation and storage at source,
primary collection, secondary storage, transportation, secondary segregation, resource
recovery, processing, treatment, and final disposal of solid waste.”
Under the provisions of SWM, the local bodies are to prepare Detailed Project Reports in
consultation with the state government based on the identified needs of the City Sanitation
Plans. Provision also mentions clustering of smaller cities for attracting Private investment.
The DPRs should be prepared in lines with Govt. of India’s goals outlined in the NUSP 2008,
SWM rules, advisories, CPHEEO manuals (including cost recovery mechanisms), O&M
practices and Service-level Benchmark advisories released by M/o UD and Manual on
Municipal Solid Waste Management, 2016.
States will contribute a minimum of 25% funds for SWM projects to match 75% Central
Share (10% in the case of North East States and special category states). 80% of the urban
population to be covered by SWM services (allowing for a 2% increase year on year)
covering all statutory towns. 1 Central government Grant/ VGF may also be used to promote
projects of waste to energy.
1.4.5 Finance Commission Recommendations
Constituted by the President of India, under Article 280 of the constitution, the Finance
Commission is to recommend on distribution of central tax revenues between the Union
and the States. Supporting Local bodies through grant, subsequent to the passage of the
73rd and 74th constitutional amendments was first time announced in the 10th Finance
Commission for providing basic services at the grassroots level and strengthening
decentralization.
The 13th Finance Commission has recommended two categories of Grants to Local Bodies
namely (1) General Basic Grant and (2) General Performance Grant. The Basic Grants will be
released on furnishing the U.Cs for the last releases and the General Performance Grant will
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
13
be released on fulfilment of nine conditions by the State Government, as stipulated in para
10.16.1 of the report of the 13th Finance Commission by March of a particular financial
year. Performance-related funds under the 13thFinance Commission have been linked to
improvements in SLBs including SWM.
Further, in 2009, MoUD initiated Service Level Benchmarking (SLB) with respect to basic
municipal services including solid waste management. SLB has been introduced in 30 states
and across 1700 ULBs. Performance-related funds under the 13th Finance Commission have
been linked to improvements in SLBs including SWM. The 13th Finance Commission also
recommends that of all grants to be given to the ULBs, 50% should be for SWM (2010-
2015). Moreover, the Ministry of New and Renewable Energy has funded five Waste-to-
Energy plants for utilization of MSW. The grant recommended to ULBs in Andhra Pradesh is
Rs. 1919.20 crores for the XIII FC period of 2010- 2015. Under such grant every local body is
mandated preparing an Annual Development Plan where in the component integrated solid
waste management under PPP mode (excluding purchase of equipment for collection and
transport of garbage) is to be incorporated.
1.4.6 National Green Tribunal Recommendations
CPCB has framed and notified the “Action Plan for Management of Municipal Solid Waste
(MSW)” in compliance with the National Green Tribunal order dated 5th Feb-2015 in the
matter of OA No. 199 of 2014. The Action Plan emphasizes on strengthening the planning
exercise at national, state as well as city level by improvising through the waste
management value chain. In addition to that, The Plan suggested the concept of regional
cluster approach as well as technology options on the basis of quantum of MSW generation
which has been re-produced below in nutshell.
The Regional Cluster approach is based on the concept of discouraging setting up of
individual waste processing and disposal facilities leading to mushrooming of innumerable
facilities which are difficult to monitor and sustain. The approach requires a detailed survey
of the study area and identification of location for regional facility with adequate size of land
free from public objections. An indicative distance of say up to 50 km for each local body
may be feasible based on local condition, fixing of criteria by the local body to transport the
waste for common disposal point without causing public nuisance and traffic hurdles.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
14
However, alternate options can be worked out for smaller local bodies. Common facility
should be ‘integrated’ with facilities for sorting, compost, RDF and energy plant and
followed by inert recycling/re-use. Only a fraction of inert waste should go for land-filling.
The Action Plan has outlined indicative plan based on the quantum of waste generated in
the cluster. The indicative plans have been given for towns in four ranges of waste
generation.
TABLE 1-1: INDICATIVE PLANS FOR MUNICIPAL SOLID WASTE MANAGEMENT
Range Plan
>500 TPD
Modernization/ mechanization of waste storage and transportation facilities Privatization/ contract with ‘operators’ for collection of waste from various sources and its transportation Seeking support of Private entrepreneurship in setting up of waste processing and disposal facility
Between 100-500 TPD
Modernization/ mechanization of waste storage and transportation facilities Privatization/ contract with ‘operators’ for collection of waste from various sources and its transportation Seeking support of Private entrepreneurship in setting up of waste processing and disposal facility
Less than 100 TPD
Proper system for waste collection, storage and transportation considering the local situation Aerobic composting ·Such towns can be the member of Cluster/Regional facility
Less than 50 TPD
Technological solutions which could be managed without high skill operations ·Proper collection of waste and motivating citizens for segregation of waste Composting.
1.5 Project Background & Objectives
There is a need to enhance the existing MSWM system for Town Panchayat (TP) and thus
improve the health and living standards of its residents. The purpose of this project is to
identify the existing MSWM practices within the town, recognize deficiencies/gaps in the
present system and propose a comprehensive plan for MSWM including segregation,
collection, and transportation and regional/cluster approach for processing & scientific
disposal in Integrated Municipal Solid Waste Management Facility in compliance with the
MSW Rules 2016. In addition, analyze options for waste processing for effective and
scientific management of MSW generated.
1.6 Scope of Study
• Realistic assessment of quantity, Characterization and classification of MSW
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
15
• Detailed survey of the prevailing conditions
• Situation/Gap Analysis of the existing condition with respect to MSW Rules, 2016
• Detailed planning for resource requirement & implementation strategy
• Design of MSW management system viz. Collection System (Primary/ Secondary) ,
Transportation & Fleet Management Plan, waste processing system and sanitary
landfill in accordance with MSW Rules 2016& CPHEEO Manual, Govt. of India
• Techno economic and environmental analysis of various options for MSWM
• Preparation of conceptual and detailed drawings
• Preparation of Bill of Quantities (BOQs)
• Capital and Operation & Maintenance (O&M) cost estimates
• Identification and formation of the clusters on the basis of geographical locations
• MSW management model including privatization aspects
• Preparation of Detailed Project Report (DPR)
The deliverables will ultimately achieve the following goals:
• 100% source segregation of wet & dry waste
• Primary collection of waste
• Secondary collection and transportation of waste
• Creating and sustaining a supply chain for recycled waste
• Streamlining and optimization of transportation system
• Analysis for the need of transfer station and its basic design
• Innovative processes and their enforcement for making the habitations litter free,
bin free and dump free to prevent the health hazard.
• Options for processing the biodegradable waste
• Feasibility study for the exploration of waste to power on the basis of cluster
approach
• Options for using the inert material like construction & demolition material
• Reclamation and bio-mining of old dump sites
• Innovative incentive structure to the operating personnel for motivation
• Financial model and institutional framework
• Measures for the involvement of all stakeholders
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
16
• Information, Education and Communication (IEC) campaign models and enforcement
plans
1.7 Report Overview
The Khanapur Town Panchayath (TP) is looking for improving efficiencies in solid waste
management (SWM) practices focusing on improving efficiency of collection, transportation
and processing of the municipal waste generated in the city. This report brings out the
present situation of solid waste management at Khanapur and the proposals to improve the
same.
The project activity aims at
• Establishing effective waste collection mechanism with a view point to collect more
than 85% of the solid waste generated in the municipal area.
• Conducting efficient waste transportation mechanism to be able to carry out 100 %
of the collected waste.
• Processing and recycling of the Municipal Solid Waste.
• Environmental consciousness and job creation for the local youth.
The broad scope of work for the project includes development of technical and
economically viable solid waste management plan along with the design of collection,
transportation, treatment disposal infrastructure. The outline of scope of work for the
overall project includes the following activities.
a. Collection & compilation of data b. Interaction with ULB, local stakeholders and obtaining preliminary information c. Submission of draft DPR d. Presentation of the plans and receiving comments and inputs. e. Submission of final DPR
The structure of the detailed project report has been detailed in the next section.
1.8 Work Done in this Study
To draft the detailed project report for Khanapur, The following sets of activities have been
done by All India Institute of Local Self Government.
1.8.1 Field visits and data collection
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
17
A team of consultants from All India Institute of Local Self Government had visited the city.
The team visited various parts of the city to understand the existing infrastructure and SWM
mechanism in the city. The team interacted with various stakeholders of SWM system.
Following table gives details of the team’s visit in Khanapur.
TABLE 1-2CONSULTANT TEAM’S FIELD VISIT DETAILS Activities Day Visited Activity
Primary data collection
16 - 18 Nov 2015
The expert team from AIILSG visited the TP office and consulted the officers in charge and the primary and secondary data is collected.
Physical character analysis at Land Fill (For 2 Days)
23 - 25 Nov 2015
2 samples are to be analyzed using the quartering technique for understanding the waste character.
Each sample was segregated to take weights of the components in MSW.
Waste quantity analysis (For 2 Days)
23 - 25Nov 2015
Waste Generation for each category of generators is actually weighted for consecutive 3 days and then average rate of waste generation is calculated.
Hiring of an Weigh Bridge at Khanapur for measuring Full and Empty Vehicles carrying waste to dumping location
Vehicle wise Details to be listed in the annexure and total waste generated is to be averaged for current scenario
Commercial Survey
23 - 25 Nov 2015
The team along with sanitary inspectors needs to visit each and every ward and counted the number of different commercial establishments including shops, hotels, education
Institutions, medical centers and etc.
Determining ward wise type of Waste generator.
Street Sweeping Survey
18 - 20 Nov 2015
Categorization of Roads as per there importance during mapping
Demarcating the current Scenario of Street Sweeping on each road
Calculating the length of road allocated to each Sweeper
Finalization of Type A, B, C road on basis of the discussion with sanitary inspector and man power deputation plan for the future.
Open Dumping areas in the city
09 - 10 Nov 2015
Location of Open dumping areas in the city
Topographical Survey
05 - 06 Nov 2015
Topographical Survey Done
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
18
1.8.2 Primary data collection undertaken
Primary data collected for preparation of this report includes the following key features
• Average waste generated by key waste generators in Khanapur, • Physical character of the waste disposed at Khanapur, • Quantity of the waste collected and transported to the landfill • Type of roads swept daily, twice a week and once in a week • Average length of street swept by each SWM staff. • Waste movement mechanism in the city. • Location of secondary bins for waste collection • Approximate estimation of open points in the city. • Survey on commercial establishments of the city in all wards
1.8.3 Secondary Data Collection & Assessment
Secondary data required for the report like existing ward wise population of the city,
weather information, standard average quantity of waste generated per waste generator,
area of the city, total population of city in the past, other reports on SWM were gathered
from various sources. A review of the available documents about Khanapur and the previous
studies on solid waste management systems in Khanapur was done. The gathered data was
compiled as per the requirement of DPR.
1.8.4 Design and report preparation:
Using the data collected by the primary resources, secondary resources and interaction with
stake holders and TP staff a collection, transport DPR is prepared. The DPR has considered
the future population growth and prospective increased growth in the city. A detailed cost
estimation and financial sustainability analysis has been done and presented in the report.
All the designs and estimates are provided along with the report as annexure.
1.8.5 Review process
The draft report, cost estimates, designs and drawings were submitted to TP for review. This
final DPR document has been prepared by incorporating all the suggestions, comments and
inputs of TP. The TP shall further review the report, seek the state government clearance as
required and the final report would be drafted to meet the requirements of using the
document for implementation.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
19
1.9 Structure of the Report
Chapter Heading Contents 1 Introduction The chapter provides and introduction to study, the
terms of reference, study methodology and outline of the study.
2 Town Profile The Town profile brings out the nature and details of the town. The demography, importance, climate and structure of the town are brought out.
3 Present SWM scenario in Khanapur
The existing waste management systems in the town in presented. The waste assessment undertaken is presented. The strengths and lacunae of the systems are brought out to enable further planning.
4 Issues & Gaps in Present SWM
Gaps in present system of Solid Waste Management
5 Proposed SWM Action plan for Khanapur
The proposed efficient plan for waste management in the Town.
6 Proposed Processing Facility
This provides detailed design for Operations and working of Compost Plant
7 Land fill Site This provides detailed design for Operations of Landfill Site
8 Institutional Aspects & Capacity Building’ & Public Awareness
The team for solid waste management, the institutional structure and the capacity building requirements are presented. Information Education and Communication is a significant component of the solid waste management process of a town. A concept and operational schema for the public awareness required has been presented in this chapter.
9 Summary of Financial Requirements
Detail BOQ, Final Summary for financial requirements of the proposals is presented in this Chapter
Annexure List if Annexure includes Chemical Analysis Report for Solid Waste Sample, Sample Description for primary survey.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
20
2 Town Profile
2.1 Background & History
Khanapur is taluka headquarter in the Belagavi District of Karnataka state, India. The town is
situated in the south part of Belagavi district which is located in northwestern parts
of Karnataka and lies at the border of two states, Maharashtra in the north and Goa on the
west. It is located at a distance of 500 km from Bangalore which is the capital town of the
state of Karnataka.
MAP 2-1: GEOGRAPHICAL REGIONAL SETTING OF THE TOWN
2.2 Profile of the town
Khanapur Town is located around 30km from Belagavi on the Belgaum – Panajim National
highway. Though primarily an agricultural outpost, Small scale industries in Khanapur town
on the bank of the river Malaprabha is main industrial area. It is run by Khadi village Gram
udyog Commission. The bridge instructed during British period to Malaprabha River
"CHOUDA MASHI" is a function place for visitors. The Chunamuri produced here is used as a
food and also transported to other places.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
21
2.3 Topography and Climate
Being situated in south region of Belagavi district which lies in the rugged terrain of north-
western Karnataka, Khanapur is known for its moderately hot climate throughout the year
except for the monsoon. Khanapur receives rainfall from both the northeast and the
southwest monsoons and the wettest months are June–September. Average rainfall in the
town is 810mm. It has a distinct wet and dry season. December & January are generally cold
as compared to the rest of year. The temperature during summer is 19°C to 39°C and the
temperature during winter is 13°C to 37°C.
FIGURE 2-1 AVERAGE RAINFALL FOR BELAGAVI DISTRICT
FIGURE 2-2 AVERAGE TEMPERATURE FOR BELAGAVI
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
22
2.4 Population of the town
As per Census 2011 population of TP Khanapur is 19,309. The population of town was
16,567 in year 2001 and 14, 728 in 1991. The last two decade showed considerable growth
rate of 12&17 percent. The growth rate of the town is varying. There was constant increase
since 1961 to 1981 and sudden drop in 1991 and in 2011. The trend of population growth is
explained in Table 2-1.
TABLE 2-1: POPULATION OF KHANAPUR
Year Population Population Growth Rate (%)
1951 6175
1961 8127 31.6%
1971 10193 25.4%
1981 12513 22.8%
1991 14728 17.7%
2001 16567 12.5%
2011 19309 16.6%
Source: Census 2011
FIGURE 2-3 POPULATION GROWTH RATE OF THE TOWN
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0
5000
10000
15000
20000
25000
1951 1961 1971 1981 1991 2001 2011
Population
Rate of Growth Per Decade
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
23
FIGURE 2-4 WARD WISE MAP OF THE TOWN
Source: TP Khanapur
The town is divided into 16 political wards for the purpose of administration. The ward wise
population as per 2011 census is shown below in Table 2-2.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
24
TABLE 2-2: WARD-WISE POPULATION
Ward Number No of HH for year 2011 Population of Census Year 2011
1 338 1384
2 334 1441
3 371 1478
4 194 798
5 271 1195
6 192 850
7 196 882
8 200 878
9 193 955
10 213 974
11 238 1105
12 341 1546
13 235 1111
14 374 1861
15 397 1682
16 275 1169
Total 4362 19,309 Source: Census 2011
2.5 Slum Population
As per the 2011 census data, there are 3 slum settlements in Khanapur TP, all those are
notified, wherein about 433 families stay.
TABLE 2-3: SLUM SETTLEMENTS
Sr. No. Slum Name Notified No of Households Population 1 Dambari Colony Yes 103 403 2 Harijanagalli&Dorgalli Yes 70 140 3 Naik Galli Yes 260 782 Total 433 1325 Source: census 2011
Particulars Nos.
No. of slum settlements 3
Slum population 433
Slum households 1325 Source: census 2011
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
25
2.6 Population Density
As per census 2011, the population density of the town is 3616 persons per sq km. Most of
the population is concentrated in the core town area in the old town.
2.7 Floating Population
Total floating population of the town at 5% of the population is about 1048.
2.8 Major tourist centre’s
Khanapur is located 500 km from Bangalore and 110 km from Panajim. Nestled in the hilly
terrain of the central Belgaum region, it enjoys a moderately warm climate and is
surrounded by mountainous vegetation and rivers.
Halasi or Halshi is one of the ancient towns in Belgaum district. It was second capital of early
kadambas and a minor capital (during 980 AD-1250 AD) under later Kadambas. Where there
are Bhu Varaha Narasimha temple, Suvarneshwara temple, Kapileshwar temple,
Hatakeshwar temple and a Jain basadi built by the Kadamba rulers. Halasi was a centre of
confluence of Jainism, Vaishnavism and Shaivism during early Kadambas. It was
headquarters of Halashi-12,000 province including parts Belgaum, Dharawad and Haveri
district
Vajrapoha Falls (also Vajrapoya waterfalls), a waterfall in the Belgaum district of Karnataka
in South West India, is situated about in the mountainous forest 4 kilometres (2.5 mi) from
the village of Jamboti. Between the village of Gavali and Chapoli on an elevated hillock, the
Mandovi River that flows to the beautiful Vajrapoha Falls that fall for up to 200 metres
(660 ft) and are best seen after the monsoon season (June–October). The falls are about 1.5
hours southwest of Belgaum.
Bhimgad Wildlife Sanctuary is a protected area in the Western Ghats, in Khanapur Taluk of
Belgaum District near Jamboti Village, Karnataka state, India. This 19,042.58 ha
(73.5238 sq mi) of Tropical and subtropical moist broadleaf forests forest area was long
awaiting to be a wild life sanctuary and finally declared in December 2011.The Bhimgad
forests are notable for the Barapede caves, the only known breeding area of the
Wroughton’s free-tailed bat, a threatened species on the verge of extinction. The sanctuary
is also home to other rare species of flora and fauna.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
26
2.9 Khanapur Town Panchayath
Khanapur town Panchayath was constituted in 1973 by the Government of Karnataka.
FIGURE 2-5 ORGANIZATION STRUCTURE OF THE ULB
2.9.1 Administrative Wing
The administrative or executive wing is headed by the Municipal Commissioner, appointed
by the state government. The town is arranged into 16 wards for effective service delivery
and management. The Executive wing is arranged into functional departments that are
responsible for day to day functioning of the council.
2.9.2 Elected Wing
The Elected wing is represented by the General Body (GB) constituted by 16 elected
members. Apart from General body there are committees constituted from elected
representatives including standing committee of 8 elected members. There committees are
formulated to address matters related to Administration / provision of civic services in most
appropriate manner.
Khanapur Town Panchayat
Elected Wing
President
Vice President
Standing Committee
Executive WIng
Cheif Officer
Accounts Office Suprerintendent City Engineer
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
27
3 Present System of Solid waste
Management 3.1 The Present Scenario of SWM system in Khanapur
3.1.1 Actual calculation of Solid Waste Generation
A detailed estimate of the MSW generation has been carried out with a sample survey. Actual
waste generation by each category of waste generators is calculated for consecutive 3 days.
Based on the average waste generation by each category total waste generation is estimated.
Sample are selected from each category of waste generators such as households, commercial
shops, worship, institutions, markets, meat/chicken shops, hotels and restaurants and Street
Sweeping. The following table shows number of sources and the average waste generated in
each source based on the waste estimation.
TABLE 3-1: WASTE GENERATION ESTIMATION
S. N. Waste Generators No of Generators
Avg. waste / day in Kg
Total waste(Kg)
Total ( Tones)
1 Household 4173 0.90 3780 3.787 2 Slum 408 0.90 371 0.37 3 Large Hotels 8 4.2 34 0.03 4 Small Hotels 35 3.1 109 0.11 5 Veg. Markets + Marriage Halls 2 660 1320 1.32 6 Meat/Chicken Shops 5 12.0 60 0.06 7 Institutions 6 4.0 24 0.02
8 Petty Shops 100 1.3 126 0.13 9 Street Sweeping 0.46 10 Floating population 1048 0.3 310 0.31 11 Construction & Drainage waste 0.50
Total 7.09
The major sources of generating waste in Khanapur are households, commercial
establishments, institutions, markets, hotels and street sweeping operations. To arrive at
number of waste generators in the city, data like ward wise population, slum and non-slum
households and street lengths of all type of roads were obtained from secondary sources.
Households are taken from the census, street length from the TP. Major Markets were
individually assessed by the survey team.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
28
3.1.2 Normative Waste generation
In the present year 2017 estimated population of the Khanapur city is 20,959. Considering
the Solid Waste generation at the rate of 350 gm per capita per day the total waste
generated is 7.34 T / day. The normative waste generation is at higher side and it is
considered for future projections.
TABLE 3-2: WARD WISE WASTE GENERATION
Ward Number No of HH projected
for yr 2017 Projected for
Year 2017 Waste Generation in MT (Yr 2017 @350 gm/capita/day)
1 339 1502 0.53 2 353 1564 0.55 3 362 1604 0.56 4 196 866 0.30 5 293 1297 0.45 6 208 923 0.32 7 216 957 0.34 8 215 953 0.33 9 234 1037 0.36
10 239 1057 0.37 11 271 1199 0.42 12 379 1678 0.59 13 272 1206 0.42 14 456 2020 0.71 15 412 1826 0.64 16 287 1269 0.44
Total 4735 20959 7.34
3.2 Population Projection
For the Proposed Detailed Project Report, it is necessary that future population growth and
their requirements are estimated to understand the gaps and shortfall in meeting various
requirements.
The planning horizon of 5 years (till 2022) has been considered and population projections
have been made for 20 years. Three methods; Arithmetic Method, Incremental method and
Geometric Progression method have been used to project the population for Khanapur and
the projected figures are given below.
The history of Khanapur indicates moderate population growth trends in the past but
declined during the last decade. In absence of any major commercial or industrial
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
29
developments, it is assumed that the declining growth trends may continue in future and
stabilize with the district average. Incremental Increase gives a negative trend due to
negative growth recorded during 2001-2011. Geometric method gives a prolonged period of
high growth rate in the future years. Hence an average of three methods is considered.
The Population projection is presented below in Table 3-3. It is expected that total
population of the town will be 22,415 in the year 2022 and population will be 29,102 in the
year 2042.
TABLE 3-3: POPULATION PROJECTIONS
Projected Population Growth rate
Arithmetic Incremental Method
Geometric Average of three
2011 19309 19309 19309 19309 2017 20,622 20,698 21,557 20959 2022 21,717 21,899 23,629 22415 2032 23,906 24,420 28,390 25572 2042 26,095 27,099 34,111 29102
Source: Analysis AIILSG
FIGURE 3-1 POPULATION PROJECTION FOR THE ULB
3.3 Waste Generation Projection
In the present year 2017 estimated population of the Khanapur Town is 20959. Considering
the Solid Waste generation at the rate of 350 gm per capita per day the total waste
generated is 7.34 MT / day. The present waste generation will grow from the 7.34 TPD to
7.85 TPD in the next 5 years. The estimated projections for the MSW for 25 years are as
below.
15000
20000
25000
30000
35000
40000
2017 2022 2032 2042
Arthematical Increase
Incremental Increase
Geometric Increase
Average of Three Methods
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
30
TABLE 3-4: ESTIMATED SOLID WASTE GENERATION IN FUTURE
Year Projected Population
Solid Waste Generated in Tons/Day
Total Solid Waste TPD
Biodegradable (50%) TPD
Recyclable (30%) TPD
Inert (20%) TPD
2017 20959 7.34 3.67 2.20 1.47 2022 22415 7.85 3.92 2.35 1.57 2027 23951 8.38 4.19 2.51 1.68 2032 25572 8.95 4.48 2.69 1.79 2037 27287 9.55 4.78 2.87 1.91 2042 29102 10.19 5.09 3.06 2.04
3.4 Waste Collection
3.4.1 Primary Waste Collection
Door to Door Primary Collection of waste started by ULB in all 16 Wards- Vehicles &
Equipment’s Purchased- Primary Collection is being done in 2 shifts to improve the
collection efficiency with available vehicles. Some of the drivers &assistants required on
Primary Collection Vehicles are permanent and some are outsourced. Door to door primary
collection of waste is in practice in the town with help municipal vehicles. Auto tippers,
Tractor Trailers and pushcarts are deployed for the door to door collection purpose. To get
maximum primary collection efficiency, door to door collection is being done in 2 shifts for
Shops and establishments, Markets, Hotels and Restaurants from morning 0600 hrs to 1330
hrs and 1430 hrs to 1730 hrs. Few drivers and assistants required on these vehicles are
permanent and few are outsourced.
TABLE 3-5: EXISTING VEHICLE DETAILS
Sr. No Vehicle Model Vehicle No Type of Vehicle Year of Procurement
1 Tractor - Trailer MEI 5976 Solid Waste Cleaning
1983
2 Tractor - Trailer KA 22 V 1587 B 1588
Solid Waste Cleaning
2009
3 Ape Auto Hydraulic Systems
KA 22 C 2405 Auto Tipper Ghanta Gadi 2015
4 Ape Auto Hydraulic Systems
KA 22 C 2406 Auto Tipper Ghanta Gadi 2015
5 Ape Auto Hydraulic Systems
- Auto Tipper Ghanta Gadi 2015
TABLE 3-6: QUANTIFICATION BASED ON NO. OF TRIPS TO THE LANDFILL SITE
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
31
Type of Vehicles Number of Vehicles
Average qty. of waste / vehicle in TPD
No. of trips/ day
Total qty. of waste transported to landfill site in TPD
Auto tippers / Mini tippers
3 0.5 2 3
Tractor trailers 2 1.5 1 3 Tipper trucks (407) Dumper placers - - - - Compactors - Qty. of waste unlifted Total 6
3.4.2 Commercial areas and Markets:
The town has 1 market and it is estimated to generate about one ton of waste daily. The
Shops and other commercial establishments are estimated to generate about 2 tons of
waste daily.
3.4.3 Hospital and Nursing home wastes
Bio medical waste generated by Hospitals and clinics is separately collected by a bio Medical
Waste Collection Agency from Belgaum. It caters to all the healthcare establishments of the
city and independently handles the process of collection, transportation, treatment and
disposal of healthcare waste from medical establishments.
3.4.4 Hotels and Restaurants Waste
In Khanapur town there are 43 number of restaurants and hotels with lodging facilities.
Most of them are located near in the main city. The quantity of waste generated is relatively
small therefore waste is collected by door to door collection vehicles with the help of
Tractor trailer.
3.4.5 Construction Waste
Construction and demolition waste mostly consist of inert and non biodegradable material
such as concrete, plaster, metal, wood etc. These wastes are heavy, having high density
often bulky and occupy considerable storage space either on the road or communal waste
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
32
bin/container. Construction debris waste is presently collected by the owners of the waste
producing sources and it is not handled by the SWM department
3.4.6 Slaughterhouse Waste
At present there is no separate functional Slaughterhouse in the city. Small scale
Slaughtering activity is undertaken by Chicken Mutton Shops in their private premises. At
present there is no separate facility available for treatment and disposal of Slaughterhouse
waste.
3.5 Transportation of wastes
Transportation of the solid waste generated in the town is being managed by TP. Primary
transportation refers to transporting of waste generated from waste generators to the
waste storage depot. Primary transportation of waste is not practiced presently in
Khanapur. There are no intermediate storage depots in Khanapur.
Secondary transportation refers to collection of waste from intermediate storage points like
dumper bins and open points to disposal unit. TP is presently managing the secondary
transportation with its vehicles. Auto Tippers and tractor trailers are used as secondary
transportation vehicles.
The following are the vehicle squad available with Khanapur Town Panchayat for secondary
transport of the MSW.
TABLE 3-7: MSW TRANSPORTATION VEHICLES
Sr. No
Type of Vehicles Capacity (Tons)
No. of Vehicles
No of Trips Total Waste Collected
1 Tractor Trailer 1.5 2 2 3
2 Auto Tipper 0.5 3 6 3
Total 6 Source: Khanapur Town Panchayat
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
33
PICTURE 3-1: TRANSPORTATION OF MSW
Collectively the Khanapur Town Panchayath transports 6 TPD of Municipal Solid Waste. The
solid waste dumping site located 4 km away from the Town Panchayath office of Khanapur
at survey no 143.
3.6 Street Sweeping
The total area of the town is 5.34 sq. Km and total road length 41 kms. The street sweeping
work is carried out from 6.00 AM to 12.00 PM in the morning hours. The shift could extend
till 1 PM in case of excess waste or inefficient operation of sweepers. Street sweeping
happens usually in single shift unless there is a lot of waste generated in a day or there are
special occasions in the town. The garbage along with construction waste and drain silt after
seeping is transported to dumping site with the help of tractor.
TABLE 3-8FREQUENCY FOR STREET SWEEPING
Sr. No Type of Road Length of road Frequency of Sweeping 1 Type ‘A’ 6.15 Everyday 2 Type ‘B’ 12.3 Two or three times a week 3 Type ‘C’ 22.55 Once a week Total 41.00
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
34
3.7 Tools Used
Significant amount of waste is disposed on the streets. Most of the main streets consist of
waste materials like plastic covers, paper waste etc. The Sweeping staffs are provided long
hand brooms, metal plates and wheel barrows. The street sweeping staffs are provided
with, gloves, masks, sweeping carts, gum boots and metal trays. None of the workers wear
jackets or mask to cover themselves from dust while sweeping. Sweepers use their hands
and brooms sometimes to collect waste from waste heaps and put into plastic bags.
3.8 Processing and disposal of waste
TP had bought site for Solid Waste disposing near Manasapur to the south of the town. The
landfill is located at a distance of about 4 Kms from the town center. The total area of the
landfill site is about 8 Acres. The landfill site is partially provided with compound wall. There
is facility for a watchman’s room. TP has not deployed any trip entry recorders for the trips
of each vehicle on all days. The disposal site is provided with a 24 hour watch man. The
landfill sites do not have weighing bridge. The waste brought to the depot by tractors is
dumped inside and Back Hoe Loader is deployed from time to time form heaps of the
wastes. The waste heaps are not covered with inert material.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
35
FIGURE 3-2 CONTOUR MAP FOR SWM SITE KHANAPUR
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
36
3.8.1 Approach Road & Internal Road
There is a tar road connecting the town to the landfill site. The internal main road and
other roads within is tar road.
3.8.2 Compound wall & Watchman Shed:
Khanapur Landfill site has a compound wall present along most of its perimeter.
Watchman shed has been constructed and is in use presently.
3.8.3 Bore well and Water Tank
2 bore wells are drilled in addition to a water tank at the landfill site to fulfill the water
requirement in landfill site.
3.8.4 Platform:
A RCC Windrow Platform has been constructed.
3.9 Staff involved in SWM
Following are the number of staff involved in the management of Solid Waste.
TABLE 3-10 MAN POWER EMPLOYED FOR SOLID WASTE
Sr.No Position Permanent basis Contract Basis
1 Sanitary Inspector 1
2 Mukadam 1
3 Drivers 0 28
4 Pourkarmikas 7
Total 9 28 SOURCE: Khanapur Town Panchayath
3.10 Municipal Solid Waste Composition
3.10.1 Physical Composition of Waste
The composition of the waste becomes crucial to decide an efficient SWM system. To
understand the waste character disposed in the land fill in Khanapur, An analysis of the
composition of the fresh waste was conducted for 2 days. 4 samples were selected and
analyzed for 2 consecutive days by using the quartering technique.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
37
40 kg of fresh waste was selected randomly by the waste carrying vehicles for conducting
the quartering technique. About 10 kg of waste from the selected 40 kg of waste was
selected for conducting waste composition analysis. The selected 10 kg sample was
segregated with the help of rag pickers and each segregated material is weighed.
The analysis shows an organic content in the waste of 42 %, 14.8 % recyclable materials,
27.9% of silt and stones and miscellaneous items of 10%. The quantity of silt and stone is
high because of collection of waste from roads while sweeping.
The particulars of waste composition and analysis conducted are presented below based on
the analysis conducted at the landfill. The table below gives the average waste composition
of selected samples.
TABLE 3-9 PHYSICAL COMPOSITION OF WASTE IN PERCENTAGE
Sr. No Particulars Day 1 In %
Day 2 In %
Average In %
1 Plastic Material 7.8 9.1 8.45 2 Paper 9 7 8 3 Cloth pieces 9.5 8.5 9 4 Organic Waste 41.3 42.7 42 5 Glass Pieces 0.9 0.6 0.75 6 Wood Pieces 2.6 3 2.8 7 Metal Pieces 0.8 14 1.1 8 Silt, Stone, & Moisture 28.1 27.7 27.9 E-waste Negligible Total 100 100 100 Source: Analysis by AIILSG
3.10.2 Chemical Composition of MSW
Plastic Material
8.45%Paper
8%
Cloth pieces9%
Organic Waste42%
Glass Pieces0.75%
Wood Pieces 2..8%
Metal Pieces1.1%
Silt, Stone, & Moisture
27.9%
Physical Composition of Municipal Solid Waste
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
38
The chemical composition of waste is conducted. The results of the findings are as below.
Date of Sampling – 02/12/15 Type of Sample – Municipal Solid Waste Sample received on date- 03/12/15 Analysis Date- 04/12/15 to 05/12/15 Reporting date- 05/12/15 Sample Location – TP Khanapur, Karnataka
TABLE 3-10 CHEMICAL COMPOSITION OF THE WASTE
No. Parameters Results Unit
1 Moisture Content 20.37 % 2 pH of 10% Solution 6.27 - 3 Total Nitrogen (N) 0.27 % 4 Total Phosphates (P2O5) 0.20 % 5 Potash (K2O) 1.46 % 6 Organic Carbon 25.70 % 7 Carbon: Nitrogen Ratio (C : N) 169.1 - 8 Gross Calorific Value in Cal/gm 1049 Cal/gm
3.11 Segregation of recyclables wastes
There is no systematic mechanism of Segregation of recyclable waste in Khanapur. Segregation
of waste is not practiced at generator level or at disposal. The waste generators like
households, commercial establishments and other institutions usually dump recyclable and
non recyclable waste together in open points or in container bins located nearby. Very few
of the commercial establishments like hotels practice the segregation of waste by storing
food waste separately which is given to animal husbandry units. Presently there is no
mechanism of separate collection, transportation or processing of the bio degradable and
non bio degradable waste in Khanapur.
3.1 Present expenditure on Solid Waste Management
The following table explains the expenditure on Solid Waste Management.
Sr. No Item Rs in Lakhs 1 Salary of permanent PKs 32.88 2 Wages for outsource PKs 57.00 3 Vehicle running and Maintenance cost
11.81 4 Consumable etc. Total 101.69
Source: - TP Khanapur
The following table explains the revenue from Solid Waste Management in the yr 2014-15.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
39
Particulars Amount (Rs. in lakhs)
% of Property tax reserved towards SWM and cleaning activities 4.99
SWM Cess 5.38
Sale of compost, recyclables, RDF etc ----
Components of Town planning Fee, advertisement tax, birth / death certificate fee etc towards SWM and cleaning activities
0.34
Fines and fees available for SWM and cleaning activities ---
Others ---
Total 10.72
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
40
4 Issues and Gaps in the present
Management System of MSW
4.1 Gaps and issues in Khanapur
The analysis of the preliminary information collected of Khanapur town, highlights certain
good measures and systems adopted by the town and certain areas that require
improvement and infrastructure development.
Door to door waste collection is undertaken in many parts of the town (83%). Street
sweeping and drain cleaning are also done frequently. The town has made provision for
adequate landfill site and has constructed a vermicomposting facility.
The preliminary issues and gaps identified are:
• As people do not practice segregation of waste at source, there is need for awareness generation.
• Although door to door collection is 83%, people also tend to throw the waste on open ground, which is why the council has provided bins along the streets. Despite this, there are some points in the town having open dumping.
• Currently all the waste collected is only partially processed at the landfill site without prior segregation, leading to the remaining waste lying there as it is.
• There is lack of personnel operating at the processing facility. • The current collection and transportation system is not optimized. • The entire solid waste management system has to be gradually up scaled to meet
the future needs of the town. The system has to be planned for the increased quanta of waste which have to be handled properly.
• The Landfill site has to be retro-fitted to become a sanitary landfill site. The procedures for its operation and maintenance have to be prepared and operationalized.
• The financial management plans for the Solid waste management system have to be reviewed and improved to assist in revenue generation and creating a sustainable and self sufficient system.
• Training for the staff in the solid waste management department to improve efficiency and safety standards may be required.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
41
5 Potential Strategies suggested for
MSWM
5.1 Proposed Concept for Waste Management
The mechanism of solid waste management system in Sankeshwar requires a reorganized
model to meet the requirements of the MSW rules 2016. The major effort required in this
regard is towards the procedural improvements of the waste segregation at source,
transportation and disposal. TP at present is collecting 81% of waste generated, but public
awareness on the solid waste management is lacking. The strategies are suggested in the
following four areas:
Public awareness: Waste generation is increasing in urban areas as the use of packaged
consumer goods is increasing. The impacts of inefficient solid waste management are
directly related to public health. It is thus very essential that the citizens of the town be
equal partners with the city administration to reduce the problem of waste. Public
participation is thus the cornerstone in a successful solid waste management plan. Public
participation is essential in the following activities.
1. Reduce, Reuse & Recycling (R R R) of waste. 2. Not to throw the waste/litter on the streets drains, open spaces, water bodies, etc. 3. Storage of organic/bio-degradable and recyclable waste separately at source. 4. Primary collection of waste 5. Community storage/collection of waste in flats, slums, societies, commercial complexes,
etc and other waste source generators. 6. Pay adequately for the services provided.
Generating public awareness on these issues and garnering public participation for an
effective solid waste management in the city requires a sustained approach and efforts by
the administration and the elected representatives.
Collection of waste: Collection from all the waste generators has to be at door step in each
of the existing 16 wards. This would include residential, commercial and institutional
facilities.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
42
Door to door collection of waste will reduce the burden of secondary collection system due
to reduced number of open points. The MSW from markets and other common places
would be collected through sweeping teams. The waste collected from door to door system
and by the sweeping teams deployed for market areas and other public spaces will be
disposed in the landfill. Roads sweeping and drain cleaning would be a separate waste flow
from collection to disposal.
FIGURE 5-1: TWO (2) -BIN SYSTEM FOR DRY AND WET WASTE
Collection of segregated municipal waste from the source of its generation is an essential step in solid waste management. Inefficient waste collection service has an impact on public health and aesthetics of towns and cities. Collection of wet and dry waste separately enhances the potential of cost effective treatment of such wastes and of deriving optimum advantage from the recyclable material fed into the system. 2 differently coloured bins, 10-15 litres each per household are recommended to promote and ensure segregation: • Covered Green Bin: Wet waste • Covered Blue Bin: Dry Waste
FIGURE 5-2: STORAGE OF MUNICIPAL SOLID WASTE IN PUBLIC PLACES/PARKS
Waste Collection bins at optimum distance(between 25-250 meters)should be placed at public places to avoid littering
On site composting of yard waste/
green waste could also be promoted
The proposed concept requires establishing primary waste collection and transportation
system. This would result in reduced burden of solid waste management on secondary
transportation and will reduce the number of open points in the city. Resource recovery is a
significant component of the new proposal. Dry waste collection centre would be set up as
per design requirements. It is also proposed to integrate the informal and recycling sector
involving rag pickers and kabadiwalas prevalent in Sankeshwar into the formal system by
recognizing their work and by providing required support services.
Role of the Informal Sector in Primary Waste Collection The involvement of the informal sector is also to be examined and integrated into the waste
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
43
management system of the city. The informal sector in any city comprises of two systems
i.e. the kabadi system or the rag pickers.
The informal “kabadi system” network forms an important link in the overall waste recycling
system prevalent in the country. They can be compared to micro-entrepreneurs who buy
reusable and recyclable material like newspapers, metal, glass, cardboards, plastics, etc.
from households or commercial areas. Citizens should be encouraged to continue the
practice of selling recyclable wastes to the “kabadi system”, as they constitute the first link
in the waste recycling system.
Rag pickers are also an important part of the informal recycling system and are instrumental in recovering discarded recyclables in disposed municipal waste that have not been bought by the kabadi system. In an ideal system, rag pickers should be integrated into the system by training and employing them for door-to-door collection of waste by the RWA’s, NGOs, CBOs and the like. The rag pickers who work as waste collectors should be allowed to collect recyclables separately alongside wet and dry fractions.
Rag pickers may also be encouraged to form cooperatives, through the involvement of local NGOs/Self-Help Groups (SHGs) and may be allowed to collect recyclables from households. Such initiatives will not only ensure a higher level of income to rag pickers, but will also ensure hygienic conditions for rag pickers and environmentally safe waste recycling practices. Also, a lot of rag pickers are usually harassed by the police, property owners, shop keepers in the vicinity. Many of them have to justify their work to various people and are condemned by society. Many of them are in fact women, who have to live with the insecurity of harassment and threat to their livelihood. Organizing them into cooperatives tend to protect their rights thereby retaining their dignity of labour, work, their right to livelihood and right to access recyclables.
ULBs should make concerted efforts to integrate the informal sector of rag pickers into regular waste collection operations through the private sector, NGOs, RWAs etc Transportation of waste:
The transportation of the waste will be classified into primary and secondary transportation.
• The primary transportation vehicles will be auto tippers, hand carts and 4 wheeled
vehicles involved in door to door collection. These primary transportation vehicles
will collect the waste from the generators on a daily basis and dispose the waste at
intermediate transfer stations.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
44
• The secondary transportation of waste from road sweeping and drainage cleaning
will be done by tractor trailers. Tractor trailers will be used to transport drainage
waste and construction and demolition debris.
Street sweeping and drain cleaning waste is to be collected in separate bins and transported directly to the sanitary landfill facility
Both manual and mechanical street cleaning are suggested. However manual street cleaning is preferred in narrow, congested streets and in streets where the road carpeting is damaged.
Skip Trucks are recommended for transportation of large quantities of C&D and inert waste
Truck mounted with pressure water jetting and suction machine
In order to ensure that sweepers do not dispose waste into drains, same staff that is responsible for cleaning street should be made responsible for cleaning adjacent drains as well Silt removed from surfaced rains and stored on the shore of the drain should be collected as soon as possible and transported directly to the landfill
Disposal of Waste:
The final disposal of the waste has to be through a sanitary landfill site, after removal of the
recyclable and biodegradable waste. This need to be processed separately and only inert
and non biodegradable waste should be taken to the landfill site. The handling of waste and
the landfill site has to be scientific to avoid accidents.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
45
5.2 Proposed Waste Flow Processes
The municipal wastes generated in the city will be collected using the following different types of collection systems as follows.
FIGURE 5-3PROPOSED WASTE FLOWCHART FOR KHANAPUR
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayat Khanapur
46
5.3 Storage of waste at Source
No waste should be thrown on the streets, footpaths, open spaces, drains or water bodies,
nallas etc. Waste should be stored at source of waste generation in three bins/ bags, one for
food waste/ bio-degradable waste, another for recyclable waste such as papers, plastic,
metal, glass, rags etc, and the third one for wastes such as batteries , containers for
chemical plastics pesticides, discarded medicines and other toxic or hazardous household
waste.
5.4 Segregation of Waste at Source
The TP has conducted IEC campaigns to achieve waste segregation at source. The local body
may draw up a program of conducting awareness campaign in various wards of the town
utilizing the ward committees, local NGO’s and resident welfare association. Detailed IEC
programme is provided in Chapter 8. The waste segregated at source is a resource itself.
[Recent Source segregation Promotional activity carried out by Bruhat Bangalore Mahanagaran Palike]
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
47
5.5 Door to Door Collection and routing plan
Collection of municipal wastes from Households and commercial establishments like
provision stores and institutions like colleges, temples, theatres, malls etc would be part of
door to door collection system. The primary transportation vehicles like hand carts, auto
tippers or 4 wheeled tippers will be used for door to door collection. The deployed door to
door collection vehicles would visit each and every waste generator in the deployed area.
The collected waste will be disposed by these vehicles directly to the Landfill site.
The collected waste will be disposed by these vehicles into the landfill site directly. There is
no provision of Secondary Storage proposed. The containers bins used for secondary
storage are not viable or inefficient SWM system.
Door to door collection of waste would be introduced for collection of waste from
residential and commercial waste generators in Khanapur. Khanapur Town Panchayat would
be responsible for conducting door to door collection operations in the allotted packages.
The TP shall provide the man power, vehicles and equipments required for the door to door
collection mechanism.
The residents and other waste generators are expected to store the waste and hand over
the waste to the door to door waste collection staff. TP should insist the waste generators
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
48
to dispose the waste only through door to door step mechanism and avoid throwing the
waste into open points and drainages. The door to door waste collection staff would collect
the waste each and every day including national holidays and Sundays
TP should make it mandatory to waste generator that waste need to be segregated at
source. Also it has been advised to procure 3 Plastic bins at waste generator, so that waste
can be stored separately. The segregated dry waste and wet waste will be collected by Auto-
Tipper or four wheeled tipper. Auto Tipper or Ghantagadi will carry this waste to Dry Waste
collection centers to deposit dry waste separately and only wet waste will be carried to
Landfill site for further processing and disposal. The dry waste or Recyclable material can be
collected at regular intervals as may be convenient to the waste producer and the TP.
The door to door collection operations will be done using a combination of auto tippers,
three wheeler carts. The numbers of each type of vehicles required for door to door
collection have been calculated in the estimates for each individual package.
Optimized Route Micro plan for Auto tippers
Khanapur TP Microplanning of Door to Door Waste Collection
Vehi
cle
No.
Trip
s
War
d N
o.
Rout
e Zo
nes
No.
of H
H (2
017)
Star
t Poi
nt
Area
Co
vere
d
End
Poin
t
Auto tipper
1
1 8,9,7,11
Zone 5 871 TP
Nadarkar Galli,Vittal Galli,Basti Galli,Gaurav Galli,Gadhi Galli,Harijan Galli,Bazar Peth,Sammadevi Galli,Khanchapur Galli,Bardashkar Galli,New Naik Galli.
Landfill Site
2 5,10 Zone 6 504 TP
Naik Galli,Khanapur Road,Harijan Galli,Ravivar Peth,Parishwar,Tipu Sultan Circle,Parishwar,Tipu Sultan Circle,Parishad Road,Khanapur Road,Basweshwar Circle,Khanapur Road.
Landfill Site
Auto tipper
2
1 4,1,2 Zone 1 886 TP
Nhave Raste,Ningapur Galli,Ghode Galli,Wagle Galli,Sayyad Galli,Desai Galli,Upatgiri Road,Mittal Galli, Math Galli,Mningapur Galli,V Market Road.
Landfill Site
2 16,15 Zone 4 792 TP
Station Road,Ashrey Colony,Varde Colony,Basweshwar Circle,Khanapur Road,Bus Stand,Vidya Nagar.
Landfill Site
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
49
Auto tipper
3
1 3,14 Zone 2 750 TP
1 st Class Road,2 nd Class Road,KSRP Road,Ningapur Galli,V Market Road,Station Road,PWD Guest House,Asaga Road.
Landfill Site
2 6,13,12
Zone 3 778 TP
Station Road,Chamurkar Galli,Nadarkar Galli,Bardashkar Galli,Laxmi Nagar,Naik Galli,New Naik Galli,Green Road,Laxmi Nagar,Burud Galli,Bus Stand.
Landfill Site
• One auto tipper is suggested for 1400 HH (Assuming daily two trips to landfill site)
for individual Door to Door collection.
• One pushcart is suggested for 200 HH in slum and congested areas.
5.5.1 Streets sweeping
Conducting street sweeping operations, cleaning and removal of waste from public places,
office areas, administrative areas, markets, parks and other general places are considered
for collection of waste using sweeping mechanism. The street sweeping staff would clean
these areas regularly considering the quantity of waste generated in these generators. The
requirement of Push Carts and Tractor for the street sweeping are explained in the section
below. The sweepers should be compulsorily given safety equipments. The table below gives
the details of the safety equipments to be given to sweepers
TABLE 5-1: DETAILS OF PERSONAL PROTECTIVE EQUIPMENTS
S.N
Safety equipment Safety against Specifications Picture
1 Face mask Protect against dust/ infection Standard surgical mask
2 Full arm Uniform Protection against dust Factory wear uniforms
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
50
S.N
Safety equipment Safety against Specifications Picture
3 Safety shoes Minor wounds while sweeping PVC make, water proof shoes
4 Hand gloves Protection against infection Standard toilet cleaning gloves
5 Eye glasses Protection against dust Transparent factory wear
6 Head cover Protection against dust Standard surgical wear
7 Brooms Fan shaped &bunched (Delhi model) filament brooms
5.5.2 Targeted Waste Collection of Vegetable Market and Hotels
The Bulk Waste generators which generate more waste will be cleaned daily. Separate Auti
Tippers required to be deployed for waste collection from Veg Market, Kalyan Mandap and
Hotels.
TABLE 5-2 VEHICLES REQUIRED FOR WASTE COLLECTION AND TRANSPORTATION
Type of Vehicles Proposed (DPR) Existing nos. Nos. to be procured Push carts 14 - 14 Auto tippers 3 2 1 Tractor trailers 3 3 0 Back hoe loader 1 0 1
5.6 Slaughterhouse Waste
The ULB should collect all the slaughterhouse waste directly from the Generators and
disposed to the processing site in the windrows for aerobic composting. An alternative
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
51
method which can be used is that the Ulb shall treat the slaughter waste in RCC compost
pits of adequate size using bioculture. Good quality manure is produced in 6-8 weeks.
Leachate from the slaughter waste compost pit is collected and treated in a RCC tank and
the treated leachate may be used for spraying on windrows.
5.7 Biomedical Waste
Currently, the hospital and nursing home waste is collected and disposed by a biomedical
waste collection agency. It is proposed that this system should be continued in the future as
well.
5.8 Dry Waste and E waste Collection Centre
Dry waste collection centers are the decentralized units dedicated for collection of in
organic/ dry waste in the urban cities. The TP can generate revenue by conducting this
operation.
The dry waste collection centers would function as a social enterprise. The collection
centers would buy the recoverable from the waste generators and sell it to the whole sale
scrap dealers. The additional monetary benefits would be used for O & M of the facility.
The TP should insist on the private parties that the dry waste collection centers should be
set up and operated.
It is suggested that 1 dry waste collection center (DWCC) need to be installed at Survey No.
166 having area of 1000 sq.m. Segregation of garbage into wet and dry waste is a simple and
easy to identify. However, segregating dry waste is more challenging.
Dry waste includes materials such as paper, plastic, glass, wire, cloth, leather, wire,
thermocol, metal, wood, rubber, rexine and fabric.
Households will need to encourage separately store dry waste at their premises. The TP
would collect dry waste from their homes. Once a week, collection vehicle will separately
collect dry waste from homes, which will then be taken to Dry Waste Collection Centers
(DWCCs). Citizens on their own could also take their dry waste directly to DWCCs. This waste
will be segregated into different types of dry waste and then sold to recyclers.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
52
However, this will only works if the dry waste is free of any wet or food waste. People will
have to separately store the dry waste in their homes and if it is mixed with wet waste it will
only cause problems to them. The Pourkarmikas will not collect mixed waste from the
citizens and dry waste will be collected in the twin compartment tipper.
Set up Dry Waste Collection Centre (DWCC)
Reduction of waste is also possible by setting up purchase / processing centers for dry
waste, like plastics, paper, etc. Dry waste collection center shall be set up by TP in all the
wards. Dry waste–shall be stored and delivered to the dry waste collection vehicle which
shall be provided by TP or to the licensed DWCC set up on municipal / Government / private
lands. NGO’s, RWA’s, SHGs, collectives. Institutions, Trusts, Universities, Companies,
licensed recyclers or scrap dealers may be appointed as the sole Licensed Agents of TP for
maintaining dry waste collection centers and /or operating such dry waste sorting centers.
SHG’s/Waste pickers need to be identified and encouraged to come forward to maintain the
DWCC. Such centres would ensure that the recyclable material is sold through properly
created channels to ensure that the recycled goods are not misused. According to dry waste
the DWCC shall pay the Pourkarmika /Waste-picker or any individual who bring the waste to
the centres as notified by TP from time to time, this will encourage the public to segregate
the waste at source.
DWCC shall perform secondary and tertiary sorting of the waste, DWCC before finally selling
it to recycling centre’s. Collecting in bulk provides these informal sector workers with larger
returns, and creates more jobs. They aim to keep as much waste out of the landfills/ waste
dumps as possible and to help make waste useful and profitable. In the process they also
educate people about the importance of segregation, and provide safe and hygienic work
conditions to waste management workers.
It is proposed to procure weigh machine and Plastic Bailing machine at DWCC.
These DWCC will further segregate the dry waste collected from the garbage and sell them
in recycling market. The plastic waste is reused/recycled for manufacturing various
products.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
53
For Collection of E – Waste – E-waste should be collected and transported to the DWCCs
which shall have separate containers for this waste. As per the guidelines of hazardous
waste management division of Central Pollution Control Board, there is a need to encourage
recycling of all useful and valuable material from e-waste so as to conserve the ever
depleting natural resources.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
54
5.9 Construction and Demolition waste
Construction and demolition waste has been defined as ‘waste which arises from
construction, renovation and demolition activities. Also included within the definition are
surplus and damaged products and materials arising in the course of construction work or
used temporarily during the course of on-site activities’. The various streams of wastes to be
considered will include; Excavated materials, Concrete, Tiles, brick, ceramics, asphalt
Concrete, Plaster, Glass, Metal and steel, Plastics, Wood, asphalt, and Concrete rubbles, etc.
It is mandatory that every waste generator shall keep the construction and demolition
waste within the premise or get the waste deposited at collection centre so made by the
local body or handover it to the authorized processing facilities of construction and
demolition waste; and ensure that there is no littering or deposition of construction and
demolition waste so as to prevent obstruction to the traffic or the public or drains. Town
Panchayath should dump all C & D waste into low lying area which has been identified near
APMC yard, Renuka Sagar as suggested by TP.
5.10 Zero Waste Management
It is proposed that the ULB should begin zero waste practices in 2 wards during the DPR time
frame, and this area should be widened and broadened in a phase-wise manner in the
coming years. The process to achieve the same is explained in the following flow chart.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
55
By definition, zero waste management begins at source, namely by segregating waste
generated into three main categories. These categories are broadly as follows –
Wet Waste
Dry Waste
Inert Waste
Segregated waste will be collected at source in the designated zero waste ward. The wet
waste will be composted using aerobic composting or vermicomposting as prime methods
or will be deposited in a biogas plant within the ward. The byproducts (compost and/or
biogas) produced after processing of the wet waste will be used for gardening and
plantations within the same wards. Biogas/biomethanation plants of small scale (500kg)
shall be sufficient for each ward. The dry waste produced within the same designated
ward(s) shall be collected by dedicated rag pickers and shall be bailed or sold to scrap
dealers. 2-3 rag pickers are proposed at each ward level for this purpose. Plastic and tetra
packs shall be bailed and the remainder along with metal and paper shall be sold as
recyclables. The quotations provided by a few scrap dealers are attached in the annexure for
further reference. The inert waste or C&D waste generated shall be deposited to low lying
areas and shall be used as filling material in construction of roads (within the wards).
IEC and Public awareness activities play a huge role in the achievement of zero waste
management. The ULB shall employ campaigns, rallies, and leaflet and pamphlet
distribution within the designated ward to educate the common man about the advantages
of zero waste management. Motivational activities should be conducted to promote the
same. Elaborate details for conducting IEC campaigns are given in Chapter 8.9 Public
Awareness and IEC.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
56
6 Proposed Processing Facility The integrated waste management facility at Khanapur is proposed to be set up at existing
dumping ground. The area available at the processing and landfill site is 7.10 acres located
at distance of 4 kilometers from the town.
6.1 Technology Selection
The moisture content in Indian waste is high due to the high food and other organic content
in waste. In Khanapur if the silt wastes are removed from the waste stream the organic
matter is about 40-60 %. Such high moisture contents lead to low calorific value on as
received basis. Thermal processing is difficult and would require energy addition. Further as
mixed wastes are received there is always a threat of combusting plastics which can lead to
dioxins and furans release. It is recommended that no thermal processing technologies be
adopted in Khanapur.
Compost, vermicompost and Biomethanation plants are working successfully in many places
in India. These technologies recover the organic matter and make them into compost which
is a good soil conditioner and useful for soil management. Biomethanation has many useful
by-products like biogas, compost and potential use of the liquid as pest repellent etc. From
the agrarian environment of Khanapur the adoption of organic recovery solutions like
composting and vermicompost are the preferred options. We do not recommend
biomethanation at present as segregation is a primary requirement for successful operation
of biomethanation plants and this is not yet in practice. The Physical processing
technologies are useful to recover some of the non organic matter and should be integrated
into the main technology solution linked to organic waste recovery through composting.
Based on the above analysis it is recommended to have Composting and Vermicomposting
based waste management facility. This would be supported by the recycling of plastics and
other in organics. This technology proposed is simple and easy to implement with potential
to meet the overall objectives of waste management elucidated above. This is cost effective.
The integrated waste management facility would consist of waste receipt and segregation
facility, composting, vermicomposting, plastic recycling, brick making and landfill. The waste
flow for the integrated waste management facility for Khanapur is given below.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
57
6.2 Aerobic Composting
Aerobic composting is a process of microbial degradation where organic matter is broken
down by a succession of organisms in a warm, moist aerobic environment (controlled
conditions).
Composting is a form of recycling. Like other recycling effort, the composting of municipal
solid waste can help decrease the amount of solid waste that must be sent to a landfill
thereby reducing disposal costs. Composting also yields a valuable product that can be used
by farmers, landscapers, horticulturists, government agencies and property owners as a soil
amendment or mulch. The compost product improves the condition of soil, reduces erosion
and helps suppress plant diseases.
Composting is an age old practice and the word compost is as old as agriculture itself. The
solid wastes of plant and animal origin are utilized for conservation of carbon and
mineralization.
6.2.1 Use of Inoculums
Special inoculum containing several pure strains of developed, laboratory-cultured micro-
organisms, which are essential in the decomposition of organic matter, can be used for
accelerated decomposition and quality improvement.
Microorganism used can be:
• Bacillus sp.
• Trichoderma sp.
• Aspergillus sp.
• Phanerochaete sp.
6.2.2 Layout Planning of Facil ity
The integrated facilities have been planned at waste site. Detailed layout plan and other
drawing of the waste processing and disposal facility is given in annexure.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
58
TABLE 6-1 EXISTING AND PROPOSED CIVIL STRUCTURES
Existing Area of Khanapur Site 28742
Items to be Considered Existing Proposed Area Sq.mt
Site Office and Lab
Landfill Site No 1 Yes Yes (Extension) 1238
Landfill Site No 2 Yes 1287
Lab Yes 96
Office Yes 48
Toilet yes 37
Security Cabin Yes 26
VCB Shed 1 Yes 138
Vehicle Parking Yes 165
Weighbridge yes 30
Vehicle Washing area Yes 96
Segregation Shed Yes 220
Machine Shed Yes 220
Windrow compost pad Yes 670
Shed Yes 55
leachate Collection Tank yes 12.64
Prop. Leachate Drain off windrow yes 14.32
Leachate collection Sump yes 18
Leachate drain off to sump yes 34
Road Areas yes 533.95
Storm Water drain yes 1068
Total 6006.91
Leachate drain off windrow yes 87.1m
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
59
FIGURE 6-1 LAYOUT PLAN FOR SWM SITE KHANAPUR
The overall concept is to design waste processing and landfill site in coherence with the
existing facilities. It proposed to place the Waste Processing facilities towards the central
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
60
side of land. Adjacent to security building and additional office and lab building would be
constructed. Toilet facilities would also be provided. A parking area for vehicles, additional
composting facility, and vehicle cleaning unit is provided.
TABLE 6-2: DETAILS OF COMMON FACILITIES PROPOSED AT SITE
S.No Component Details
1 Boundary Wall There is an existing boundary wall all around the site
2 Internal Roads 215 m length road of 6m width has been proposed
3 Entrance gate Gate is present at the entry of the facility. 4 Weighbridge It is proposed to have 30 tons weighbridge of electromechanical type with 3
m x 9m loading platform at the entry of the waste management facility. The weigh bridge system would have a vehicle monitoring and staff time monitoring system.
5 Office building, Lab and toilet block
It is proposed to have office Building 5.9 X 9.3 Sq. M, Lab 9.8 X 9.3 Sq. M & 4.5 X 3.8 Sq. M two toilet blocks with separate provision for men and women.
6 Vehicle Parking It is proposed to have a vehicle parking at Landfill site.
7 Power facilities Power connection is available at the facility. In addition it also proposed to have a back up D G set of 60 KV capacity.
8 General Services The general services include the lighting of the facility for minimum 20 lux. No night operations are proposed and hence limited lighting is adequate. Fire fighting tools are services are proposed including preparation of a fire fighting requirement assessment and plan preparation.
10 Plantation around the boundary
It is proposed to have plantation around the landfill site as a buffer area.
TABLE 6-2 DETAILS OF CIVIL STRUCTURES PROPOSED
Name of the building / civil structure Cost / Sq. M , Cost / RMT Or Unit cost
Total Cost (Rs. in Lakhs)
Weighbridge room 5.61 Machine and Monsoon shed Platform 2648 11.66 Vermi degradation Platform 2648 5.83 Processing shed and Monsoon shed (screening, packaging etc)
7197 31.66
Laboratory 12648 25.14 Workers quarters / Rest rooms / toilets etc Others (Storm water gutter) 128 13.76 Road 4880 10.49 Leachate Collection Drain 780 0.68 Total cost 104.84
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
61
6.3 Processing Decomposed Garbage
The un-segregated garbage when completely decomposed turns into black color, earthy
aroma and free from pathogens. This decomposed material is passed through the process
machineries, which are simple and highly effective.
The contraries that are non-degradable materials like plastics, metals, glass, rubber and
other inert materials are easily separated in four stages of screening. The sieving operations
eliminates bits, sticks, gravels, metals and glass pieces making the end product highly
uniform in size and quality.
Use of inoculum like consortium of degrading microorganisms / cow dung solution has been
recommended mainly to reduce period of decomposition to around 40 to 45 days and also
to prevent foul smell and leachate generation.
6.4 Proposed Infrastructure at Landfill Site
6.4.1 Windrow Platform
This is an area where the entire waste received is turned at regular intervals. A windrow
platform of 20 X 33.5 metres is proposed to be constructed at the landfill site at Athani. In
the instant case the concrete yard is designed in such a way that the fresh garbage received
during the first 30 days is decomposed so that the volume and weight of the organic matter
is considerably reduced. Inertisation is attained and the stability of organic matter is
expected after 30 days. Decomposed matter is processed to obtain coarse organic manure
(semi processed organic manure). The semi processed organic manure is allowed for
stabilization for another 15 days and screened so that the final end product in the form of
organic manure is received after passing through 4mm sieve. Such organic manure is a
completely decomposed organic matter which is sanitized and stabilized.
6.4.2 Office building and Laboratory
An office building with a laboratory and toilet facility is proposed at the landfill site.
6.4.3 Tree Plantation
Three rows of Plantation are proposed so that the nearby habitation will not disturb the
project in future.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
62
6.4.4 Processing Machinery, Vehicles and Equipments
Mainly, 4 mm sieve trommel is proposed to be present at the landfill site. Their respective
feeder and reject conveyors are also proposed.
A tractor trailer shall be used for internal transport of waste in the landfill site. A backhoe
loader is proposed to be used for turning of waste in the windrows.
6.4.5 Machinery shed
A shed of 20 X 11 sq. m with 5 meter ceiling height are proposed for Trommels
(35/14/4mm) and their conveyors. This shed will also be used as a monsoon shed, to
accommodate the processing machinery; a shed of 20 X 11 sq. m with 5 meter ceiling height
is made to process the waste even during rainy season as 8 to 10 days material will be
protected from rain water. This shed is also to be used for storing accessories, various parts
of the machineries, processing equipment’s, oil & lubricants etc. Packaging of compost and
its storage will also be carried out in this shed. Compost packaging and storage unit should
also be accommodated here.
6.4.6 DG set
A 60 kV DG set is proposed as an alternative power.
6.4.7 Power Supply
A total power supply of 70 KW is necessary to take care of composting activity including
lighting in the composting area. A transformer with poles and sodium light is also found to
be necessary in order to help continuous supply of power.
6.4.8 Rain Water Harvesting
Rainwater harvesting is accumulation & deposition of rainwater for reuse on-site, rather
than allowing it to run off. Rainwater is collected from roofs, and in many places the water
collected is redirected to a deep pit (well, shaft, or borehole), a reservoir with percolation.
This water can be used for watering plants, vehicle cleaning etc. The harvested water can
also be used as drinking water, longer-term storage and for other purposes such as
groundwater recharge.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
63
For Construction of Rainwater Harvesting Project, which would carry rainwater runoff from
rooftops & along the roof lining, buildings for Office and commercial sectors needs specific
requirements as stated below.
• Maximum roof coverage area should be considered, which includes monsoon shade,
machine shade and vermicomposting shades and any other temporary or extended
shades which are along the office building.
• Pipelines carry the water to the recharge pits provided inside the premises.
• Every recharge pit is measuring of 4 x 3 x 3 cum.
6.4.8.1 RECHA RGE PIT BU ILDING
• Dig a pit 4m wide near the office or structure till you reach the water level.
• Dig one more meter deep and put a layer of charcoal and 1/2 meters of river sand
which acts as a strainer. If required, use an iron sheet all around the pit to keep the pit
from collapsing. Remove the sheet after you put charcoal and one and half meters of
river sand.
• Connect one pipe to the DOWNPIPE that comes from the roof.
• A strainer at the top will keep leaves and other wastes from going down along with the
rainwater.
• Rainwater displaces the dense hard water underground. If water comes up to the
surface, put half a meter of ordinary sand on top of river sand. This will prevent the
water from overflowing. Once a week, pour bleaching powder solution through the pipe
on the roof. This will cleanse the pipe thoroughly on regular basis.
FIGURE 6-3 DETAILS OF DIFFERENT LAYERS IN RECHARGE PIT
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
64
6.4.8.2 MAINTENA NCE OF RECH ARGE PIT
The Recharge Pits have to be cleaned regularly as it would have clogged with run-off sand,
mud, leaves etc. Clean the recharge pit once a year. Dig out the filler material. And fill it
once again with clean materials.
6.5 Design of recommended processing and disposal options
The detailed drawings of the processing and disposal facilities have been provided in
annexure. The design details are provided for each of the facility below.
6.5.1 Waste Segregation Facil ity
The waste arriving at the integrated waste management facility is weighed at the gate and
data recorded. The vehicles arriving are smart segregated. Waste from the markets and
segregated wet waste to an extent of 0.5 tons per day is sent to the vermicompost facility.
The balance of the materials are taken to the segregation facility and tipped, which is
followed by aerobic composting process.
6.5.2 Aerobic composting facil ity
Aerobic Composting is used for stabilizing organic matter. Composting can be used for
mixed wastes and results in production of stable product- compost which depending upon
its quality can be used as soil conditioner or potting medium. In this section the detailed
design and technical specifications of the compost facility are discussed.
Aerobic Waste decomposition processes: an overview
Aerobic composting involves the stabilization of the organics into compost by
microorganisms, which require the oxygen in air for their survival and growth. During this
process of conversion heat is released. There are ideal limits for different parameters within
which these microorganisms survive. Adequate moisture is required for the microorganisms
to survive and composting to take place. If these conditions are ensured to be stable the
compost quality and time of composting process can be controlled. In batch conditions the
composting process continues at progressively reducing rate as the oxygen becomes a
limiting factor or organics get consumed. To ensure the survival of these organisms the
availability of oxygen in the waste being composted has to be ensured through provision of
air. For economic reasons the time of composting is restricted till the major conversion is
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
65
done and subsequently compost maturing is taken up till the compost is safe for application
to plants. The organics typically have high moisture and in the compost process this is
removed. There are different possible configurations of holding waste and providing air for
aerobic composting. The selection of this is based on economics and competence in
handling technology.
The various parameters that affect the composting process and the compost quality are
organisms’ population, carbon Nitrogen ratio, temperature, aeration and moisture. The
above-mentioned controlling parameters need to be monitored in the industrial scale plant.
In large composting operations it is necessary to monitor the wastewater, which comes out
of the organic waste, called leachate. The production of this leachate has to be minimized
and whatever leachate is generated has to be collected and reused for maintaining the
moisture content of the heap and as an inoculum.
Design choices There are many alternative approaches, which have been adopted for
composting of municipal solid wastes based on the broad principle of aerobic composting.
The following approach has been adopted for Khanapur.
The waste as received is pre-sorted. The waste is formed into windrows and aerated. Roof is
proposed for the composting yard. The design is based on a 35-day waste composting cycle
with 15-day additional provision in concrete yard for additional waste load and for
management during monsoons.
Sizing of plant
The composting plant has been grouped into 3 parts. The inertising part, which is the basic
composting process consisting of the wastes windrowing process including aeration so that
a stabilized material is produced. The second part is the compost segregation plant also
called the processing facility where the stabilized wastes are segregated into compost and
rejects and finally maturation and storage part.
The process Flow
The proposed type of waste processing facility is Windrow Composting system. Turning of
windrows is done using front-end loaders and optional primary air supply is through
blowing. The step-by step process operations are given below. The various aspects, which
come into play at each of the steps, are also given.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
66
FIGURE 6-4: SQUEEZE TEST TO ESTIMATE MOISTURE CONTENT
Stabilizing Facility
Step 1: The waste is transferred from segregation facility to the aerobic composting yard.
Step 2: The segregated waste is sent to the windrow platform. The windrow is then sprayed
with cow dung or bio culture slurry. The cow dung or bio culture slurry is made in mixing
tank provided.
Step 3: The windrow is maintained for 7 days. The temperature is monitored to ensure that
the composting process is ongoing. The leachate from the windrow comes out and is
collected in the drain. The drain is connected to the leachate tank. The leachate from
leachate tank is used for making the inoculums slurry.
Step 4: At 7 days from start the first windrow is reorganized. The waste volume would have
reduced by about 20 % compared to start with moisture reduction and degradation. While
re-forming the windrow addition of inoculums slurry and water to maintain the moisture is
done using the trailer mounted slurry tank. The temperature profile in the second windrow
is monitored. The leachate from the windrow may come out and is collected in the drain.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
67
Step 5: At 14 days from start the second windrow is reorganized. The waste volume would
have reduced by about 20 % compared to start of windrow 2 with moisture reduction and
degradation.
The balance of the waste is reformed into the third windrow. Addition of water is
undertaken if required. The temperature profile in the third windrow is monitored. No
leachate is expected from now on.
Step 6: At 21 days from start the third windrow is reorganized. The waste volume would
have reduced by about 20 % compared to start of windrow 3. The wastes are reformed into
the fourth windrow. Addition of water is undertaken if required. The temperature profile in
the fourth windrow is monitored.
Step 7: At 28 days from start the fourth windrow is reorganized. The waste volume would
have reduced by about 5 % compared to start of windrow 4. The wastes are reformed into
the fifth windrow. Addition of water is undertaken if required. The temperature profile in
the fifth windrow is monitored. This is the maturing stage of the compost.
Step 8: At 35 days the waste is now composted and it is transferred to the processing line
initial hopper.
Waste processing facility
Step 9: The aerobic composting waste is fed into the trommel in the processing line using a
front-end loader. The waste is drawn from the hopper using a conveyor. It is transferred to
another conveyor, which lifts it into the first rotary sieve. The rotary sieve has 35 mm
punched holes.
The waste not passing through the sieve is the reject, which is then transferred using the
belt conveyor to the reject platform. The material passing is then transferred to the second
rotary sieve using belt conveyors. The second sieve has 14 mm holes. The materials not
passing through the sieve is transferred out using a chute. The materials passing through the
sieve is transferred using a chute to a heap. The compost at the heap is further processed
with admixtures or directly bagged for sale.
The material of size between 35 mm and 14 mm is sold as grade II compost and the
materials less than 4 mm is grade I compost. Additional products with different admixtures
are made and sold as niche products. The present design does not provide the mixing and
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
68
grinding facility for compost upgradation, as this would depend on marketing plans. Space
for provision of these facilities is provided. Bagging is proposed manually.
Step 10: Materials recovery from the rejects is undertaken and the recyclables are stored in
the recyclables shed.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
69
The reject are taken out for disposal in landfill daily. The recyclables are sold when adequate
quantity is available for transport. The compost is sold as per demand.
TABLE 6-3 MATERIAL FLOW
Process Material Flow Khanapur (TP)
Pro
cess
ing
Ist Stage Incoming Waste Feed Material Town Garbage Material Properties Mixed MSW TPD Volume Reject
Incoming Garbage Inoculants Addition 7.34 12.23 Moisture Addition Sanitisation (at 55-65o C) for two weeks
Ist Heap / Windrow Formation (Moisture: 55 - 65%) 5.87 8.01
2.20
IInd Heap / Windrow Turning (Moisture: 55 - 62 %) 5.14 7.28
Decomposition (at 55-65o C)for two weeks
IIIrd Heap / Windrow Turning (Moisture: 55%) 4.40 5.24
IVth Heap / Windrow Turning (Moisture: 55 - 62 %) 4.03 4.00
Shifting in Rain shed 3.67 3.64 IInd Stage Feed Material Digested Compost (from Yard) Material Properties Moist, Bumpy, Heterogeneous, Sticky Coarse Segregation
Lump breaking, opening up , segregation and screening of fine material. (Below 35 mm)
3.67 3.31 0.73
Screening and Separation of material 2.93 2.38
1.10 (Below 14 mm) Oversized Rejections 1.83 1.49 (For recycling or sanitary land filling) IIIrd Stage Feed Material Screened material (Below 14 mm) Material Properties Moist, Lumpy, Sticky Curing Shifting of material to curing section for
further digestion / maturation &moisture management
1.15 0.93
0.23 Addition of Rock Phosphate, mixing & 0.92 0.74
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
70
Process Material Flow Khanapur (TP) turning
Shifting of material to refinement line.
Com
post
Ref
inem
ent S
ectio
n
IVth Stage Feed Material Screened Material (Below14mm) Material Properties Moist , Sticky Refinement Screening and separation below 4 mm,
Oversized rejections sent for re-sanitisation.
0.73 0.60 0.18
Separation of heavy impurities as sand , glass , stones etc. 0.55 0.45 0.04
Standardization and Quality control.
Mixing of additives (Liquid/ Granules) to improve quality of end products.
0.51 0.42
-0.04
Storage Finished goods packing and shifting to storage section.
0.55 0.45
Rejects going into the Landfill 1.14
FIGURE 6-5 : SWM WASTE PROCESS FLOW CHART
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
71
TABLE 6-4: ARRANGEMENT AND TURNING OF WINDROWS
In general, as the average windrow shape is between an oval and trapezoid a factor of 0.66 is assumed to estimate windrow volumes, therefore the equation for volume of the windrow is: Volume = Height X Width X Length X 0.66
Windrow dimensions should allow conservation of heat generated during composting process while also maintaining diffusion of air to the deeper portions of the windrow Windrows should be turned frequently, once a week over 5 weeks to maintain aeration, porosity and enhance degradation Frequency of turning depends upon: • moisture content, • porosity of material, • rate of microbial activity, and • desired composting time
6.6 Vermi composting
The mostly organic waste arriving at the facility is directed to the vermicomposting
decomposing yard. The waste is windrowed for a period of 15-20 days to undergo partial
decomposition. The vermi composting process starts with partially decomposed waste. A
separate covered shed with 0.5 TPD capacity is already present at the site..
The earthworms eat the partially decomposed waste and produce casting. The casting of the
worms is the vermicompost. The degradation process in vermi composting takes places
inside the worm body by microorganisms. The selection of worms to obtain the best yield
per worm is available. The crux in this process is to get the worms to survive. The conditions
for survival of the worms have to be maintained in terms of the food availability, food
quality, moisture content and safety from predators. Another important aspect is that the
vermi castings have to be routinely removed. The whole vermi composting operation has to
be done manually and require more care and effort. In terms of the infrastructure
requirement the vermi composting takes off from the aerobic composting and simple
covered sheds are adequate.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
72
7 Design of Landfill
7.1 Design and Development of Sanitary Landfill Facility
The construction of landfill facility for all the cells shall be as per the specification and
drawings. Design of each cell of landfill facility is decided as per the topographical conditions
of the site area, subsequently development should be in same sequence. The Design
Fundamentals of Sanitary Landfill site at Khanapur is presented in the table below.
Sr.No. SLF Components Units Details 1 Total Waste to be disposed in SLF for next 25 year Ton 82125 2 Waste to be disposed in SLF every year Ton 3285 3 Waste to be disposed in SLF daily Ton 9 4 Present Available area for SLF activity Sq. m 2439 5 Number of proposed Cells Number 2
6 Dimension of Proposed Landfill Cell L1 (Height of Cell Total 10 M - 5 M below ground and 5 M above ground Level)
Length (M) 48
Breadth (M) 25
7 Dimension of Proposed Landfill Cell L2 (Height of Cell Total 10 m - 5 M below ground and 5 M above ground Level)
Length (M) 59
Breadth (M) 21
8 Required Area for next 25 year for SLF + Bund area Sq. m. 2511 9 Existing Area can cater to the requirement for next Years 24
10 Additional Landfill are Required for ULB after complete use of Existing Site
Sq.m 72
11 Bulk density of compacted solid waste Ton / M3 0.8 12 Waste application height meters (above
ground level) 5
13 Bottom liner slope (Transversely) % Towards center of each
cell.
1%
14 Leachate drainage slope (Longitudinal) % Towards leachate sump.
1%
15 Inner side slopes of Embankment (V: H) 01:02.5 16 Outer side slopes of Embankment (V: H) 01:02.5
7.2 Bio Remediation at previous engineering site
Bio-remediation is use biological organism to solve environmental problem. It is the
collective range of cleanup methods by using natural micro-organism (such as bacteria,
plant, Fungi etc) to degrade hazardous organic contaminants to environmentally less toxic.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
73
FIGURE 7-1: OPTIONS FOR TREATMENT OF EXISTING MSW DUMP ON THE SITE
Process of Bio-augmentation - Since the treatment is proposed only for the remaining
degradable waste on site, the process of bio-augmentation is very simple and cost effective.
• Step 1 – Loosening of waste using tractor or Back Hoe Loader.
• Step 2 – Spraying of Bio-culture on the waste ( for decomposition of remaining waste)
• Step 3 – Sieving the degraded waste - Sieved out waste can be used as manure.
• Step 4 – Rejected waste will be recyclable and inert. - The recyclable waste will be recycled and the inert waste will be used for leveling at dumping site.
Following table explains the
TABLE 7-1: AREA AT LANDFILL SITE AFTER BIOREMEDIATION AND SEGREGATION
Area of the previous engineering landfill site 2379 sq m Assuming Depth of previous engineering landfill site 2.5 m Volume of Waste to be Bio remediated from previous engineering landfill site 5947.5 cu m Assuming Density of Waste 0.7 Total weight of Waste in previous engineering landfill site 4163.25 Ton Inert waste (10%) to be resent to landfill 416.325 Ton Area required to be deducted (to resent inserts to landfill) 59.5 sq m Net area available from previous engineering landfill site after Bio Remediation 2320 sq m Existing Area can cater to the requirement for next 24 Year Total area available for landfill site after application of Bio remediation to previous engineering landfill site 4759
sq M
Total Area can cater to the requirement for next 47 year
Existing Dumping Site
Bio Remediation Segregation
Compost Plastic Paver Block Construction
Inert
Packaged & Sold Off
RDF & Road Construction
Debris for Road Construction
For Land filling
New Sanitary Landfill Site
Recyclables
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
74
The following method of Bio remediation; i.e. Bio Augmentation will be suitable for the
treatment of the dumped waste. In Bio Augmentation, the current solid waste has to be
loosened with a tractor or Excavator. After the loosening, the culture will be sprayed on the
solid waste. It will increase the rate of degradation of the waste. After this stage, sieving of
the degraded waste will be done and sieved out waste will be manure and can be used as
compost. The rejected waste which will be inert or recyclable can go into landfill or into
suitable processes for recyclable waste.
Sl. No. Fractions Resource
Description % recovery Application Remarks
1 Finest Fraction
Organic matter + fine Soil Bio-Earth A grade
30% Manure in organic farming
As a soil improver, restoring alkaline or saline soils to fertility, improves soil breathing and water retention capacity
2 Coarser Fraction
Coarse Organics and sand Bio-Earth B grade
30%
Manure cum soil aggregate in farm applications
Used to control soil erosions, as a organic manure in tree pits, improves soil breathing and water retention capacity
3
Heavy Fraction
Pebbles (Between 20 and 40 mm)
10% Construction and filling in low lying areas
Used for road shoulders
4 Pebbles (Between 40 and 80 mm)
8% Construction and filling in low lying areas
Used for road shoulders
5 Tender cocoanut shells 2% As a Fuel Used to produce bio-bricks and
in hydroponic cultivation
6 Light fraction
Plastic and other recyclables 10%
Recycling Reduces the use of virgin materials
7 Non recyclable combustibles
P2F (Plastic to Fuel)
Increasing diesel prices making P2F more attractive
8 Residuals Inert materials 10% Land filling Extends the life span of land fill sites
On the landfill site of the 10% of inert waste need to be re dumped on landfill after
bioremediation. As explained above, the required area considering the volume to be
deposited on landfill after Bioremediation and segregation along with the volume required
for sanitary landfill site is given.
7.2.1 Construction Procedure
Construction of landfill should be followed in the sequence given below:
S. No. Activity Possible Parallel / Independent Activities 1. Grading and leveling Service road around the site, fencing & green belt area
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
75
S. No. Activity Possible Parallel / Independent Activities
2. Side soil bund Power supply, water supply, Workshop, leachate pond, office buildings, compost yard, weigh Bridge, waste segregation platform
3. Bottom liner system Storm water drain around the side soil bund
4. Leachate collection and conveying system
Leachate collection sump
5. Side liner system Bottom liner system 6. Leachate collection sump Installation of pumps
7. Installation of pumps for Transferring leachate
8. Storm water drain around the side soil bund
Peripheral service roads, green belt
9. Monitoring wells 10. Approach Road Storm water drain 11. Green belt area 12. Top liner system
7.2.2 Grading, Leveling and Base Formation
Before the construction of landfill facility, site shall be properly cleared from any shrubs and
bushes. A benchmark has to be fixed at an immovable known point. Site shall be leveled and
compacted. As the highest ground water table is at about 1 m from ground level, it is
suggested to have filling by hard murum of 0.5 m thick and compacting the same. The filler
material is leveled to get the desired slope of 1 %.
FIGURE 7-2: LINE PLACEMENT AT EDGES OF LANDFILL
FIGURE 7-3: LINE PLACEMENT AT EDGES OF LANDFILL
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
76
7.2.3 Side Soil Bunds
In order to prevent the sliding movement of the waste, earth bunds has to be constructed
over the sides of landfill. The soil bunds are of trapezoidal shape. As per the design, the
landfill is 6 meters above the ground level and 4 meters below ground level. Total height
considered is 10 meter. The inside slope is of 1:2.5 (V: H). Soil bunds shall be of hard murum
with required specification. The soil has to be tested as per the parameters mentioned in
Quality assurance plan. During construction of bunds, soil has to be laid in layers of about 30
cm and each layer has to be well compacted before going for next layer. During compaction
the soil shall be at its optimum moisture content so as to achieve maximum compaction.
Soil bund is of 3 meters height with inner and outer slopes of 1: 2.5 (V: H). the top width of
soil bund is 3 meters.
FIGURE 7-4: PLACEMENT OF THE HDPE LINER OVER THE CLAY LINER
FIGURE 7-5: PLACEMENT OF THE GRAVEL DRAINAGE LAYER AND GEOTEXTILE OVER THE CLAY LINER
FIGURE 7-6: LEACHATE COLLECTION PIPES ARE TO BE CONNECTED TO A SUMP, THROUGH THE LINER
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
77
7.2.4 Bottom & Side Liner System of Sanitary Landfil l Facil ity
A liner system is the barrier that separates waste from the environment. The bottom and
sideliner system must effectively stop the migration of leachate from the landfill for many
years. In order to prevent the migration of leachate from the landfill facility, the bottom and
side lining system is of minerallic type, with different layers and specifications. First after
grading and leveling the site, filling by hard murum is carried out as per the designed slope.
Over the filled material, 90 cm thick clay liner has to be laid. While laying clay liner, the
permeability of clay should be lesser than 1 x 10-7 cm/sec and the moisture content shall be
at its optimum moisture content. Clay layer of bottom liner shall be laid in layers of about 45
cm thick and should be well compacted with a vibrating Roller of 4 to 5 tons. After
compaction the clay layer shall be left out for natural drying and settlement for at least 5 to
6 days. If any cracks develops in clay liner that has to be grouted with bentonite.
FIGURE 7-7: WELDING OF HDPE GEOMEMBRANE
Over the clay liner, a High Density Poly- Ethylene (HDPE) liner of 1.5 mm thick has to be
provided. The joints of the HDPE liner have to be welded by Lap joint method. HDPE liner
shall be of two sides textured. Over the HDPE liner, a Geo-textile membrane of 1.5 mm thick
of non-woven type & Poly-propylene (PP) make should be laid. The textile portion of geo-
textile shall be facing upside. The purpose of Geo-Textile is to protect HDPE sheet from any
shock loads, which may be due to vehicle movement. Over Geo-Textile liner, a drainage
layer of thickness of about 30 cm has to be laid uniformly on entire bed of bottom area. This
drainage layer is for effective collection and conveyance of leachate coming out from waste.
Therefore, the permeability of the drainage layer shall be greater than 1 X 10-2 cm /sec.
The sideliner system should be same as bottom liner.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
78
BOTTOM AND SIDE LINER SYSTEM
7.2.5 Leachate Collection & Conveyance System:
In order to collect and convey the leachate to the collection sump, the leachate collection
channel has been designed. The leachate collection drain, from the middle of each cell as
shown in drawings has to be constructed first. The generated leachate will be collected in
the channel due to bottom transverse slope of 1.0%, and conveyed by gravity to sump due
to longitudinal slope of 1.0%. For collection and conveyance of leachate to sump, a
perforated HDPE pipe of 30 cm ID has to be laid as shown in drawings. The pipes should
have rectangular slots of size 20 mm x 5 mm, placed at spacing of 100 mm/cc in the
longitudinal direction and 50 mm spacing laterally. The slots shall be placed along the length
of the pipe only on the sides with 20 mm side of slot being parallel to the longitudinal axis of
the pipe, in a zigzag pattern as shown figure below:
SCHEMATIC DIAGRAM SHOWING PLACEMENT OF RECTANGULAR SLOTS IN LEACHATE COLLECTION PIPE
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
79
The leachate collection channels have to be packed with drainage material. The slopes of
the pipe should be such that, the leachate should flow easily into the leachate collection
sump later on the leachate from sump has to be transported for treatment.
FIGURE 7-8: WELDING OF LEACHATE PIPES
7.2.6 Leachate Collection Sump
RCC sump of 6 X 3 X 1.8 cum temporarily covered with RCC slab has been recommended to
be constructed for collection of leachate from “leachate collection system”. The
construction of the sump shall be gradual with the filling of the waste. A clear depth of 1
meter has to be maintained between the bottom of sump and leachate connection pipe.
About 20mm thick plastering has to be done at the inner and outer side of sump. Epoxy
powder (which acts as water proof agent) has to be used during plastering. The RCC slab has
been provided with a manhole of 1 m x 1 m through with a monkey ladder. The manhole
has to be covered with hinged steel gate in order to avoid the entry of rainwater into the
sump. The collected leachate from sump has to be transferred to leachate pond by
pumping. After closure of Sanitary landfill Facility, appreciable quantity of leachate is not
expected to be generated, however, if any leachate is generated it has to be transferred to
leachate pond.
7.2.7 Installation of Pumps for Transferring Leachate
The leachate has to be pumped to the leachate pond. Two pumps (non-corrosive type) of 2
HP each (discharge 25 m3 /hr and total maximum head of 25 m) have to be installed in each
leachate collection sump. These pumps may be installed at the RCC slab of collection sump
with proper rainwater protection. While one will be active the other will serve as standby.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
80
During heavy rainfall, both the pumps can be operated. The sump has to be covered and
protected against rainwater.
FIGURE 7-9: SUPPORT OF LEACHATE PIPES
7.2.8 Storm Water Drainage System of Landfil l
Storm water drainage is one of the main components of landfill facility. The arrangement
shall be such that, the storm water from landfill facility has to be collected effectively in
drainage system and conveyed away from facility with in short time. Storm water drain shall
be of trapezoidal shape with brick lining. The inside part of drain has to be plastered with
cement motor. Storm water drain shall be constructed all along the outer periphery of soil
bund
7.2.9 Monitoring Wells
Monitoring wells have to be constructed around the facility for periodic monitoring of the
quality of ground water. The monitoring wells to be provided along the four corners of
landfill facility. The groundwater at a regular time interval must be monitored for the
specified parameters. The frequency of monitoring can be monthly in the first 5 years of
operation of the facility, thereafter quarterly up to 25 years or till the life of the facility is
exhausted and semi-annually after closure of the facility (for 5 years after closure of the
facility).
7.2.10 Approach Road and Service Road at the Facil ity:
A main approach road of 6 m wide from the main gate running parallel between the landfill
and compost yard till the southeast end of the facility is suggested.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
81
7.2.11 Green Belt Development:
The green belt development around landfill facility will ensure the reduction in soil erosion
and air pollution due to dust suppression. This also increases aesthetic value of the area. As
per the design, about 3 m wide green belt along the periphery and shall be developed
accordingly.
7.2.12 Office Building & Laboratory:
In order to manage the operation and maintenance of the facility and to maintain the record
of daily waste disposal, an office with necessary furniture and other facilities has to be
established at the site area. A laboratory will have to be set up in order to analyse waste
samples and to carry out monitoring activities with regard to air and water and some time
soil if required.
7.2.13 Other Infrastructure Facil ities:
Apart from above, other facilities such as electricity for lighting arrangement in SLF area,
weighbridge, fire protection equipment, personnel protective equipment, drinking water,
storage area for equipment, shelter for machinery & vehicles and security cabin will be
required during operation and maintenance of SLF. Periodically, crawler dozer will be
required for layer wise compaction of waste. A 300-micron thick LDPE/HDPE sheet, sand
filled bags will also be required for intermediate covering of waste during rainy seas
7.2.14 Final or Top Cover
The prime function of a final cover or the top liner system is to minimize infiltration of
precipitation. Other functions include preventing the contamination of surface run off, wind
dispersion of municipal solid waste and direct contact of the municipal solid waste with
humans and animals. For long-term performance with minimum maintenance, the final
cover is designed to promote surface drainage and minimize erosion. After the operational
life, each cell of landfill facility has to be closed and covered with suggested top cover
system, as shown below:
• Over the foundation layer, 30 cm thick gas drainage layer has to be laid with 16-32
mm size gravel.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
82
TOP LINER SYSTEM
• The gas outlet pipe should be connected to the gas drainage layer. The gas outlet
pipe is to remove the gas generated from consolidated waste after complete closing.
• Over the gas drainage layer, 60 cm thick clay layer should be laid. The permeability of
clay should be less than 1 X 10-7 cm/sec. During laying of clay layer, the moisture
content in clay should be as per the optimum moisture content in order to achieve
permeability factor shown above. The clay liner shall be laid in two layers each of
thickness 300mm. Each layer of clay shall be well compacted with a vibratory roller
of 4 to 5 tons.
• Over the clay liner, 30 cm thick storm water drainage layer has to be laid with 16-32
mm size gravel. The permeability of drainage layer should be more than 1 X 10-2
cm/sec.
• Over the drainage layer, 45 cm thick native soil should be provided for vegetation in
two layers. The first layer has to be compacted, other two layers has to be left loose
for the growth of vegetation. A vegetation cover has to provide at the top of the soil
in order to prevent the soil erosion due to precipitate and also for better landscaping
7.2.15 Tentative Cost Estimate for Sanitary Landfil l
The tentative cost estimate for development of the sanitary landfill and other infra-
structural facilities is presented in the following tables:
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
83
Sl. no Description of Work Quantity Unit Rate/Unit Cost (in Lakhs)
1 Grading and leveling 2511 m2 13 0.32 2 Filling material 2029 m3 180 3.66 3 Soil bund 1255 m3 180 2.26 4 Bottom liner system 0.00 30 cm thick drainage layer (K=1X10-2
cm/sec) 1883 m2 180 3.39
1.5 mm thick geo-textile 1883 m2 135 2.55 1.5 mm thick HDPE liner 1883 m2 451 8.48 90 cm thick clay liner (K<1 X10-7 cm/sec) 1883 m2 360 6.79
5 Side liner system (same as bottom liner) 301 m2 1171 3.53 6 Leachate collection drain including HDPE
pipe 291 RM 6307 18.35
7 Leachate collection sump (RCC) & pump for transferring leachate to ETP
14.4 m3 12615 1.82
8 Cover liner system 1255 m3 1171 14.71 9 Leachate pond 7.72 7.72 7.72 7.72
Sub-total 75.72
Adding 10% contingency 7.57
Total for sanitary landfill facility (25 years) 83.29
Total for sanitary landfill facility (12.5 years) 41.64
Total for sanitary landfill facility (12.5 years) – As per updated DSR 2016-17 46.63
7.2.16 Leachate from Landfil l
The Leachate from the landfill is mainly due to the rain water. Therefore, the Leachate
depends on the rainfall in the town.
TABLE 7-2 LEACHATE GENERATION
S.N Particulars Details Units 1 Annual Peak Precipitation 678 mm 2 Area of the Land fill 5213 sq. m 3 Monsoon duration 90 days 4 Leachate Generate from the SLF 39 litres
Leachate from the Waste processing, composting and SLF shall be collected & treated
together in Planted Gravel Filter.
TABLE 7-3 ESTIMATION OF LEACHATE TANK
S.N Particulars Units Details 1 Leachate Generate from the SLF 39 cum / Day 2 Leachate from Windrow & Waste processing area 10 cum / Day 3 Total Volume of Leachate Generation 49 cum / Day 4 Capacity of the Tank required 54 cum / Day
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
84
5 Total required length of the tank 8.5 M 6 Total required Width of the tank 2.5 M 7 Total required Depth of the tank 2.5 M 8 Total Volume of the Tank 54 cu m
7.2.17 Treatment of Leachate –Phytorid Treatment Plant
It is proposed to treat leachate from the landfill site using Phytorid Treatment Technology.
The treatment process has to have low operation and maintenance cost.
FIGURE 7-10 PHYTORID TREATMENT
This is the technology developed by National Environmental Engineering Research Institute (NEERI), Nagpur for the treatment of municipal and industrial waste water. The technology combines the physical, biological and chemical process without requiring any mechanical equipment (thus eliminating the need for electricity and maintenance of equipment). The Technology provides clean and aesthetic solution for the treatment of wastewater which is generally thrown in open at the disposal points. BOD and COD removal is reported to be achieved as 80 – 90 %. The components of the technology include
• Primary Settling cell (PSC) for the purpose of anaerobic pre- treatment of suspended solids.
• Secondary Advanced Filter cell (SAFC) that contains different sized stones and gravel wherein anaerobic digestion occurs.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
85
• Tertiary Biological wetland Cell (TBWC) made up of life supporting media (again stone and gravel) and planed with aquatic flora such as Typha, Scirpus, Cyperus, Peltandra, Phragmites etc. This is fairly new technology and has been tested successfully a few places in Maharashtra
7.3 Material Specifications for Sanitary Landfill
The specifications and quality aspects of the Landfill facility is very important, in order to
achieve designed performance of sanitary landfill facility. Liner system of landfill facility has
been designed in consideration with following points;
• To prevent migration of waste, leachate to the adjacent subsurface soil or ground water or surface water.
• Material specified for liner has adequate chemical properties, physical properties and engineering properties to prevent failure on account of loads, climatic conditions, and contact with waste or leachate.
• Slopes at bottom and sides area designed to withstand Liner material safely without any sliding movement.
7.3.1 Material Specifications for Liners and Drainage System
7.3.1.1 BOTTOM & SIDE L INE R
1) 1X90 cm thick compacted clay or compacted amended soil with permeability less than
1X10-7 cm /s with the following specifications:
• Permeability to be checked before and after laying • Free of any stones, kankars and any other foreign material • Moisture content to be maintained during laying as per OMC. (Optimum Moisture
Content) • To be compacted so as to achieve Proctor Density • To be laid in 2 layers each of 30 cm thick • Permeability & moisture content has to be checked in each layer. • To be kept covered during installation so that moisture is not evaporated.
2) 1X 1.5mm thick HDPE Geo-membrane of following specification:
• Tensile strength at yield greater than 18 KN / m. • Tensile Strength at break greater than 30 KN / m. • Tear Resistance greater than 150 N • Puncture Resistance greater then 250 N
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
86
3) 1 X 1.5 mm thick Geo-textile;
• Type – Non woven • Make – PP • 200 GSM
4) 1 X30 cm thick Leachate drainage layer;
• Material – Sand or any other granule with permeability greater than 1 X 10 –2 cm /sec
• Size Gradation – 16 to 32 mm • Dust free • Kankar free • Rounded gravels • Free of any angular or sharp aggregates • To be laid as 30 cm thick uniform layer
7.3.1.2 LEACH ATE DRAINA GE SY STE M
The construction details of leachate drain is as follows:
• Longitudinal slope of leachate collection pipe shall be 1.0%. • The bottom and sides of HDPE pipe has to be filled with the mixture of cement,
bentonite and sand. • The HDPE pipe has to be covered with 200 GSM geo-textile to prevent clogging of
slots by drainage material / other solids. • Over HDPE pipe Gravel size of 16mm to 32mm has to be laid uniformly.
The specification of material to be used for leachate drain is given below:
1) 1 X 1.5mm thick geo-textile – 200 GSM
2) Mixture of sand, cement and bentonite shall be in ratio
94%: 3% : 3% respectively.
3) Specification for HDPE pipe.
Internal Dia. –285 mm Outer Dia. – 300mm Wall Thickness –15mm Pressure Rating- 4 Kg/cm2
7.3.1.3 TOP LINE R SYSTE M
1) 1 X 60 cm thick compacted clay or compacted amended soil with permeability less than
1X10-7 cm /sec.
Permeability to be checked before and after laying Free of any stones, kankars and any other foreign material
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
87
Moisture content to be maintained during laying as per OMC. (Optimum Moisture Content)
To be compacted so as to achieve Proctor Density To be laid in 2 layers each of 30 cm thick Permeability & moisture content has to be checked in each layer.
2) 1 X 30 cm thick drainage layer
Material – Sand or any other granule with permeability greater than 1 X 10 –2 cm /sec
Size Gradation – 16 to 32 mm
Dust free
Kankar free
Rounded gravels
Free of any angular or sharp aggregates
To be laid as 30 cm uniform layer
3) 1 X 45 cm, fertile soil for vegetation
To be laid in two layers; the bottom layer to be compacted mildly and the top layer to be kept loose for growing vegetation.
Vegetation cover with Grass, shrubs etc. having root length <30 cm
7.4 Operation Plan of Sanitary Landfill
7.4.1 Construction and Operational Plan
The operation of a landfill shall consist of the following steps:
• Operation before waste is transported to landfill facility
• Operation during disposal of waste into landfill facility
• Closer plan
• Record keeping
• Monitoring
7.4.2 Operation before Transportation of Waste
7.4.2.1 SITE DEVE LOPMENT:
The following construction activities shall be carried out along with construction of landfill
facility before disposal of waste.
• Construction of perimeter fence, entrance gate, weighs bridge and green belt.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
88
• Construction of main access road near the entrance gate with parking area.
• Construction of service road along the perimeter of the site and well as construction
of approach road.
• Construction of waste inspection facility, equipment workshop and garage, vehicle
cleaning area.
• Installation of direction sings, site lighting, fire fighting facilities, communication
facilities.
• Construction of water supply and waste water/sewage disposal.
• Construction of surface water drainage system.
• Construction of main leachate pipe, sump and leachate pond.
• Installation of environmental monitoring facilities.
• Construction of emergency exit gate.
7.4.2.2 SITE PROCE DURE S: REC ORD KEE PI NG & WA STE INSPECT I ON:
Records shall be kept on a daily, weekly and monthly basis. In addition a site Manual shall
be kept at the site office giving all site investigation, design and construction details The
following records shall be maintained during operation of landfill
(i) Landfill Manual: The site manual shall contain the following information:
• Data collected during site selection
• Environmental assessment report
• Site investigation and characterization data
• Detailed topographical map
• Design of landfill components
• Landfill layout and its cells
• Construction plans
• Details of leachate management plan
• Details of gas management plan (optional)
• Environmental monitoring program
• Closure and post-closure plan
• All permissions / license from concerned authorities.
(ii) Site Reports: The daily, weekly and monthly reports shall comprise of the following:
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
89
• Weighbridge data (daily inflow and outflow for each vehicle)
• Waste inspection data (daily)
• Materials, stores etc. (daily)
• Bills/accounts (daily)
• Visitor record (daily)
• Complaints record from nearby areas (daily
• Topographic survey at operating cell (daily/weekly)
• Photographic record at operating cell (daily/weekly)
• Environmental monitoring data (weekly/monthly)
• Waste filling plan and actual progress i.e., cell construction (daily/weekly) and review
(monthly)
• Leachate generation and gas generation (weekly/monthly/extreme events)
• Weather/climatic data (extreme events)
• Accidents etc.
• Others.
(iii) Vehicle Inspection:
Each vehicle carrying the waste shall be checked for:
• Incoming weight (full)
• Outgoing weight (empty)
• Available of relevant documents
• Visual check at weigh-in (if feasible)
• Visual inspection after discharge at tipping area (inspection report to be filed for
each vehicle). A visual inspection checklist must be framed which should list visual
features for identification of unacceptable material. This checklist shall be filled for
every unloading by a vehicle in tipping area at the working cell in the landfill.
7.4.3 Operation during Disposal Of Waste Into Landfil l Facil ity
At the design stage, the cells of a landfill are clearly demarcated. Operation of a cell
requires planning and execution of daily activities such as daily waste filling plan and
demarcation, waste discharge & inspection, waste placement, waste compaction, daily
covering of waste, prevention of pollution & fires, etc.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
90
7.4.3.1 DAILY WA STE FILLING PLA N A ND DE MA RC AT I ON AT SITE:
On the completion of a cell and before the start of a new cell, a waste-filling plan for daily
cells shall be evolved. A study of the landfill base contour maps and the final cover levels of
the cell allows such a plan to be developed. If a cell is to be operational for 365 days, all 365
cells must be marked in plan and in sectional drawings. These may require revision as a
landfill is constructed because waste quantities may vary in an unforeseen manner. The
area and height proposed to be filled every day should be demarcated at the site on a daily
or weekly basis using temporary markers or bunds.
7.4.3.2 WASTE DISCHA RGE & IN SPEC TION
Waste shall be discharged by tipping at the working area of a landfill, within the area
demarcated for the cell. A designated operator shall visually inspect every discharged load.
Working area personnel shall be trained and competent at waste identification in order that
they can recognize waste, which may be non-conforming. In the event of reasonable doubt
as to the waste acceptability, the operator shall inform the waste reception facility and/or
the site manager immediately.
7.4.3.3 WASTE PLACEME NT (SP READ IN G) & COMPA CTI ON
Once waste has been discharged it shall be spread in layers and compacted in a well-defined
manner to ensure that the completed slopes of a daily cell are at the designed gradients.
Waste placement (spreading) can be done by the following methods:
• Face tipping method: Waste is deposited on top of existing surface and spread
horizontally by tipping over an advancing face.
• Inclined layering method (onion skin tipping): Similar to (a) but inclined layering
(gentile slope) done instead of advancing of face.
• Working upwards: Waste is deposited on the lower surface and pushed upwards.
It is necessary to level and compact the waste as soon as it is discharged at the working
area. Steel wheeled mobile landfill compactors (smooth / cleared / spiked / special wheels)
are generally accepted as the best equipment for this purpose. They have largely replaced
the small crawler tracked machines, which were previously in general use.
7.4.3.4 POLLU TION PREVE NTION & SA FET Y DU RIN G OPE RA TI ON:
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
91
The following measures are needed to ensure that the landfill operation shall not adversely
affect local environment within and outside the landfill.
• Traffic: Heavy lorry traffic shall give rise to nuisance, damage to road surface and
verges and routing problems. The following measures are helpful.
o Routing to avoid residential area. o Using one-way routes to avoid traffic conflict in narrow roads. o Carrying out road improvements, for example strengthening or widening
roads, improved provision of footpaths, improvement of sight lines, provision of passing places, provision of new roads.
o Limiting the number of vehicle movements. o Restrictions on traffic movement hours, which are staggered with respect to
peak traffic hours. • Noise: Adverse impacts on the local community from noise may arise from a number
of sources including: throughput of vehicles and fixed and mobile plant for example
compactors, generators at the site. Peripheral noise abatement site measures shall
be adopted.
• Odour: Offensive odours at landfill sites may emanate from a number of sources,
including waste material, which have decomposed significantly prior to land filling,
leachate and leachate treatment systems, and landfill gas. Good landfill practices
shall greatly reduce general site smell and reduce impact from odours, which could
lead to complaints from the local community, site users and site staff.
• Good practice includes: (a) adequate compaction; (b) speedy disposal and burial of
malodorous wastes; (c) effective use of appropriate types of daily cover, (d)
progressive capping and restoration; (e) effective landfill gas management; (f)
effective leachate management and (g) consideration of prevailing wind direction
when planning leachate treatment plants, gas flares, and direction of tipping.
• Litter: Poor litter control both on and off site is particularly offensive to neighbors.
Good operational practice shall be adhered to in terms of temporary fencing, waste
discharge, placement, compaction and covering to minimize the occurrence of
windblown litter.
• Bird Control: Birds are attracted to landfill sites in large numbers where sites receive
appreciable amounts to bio wastes. Measures, which can be used to mitigate birds’
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
92
nuisance, include good landfill practice, working in small active areas and progressive
prompt covering of waste, together with the use of bird scaring techniques.
• Vermin and Other Pests: Landfills have potential to harbour flies, rodents and
vermin, particularly where the waste contains biomaterials. Modern land filling
techniques including prompt emplacement, compaction and covering of wastes in
well-defined cells are effective in the prevention of infestation by rodents and
insects.
• Dust: Dust from landfill operations is mainly a problem during periods of dry weather
but can also arise from dusty waste as it is tipped. Dust is generally associated with
(a) site preparation and restoration activities, (b) the disposal of waste comprising of
fine particles, for example powders, and (c) traffic dust. Dust suppression can be
effected by (a) limiting vehicle speed; (b) spraying roads with water and (c) spraying
site and powder type waste with water; (d) covering powder type waste with daily
soil cover.
• Mud on the Road: Mud on the public highway in one of the most common causes of
public complaint. It is therefore, in the interest of the landfill operator to provide
adequate wheel cleaning facilities to ensure that mud is not carried off site by
vehicles.
• Landfill Fire Management: Fires in waste on landfill sites are not uncommon and it is
important for site operators to be aware of the dangers, how to treat fires and to
address the problems associated with them. All fires on-site shall be treated as a
potential emergency and dealt with accordingly.
• Landfill Safety Aspects: Training of employees shall include: site safety, first aid and
the handling of dangerous materials where appropriate. Since landfill sites can pose
dangers to both site operator and users, emergency plans shall be laid down. Landfill
sites shall be regarded as potentially hazardous locations and the operator shall have
a written safety plan for the site. Safety hazards present at landfill sites may include;
(a) moving plant and vehicle; (b) steep slopes; (c) bodies of standing water; (d)
contaminated, putrescible, toxic flammable or infective material and (e) noxious,
flammable, toxic or hazardous gas. All employees and visitors to the site shall be
made aware of the potential hazards and the safety procedures to be implemented
including fire safety.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
93
7.4.4 Closure and Monitoring Plan Of Landfil l Facil ity
As each cell is completed and as the final cover level is reached in successive cells, the
following interconnectivities are established:
(a) The leachate collection system of each cell is sequentially connected (if so designed)
The surface water; drainage system at the cover of each cell is sequentially connected (of so
designed)
(b) Upon completion of all cells a final check is made of the proper functioning of all inter
connected systems.
An access road is provided on the landfill cover to enable easy approach for routine
inspection of the landfill cover.
7.4.4.1 POST CLOSU RE VE GETATIVE STA BIL IZA TION (LON G TE RM)
If a landfill cover is intended to be used for a specific purpose e.g. park or vehicle parking
area, then the cover shall be stabilized in such a manner that the end-use is achieved.
However, if no specific end-use is envisaged, then long-term vegetative stabilization shall be
undertaken to return the land to its original and natural vegetative landform.
Vegetation is by far the most common and usually the preferred stabilization option after
closure of landfills. If a self-perpetuating vegetative cover can be established, not only can
wind and water erosion be minimized, but also the landfill can be returned to some
semblance of its original appearance and land use. In favorable climates, re-vegetation may
require only modest effort or may occur by natural process during a reasonably short period
of time. However, in arid climates or a harsh environment, establishment of vegetation may
be a difficult and costly process and alternative techniques may be examined for vegetative
stabilization.
While the specific procedures are unique to each landfill and climatic regime, the following
representative elements of the process shall be adopted in all procedures.
(a) Short-term Vegetation: It is common practice, in both humid and dry environments, to
rely largely on grasses for the primary initial source of short-term land cover. Usually several
species are included in the initial seeding mixture to increase diversity and reduce the
chance of total community failure. Short-term vegetation is usually assisted by irrigation.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
94
(b) Long-term Vegetation: To achieve the ultimate goal of attaining a self-sustaining and
stable community, a transition between short term and long-term vegetation must occur. In
some cases, this may be left to invasion by native species after short-term vegetation is
assured and soil development is well under way. In other cases – for example, when
irrigation has been used temporarily to establish the short-term community, it may be
necessary or desirable to enhance the natural succession process by replanting with a more
diverse mix of species suited to the next stage of community succession. The need for
artificial enhancement of the successional process shall depend on the success of previous
short-term efforts and on the ultimate intended land use. All vegetation efforts, however,
shall work toward self-generation and minimum management in the long term.
7.4.5 Record Keeping
7.4.5.1 DURING CONSTRUC TION OF LI NERS AND COVE RS
• During the construction of liners and covers, inspection shall be carried by
independent agency / KSPCB (or its nominee) at least twice during each cell to
ensure that construction procedures and quality assurance plan are being followed.
• Immediately upon the completion of construction of a liner in each cell, the
complete set of construction records and quality control test results shall be
provided by the TP to the KSPCB for verification and record keeping. The same will
also be done upon the completion of cover system in each cell.
7.4.5.2 DURING OPE RATION
• The owner/operator shall monitor and keep a record of the following in the
operation period:
o Functioning of the leachate management system (including levels in leachate
holding tank) (weekly).
o Functioning of the surface water run-off system (weekly)
o Functioning of the gas management system (weekly)
o Waste filling records shall be kept on daily basis.
o Leachate sampling and monitoring shall be done 1 to 2 times a month.
Leachate shall be analysed for the parameters specified in Para 6.5. The
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
95
results shall be recorded and compared with the permissible limits provided
by the KSPCB.
o After a major storm, the occurrence of the storm and functioning of various
systems shall be recorded.
• The KSPCB (or its nominee) shall inspect all facilities at least twice a year. The
owner/operator shall provide a copy of the environmental monitoring record to the
KSPCB on a yearly basis.
7.4.5.2.1 DURING CLOSU RE AND POST CLOSU RE PER IOD:
Period inspection and routine maintenance at a closed landfill site shall be carried out for a
period of 15 years after closure. The KSPCB shall inspect all facilities during the closure and
post closure period at least once a year. The owner/operator shall provide a copy of the
environmental monitoring record to the KSPCB once a year. The following components of a
closed landfill shall be inspected visually after landfill closure to confirm that all functional
elements are working satisfactorily and inspection report will be recorded. A maintenance
schedule with specified reporting formats is drawn up after each inspection.
(a) Cover System:
The final cover is inspected 2 to 4 times a year (a) to check that vegetation growth is
occurring satisfactorily and that plants are not showing stunted growth (b) to detect if any
erosion gullies have been formed thereby exposing the barrier layers, (c) to earmark
depressions that may have developed with time and (d) to identify pounding of water on
the landfill cover. At least one inspection shall be carried out during or immediately after
the peak of the monsoon season.
Closed landfills show significant settlement. Rectification measures shall not only re-
establish the initial slope of the cover (for proper surface water run-off) but shall also ensure
that all the components of the landfill cover system continue to perform as originally
envisaged. TP shall have sufficient equipment and funds to periodically carry out
maintenance work in the form of soil filling, re-grading the cover and re-vegetating the
landfill cap.
In areas where extensive erosion gully formation is observed, filling of cover material,
regarding of cover slopes and re-vegetation must be routinely undertaken.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
96
(b) Surface Water Drainage System:
The surface water drainage system is also inspected 2 to 4 times a year (i) to identify cracks
in drains due to settlements. (ii) to delineate clogged drains requiring immediate clean up
and (iii) to study the level of deposited soil in the storm water basin and initiate excavation
measures. Broken pipes and extensively cracked drains may require replacement after
filling soil beneath them to establish slopes for gravity flow. In extreme cases where long-
term settlement shall be excessive, it shall become necessary to make sumps and operate
storm water pumps for removal of accumulated water in the drainage system.
(c) Leachate Management Systems:
A weekly operating record of leachate management systems shall be kept in the post-
closure period. Periodic inspection of the leachate collection systems (2 to 4 times a year) is
undertaken to identify broken pipes, leaking gas (if any) and damaged or clogged
wells/sumps. Repair work requires skilled manpower and shall be carried out by the
agencies operating the gas treatment and leachate treatment facilities. One may often have
to install new gas extraction wells and leachate collection wells if the damaged / clogged
facilities are inaccessible and irreparable.
7.4.6 Environmental Monitoring Systems:
Ground water monitoring wells, air quality monitoring systems shall be periodically carried
out to check that all systems are functioning satisfactorily and that well caps sampling ports
are not subjected to damage due to excessive settlement or vandalism.
Environmental monitoring systems have to be maintained during the entire post-closure
period. Wherever possible, monitoring instruments must be periodically re-calibrated.
Sampling devices shall be routinely detoxified and also regularly checked for proper
functioning of the opening and closing of valves or spring-loaded mechanisms.
The activities to be carried out under environmental monitoring plan are as follows:
Sl. No.
Activities to be Carried Out
Parameters to be Monitored Duration of Monitoring
1 Monitoring of groundwater quality at up and down streams in monitoring wells
pH, TDS, Cl, Sulphates, Nitrates, Total Hardness (as CaCO3), Phenolic Compounds (as C6H5OH), Fe, Zn, As, Cd, Cr6+, Cu, CN, Pb, Hg & Ni
Monthly
2 Monitoring of ambient air Suspended Particulate matter, CH4, SO2, NH3& Bimonthly
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
97
Sl. No.
Activities to be Carried Out
Parameters to be Monitored Duration of Monitoring
quality at landfill CO
3. Monitoring of leachate quality before and after treatment
pH, Turbidity, TDS, TSS, Ammoniacal Nitrogen, Kjeldahl Nitrogen, CN, Nitrates, Total Hardness (as CaCO3), Cl, F, Sulphates, Kjeldahl N, BOD, COD, Phenolic Compounds (as C6H5OH), Heavy Metals such as As, Hg, Pb, Cd, total Cr, Cu, Zn, Ni, CN etc.
Monthly during rainy season
4. Monitoring of landfill gas quality
CH4, CO2 & CO Monthly
5. Monitoring of surface water quality from drain channel at the exit of landfill
BOD, COD, TSS, TDS, Cl-& Heavy Metals Monthly during rainy season
7.4.7 Post-Closure Criteria:
After closure of the landfill, the owner/operator of the landfill shall maintain the integrity of
the final cover systems including making repair, as necessary to rectify the settlement,
subsidence or erosion of the cover.
After closure of the landfill, the owner/operator shall continue to operate all leachate, gas
and surface water management systems as well as continue environmental monitoring of
the landfill for a period of 15 years or until such time that harmful leachate is not produced
for 5 continuous years.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
98
8 Institutional Aspects and Capacity
Building The subject of solid waste management has remained neglected for the past several
decades with the result that the level of service is highly inadequate and inefficient. For
improving the solid waste management services it is essential to adopt modern methods of
waste management, have a proper choice of technology, which can work in the given area
successfully. Simultaneously, measures must be taken for institutional strengthening and
internal capacity building so that the efforts made can be sustained over a period of time
and the system put in place can be well managed. Institutional strengthening can be done
by adequately decentralizing the administration, delegating adequate powers at the
decentralized level, by inducting professionals into the administration and providing
adequate training to the existing staff. It will also be necessary to fix work norms for the
work force as well as for supervisory staff and the output expected from the vehicles and
machinery utilized. NGO/private sector participation also needs to be encouraged to make
the service competitive and efficient
8.1 Decentralization of Administration
In the Town of Khanapur, the SWM services can be performed effectively by
decentralization of administration. The SWM functions are proposed to be decentralized as
under:
8.1.1 Ward Level administration
The ward level administration should be fully responsible for ensuring storage of segregated
waste at source, primary collection of waste, street sweeping and taking the waste to bulk
community waste storage sites clearing debris and cleaning surface drains and public
spaces. The cleaning of each street, lane, by-lane, markets and public space should be
regularly supervised by the ward-level supervisors. Qualified supervisors having a diploma
of sanitary inspectors should be appointed as a ward level supervisor and he could be
designated as sanitary sub inspector. He should work under a sanitary inspector who should
supervise at least three wards.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
99
8.1.2 Town Level Administration
The Town level administration should supervise and support the zonal level administration.
The central SWM department should also be responsible for the procurement of vehicles,
equipment, and land for processing and disposal of waste. As a head office it should take
policy decisions and co-ordinate the activities of all the zones and the wards and be
answerable to the chief executive officer and elected body for the efficient functioning of
the department. It should look after the recruitment of manpower, human resources
development, training etc.
8.2 Delegation of Powers
Authority and responsibility should go hand in hand. For fixing accountability there should
be adequate delegation of fiscal and disciplinary powers to the officers and the supervisory
staff responsible for managing solid waste and carrying out all day-to-day functions
smoothly.
The Head of the SWM department should also have the power to punish subordinates
including supervisory staff. Adequate in-built checks may be introduced to ensure that the
delegated powers are not misused.
8.3 Work Norms
Norms of Work for Street Sweepers
The sweepers may be assigned “Pin point” individual work assignments according to the
density of the area to be swept. The yardsticks given earlier may be adopted.
As per normative standards of GOK one sweeper is allotted for every 1000 M of road length.
The norms of work for the supervisors may also be prescribed and monitored by the Town
Panchayath, for the extent of sweeping areas and the number of garbage collection points
to be inspected each day by the various levels of supervisors and inspection of processing
and disposal sites etc. to ensure adequate output of the supervisory staff.
All Supervisory Officers right from sanitary sub-inspectors to Health Officer and Engineer in-
charge of SWM department must remain on the field for 4 hours in the morning between
the time of street sweeping and lunch break. The timings for the middle level supervisor
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
100
could be from 7.00 a.m. to 11.00 a.m. and for senior levels from 8.00 a.m. to 12.00 noon or
8.30 to 12.30 in the morning. The junior level supervisors should supervise them till the end
of the working hours of the street sweepers and transport staff. This supervision will have a
direct impact on the quality of service.
For capacity building of the department, senior officials should be frequently exposed to
developments taking place in various parts of the State and country by sending them out on
Town visits and to attend seminars, workshops and training courses. They should also be
involved in all decision making processes.
The sweepers may be directed to sweep the roads and footpaths in the area allotted to
them as well as to collect the domestic, trade and institutional wastes in their handcart from
the households, shops and establishments situated on the road/street allotted to them. The
above sweeping norms are for cleaning the streets in the first 4 hours of the working day. In
the remaining hours of the day, if there is a continuous 7/8 hours duty, or in the evening
session, if there is broken duty, the sweepers should be assigned pin point work for cleaning
the streets in slums and unauthorized settlements to ensure hygienic conditions in the town
and prevent the problems of health and sanitation arising in such areas.
The roads, which have a central verge or divider, should be considered as two roads. In such
cases, the length of the road allotted for sweeping should be reduced to half or alternatively
separate sweepers may be engaged for sweeping two sides of the road.
Norms of work for supervisors may be prescribed and monitored by the local body for
inspection of sweeping done, clearance of waste storage depots, transportation of waste
carried out, etc. Inspection of processing and disposal sites by various levels of supervisors
may also be prescribed to ensure adequate output of all the supervisory staff.
The first level supervisors could be asked to inspect the work of all the sweepers at least
once in two days. The sanitary sub-inspectors should inspect all the beats twice a week and
the sanitary inspector at least once a week. All temporary waste storage depots must also
be inspected by the same level of supervisors with the same frequency. All Supervisory
Officers right from Sanitary Sub Inspector to Health Officer/Chief Engineer in-charge of
SWM department must remain on the field for 4 hours in the morning between the time of
street sweeping and lunch break. The timings for the lower and middle level supervisor
should extend beyond the duty hours of the sanitation workers in the afternoon/evening to
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
101
verify whether work has been done properly. This supervision will have a direct impact on
the quality of service.
For capacity building of the department, senior officials should be frequently exposed to
developments taking place in various parts of the State/ country by sending them out on
town visits and for attending seminars, workshops and training courses. They should also be
involved in all decision making processes
8.4 Induction of Environmental/Public Health Engineers
The subject of solid waste management, so far being handled by Health Officers (who are
medical doctors), and now needs to be handled by environmental engineers or public health
engineers with the support of mechanical/automobile engineers to handle the workshop
facilities. Qualified engineers should, therefore, be inducted as under.
i. Public Health/Environmental Engineers of the level of Executive Engineer to head
the SWM department.
ii. Qualified Sanitation Diploma holder/Sanitation Officer @ 1 S.O. per Zone.
iii. Qualified Sanitation Diploma holder Sanitary Inspector (S.I.) @ 1 S.I. per 50,000
populations.
iv. Qualified sanitation diploma holder Sanitary Sub-inspector. Per 25,000
population or part thereof.
8.4.1 Need of Manpower
A. Professionals and supervisors for Collection and Transportation
Sr. No Grade Present Required as per Norm (till 2022*) 1 Environmental Engineers 0 1 2 Sanitation Officer 0 1 3 Sanitary Inspector 1 1 4 Sanitary Sub-inspector 2 2 5 Pourkarmikas
7 27
6 Drivers 7 7 Supervisory Staff at DWCC 0 0 8 Security Person at Landfill site 0 1 *After yr 2022 numbers would require to be updated as per prevailing norms in yr 2022.
B. Professionals and supervisors.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
102
Sr. No Grade Qualification Experience Number
1 General Manager B. E. 2 -3 years 1
2 Shift In charge Diploma 1 - 2 years 1
3 Mechanic ITI 3 years 1
4 Plant Operator H.S.C. 1 - 2 years 1
5 Chemist B. Sc 1 years 1
6 Accounts Officer B. Com 3 years 1
7 Skilled Worker 2 -3 years 2
8 Semi Skilled Worker 2
9 Un Skilled Worker 4
10 Driver 2 -3 years 4
11 Contracted Labour 6
Total 24
8.5 Human Resource Development
Human Resource development is very essential for internal capacity building for any
organization. Training, motivation, incentives for outstanding service and disincentives for
those who fail to perform are essential for human resources development.
Concerted efforts should be made by the Town Panchayath to inculcate among its officers
and staff a sense of pride in the work they do and to motivate them to perform and give
their optimum output to improve the level of services of the Town and the image of the
Town Panchayath.
8.5.1 Training
Solid Waste Management has been a neglected subject for the past several decades.
Systems have, therefore, not developed to improve the service. Knowledge of new
technology and methods coupled with training at all levels is necessary. No specialized
courses have so far been designed to meet need of different levels of staff. Short and
medium term courses should, therefore, be designed for the sanitation workers and
supervisory staff. Special training and refresher courses may also be conducted as under:-
8.5.2 Special Training to Unqualified Staff
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
103
Unqualified supervisory staff should be given in service training to qualify for supervising
sanitation works. They may be sent out for training to the All India Institute of Local Self
Government or such similar institutions which designs special courses for sanitation
supervisors.
8.5.3 Refresher Courses for All Levels of Staff
Refresher courses should be conducted for the sanitation workers as well as supervisory
staff at least once in every 5 years, or they should be sent for training to get an exposure to
advance in this field.
8.5.4 Exposure to Municipal Commissioner/ Chief Executives
It is necessary to give an orientation to the Municipal Commissioners/Chief Executives of the
local bodies and make them aware of this important aspect of Urban Management. They
may therefore be given exposure to SWM through short training programs.
8.5.5 Exposure to Elected Members
Whereas the Municipal Commissioners or the Chief Executives are responsible for day-to-
day affairs of the urban local bodies, the elected members are the policy makers and their
sanctions are essential for any major investments or improvements in SWM services. It is,
therefore, necessary that the members of the elected wing such as the Mayors/Presidents
of the Corporations/Municipalities and other important office bearers of the local bodies
are given appropriate orientation towards the need of modernization of solid waste
management practices in the urban areas and the importance of the same in terms of
health and sanitation in the cities/towns. If these members are given an appropriate
exposure, they would automatically support adequate financing for solid waste
management services and strengthen the hands of chief executives in the implementation
of modern methods of waste management and they would also help in getting public
support through their network of field workers.
8.5.6 Design SWM Courses
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
104
SWM courses may be designed and regularly updated for Engineering, Medical and applied
science disciplines. Academic institutions at the national and state levels should be involved
in this exercise by the concerned departments of Central and State Governments
respectively. The syllabus of the engineering colleges, medical studies as well as sanitary
inspectors’ diploma courses should lay adequate emphasis on solid waste management.
Following Table Summarizes the training requirement for specific category of Solid Waste
Management workers
TABLE 8-1: TRAINING REQUIREMENT FOR MUNICIPAL WORKERS
Sr. No Designation Training Requirement 1 Municipal Commissioner / Chief
Officer / President of ULB Training on Public Private Partnership, Project Finance Exposure Visits to Best Practices in MSWM
2 Environment Engineer Training on Staff Management, Operation and Maintenance of Solid Waste Management Facilities Exposure Visits to Best Practices in MSWM
3 Sanitary Inspector Training on Collection, Transportation, Processing and disposal practices of MSWM Training on IEC Practices
4 Pourkarmikas / Street Sweeping Workers
Training on Health and Safety during MSWM
8.5.7 Promotional Opportunities
Adequate promotional opportunities should be available in the decentralized SWM
hierarchy to maintain the interest of the supervisory staff to remain in the department.
• Special Training to Unqualified Staff
• Unqualified supervisory staff should be given in service training to qualify for
supervising sanitation works.
• Refresher Courses for Supervisory Staff
• Refresher courses should be conducted for the supervisory staff at least every 5
years, or they should be sent for training to get an exposure to advance in this field.
8.6 The Entire Administration of SWM Department to Be Under
One Umbrella
With a view to avoid the problems of lack of coordination and passing of responsibility to
others, it is necessary to have one person exclusively in charge of SWM in the Town. The
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
105
overall control in relation to collection, transportation, processing and disposal of all waste,
including workshop facilities, should lie with him. He should also be responsible for the
cleaning of open drains under 24” depth, collection of silt, construction waste and debris
and vehicle deployment and maintenance. This work should not be left to the Engineering
Department, which should however continue to be responsible for the removal and
transportation of silt from the underground drains, storm water drains or surface drains
exceeding 24” depth, and the left over waste material from their Engineering and major
road works.
8.7 Inter Departmental Co-Ordination
Since the SWM department depends greatly upon the support of various departments of
the Town Panchayath, more particularly the Engineering department, the Municipal
Commissioner may hold regular monthly co-ordination meetings to sort out problems faced
by the SWM department such as expeditious repairs of roads, drains, water-supply pipe-
lines etc. which cause hindrance to street and Town cleaning. The reinstatement of roads
dug up by utility services should also be given priority.
The procurement procedures for the SWM equipment also need to be expedited and
simplified in such meetings. A Rate-contract system should replace time consuming
tendering procedures.
There should be an Apex Committee comprised of representatives of various utility services,
headed by the Municipal Commissioner to co-ordinate the laying of underground services in
the Town by various utilities and the reinstatement of the roads as soon as the underground
services are laid. The Apex Committee should ensure that repeated digging of road is
avoided for laying of services by various utilities at time. The works to be carried out by
various utilities on a particular road should be coordinated to prevent frequent digging of
roads.
Laying and maintaining of services in slums, provision of public health engineering services
and water supply for public toilets and road construction in the slums to improve overall
health and sanitation in the Town may also be regularly reviewed in the co-ordination
committee meetings.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
106
8.8 Encouragement to NGO’S and Waste Collector Co-Operatives
NGOs may be fully involved in creating public awareness and encouraging public
participation in SWM planning and practice.
The Town Panchayath may also encourage NGOs or co-operative of rag pickers to enter this
field and organize rag pickers in doorstep collection of waste and provide them an
opportunity to improve their working conditions and income. The TP can give incentives to
NGOs in their effort of organizing rag pickers in primary collection of recyclable and/or
organic waste, and provide financial and logistic support to the extent possible.
8.8.1 NGO/Private Sector Participation
SWM services are highly labour intensive on account of increased wage structure of the
Government and municipal employees this service is becoming more and more expensive.
Besides, the efficiency of the labour force employed in the TP is far from satisfactory. High
wage structure and inefficiency of the work force results into steep rise in the cost of service
and yet the people at large are not satisfied with the level of service being provided by the
TP. Efforts to increase the efficiency by H.R.D. and institutional strengthening will, to some
extent improve the performance but they may not be enough. It is, therefore, necessary
that the TP seriously consider augmenting NGO/private sector participation in solid waste
management.
Private sector participation or public private partnerships may be considered by TP keeping
in mind the provisions of the Contract Labour (Regulation and Abolition) Act 1970 of the
Government of India under which state governments can prohibit contracting out the
services already being provided by the TP. Therefore, while considering any measure of
privatization it is necessary to keep in mind the provisions of the above law, the directions
that may have been issued by the state government under this law in those areas which are
not prohibited and where TP is not currently providing a service. This will check growth in
the establishment costs, bring in economy in expenditure and introduce an element of
healthy competition between the private sector and the public sector in solid waste
management services. There should be a right mix of private sector and public sector
participation to ensure that there is no exploitation of labour as well as of the management.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
107
NGO/private sector participation can, therefore, be considered in newly developed areas,
under-served areas and particularly in areas where TP have not been providing service.
Some examples are given below:
NGO/private participation is recommended in the areas of door to door collection of
domestic waste, door to door collection of commercial waste, door to door collection of
hospital waste, hotel waste, construction waste, and yard waste, and in the area of
awareness and creating public participation. The private sector may also be brought in for
the operation and maintenance of compost plants and other treatment plants and O& M of
engineered landfill facility.
Major repairs and maintenance of vehicles at a private garage may also be considered
seriously.
8.8.2 Incentives to the NGO/Private Sector
Solid waste management, processing and disposal are an area where the private sector has
still not shown much interest. The private sector has, therefore, to be given some incentives
by way of long term contract, assured supply of garbage at the plant site, lease of land at
nominal rates for entering this field.
NGO as well as Private sector participation may be encouraged in such a way that it does
not affect the interests of the existing labour; it does not violate the provisions of the above
law, does not exploit the private labour and yet reduces the burden of the TP. This will
substantially help in improving the quality of service of the TP, effect economy in
expenditure and also give scope to the private sector to enter the waste management
market.
8.9 Public Awareness and IEC
8.9.1 Introduction
Everyone is concerned with the growing problems of waste disposal in urban areas with the
scarce availability of land for processing and disposal of waste and environmental
remediation measures becoming ever more expensive. It is therefore necessary to not only
think about effective ways and means to process and dispose of the waste that we generate
each day, it is also essential to seriously consider how to avoid or reduce the generation of
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
108
waste in the first place and to consider ways to re-use and recycle the waste, so that the
least quantity of waste needs to be processed and disposed off.
8.9.2 Reduce Reuse Recycle (R-R-R)
In Khanapur there is very negligible action on Reduce, Reuse and Recycling of waste. The
quantity of packaging waste material and non-bio-degradable waste is going up alarmingly
every year. This increases the burden on local bodies to deal with the problem of no
biodegradable and non-recyclable components of waste landing up at processing and
disposal sites.
8.9.2.1 REDUCE OF WA STE BY ALL C ONCE RNED:
All manufacturers producing a variety of domestic and non-domestic products, food as well
as non-food should be persuaded to seriously endeavor to use re-usable packaging
materials so that after the delivery of goods, the packaging materials could be collected
back and used over and over again. They could also consider minimizing or avoiding use of
unnecessary packaging materials by innovative methods.
Incentives & product discount should be given to consumers for the return of packaging or
bottling materials in good condition, to the waste producers or retailers to promote re-use.
The cost of packed articles and article without packaging material could be kept different
with a choice to consumers to take the article without the packaging material at low cost.
8.9.2.2 REUSE:
Efforts should be made to encourage collection of re-usable material through waste
collectors, waste producers, NGOs and private sector instead of allowing reusable waste to
land up on the disposal sites. Bottles, cans, tins, drums and cartons can be reused.
8.9.2.3 RECYCLIN G:
In this era of excessive packaging materials being used, a lot of recyclable waste material is
generated. All-out efforts are necessary to retrieve recyclable material from the households,
shops and establishments and fed to the recycling industries through intermediaries such as
waste purchasers, waste collectors/NGOs, etc.
8.9.3 Public Participation
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
109
Public participation is the basis for improving the solid waste management. This requires lot
of effort. Public participation is essential in the following activities.
7. Reduce, Reuse & Recycling (R R R) of waste. 8. Not to throw the waste/litter on the streets drains, open spaces, water bodies, etc. 9. Storage of organic/bio-degradable and recyclable waste separately at source. 10. Primary collection of waste 11. Community storage/collection of waste in flats, slums, societies, commercial complexes,
etc. and other waste source generators. 12. Pay adequately for the services provided.
The local body should decide the methodology to be adopted for reaching the community
and seeking their cooperation and effective participation in SWM services. This is a very
difficult area of activity and unless this is done meticulously, desired results will not be
achieved.
The essential steps in this direction is to select representative samples of the community
and go through a consultative process to ascertain the perceptions of the people about the
SWM services being given to them, their expectations and extent to which they are willing
to support and participate in the process. Their choice of technological options available
also needs to be ascertained.
There is a need to interact with the community to identify problems of waste management
through site visits and consultation with local population at the time when the community is
generally available for interaction. It may either be in early morning or late evening. The
areas may be selected by following the method of drawl of representative samples.
Situation analysis may be done by the persons who know the subject reasonably well, know
local language and can communicate with local population effectively. Such persons may be
Non-Governmental Organizations, Community Based Organizations or knowledgeable
individuals. They should try to find out the prevalent situation of waste management in the
area under observation and ascertain the perceptions of the people about the services
provided. In this exercise the local councilors, local leaders, NGOs, etc., may be invited to
participate.
8.9.3.1 FIND ING OU T OP TIONA L SOLU TI ON S
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
110
Having identified the deficiencies in the system and known the public perceptions, the next
essential step is to think of optional solutions to tackle the problems, workout the cost
implications and level of public participation needed.
8.9.3.2 CONSU LT C OMMU NITY ON OP TI ON S AVA ILABLE:
There should be second round of consultative process where the options worked out may
be discussed with the community along with cost implications and their support required.
Their suggestions may be sought on each solution proposed. The community may be
encouraged to give their views. If we ask the people straight away the solutions of the
problems they may not be able to give right kind of suggestions as they have no exposure of
various technological options. Therefore, they must be first appraised of the options
available and then asked to give their considered opinion on what will work in their area and
how much they are willing to cooperate.
8.9.4 IEC & Capacity Building
There is a need for capacity building to promote the concept of waste segregation at source.
A detailed plan for capacity building has to be developed. An overview of the concepts, mass
awareness program involved and training is presented here. A budget for the mass
awareness campaign has been included in the estimates. The success of the segregation
concept is based on the consistent follow up over a long period of time. Multiple
approaches have to be adopted for creating awareness and participation including -
• Conducting IEC campaigns • Providing access to repositories of information and resources (e.g. databases,
libraries • and web sites) • Trainings (public, customized or on-line) • Consultation (e.g. coaching, facilitating, expert advice and conducting research) • Publications • Coordinating alliances • Web based forum for interaction among different players
Information, Education and Communication (IEC) campaigns are critical for working with
individuals, communities and societies to promote positive behaviors. The IEC strategies
should combine approaches and methods that enable individuals, families, groups,
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
111
organizations and communities to play active role in achieving, protecting and sustaining the
desired behavioral change. Solid Waste Management is an activity in which volunteerism
and public participation are the keys to success. It is not only the technology but public
attitude and behavior that are going to make the difference. A participation model for
implementation of Segregation and a table giving details of activities to be practiced are
presented below.
TABLE 8-2 ACTIVITIES TO BE PRACTICED FOR PARTICIPATION MODEL FOR IMPLEMENTATION OF SEGREGATION
Target Group Area covered in brief
Topics
Elected Representatives- Group 1
General Orientation on: Solid Waste Management- Technical, Institutional, Financial and legal aspects
Technical Aspects: 4R Concept-Reduce, reuse, recover, recycle Institutional Aspects: Collection & Storage Transportation Transfer Stations Role of NGOs/ CBOs Financial Aspects: Budgeting for SWM Cost recovery for SWM services Legal Aspects: MSW(M&H) Rules, 2000 MSWM in Kerala Municipalities Act Byelaw
Mobilization for Action, Human Resource Development
Interactive process for Strategic thinking (by communities, NGOs, professionals& ULB) to prioritize SWM issues and to identify resources to address them. Interactive process for improving the efficiency, effectiveness and the performance of local SWM systems. (iii) Steps for Improving SWM
Senior Officers General Orientation on SWM Plan Preparation and Implementation including technical & technological aspects
Need for Planning-present inadequacies and shortfalls. How to prepare an SWM Plan (preliminaries like quantitative and qualitative survey of MSW , Identification of technology options, community mobilization, facilitating alliances Implementation of SWM Plan Different technology options Role of different players
Financial Management
Budgeting for SWM Cost recovery for SWM Services
Legal Policy aspects
MSW(M&H) Rules, 2000
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
112
Target Group Area covered in brief
Topics
Monitoring & Evaluation
What is Monitoring? What is Evaluation? Record keeping and Documentation Importance of Monitoring& Evaluation Monitoring Tools
Human Resource Management for SWM
Human resource for SWM- Capacity Assessment Human Resource Development For SWM(developing personal and organizational skills, knowledge, abilities of staff; opportunities for employee training, employee career, performance, coaching, mentoring, succession planning, key employee identification etc. ) Human Resource Management System for SWM(payroll, work time, benefits, recruiting, training, performance
Field Workers Orientation on Effective Collection, Segregation and Transportation of Solid Waste
Different Types of MSW Handling of Hazardous/dangerous items Primary Collection and Transportation Tips for effective collection and transportation
Source: AIILSG Analysis
As part of this project awareness creation has been included with the following objectives.
a) To undertake an awareness campaign to reach about 80,000 household, commercial
establishments and institutions on a door to door basis using Pamphlets and one to
one interaction over a period of 3 months.
b) To undertake a campaign for organizing awareness days at about 150 schools,
educational institutions and other centers across the city.
c) Carrying out 'Waste Management waste Day Events' once a week for a period of 6
months.
These activities would be carried after the procurement of the vehicles and setting up of the
integrated waste processing management facility with scope for processing segregated
waste and recovering resources from the collected segregated waste. The message in the
IEC would be communicate the action taken by the TP and the expectations from the
community for ensuring that an segregation based integrated waste management facility
becomes a reality.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
113
TABLE 8-3 ACTION PLAN FOR IEC
Sr.No. Target Groups
Target Group Details Action Plan
1 Waste Generator
Residential Areas (Women (household), Maids, children and Youths). Commercial Areas (Shopping areas, Vegetable markets, Offices, Hotels, Restaurants). Institutional Areas (Jr. High Schools, Colleges)
Holding locality-wise meetings, seminars, targeted community meetings with self-help groups, through street plays, technical and pictorial presentation along with aware them about health hazards and remedial measures and sanitation improvement. Informing and suggesting them about the segregated waste management and their important role.
2 Waste Collector
Sweepers Rag pickers Waste loaders Truck drivers Landfill supervisors
They all should be involved and sensitize about the need of segregated waste collection and sanitation Improvement. The waste collection, transportation and disposal of the waste in proper timing so that waste could not be overflow. The waste collector should be trained about the collection of segregated waste.
3 Waste Managers
Administrators and supervisors Control and monitoring team Complaint handlers Computer software operators and specialists
Presenting them about the Rules and Regulation and updating them about the ongoing activities and techniques for MSW management. Training programs for the technical staffs Providing the reviews of progress and monitoring activities
4 Leaders Political Leaders (Local MLA, MP) Religious Leaders Community Leaders
These leaders can be motivated to participate actively in promotional efforts of community involvement in segregated solid waste management.
5 School Teachers and Students
Primary Schools Jr. High Schools Public Schools
School teachers can be informed and involved in the segregated solid waste management scheme and can be motivated to educate the children for the sanitary improvement. The students can be educated and trained for the segregated waste management system and they can be great awareness creators for the societies. Some groups of students can be created as monitoring and awareness team for sanitation improvement which will make a great impact on societies and communities.
6 Media Print Media Electronic Media
Launching mass campaign for educating and motivating local communities and families about the need of segregation of Solid Waste and its management for
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
114
Sr.No. Target Groups
Target Group Details Action Plan
sanitation and hygienic improvement. 7 Elite groups
or social organizations
NGOs, Societies CBOs Sr. citizens Association Rotary Clubs/ Lions Club
Sensitize and motivate local influential people like Sr. citizens, leading businessmen, social club members, NGOs and CBOs etc. to undertake or sponsor such activities for solid waste management for effective strategy of public participation and awareness.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
115
9 Summary of Financial Requirements
The summary of financial requirement for proposed Solid Waste Management DPR is given
in this section. It is recommended to set up and operate an efficient solid waste
management system in the town.
9.1 Requirement of Capital Cost
The table below gives details of the financial requirement as capital expenditure for
improving efficiency of waste management.
Vehicles/Equipment 2017 - 22 Cost/ Vehicle Total Cost (Lakh Rs.) Plastic Bins (2 nos.) for Door-to-door collection Gross Requirement No.s 9162 available at present No.s 0 To be Procured No.s 9162 Rs. 0.00121 Rs. 11.09 Twin Compartment 2.0 Cum Box tippers for D2D Collection Gross Requirement No.s 3 available at present No.s 2 To be Procured No.s 1 Rs. 5.2 Rs. 5.20 Push Carts (6 Bin) for Street sweeping by ULB Gross Requirement No.s 12 available at present No.s - To be Procured No.s 12 Rs. 0.137 Rs. 1.64 Push Carts (6 Bin) for Door to Door Collection in Congested Areas Gross Requirement No.s 2 available at present No.s - To be Procured No.s 2 Rs. 0.137 Rs. 0.27 3 Cum Tractor-Trailer for Road Sweeping Waste Collection Gross Requirement No.s 1 available at present No.s 1 To be Procured No.s - Rs. 7.25 Rs. 0.00 3 Cum Tractor Trailer for targeted Bulk Waste Collection (Veg. Markets and Hotels) Gross Requirement No.s 1 available at present No.s 1 To be Procured No.s 1 Rs. 7.25 Rs.7.25 Jetting and suction machine for Drain Cleaning Gross Requirement No.s 1 available at present No.s 1 To be Procured No.s - Rs. 32.50 Rs. 0.00 3 Cum Tractor Trailer at Landfill Site Gross Requirement No.s 1 available at present No.s 1
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
116
Vehicles/Equipment 2017 - 22 Cost/ Vehicle Total Cost (Lakh Rs.) To be Procured No.s - Rs.7.25 Rs. 7.25 Backhoe loader at Landfill Site 75 HP Gross Requirement No.s 1 available at present No.s - To be Procured No.s 1 Rs. 18.35 Rs. 18.35 Total Rs. 36.56 Machinery Requirement (Trommel, Conveyor 35mm+14mm+4mm, DG Set) Gross Requirement No.s 1 available at present No.s - To be Procured No.s 1 Rs. 4
TABLE 9-1 ESTIMATED CAPITAL EXPENDITURE
Sr. No.
Description Total Estimated Amount
Contingency - 3%
Grand Total
1 Collection & Transport 36.56 1.10 37.66 2 Processing Facility 104.84 3.15 107.98 3 Sanitary Landfill & associated facilities 46.64 1.40 48.04 4 Mechanical Component at Processing Facility 41.00 1.23 42.23 5 Leachate Treatment Cost - {Phytorid Technology 9.18 0.28 9.46 6 Recycling facilities 10.00 0.30 10.30 7 Social Forestry 6.00 0.18 6.18 8 Rainwater Harvesting 1.02 0.03 1.05 9 Dry Waste E Waste Collection Centre 4.46 0.13 4.60
10 Bio Mining/Bio Remediation 5.00 0.15 5.15 Total Estimated Amount 264.71 7.94 272.65
9.2 Funding Pattern
S. No.
Government Project contribution source Amount in Rs. Lakhs
% share by Govt. entity
1 Central SBM Grant 95.43 35.00% 2 State Grant towards its share in project 63.61 23.33% 3 Committed contribution by the TP 113.61 25%
Total 272.65
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayat Khanapur
117
9.3 Detailed BOQ and Estimates
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
1 Earth work excavation in hard soil for foundation of structures by mechanical means as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally up to 1 km lead.(Depth up to 3 Mts) Ref. DSR 2016-17 North Karnataka circle Sl. No. 2.23.1 pg.no. 7
F1 5 1.75 1.55 1.6 21.70 F2 6 1.75 1.65 1.6 27.72 F3 2 1.95 1.75 1.6 10.92 F4 2 1.95 1.75 1.6 10.92 Cum Total 71.26 71.26 56 3966 2 KSRB 4-2.1 Providing and Laying in position plain cement
concrete of mix 1:3:6 for Foundation and bedding with OPC cement @ 220 Kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.892cum and fine aggregates @0.465 cum machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
118
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
Sl. No. 4.2 pg.no.12
F1 5 1.75 1.55 0.1 1.36 F2 6 1.75 1.65 0.1 1.73 F3 2 1.95 1.75 0.1 0.68 F4 2 1.95 1.75 0.1 0.68 Cum 4.45 4.45 5637.45 25108 3 KSRB 4.2.2 Providing and Laying in position Reinforced
cement concrete of design mix M20 with OPC cement @ 320 kgs, with 20mm and down size graded granite metal coarse aggregates @0.69 cum and fine aggregates @ 0.460 cum, with super plasticisers @ 3 litters conforming to is 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, columns and plinths etc., including the cost of all material, labour, HOM of machinery, compacting, curing complete but excluding the cost of reinforcement as per specifications. Ref. DSR 2016-17 North Karnataka circle
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
119
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
KSRB 4.2.2, Sl.No.4.11, pg.no. 13
F1 5 1.6 1.4 0.45 5.04 F2 6 1.6 1.5 0.45 6.48 F3 2 1.8 1.6 0.45 2.59 F4 2 1.8 1.7 0.45 2.75 Footing
total 16.87
Column up to Plinth Level CG1 4 0.23 0.375 1.55 0.53 Column up to Plinth Level CG2 11 0.23 0.45 1.55 1.76 Column
total 2.30
Cum Total Qty 19.17 19.17 6540.45 125351
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
120
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
4 KSRB 4.2.8: Providing and laying in position Reinforced cement concrete of design mix M20, machine mixed, concrete laid in layers not exceeding 15cms thick, vibrated for beam, Roof slab including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.4.13, pg.no. 14
Plinth Beams 1 89.82 0.23 0.38 7.85 0 Roof Beams 1 106.66 0.23 0.45 11.04 0 Column Above Plinth Level CG1 4 0.23 0.375 3.9 1.35 Column Above Plinth Level CG2 11 0.23 0.45 3.9 4.44 Cum Total
Qty 24.68 24.68 6473.25 159729
5 KSRB 2.3: Filling available excavated earth in sides of foundations up to plinth in layers not exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with lead up to 50m. and lift up to 1.5 m. including cost of all labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.no. 2.10, pg.no. 6
Filling in Footing F1 5 1.75 1.55 1.5 20.34 F2 6 1.75 1.65 1.5 25.99 F3 2 1.95 1.75 1.5 10.24 F4 2 1.95 1.75 1.5 10.24
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
121
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
66.81 Deductions F1 5 1.6 1.4 0.45 5.04 F2 6 1.6 1.5 0.45 6.48 F3 2 1.8 1.6 0.45 2.59 F4 2 1.8 1.7 0.45 2.75 16.87 Filling in Footing 49.94 Filling below Plinth Beam 1 0.45 1.55 0.07 0.05 Lab 1 9.84 9.3 0.45 41.18 Office 1 9.31 5.81 0.45 24.34 Toilet Block 2 4.6 3.8 0.45 15.73 Cum Total 131.24 131.2
4 133.35 17501
6 KSRB 4-6.1: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of Columns for mass concrete including cost of all materials, labour complete as per specifications .Ref. DSR 2016-17 North Karnataka circle, Sl.No.4.28, pg.no. 15
F1 5 6 0.45 13.5 0 F2 6 6.2 0.45 16.74 0 F3 2 6.8 0.45 6.12 0 F4 2 7 0.45 6.3 0 Column up to Plinth CG1 4 0 1.05 0 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
122
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
Column up to Plinth CG2 11 1.21 1.05 13.9755 0 Sq.m. 56.6355 56.64 237.3 13440 7 KSRB 4-6.5: Providing and removing centering,
shuttering, strutting, propping etc., and removal of form work for columns, pillars, post and struts, square/ rectangular/ polygon in plan including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.35, pg.no. 16
Column above Plinth CG1 4 1.21 3.9 18.876 0 Column above Plinth CG2 11 1.36 3.9 58.344 0 Sq.m. 77.22 77.22 384.3 29676 8 KSRRB M400-6.2 Construction of granular sub- base by
providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method by rotavator at OMC and compacting with vibratory power roller to achieve the desired density , complete as per specification.(Grade 2) Ref. DSR 2016-17 North Karnataka circle KSRB 20.5.2, pg.no. 155
Column above Plinth CG1 4 1.21 3.9 18.876 0 Column above Plinth CG2 11 1.36 3.9 58.344 0 Sq.m. 77.22 77.22 4128.6 318810
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
123
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
9 KSRB 4-6.7: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beams haunching, cantilever, girders, bressumers and lintels etc not exceeding 1 M in depth including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.34, pg.no. 16
Plinth Beam 1 89.82 1.22 109.580 0 Roof Beams 1 106.66 1.36 145.057 0 Sq.m. 254.638 254.6
4 268.8 68447
10 KSRB 4.2.8: Providing and laying in position Reinforced cement concrete of design mix M20, machine mixed, concrete laid in layers not exceeding 15cms thick, vibrated for beam, Roof slab including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.4.13, pg.no. 14
S1 4 4.47 4.95 0.15 13.28 0 S2 2 3.94 4.77 0.15 5.64 0 S3 2 4.77 5.95 0.15 8.51 0 Slab
Total 27.43 0
D1 2 1.2 0.23 0.23 0.13 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
124
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
D2 3 0.9 0.23 0.23 0.14 0 W1 6 1.5 0.23 0.23 0.48 0 V1 3 0.6 0.23 0.23 0.10 0 Lintel
Total 0.84 0
Cum Total Qty 28.27 28.27 6473.25 182996 11 KSRB 4.2.10: Providing and laying in position Reinforced
cement concrete of design mix M20, with machine mixed, well compacted for plain chajja of 7.5 cms. Average thickness, upto ground floor level, including cost of all materials, labour, machinery, finishing, curing, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.4.19, pg.no. 14
D1 2 1.2 0.75 0.075 0.14 0 D2 3 0.9 0.75 0.075 0.15 0 W1 6 1.5 0.75 0.075 0.51 0 V1 3 0.6 0.75 0.075 0.10 0 Cum 0.89 0.89 498.75 446 12 KSRB 4-6.1: Providing and removing centering,
shuttering, strutting, propping etc., and removal of form work for suspended floors, landings, thickness up to 200 mm including cost of all materials, labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle, Sl.No.4.30, pg.no. 15
Slab bottom 1 19.3 10.3 198.79 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
125
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
Slab sides 1 59.2 0.15 8.88 0 Sq.m 207.67 207.6
7 294 61055
13 KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonne 5.3 5.30 63452.55 336299
14 KSRB 6-4.3: Providing and constructing Burnt Brick Masonry for Superstructure, with approved quality of non- modular bricks of standard size of class designation 3.5 Newton per sq mm with cement mortar 1:6, including cost of materials, labour charges, scaffolding, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 6.14 pg.no.28
Total outer and inner wall lengths 1 89.82 0.23 3.67 75.82 0 Deduction D1 2 1.2 0.23 2.1 1.16 0 D2 3 0.9 0.23 2.1 1.30 0 W1 6 1.5 0.23 1.2 2.48 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
126
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
V1 3 0.6 0.23 0.9 0.37 0
Total deductions
5.32 0
Cum Total Qty 70.50 70.50 6079.5 428587
15 KSRB 15-3.11: Providing 18 mm thick cement plaster in single coat with cement mortar 1:3 to brick masonry including rounding off corners wherever required smooth rendering: providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 15.15 pg.no.113 and 114
Internal Plaster 0 Lab block 2 9.84 3 59.04 0 Lab block 2 9.3 3 55.80 0 Office room 2 9.31 3 55.86 0 Office room 2 5.81 3 34.86 0 Toilet Block 4 4.6 3 55.20 0 Toilet Block 4 3.8 1.8 27.36 0 288.12 288.1
2
Deduction D1 2 1.2 2.1 5.04 D2 3 0.9 2.1 5.67
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
127
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
W1 6 1.5 1.2 10.80 V1 3 0.6 0.9 1.62 23.13 Sq.m 264.99 264.9
9 211.05 60808
16 Providing 15 mm thick Cement plaster in single coat in cement mortar 1:3 to brick masonry including rounding off corners wherever required smooth rendering,: Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 15.12 pg.no.113
External Plaster 0 Long walls 2 19.3 4.35 167.91 0 Short walls 2 10.3 4.35 89.61 0 257.52 0 Deduction D1 2 1.2 2.1 5.04 0 D2 3 0.9 2.1 5.67 0 W1 6 1.5 1.2 10.80 0 V1 3 0.6 0.9 1.62 23.13 0 Sq.m 234.39 234.3
9 249.9 58574
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
128
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
17 Providing 12 mm thick Cement plaster in single coat in cement mortar 1:3 to ceiling including rounding off corners wherever required smooth rendering,: Providing and removing scaffolding, including cost of materials, labour, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 15.21 pg.no.114
Ceiling Sq.m 1 19.3 10.3 198.79 198.79 199.5 39659
18 KSRB 10-3: Providing and laying integral cement based waterproofing treatment including preparation of surface as required for treatment of roofs, terraces consisting of following application. (a) Applying and grouting a slurry coat of cement admixed with proprietary water proofing compound 5 over the RCC slab after cleaning the surface before treatment. (b) Laying cement concrete using broken brick bats 25mm to 100mm size with 50% of cement mortar 1:5 admixed with proprietary water proofing compound over 20mm thick layer of cement mortar 1:5 admixed with proprietary water proofing compound to required slope treating similarly the adjoining walls up to 300mm height including rounding off junction of walls and slabs. (c) After two days of proper curing, applying a second coat of cement slurry admixed with proprietary water proofing compound. (d) Finishing the surface with 20mm thick joint less cement mortar of mix 1:4 admixed
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
129
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
with proprietary water proofing compound and finally finishing the surface with trowel and neat cement slurry and making of 300*300mm square. (e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and for final test including cost of materials, labour complete as per specifications Ref. DSR 2016-17 North Karnataka circle Sl. No. 10.2 pg.no.66
Sq.m 1 18.84 9.84 185.39 185.39 931.35 172659
19 Providing and fixing Vitrified glazed tile of approved make, quality and colour of size 600*600*10mm thick fixed on bed of 12mm thick cement mortar for flooring, skirting and jointed with neat cement slurry mixed with pigment to match shade of tiles, including providing spacers at required interval and removing stains etc., complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 14.45 pg.no.107
Lab Sq.m 1 9.84 9.3 91.512 0 Office Sq.m 1 9.31 5.81 54.0911 0 Toilet 1 Sq.m 1 4.6 3.8 17.48 0 Toilet 2 Sq.m 1 4.6 3.8 17.48 0 145.60 145.6
0 1162 169242
20 KSRB 14-17.1: Providing dadoing with white glazed tiles 6mm thick on 10mm thick cement plaster 1:3 and
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
130
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
jointed with white cement slurry over existing rough cement plaster surface using glazed tiles of approved make and size including cost of materials, labour, complete as per specifications.(Ht.-1.2 M) Ref. DSR 2016-17 North Karnataka circle Sl. No. 14.40 pg.no.106
Dado Sq.m 2.00 4.60 1.20 11.04 0 Sq.m 2.00 4.60 1.20 11.04 0 Sq.m 4.00 3.80 1.20 18.24 0 Sq.m 2.00 1.20 1.20 2.88 0 43.2 Deduction V1 3 0.6 0.9 1.62 41.58 43.20 990 42774 21 KSRB 15-14.1: Providing and applying two coats with oil
bound washable distemper of approved brand and shade on wall surface including priming coat with distemper primer after thoroughly brooming the surface free from mortar drops and other foreign matter including preparing the surface even and sand paper smooth, cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 15.49 pg.no.117
Refer Section 15 Sq.m 264.99 264.99 75 19755
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
131
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
22 KSRB 15-16.1: Providing and finishing external walls in two coats with waterproof cement paint of approved brand and shade to give an even shade after thoroughly brooming the surface to remove all dirt and loose powered material, free from mortar drops and other foreign matter including cost of materials, labour, complete as per specifications.(With Primer) Ref. DSR 2016-17 North Karnataka circle Sl. No. 15.53.2 pg.no.118
Refer Section 16 Sq.m 234.39 234.39 88 20673
23 KSRB 9.4-1: Providing Red Sal Wood Frames of doors, Windows, clerestory windows, ventilators, and other frames, wrought, framed or assembled including making plaster groves (Excluding cost of cement concrete and side clamps), but including cost of materials, labours, HOM of machineries complete as per specifications. Specification No. KBS 9.33 Ref. DSR 2016-17 North Karnataka circle Sl. No. 9.13.1 pg.no.51
D1 4 2.1 0.1 0.125 0.11 0 4 1.4 0.1 0.125 0.07 0 D2 6 2.1 0.1 0.125 0.16 0 6 1.1 0.1 0.125 0.08 0 W1 12 1.7 0.1 0.125 0.26 0 12 1.2 0.1 0.125 0.18 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
132
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
V1 6 0.6 0.1 0.125 0.05 0 6 1.1 0.1 0.125 0.08 0 Cum Total 0.98 0.98 61666.5 60279 24 KSRB 9.5-1 Providing and fixing in position fully panelled
Mathi/ Nandi wood shutters for doors, with styles and rails of 40 mm. thick with bottom and lock rails 180mm wide top rail and styles 100mm wide as per drawing and panels of 25mm thick including cost of materials, labours, HOM of machineries complete as per specifications. Specification No. KBS 9.34 Ref. DSR 2016-17 North Karnataka circle Sl. No. 9.16 pg.no.51
D1 Sq.m 2 1.2 2.1 5.04 0 D2 Sq.m 3 0.9 2.1 5.67 0 10.71 10.71 3159.45 33838 25 KSRB 9-20.4 Providing and fixing in position windows
half panelled shutters at bottom and half glazed at top for window shutters with Honne wood and rails of 30 mm. thick, 75mm wide in two halves with panels filled with NUWUD (MDF) of 18mm thick, 3mm thick reeded glass for top panels fixed with wooden beading including cost of materials, labour charges, HOM of machineries complete as per specifications.(excluding cost of fixtures) Ref. DSR 2016-17 North Karnataka circle Sl. No. 9.63 pg.no.55
W1 6 1.5 1.2 10.8
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
133
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
V1 3 0.9 0.6 1.62 Sq.m Total 12.42 12.42 2905.35 36084 26 KSRB 15-17.1 Applying priming coat over new wood
surface and / or wood based surface with white lead paint priming including preparing the surface after thoroughly cleaning oil, grease, dirt and foreign matter, sand papering and knotting ready mix paint including cost of materials, labour, complete as per specifications
Refer section 24, 25 23.13 23.13 34.65 801 27 KSRB 11-1: Providing and fixing white vitreous china
clay, water closet Indian type (Squatting pan) of size 580mm with footrests, 100mm S or P trap, 10 litre low level, P.V.C. flushing cistern (all are approved make) with fittings, C.I/M.S. brackets, 32mm diameter flush pipe fittings and clamps, overflow arrangements with specials and 25mm mosquito proof coupling of approved design, painting of fittings and brackets, cutting and making good the wall and floor wherever required, including cost of materials, labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 12.1 pg.no.77
pan 2 2 2.00 3629.85 7260
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
134
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
28 KSRB 11-11.5 Providing and fixing white vitreous china clay, flat back wash basin size 450x300mm with a single 15mm C.P. brass pillar tap with C.I/M.S. brackets, 32mm C.P. brass waste of standards pattern, painting of fittings and brackets, cutting and making good the wall and floor wherever required, including cost of materials, labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 12.27 pg.no.81
Unit 2 2.00 2755.2 5510 29 KSRB 13-5 Providing and fixing water meter with stop
cock, jam nut, socket in GI pipe line including cutting and threading the pipe and making long screws including cost of all materials, labour, HOM of equipments and testing complete as per specifications. Specification NO. KBS 13.2.19/ 13.3Ref: DSR 2016-17 North Karnataka Circle Sl No. 13.23 pg no. 91
Set 1 1 1.00 1381.8 1382 30 KSRB 13.6.1-1 Providing and fixing in position brass bib
cock of approved quality 15 mm nominal bore including cost of all materials, labour and HOM of equipments with all leads complete as per specifications Ref: DSR 2016-17 North Karnataka Circle Sl No. 13.23 pg no. 91
each 5 5 5.00 242.55 1213
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
135
Name of the work : Civil Work for Common Facilities @ Khanapur
Sr No
Description of Item Unit Nos Length Width Height Qty Total Qty
Final Rate
Amount
31 KSRB 11-13.1 Providing and fixing laboratory sink of white glazed fire clay of size600X450X200mm with M.S/ C.I brackets, C. P brass chain with rubber plug, 32 mm C.P brass waste, tap with union, brass stop cock complete, painting of fittings and brackets, cutting and making good the wall and floor wherever required, including cost of materials, labour complete as per specification Ref: SER 2016-17 North Karnataka Circle Sl No. 12.34 pg no. 82
Unit 1 1 1.00 3558.45 3558 32 KSRB 13-11.1 Providing and placing on terrace,
polyethylene water storage tanks as per IS 12701:1996 with manhole lid and suitable locking arrangements, making holes of suitable diameter for inlet, outlet and over flow pipes, including cost of all materials, labour, transport charges, HOM of equipments and testing complete as per specifications (For 1000 lit capacity) Specification No. KBS 13.22Ref: DSR 2016-17 North Karnataka circle Sl. No. 13.78 pg.no.94
Nos. 1 1 1.00 8890.35 8890
Total Amount Rs. 25,14,369
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
136
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
1
Earth work excavation by mechanical means in hard/ordinary soil involving an average horizontal throw up to 2 mtrs and average lift up to 0.5mtrs. Excavated surface levelled and sides neatly dressed etc. the disposed earth to be levelled neatly after the breaking of clods completed as per specification MORTH clause 301 Ref. DSR 2016-17 North Karnataka circle Sl. No.19.2.1 pg.no.142
Cum 1 20 11 0.15 33.0 33 32 1040
2
KSRRB M300-59.1. Loosening of the ground up to a level of 400mm below the sub grade level, watered, graded and compacted in layers ( which includes watering charges and compaction by vibratory roller)Ref. DSR 2016-17 North Karnataka circle Sl No. 19.65, pg.no. 149
Cum 1 20 11 0.15 33.0 33 55 1802
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
137
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
3
KSRRB M400-6.2 Construction of granular sub- base by providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method by rotavator at OMC and compacting with vibratory power roller to achieve the desired density , complete as per specification.(Grade 2) Ref. DSR 2016-17 North Karnataka circle KSRB 20.5.2, pg.no. 155
Cum 1 20 11 0.125 27.5 28 1636 44987
4
KSRRB M600-1 Construction of dry lean cement concrete mix CC1:5:10 with OPC cement @ 160 Kg, with 25 mm down size graded granite metal coarse aggregate at 0.86 cum and fine aggregates @0.58 Cum Sub-base over a prepared sub-grade with (coarse and fine aggregate conforming to IS : 383) aggregate cement ratio not to exceed 15:1Aggregate gradation after blending to be as per Table 600-1 cement content mot to be less than 160Kg/Cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tones vibratory roller, finishing and curing complete as per specifications Ref. DSR 2016-17 North Karnataka circle KSRB 22.1, pg.no. 176
Cum 1 20 11 0.15 33.0 33 4129 136244
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
138
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
5
Construction of un-reinforced plain cement concrete pavement (PQC)thickness as per design, over a prepared sub base with OPC cement at 360Kg per cum coarse aggregate @ 0.69cum and fine aggregate @ 0.46cum, with super plastisers @3lts conforming to IS9103-1999 Reaffirmed-2008, mixed in a concrete mixer of not less than 0.6cum capacity and appropriate weigh batcher as per approved mix design, laid in approved fixed side form work (steel channel, laying and fixing of 125 micron thich polythene film, wedges, steel plates including levelling the form work as per drawing) and spreading the concrete with shovels, rackers compacted using needle, screed and plate vibrator and finished in a continuous operation inclusing provision of contraction, expansion, construction and longitudinal joints, including groove cutting charges, joint filler, separation membrane, sealant primer, joint sealant, admixtures as approved, curing compound, finishing to lines and grades as per drawing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. 22.6 pg.no.177
Cum 1 20 11 0.2 44.0 44 6128 269623
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
139
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
6
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonne 452.4667 1390.4 1842.8667 1.9 2 6345
3 122781
7
KSRRB M300-54 Construction of Earthen shoulders with approved materials obtained from excavation from departmental land or other sources with all lifts & leads, spreading, grading to required slope and compaction complete as per specifications(Which includes watering charges & compaction by vibratory roller) Ref. DSR 2016-17 North Karnataka circle Sl. 19.61 pg.no. 148
2 20 0.5 0.45 9.0 0 2 11 0.5 0.45 5.0 0 Cum 14.0 14 445 6211
Total Amount Rs. 5,82,687
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
140
Sr No
Description of Item Unit No.
Length (m)
Width (m)
Height (m)
Qty.
Total Qty
Final Rate
Amount
1
Earth work excavation by mechanical means in hard/ordinary soil involving an average horizontal throw up to 2 mtrs and average lift up to 0.5mtrs. Excavated surface levelled and sides neatly dressed etc. the disposed earth to be levelled neatly after the breaking of clods completed as per specification MORTH clause 301 Ref. DSR 2016-17 North Karnataka circle Sl. No.19.2.1 pg.no.142
Cum 1 20 11 0.15 33.0 33 32 1040
2
KSRRB M300-59.1. Loosening of the ground up to a level of 400mm below the sub grade level, watered, graded and compacted in layers ( which includes watering charges and compaction by vibratory roller)Ref. DSR 2016-17 North Karnataka circle Sl No. 19.65, pg.no. 149
Cum 1 20 11 0.15 33.0 33 55 1802
3
KSRRB M400-6.2 Construction of granular sub- base by providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method by rotavator at OMC and compacting with vibratory power roller to achieve the desired density , complete as per specification.(Grade 2) Ref. DSR 2016-17 North Karnataka circle KSRB 20.5.2, pg.no. 155
Cum 1 20 11 0.125 27.5 28 1636 44987
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
141
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
4
KSRRB M600-1 Construction of dry lean cement concrete mix CC1:5:10 with OPC cement @ 160 Kg, with 25 mm down size graded granite metal coarse aggregate at 0.86 cum and fine aggregates @0.58 Cum Sub-base over a prepared sub-grade with (coarse and fine aggregate conforming to IS : 383) aggregate cement ratio not to exceed 15:1Aggregate gradation after blending to be as per Table 600-1 cement content mot to be less than 160Kg/Cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tones vibratory roller, finishing and curing complete as per specifications Ref. DSR 2016-17 North Karnataka circle KSRB 22.1, pg.no. 176
Cum 1 20 11 0.15 33.0 33 4129 136244
5
Construction of un-reinforced plain cement concrete pavement (PQC)thickness as per design, over a prepared sub base with OPC cement at 360Kg per cum coarse aggregate @ 0.69cum and fine aggregate @ 0.46cum, with super plastisers @3lts conforming to IS9103-1999 Reaffirmed-2008, mixed in a concrete mixer of not less than 0.6cum capacity and appropriate weigh batcher as per approved mix design, laid in approved fixed side
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
142
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
form work (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the form work as per drawing) and spreading the concrete with shovels, rackers compacted using needle, screed and plate vibrator and finished in a continuous operation inclusing provision of contraction, expansion, construction and longitudinal joints, including groove cutting charges, joint filler, separation membrane, sealant primer, joint sealant, admixtures as approved, curing compound, finishing to lines and grades as per drawing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. 22.6 pg.no.177
Cum 1 20 11 0.2 44.0 44 6128 269623
6
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonn 452.4666 1390.4 1842.866 1.9 2 63453 122781
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
143
Name of the work: Civil Work for Monsoon Shed Platform @Khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
e 7 7
7
KSRRB M300-54 Construction of Earthen shoulders with approved materials obtained from excavation from departmental land or other sources with all lifts & leads, spreading, grading to required slope and compaction complete as per specifications(Which includes watering charges & compaction by vibratory roller) Ref. DSR 2016-17 North Karnataka circle Sl. 19.61 pg.no. 148
2 20 0.5 0.45 9.0 0 2 11 0.5 0.45 5.0 0
Cum 14.0 14 445 6211
Total Amount Rs. 5,82,687
Name of the work : Civil Work for Vermi-Degradation Pad @ khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
144
Name of the work : Civil Work for Vermi-Degradation Pad @ khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
1
Earth work excavation by mechanical means in hard/ordinary soil involving an average horizontal throw up to 2 mtrs and average lift up to 0.5mtrs. Excavated surface levelled and sides neatly dressed etc. the disposed earth to be levelled neatly after the breaking of clods completed as per specification MORTH clause 301 Ref. DSR 2016-17 North Karnataka circle Sl. No.19.2.1 pg.no.142
Cum 1 20 11 0.15 33.0 33 32 1040
2
KSRRB M300-59.1. Loosening of the ground upto a level of 400mm below the sub grade level, watered, graded and compacted in layers ( which includes watering charges and compaction by vibratory roller)Ref. DSR 2016-17 North Karnataka circle Sl No. 19.65, pg.no. 149
Cum 1 20 11 0.15 33.0 33 55 1802
3
KSRRB M400-6.2 Construction of granular sub- base by providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method by rotavator at OMC and compacting with vibratory power roller to achieve the desired density , complete as per specification.(Grade 2) Ref. DSR 2016-17 North Karnataka circle KSRB 20.5.2, pg.no. 155
Cum 1 20 11 0.125 27.5 28 1636 44987
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
145
Name of the work : Civil Work for Vermi-Degradation Pad @ khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
4
KSRRB M600-1 Construction of dry lean cement concrete mix CC1:5:10 with OPC cement @ 160 Kg, with 25 mm down size graded granite metal coarse aggregate at 0.86 cum and fine aggregates @0.58 Cum Sub-base over a prepared sub-grade with (coarse and fine aggregate conforming to IS : 383) aggregate cement ratio not to exceed 15:1Aggregate gradation after blending to be as per Table 600-1 cement content mot to be less than 160Kg/Cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tones vibratory roller, finishing and curing complete as per specifications Ref. DSR 2016-17 North Karnataka circle KSRB 22.1, pg.no. 176
Cum 1 20 11 0.15 33.0 33 4129 136244
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
146
Name of the work : Civil Work for Vermi-Degradation Pad @ khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
5
Construction of un-reinforced plain cement concrete pavement (PQC)thickness as per design, over a prepared sub base with OPC cement at 360Kg per cum coarse aggregate @ 0.69cum and fine aggregate @ 0.46cum, with superplastisers @3lts conforming to IS9103-1999 Reaffirmed-2008, mixed in a concrete mixer of not less than 0.6cum capacity and appropriate weigh batcher as per approved mix design, laid in approved fixed side form work (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the form work as per drawing) and spreading the concrete with shovels, rackers compacted using needle, screed and plate vibrator and finished in a continuous operation inclusing provision of contraction, expansion, construction and longitudinal joints, including groove cutting charges, joint filler, separation membrane, sealant primer, joint sealant, admixtures as approved, curing compound, finishing to lines and grades as per drawing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. 22.6 pg.no.177
Cum 1 20 11 0.2 44.0 44 6128 269623
6
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
147
Name of the work : Civil Work for Vermi-Degradation Pad @ khanapur
Sr No
Description of Item Unit No. Length (m)
Width (m)
Height (m)
Qty. Total Qty
Final Rate
Amount
anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonne 452.47 1390.40 1842.87 1.9 2 6345
3 122781
7
KSRRB M300-54 Construction of Earthen shoulders with approved materials obtained from excavation from departmental land or other sources with all lifts & leads, spreading, grading to required slope and compaction complete as per specifications(Which includes watering charges & compaction by vibratory roller) Ref. DSR 2016-17 North Karnataka circle Sl. 19.61 pg.no. 148
2 20 0.5 0.45 9.0 0 2 11 0.5 0.45 5.0 0 Cum 14.0 14 445 6211 Total Amount Rs. 5,82,687
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
148
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
1
Earth work excavation in hard soil for foundation of structures by mechanical means as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally up to 1 km lead.(Depth up to 3 Mts) Ref. DSR 2016-17 North Karnataka circle Sl. No. 2.23.1 pg.no. 7
Foundation F1 10 1.65 1.55 1.65 42.2 Foundation F2 0 0 0 0 0.0 Cum 42.2 42.2 56 2348
2
KSRB 4-2.1 Providing and Laying in position plain cement concrete of mix 1:3:6 for Foundation and bedding with OPC cement @ 220 Kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.892cum and fine aggregates @0.465 cum machine mixed, concrete laid in layers not exceeding 15 cms. Thick, well compacted, in foundation, including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.2 pg.no.12
Foundation F1 10 1.65 1.55 0.15 3.8 Foundation F2 0 0 0 0 0.0 Cum 3.8 3.8 5637 21627
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
149
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
3
KSRB 4.2.2 Providing and Laying in position Reinforced cement concrete of design mix M20 with OPC cement @ 320 kgs, with 20mm and down size graded granite metal coarse aggregates @0.69 cum and fine aggregates @ 0.460 cum, with super plasticisers @ 3 litters conforming to is 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, columns and plinths etc., including the cost of all material, labour, HOM of machinery, compacting, curing complete but excluding the cost of reinforcement as per specifications. Ref. DSR 2016-17 North Karnataka circle KSRB 4.2.2, Sl.No.4.11, pg.no. 13
Foundation F1 10 1.5 1.4 0.45 9.5 0 Foundation F2 0 0 0 0 0.0
Columns up to Plinth Level 10 0.3 0.45 1.525 2.1 0
Cum Total 11.5 11.5 6540 75272
4
KSRB 4.2.8: Providing and laying in position Reinforced cement concrete of design mix M20, machine mixed, concrete laid in layers not exceeding 15cms thick, vibrated for beam, Roof slab including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.4.13, pg.no. 14
Plinth Beam 2 18.39 0.23 0.38 3.2 0 Columns above plinth level 10 0.3 0.45 4.52 6.1 0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
150
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
5 Cum Total 9.3 9.3 6473 60352
5
KSRB 2.3: Filling available excavated earth in sides of foundations up to plinth in layers not exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with lead up to 50m. and lift up to 1.5 m. including cost of all labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.no. 2.10, pg.no. 6
Foundation F1 10 1.65 1.55 1.5 38.4 Foundation F2 0 0 0 0 0.0 Filling below Plinth Beam 2 18.39 0.23 0.07 0.59 38.4 Deduction Foundation F1 10 1.5 1.4 0.45 9.5 0 Foundation F2 0 0 0 0 0.0
Columns up to Plinth Level 10 0.3 0.45 1.525 2.1
11.5 Total 26.9 26.9 133 3581
6
KSRB 4-6.1: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of Columns for mass concrete including cost of all materials, labour complete as per specifications .Ref. DSR 2016-17 North Karnataka circle, Sl.No.4.28, pg.no. 15
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
151
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
Footing F1 10 5.8 0.45 26.1 0 Footing F2 0 0 0 0.0
Columns below plinth 10 1.5 1.525 22.9 0
49.0 49.0 237.3 11622
7
KSRB 4-6.5: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for columns, pillers, post and struts, square/ rectangular/ polygon in plan including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.35, pg.no. 16
Columns above plinth level 10 1.5 4.525 67.9 0
165.8 165.8 384 63727
8
KSRB 4-6.7: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beams haunching, cantilever, girders, bressumers and lintels etc not exceeding 1 M in depth including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.34, pg.no. 16
Plinth Beam 2 37.24 0.38 28.3 28.3 269 7608
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
152
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
5
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonne 2.00 2.00 63453 126905
6
Fabrication supplying and erecting M.S. Angular trusses of all spans as per approved drawing and design. The entire trusses is anchored in RCC column by using 4 nose of M.S. anchor bolts at each support with 10mm thick base plate and shoe plate. The work includes cutting, straightening, placing in position of M.S. angles and welding wherever necessary and applying one coat of red oxide primer coat to all the members including cost of all materials, labour charges, and hire charges of machineries for cutting, welding, grinding and erection equipments, with all lead and lift, transportation, etc., complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No. 7.30, pg.no. 41
Kg 6850 6850 128 877485
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
153
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
7
KSRB 8.3-2 Providing and laying to required line and slope roofing with semi-corrugated (Trafford) asbestos cement sheet 6mm.thick fixed with galvanized iron J or L hooks, bolts and nuts 8mm dia. C.I. plain and bitumen washers, over the existing purlins, rafters and trusses including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.8.6, pg.no. 46
Sq.m 4 20 5.7 456.0 456.0 414 188647
8
KSRB 8.3-4 Providing and fixing Ridges and hips with asbestos cement sheet roofing with G.I. J or L hooks, bolts and nuts 8 mm. dia. G.I. plain and bitumen washers, serrated or plain wings, adjustable ridges, including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.8.8, pg.no. 46
M 4 20 80.0 80.0 340.2 27216
9
Providing and laying to required line walls with GI sheet fixed with hook, bolts and nuts 8mm. Dia. GI plain and bitumen washers, at the existing angle section including cost of materials, labour, complete as per specifications. Ref. As per Market rate
1 11 3 33.0
2 17 3 0 102.0
1 8 3 0 24.0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
154
Name of the work : Civil Work for Monsoon, Machine Shed @ Khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height
Qty. Total Qty
Final Rate
Amount
Sq.m 159.0 159 515 81806
10
KSRB 15-18.1 Applying red lead ready mix priming coat over new steel or other metal surface including preparing the surface after thoroughly cleaning oil, grease, dirt and other foreign matter, and sourced with wire brushes, fine steel wool, sand papers including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl. No. 15.73 pg.no.121
Sq.m 318.0 318 29 9238
11
KSRB 15-18.2 Providing and applying enamel metal paint two coats (excluding priming coat) over new steel or other metal surface brushing to give an even shed after cleaning oil, grease, dirt and other foreign matter including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl. No. 15.74 pg.no.121
Sq.m 318.0 318 82 26044
Total Amount Rs. 15,83,477
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
155
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
1
Earth work excavation in hard soil for foundation of structures by mechanical means as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally up to 1 km lead.(Depth up to 3 Mts) Ref. DSR 2016-17 North Karnataka circle Sl. No. 2.23.1 pg.no. 7
Foundation F1 10 1.65 1.55 1.65 42.2 Foundation F2 0 0 0 0 0.0 Cum 42.2 42.2 56 2348
2
KSRB 4-2.1 Providing and Laying in position plain cement concrete of mix 1:3:6 for Foundation and bedding with OPC cement @ 220 Kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.892cum and fine aggregates @0.465 cum machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.2 pg.no.12
Foundation F1 10 1.65 1.55 0.15 3.8 Foundation F2 0 0 0 0 0.0 Cum 3.8 3.8 5637 21627
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
156
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
3
KSRB 4.2.2 Providing and Laying in position Reinforced cement concrete of design mix M20 with OPC cement @ 320 kgs, with 20mm and down size graded granite metal coarse aggregates @0.69 cum and fine aggregates @ 0.460 cum, with super plasticisers @ 3 litters conforming to is 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, columns and plinths etc., including the cost of all material, labour, HOM of machinery, compacting, curing complete but excluding the cost of reinforcement as per specifications. Ref. DSR 2016-17 North Karnataka circle KSRB 4.2.2, Sl.No.4.11, pg.no. 13
Foundation F1 10 1.5 1.4 0.45 9.5 0 Foundation F2 0 0 0 0 0.0 Columns up to Plinth Level 10 0.3 0.45 1.525 2.1 0 Cum Total 11.5 11.5 6540 75272
4
KSRB 4.2.8: Providing and laying in position Reinforced cement concrete of design mix M20, machine mixed, concrete laid in layers not exceeding 15cms thick, vibrated for beam, Roof slab including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.4.13, pg.no. 14
Plinth Beam 2 18.39 0.23 0.38 3.2 0 Columns above plinth level 10 0.3 0.45 4.525 6.1 0 Cum Total 9.3 9.3 6473 60352
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
157
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
5
KSRB 2.3: Filling available excavated earth in sides of foundations up to plinth in layers not exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with lead upto 50m. and lift up to 1.5 m. including cost of all labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.no. 2.10, pg.no. 6
Foundation F1 10 1.65 1.55 1.5 38.4 Foundation F2 0 0 0 0 0.0 Filling below Plinth Beam 2 18.39 0.23 0.07 0.59 38.4 Deduction Foundation F1 10 1.5 1.4 0.45 9.5 0 Foundation F2 0 0 0 0 0.0 Columns up to Plinth Level 10 0.3 0.45 1.525 2.1 11.5 Total 26.9 26.9 133 3581
6
KSRB 4-6.1: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for foundations, footings, bases of Columns for mass concrete including cost of all materials, labour complete as per specifications.Ref. DSR 2016-17 North Karnataka circle, Sl.No.4.28, pg.no. 15
Footing F1 10 5.8 0.45 26.1 0 Footing F2 0 0 0 0.0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
158
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
Columns below plinth 10 1.5 1.525 22.9 0 49.0 49.0 237.3 11622
7
KSRB 4-6.5: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for columns, pillars, post and struts, square/ rectangular/ polygon in plan including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.35, pg.no. 16
Columns above plinth level 10 1.5 4.525 67.9 0 165.8 165.8 384 63727
8
KSRB 4-6.7: Providing and removing centering, shuttering, strutting, propping etc., and removal of form work for sides and soffits of beams, beams haunching, cantilever, girders, bressumers and lintels etc not exceeding 1 M in depth including cost of all materials, labour complete as per specifications. Specification No. 4.6.2Ref. DSR 2016-17 North Karnataka circle Sl.No.4.34, pg.no. 16
Plinth Beam 2 37.24 0.38 28.3 28.3 269 7608
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
159
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
5
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
Tonne 2.00 2.00 63453 126905
6
Fabrication supplying and erecting M.S. Angular trusses of all spans as per approved drawing and design. The entire trusses is anchored in RCC column by using 4 nose of M.S. anchor bolts at each support with 10mm thick base plate and shoe plate. The work includes cutting, straightening, placing in position of M.S. angles and welding wherever necessary and applying one coat of red oxide primer coat to all the members including cost of all materials, labour charges, and hire charges of machineries for cutting, welding, grinding and erection equipments, with all lead and lift, transportation, etc., complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No. 7.30, pg.no. 41
Kg 6850 6850 128 877485
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
160
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
7
KSRB 8.3-2 Providing and laying to required line and slope roofing with semi-corrugated (Trafford) asbestos cement sheet 6mm.thick fixed with galvanized iron J or L hooks, bolts and nuts 8mm dia. C.I. plain and bitumen washers, over the existing purlins, rafters and trusses including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.8.6, pg.no. 46
Sq.m 4 20 5.7 456.0 456.0 414 188647
8
KSRB 8.3-4 Providing and fixing Ridges and hips with asbestos cement sheet roofing with G.I. J or L hooks, bolts and nuts 8 mm. dia. G.I. plain and bitumen washers, serrated or plain wings, adjustable ridges, including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.No.8.8, pg.no. 46
M 4 20 80.0 80.0 340.2 27216
9
Providing and laying to required line walls with GI sheet fixed with hook, bolts and nuts 8mm. Dia. GI plain and bitumen washers, at the existing angle section including cost of materials, labour, complete as per specifications. Ref. As per Market rate
1 11 3 33.0 2 17 3 0 102.0 1 8 3 0 24.0 Sq.m 159.0 159 515 81806
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
161
Name of the work : Civil Work for Monsoon, Machine Shed @ khanapur Dimensions 36.1X30 M
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
10
KSRB 15-18.1 Applying red lead ready mix priming coat over new steel or other metal surface including preparing the surface after thoroughly cleaning oil, grease, dirt and other foreign matter, and sourced with wire brushes, fine steel wool, sand papers including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl. No. 15.73 pg.no.121
Sq.m 318.0 318 29 9238
11
KSRB 15-18.2 Providing and applying enamel metal paint two coats (excluding priming coat) over new steel or other metal surface brushing to give an even shed after cleaning oil, grease, dirt and other foreign matter including cost of materials, labour, complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl. No. 15.74 pg.no.121
Sq.m 318.0 318 82 26044
Total Amount Rs. 15,83,477
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
162
Name of the work: Civil Work for Road @ Khanapur
Width of Road 6.00 M
Length of Road 215.00 M
Sr No.
Description of Item Unit No. Length Width Height Qty. Total Qty.
Final Rate
Amount
1
Earth work excavation by mechanical means in hard /ordinary soil involving an average horizontal throw upto 2 mtrs and average lift up to 0.5mtrs. Excavated surface levelled and sides neatly dressed etc. the disposed earth to be levelled neatly after the breaking of clods completed as per specification MORTH clause 301 Ref. DSR 2015-16 North Karnataka Sl. No.19.2.1 pg.no.142
Cum 215 6 0.2 258 258 32 8127
2
Providing, laying, spreading and compacting stone aggregates of specified sizes to water bound macadam grade 2 specifications including spreading in uniform thickness, hand packing, rolling with 3-wheeled steel/ vibratory roller 8-10 tonnes In stages to proper grade and camber, applying and brooming requisite type of screening/ binding material to fill up the interstices of coarse aggregates, watering and compacting to the required density complete as per specifications. Ref DSR 2016-17 North Zone, Sl.No. 20.14.1, pg.no.157
Cum 215 6 0.075 96.75 96.75 2307.9 223289
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
163
Name of the work: Civil Work for Road @ Khanapur
Width of Road 6.00 M
Length of Road 215.00 M
Sr No.
Description of Item Unit No. Length Width Height Qty. Total Qty.
Final Rate
Amount
3
Providing, laying, spreading and compacting stone aggregates of specified sizes to water bound macadam grade 3 specifications including spreading in uniform thickness, hand packing, rolling with 3-wheeled steel/ vibratory roller 8-10 tonnes In stages to proper grade and camber, applying and brooming requisite type of screening/ binding material to fill up the interstices of coarse aggregates, watering and compacting to the required density complete as per specifications. Ref DSR 2016-17 North Zone Sl.No. 20.14.3, pg.no.157
Cum 215 6 0.075 96.75 96.75 2571.45 248788
4
KSRRB M500-6. Providing and applying primer coat with S. S. bitumen emulsion on prepared surface of granular base such as WMM including cleaning of road surface and spraying primer at rate of 0.60 Kg/ Sq.m using mechanical means complete as per specification. MORTH Specifications No. 502Ref DSR 2016-17 North Zone, Sl No. 21.6 Pg no. 161
Cum 215 6 0.075 96.75 96.75 26.25 2540
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
164
Name of the work: Civil Work for Road @ Khanapur
Width of Road 6.00 M
Length of Road 215.00 M
Sr No.
Description of Item Unit No. Length Width Height Qty. Total Qty.
Final Rate
Amount
5
KSRRB M500-10 Providing and applying tack coat using 80/100 grade bitumen (VG10) in boiler fitted with spray set distributor at the rate of 0.20 Kg/ sqm on primed surfaces cleaned with mechanical broom complete as per specification MORTH Specification No. 503Ref DSR 2016-17 North Zone, Sl.No. 21.10.2, pg.no.162
Cum 215 6 0.05 64.5 64.5 9.555 616
6
Providing and laying 20mm thick mix seal surfacing Type A on prepared surface as wearing course with specified graded crushed aggregates of 5.6mm and 11.2mm size 0.027 cum/Sq.m premixed with bituminous binder at 2.20kg/Sq.m, in hot mix plant 40/60 tonne, transporting the mixed materials in tipper and laying with mechanical paver finisher to required level and grade, rolling with power roller 8-10 tonne, excluding cost of tack coat including cost of all materials, labour, machineries complete as per specifications. Ref. DSR 2016-17 North Zone Sl.No. 21.36, pg.no. 166
Sq.m 215 6 1290 1290 151.2 195048
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
165
Name of the work: Civil Work for Road @ Khanapur
Width of Road 6.00 M
Length of Road 215.00 M
Sr No.
Description of Item Unit No. Length Width Height Qty. Total Qty.
Final Rate
Amount
7
Providing and laying bituminous macadam using 40/60 TPH capacity H.M.P. with Mechanical paver Gr-2 ( 50mm to 75 mm) with 3.3 % VG-30 Bitumen on prepared surface with crushed coarse aggregates as per design mix formula for base/ binding course including loading of aggregates with F.E. loader, hot mixing of stone aggregates an bitumen in hot mix plant, transporting the mix material in tipper to paver and laying mixed materials with paver finisher to the required level and grade, rolling by power roller to achieve the desired density, but excluding cost of primer/ tack coat including lead, lift and cost of all materials, labour, HOM of machineries complete as per specifications. Ref. DSR 2016-17 North Zone Sl.No. 21.11.6, pg.no. 162
Sq.m 215 6 0.05 64.5 64.5 5749.8 3,70,862.10 Total Amount Rs. 10,49,270
Name of the work : Civil Work for Leachate Collection Drain @ Khanapur
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
166
Length of Leachate Collection Drain 526 M
Sr No Description of Item Unit Total Qty
Final Rate
Amount
1
Earth work excavation in hard soil for foundation of structures by mechanical means as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally upto 1 km lead.(Depth upto 3 Mts) Ref. DSR 2016-17 North Karnataka circle Sl. No. 2.23.1 pg.no. 7
Cum 29 56 1598
2
KSRB 12.3.1 Providing and Laying in position plain cement concrete of M 7.5 using 40 mm down size graded granite / trap metal for haunching of 300mm internal diameter half circular stoneware pipes, concrete machine mixed laid in layers not exceeding 15 cms thick, well compacted, including cost of all materials, labour, HOM of machinery, curing complete as per specifications. Ref. As per Market Rate
M 87 762 66294 Total Amount Rs. 67,892
Name of the work : Civil Work for Storm Water Gutter @ Khanapur
Length of Storm Water Gutter 1068 M
Sr No
Description of Item Unit No. Length Width Height Qty. Total Qty
Final Rate
Amount
1
Earth work excavation by mechanical means in hard/ordinary soil involving an average horizontal throw up to 2 mtrs and average lift up to 0.5mtrs. Excavated surface levelled and sides neatly dressed etc. the disposed earth to be levelled neatly after the breaking of clods completed as per specification MORTH clause 301 Ref. DSR 2016-17 North Karnataka Sl. No.19.2.1
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
167
Name of the work : Civil Work for Storm Water Gutter @ Khanapur
Length of Storm Water Gutter 1068 M
Sr No
Description of Item Unit No. Length Width Height Qty. Total Qty
Final Rate
Amount
pg.no.142 Cum 1 1068 0.75 0.65 520.65 521 32 16400
2
KSRB 4-2.1 Providing and Laying in position plain cement concrete of mix 1:3:6 for Foundation and bedding with OPC cement @ 220 Kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.892cum and fine aggregates @0.465 cum machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.2 pg.no.12
cum 1 1068 0.75 0.1 80.1 80 5637 451560
3
KSRB 4.2.2 Providing and Laying in position Reinforced cement concrete of design mix M20 with OPC cement @ 320 kgs, with 20mm and down size graded granite metal coarse aggregates @0.69 cum and fine aggregates @ 0.460 cum, with super plasticisers @ 3 liters conforming to is 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in foundation for footings, columns and plinths etc., including the cost of all material, labour, HOM of machinery, compacting, curing complete but excluding the cost of reinforcement as per specifications. Ref. DSR 2016-17 North Karnataka circle
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
168
Name of the work : Civil Work for Storm Water Gutter @ Khanapur
Length of Storm Water Gutter 1068 M
Sr No
Description of Item Unit No. Length Width Height Qty. Total Qty
Final Rate
Amount
KSRB 4.2.2,Sl.No.4.11, pg.no. 13 cum 1 1068 0.65 0.1 69.42 69 2 1068 0.1 0.45 48.06 48 117 6540 768372
4
KSRB 4.9.2: Providing TMT Fe-500 steel reinforcement for R.C.C. work including straightening, cutting, bending, hooking, placing in position, lapping and/ or welding wherever required, tying with binding wire and anchoring to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.46.2 pg.no.17
1427.74 674.98 2102.71 2.21 2.21 63452.55 140094
Total Amount Rs. 13,76,426
Name of the work: Civil Work for Common Facilities @Khanapur Sr No Component Cost in Rupees Cost in Lakhs 1 Civil Work for Common Facilities @Khanapur 25,14,369 25.14 2 Civil Work for Monsoon Shed Platform @ Khanapur 5,82,687 5.83 3 Civil Work for Machine Shed Platform @ Khanapur 5,82,687 5.83 4 Civil Work for VDP Platform @ Khanapur 5,82,687 5.83 5 Civil Work for Monsoon Shed @ Khanapur 15,83,477 15.83
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
169
Name of the work: Civil Work for Common Facilities @Khanapur Sr No Component Cost in Rupees Cost in Lakhs 6 Civil Work for Machine Shed @ Khanapur 15,83,477 15.83 7 Civil Work for Road @ Khanapur 10,49,270 10.49 8 Civil Work Storm Water Gutter @Khanapur 13,76,426 13.76 9 Civil Work Leachate Collection Drain @Khanapur 67,892 0.68 10 Weigh Bridge 5,61,000 5.61 Total 1,04,83,975 104.84
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
1
Earth work excavation in hard soil for foundation of structures by mechanical means as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally up to 1 km lead.(Depth up to 3 Mts) Ref. DSR 2016-17 North Karnataka circle Sl. No. 2.23.1 pg.no. 7
Foundation 6 0.5 0.5 1 1.5 Cum 1.5 2 56 83
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
170
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
3
KSRB 4-2.1 Providing and Laying in position plain cement concrete of mix 1:3:6 for Foundation and bedding with OPC cement @ 220 Kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.892cum and fine aggregates @0.465 cum machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in foundation, including cost of all materials, labour, machinery, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl. No. 4.2 pg.no.12
Cum 6 0.5 0.5 1 1.5 1.5 5637 8456
2
KSRB 2.3: Filling available excavated earth in sides of foundations up to plinth in layers not exceeding 20 cms. In depth, compacting each deposited layer by ramming after watering with lead up to 50m. and lift up to 1.5 m. including cost of all labour complete as per specifications. Ref. DSR 2016-17 North Karnataka circle Sl.no. 2.10, pg.no. 6
Filling in plinth 1 5 8 0.3 12 0
Cum 12 12.0 133.35 1600
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
171
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
4
Providing and laying flooring with M15 cement concrete 40 mm thick using broken granite 20 mm and down size laid to line and level in one layer and finish with a floating coat of neat cement, including cost of materials, labour, curing complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl. No. 14.8 pg.no.101
Sq.m 1 5 8 0 40.0 40.0 333 13320
5
Fabrication supplying and erecting M.S. Tubular trusses of all spans as per approved drawing and design with prefabricated steel applications using quality material and are durable, reliable and corrosion and abrasion resistant. Welding shall conform to latest structural welding code. Quality shall be on various parameters like shape, size, design gauge and polish. The entire trusses is anchored in RCC column by using 4 nose of M.S. anchor bolts at each support with 10mm thick base plate and shoe plate. The work includes cutting, straightening, placing in position of M.S.pipes and welding wherever necessary and applying one coat of red oxide primer coat to all the members including cost of all materials, labour charges, and hire charges of machineries for cutting, welding, grinding and erection equipments, with all lead and lift, transportation, etc., complete as per specifications. Ref. DSR 2016-17 North Karnataka Sl.No. 7.29, pg.no. 41
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
172
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
Kg 1610 1610 110 177100
6
Providing and laying to required line walls with GI sheet fixed with hook, bolts and nuts 8mm. Dia. GI plain and bitumen washers, at the existing angle section including cost of materials, labour, complete as per specifications. Ref. As per Market rate
Top 1 5 8 40.0 0 Short Side 2 5 3 30.0 Long Side 2 8 3 48.0
Sq.m 121.9 122 490 59731
7
Providing chain link fencing 50 mm size of 8 gauge properly stretched between existing rectangular poles and fixed with suitable bolts & nuts, the free ends shall be welded to the pole and block pipe at top and bottom as required including cost of all materials, labour, lead and lifts and as per the directions of the Engineer-in charge of the work and including providing 2 coats of approved quality paint over one coat of shop painting. Ref. DSR 2016-17 North Karnataka Sl. No. 37.3pg.no. 262
W1 1 8 1.5 12.0 W2 1 8 1 8.0 W3 2 6.25 12.5 Sq.m 32.5 33 657 21353
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
173
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
Total Amount Rs. 2,81,643 Length of Fencing for DWCC 41 M Sr No
Description of Item Unit No. Lengt
h (m) Width (m)
Height (m) Qty. Total
Qty Final Rate Amount
3
Supplying and fixing M.S. Rectangular poles made out of 2 equal angles of 65x65x6 mm welded together and fixed in CC (1:2:4) with 2 nos 16 mm dia. M.S. hold fast rods each of leangth 25 cms. Including cost of all materials, cutting, bending scaffolding wherever necessary, and nicely finishing the welded joints with all lead lifts and as per the directions of the Engineer-in charge of the work and including providing 2 coats of approved quality paint over one coat of shop painting. ( excluding cost of earthwork and concrete ) Ref. DSR 2016-17 North Karnataka Sl. No. 37.2 pg.no. 262
RM 26 3.5 91.0 91 920 83720
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
174
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
4
Providing chain link fencing 50 mm size of 8 gauge properly stretched between existing rectangular poles and fixed with suitable bolts & nuts, the free ends shall be welded to the pole and block pipe at top and bottom as required including cost of all materials, labour, lead and lifts and as per the directions of the Engineer-in charge of the work and including providing 2 coats of approved quality paint over one coat of shop painting. Ref. DSR 2016-17 North Karnataka Sl. No. 37.3pg.no. 262
Sq.m 26 2 52.0 52 657 34164
5
Providing barbed GI wire fencing of 12x12 gauge drawn into stone pillars or iron pillars including in holes wherever necessary excluding the cost of pillars but including the cost of barbed wire and binding wire etc., complete. Ref. DSR 2016-17 North Karnataka,Sl.No.37.5, pg.no. 262
M 3 26 78.0 78 28 2153
6
KSRRB M300-8.1. Planting and maintaining of flowering plants and shrubs in central verge MORTH Specification No. 307 (Duranta) Ref. DSR 2016-17 North Karnataka, Sl.No.19.86, pg.no. 151
M 26 22 579
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
175
Name of the work : Civil Work for Dry Waste Collection Centre at khanapur
Area of DWCC 40 Sq.m
Sr No
Description of Item Unit No Length
Width Height Qty. Total Qty
Final Rate
Amount
7
Providing and fixing M.S. Gate as per Chief Architect Drawing, using 50mmx50mm 14 gauge M.S. hollow pipe frame work bent to ornamental shape as shown in the drawing and 35mm x 6mm and 16mm x 16mm square rods for verticals alternatively spaced at 4cms c/c in two halves and 40mm x 6mm M.S. flats for horizontal member and at the top cast iron spikes are provided at alternate vertical members as the shown in the drawing etc., complete. All the steel surface should be thoroughly clean free of dust and painted with anti corrosive paint (shop paint) etc., complete. The work includes cost of all materials, labour charges for all items of work, hire charges for welding, cutting and grinding equipment, and electricity charges with lead and lift, loading and unloading charges, etc., complete as per specifications. Ref. DSR 2016-17 North Karnataka, Sl.No.7.37, pg.no. 43
Sq.m 1 3 1.6 4.8 5 2947 14146 Total Amount Rs. 1,34,761
Bio-digester Toilet as per SBM Guidelines including fitting, Transport 1 30000 30,000
Total Amount Rs 4,46,405
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayat Khanapur
176
9.4 Requirement of Operation and Maintenance cost
The table below gives details of required Operation and Maintenance cost for collection and
transportation of proposed Solid Waste Management System.
TABLE 9-2: REQUIREMENT OF MANPOWER
Man power requirement Required Collection & Transportation, Street Sweeping and Drain Cleaning
Drivers for Door to door collection - Auto Tipper 3 PKs for door to door collection Auto Tipper 3 PKs for door to door collection Push Cart ( Congested Areas) 2 Drivers for street sweeping and C&D collection (Tractor Trailer) 1 PKs for street sweeping and C&D collection(Tractor Trailer) 3 PKs for street sweeping (Sweeper) 12 Drivers for Tractor Trailer for Bulk Waste Collection 1 PKs for Tractor Trailer for Bulk Waste Collection 3 Driver for Jetting and Suction Machine 1 PK for Jetting and Suction Machine 1
DWCC Supervisory Staff 0
PK at DWCC 1
Processing Site Driver for Tractor Trailer and Back Hoe Loader at Landfill site 1
PK for capacity Tractor trailer at Landfill site 1 Processing Plant Manager at Landfill Site 0 PK at Landfill Site 1 Weighbridge Operator 0 Security Guard 1
TABLE 9-3 O&M COST REQUIREMENT FOR MANPOWER
Total required
Permanent
Contract/ outsource
Salary / month/ person
Monthly expenses
Yearly expenses
Driver Auto tippers & tractor trailers 7 0 6 11710.6 87829.5 1053954 Driver for JCB 1 12205.6 15257 183084 Pk's 27 7 20 13635.6 340890 4090680 Security Guard 1 0 1 10775.6 13469.5 161634 Total salary of permanent staff (existing) in Lakh Rs.
1680000
Total Salary of Proposed Staff 44
30
5489352
Total Salary of Proposed Staff (in Lakhs)
71.69
TABLE 9-4 O&M EXPENDITURE
Fuel (Rs. 55/Lit.) No of Vehicles
Fuel required (L/Day)
Auto tipper 3 3 16,200 1,94,400 Tractor Trailer for Street Sweeping 1 5 9,000 1,08,000
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
177
Loaders vehicle at land fill site 2 10 36,000 4,32,000 Jetting and Suction Machine 1 7 12,600 1,51,200 Tractor Trailer for Bulk Waste Collection 1 5 9,000 1,08,000 Bio-culture @ Rs. 60/- per Kg , plus transportation cost. Use of 800 gms per tonne of garbage
800 gms per tonne At rate of Rs. 60/- per Kg 84,729
Power consumption No. of Units
Rate per Unit
Power consumption of 70 kW/day 70 10,500 126,000 AMC Charges AMC for Vehicles at 10% of capital cost for Collection and Transport 4,50,613 AMC for Equipment and Machinery at 10% of capital cost for Mechanical Component at Processing Facility 2,05,020
Water Charges Water Supply 15 10 4,500 54,000 No of staff Rs. per year Baggage and packing cost Lumpsum 2,000 24,000 Transportation Lumpsum 2,000 24,000 Additives Lumpsum 2,000 24,000 Misc Lumpsum 2,000 24,000 TOTAL PROPOSED O&M EXPENDITURE Rs. 91,79,314
9.5 Revenue from Sale of Compost and User Charges
The sale of compost and requirement of charges to be collected from residential households
and commercial entities to run Solid Waste Management Facility is explained in the table
below.
TABLE 9-5: PROPOSED USER CHARGES
S. N.
Waste Generators No of Generators
2017 2018 2019 2020 2021 2022 Population 20959 21244 21532 21824 22118 22415
Total HH / Properties 4581 4718 4860 5006 5156 5311
1 Non Slum HH Total 4173 4298 4427 4560 4697 4838
Non Slum HH Big 1252 1289 1328 1368 1409 1451
Non Slum HH Small 2921 3009 3099 3192 3288 3386
2 Slum HH 408 420 433 446 459 473
a Veg. Markets + Marriage Halls
2 2 2 2 2 2
b Big Hotels 8 8 8 9 9 9
Small Hotel 35 35 35 35 35 35
c Meat/Chicken shops/Slaughterhouse
5 5 5 5 6 6
3 Bulk Generators (a+b+c) 50 50 50 51 52 52
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
178
S. N.
Waste Generators No of Generators
d Petty Shops 100 103 106 109 113 116
e Institutions 6 6 6 7 7 7
4 Other Commercials (d+e) 106 109 112 116 119 123
5 User Charges (Rs / Month)
a Non Slum HH Big 45 52 60 68 79 94
Non Slum HH Small 35 40 46 53 61 73
Slum HH 30 35 40 46 52 63
Veg. Markets + Marriage Halls
400 500 600 700 800 900
Big Hotels 250 300 350 400 450 500
b Small Hotel 200 225 250 275 300 325
c Meat/Chicken shops/Slaughterhouse
80 90 100 110 120 130
d Petty Shops 50 60 70 80 90 100 Institutions 100 110 120 130 140 150 6 Total Recovary form User
Charges
a Non Slum HH Big 0.48 0.57 0.71 0.84 1.05 1.30
Non Slum HH Small 0.87 1.03 1.29 1.53 1.91 2.36
Slum HH 0.10 0.12 0.15 0.18 0.23 0.28
Veg. Markets + Marriage Halls
0.01 0.01 0.01 0.01 0.02 0.02
Big Hotels 0.02 0.02 0.03 0.04 0.04 0.05
b Small Hotel 0.07 0.08 0.09 0.10 0.11 0.11
c Meat/Chicken shops/Slaughterhouse
0.00 0.00 0.01 0.01 0.01 0.01
d Petty Shops 0.03 0.03 0.04 0.04 0.05 0.05 Institutions 0.10 0.11 0.13 0.14 0.16 0.17 Total Monthly 1.68 1.98 2.45 2.89 3.57 4.36 A Revenue from User Charges
(in Lakhs) 20.15 23.77 29.42 34.68 42.83 52.32
Compost Sale
a Total Compost Generated (MT/Year)
401.63 407.10 412.62 418.20 423.83 429.53
b Sale Value of Compost (Rs/ Kg)
2.50 2.50 2.66 2.84 3.02 3.22
B Revenue from Sale of Compost
10.04 10.18 10.99 11.86 12.80 13.81
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
179
S. N.
Waste Generators No of Generators
C Revenue from Recyclable waste
0.94 1.14 1.35 1.56 1.78 2.00
D Toal Revenue (A+B+C) 31.12 35.08 41.76 48.10 57.41 68.14
E O&M Expenses Proposed 91.79 97.76 104.11 110.88 118.09 125.76
F Recovary Proposed 33.91% 35.89% 40.11% 43.38% 48.61% 54.18%
9.6 Revenue Proposed
Sl. No Description Rs. In Lakhs
1 O&M Expenses Proposed 91.79 2 Revenue by sale of compost and by-products (A) 10.04 3 Revenue by way of User Charges (B) 20.15 4 Revenue from sale of recyclables (C) 0.94 Total revenue proposed (A + B + C) 31.12 Deficit = Proposed total O&M cost – Proposed total revenue generated 60.67 5. 75% of Proposed Labour cost to be obtained from untied grants such as SFC etc. 30.68 6. 100% SFC grant for permanent staff member 16.80
9.7 Breakup of Financial Aspect
Sl. No. Particulars
Capital Cost (Rs. In Lakhs) O & M Cost (Rs. In Lakhs)
Civil Components
Vehicles & Machineries
a Door-to-door collection & transportation 16.56 1.94 b Street sweeping & other cleaning activities 1.64 2.59 c Dry waste collection centre 4.60 10.30 d Secondary collection & transportation 1.10 1.08
e Waste Processing (Aerobic Composting (organic waste) RDF (Inorganic waste) Including civil works total capital cost)
107.98 42.23 7.94
f Waste disposal and Leachate treatment 57.50 18.35 5.58 g Bio-mining if considered 5.15 h Salaries for Staff 71.69
i Others (Social Forestry, Napkin Incinerator, Rainwater Harvesting, Safety Equipments etc) 7.23 0.96
182.46 90.19 Total Cost 272.65 91.79
Cost / ton – 7.85 Tons 34.75 Lakhs 3206
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
180
Annexure 1. Legal Aspects
The legal framework for solid waste management stems from the Municipality Act, the state
policy on solid waste management and the MSW rules 2016 and associates rules. It is
advisable to incorporate in the responsibilities of the various stakeholders to enable
enforcement of proper solid waste management.
The following legal provisions may be incorporated in the ULB by-laws
Duties of waste generators.-
(1) Every waste generator shall,
(a) segregate and store the waste generated by them in three separate streams namely
bio-degradable, non bio-degradable and domestic hazardous wastes in suitable bins and
handover segregated wastes to authorized waste pickers or waste collectors as per the
direction or notification by the local authorities from time to time;
(b) wrap securely the used sanitary waste like diapers, sanitary pads etc., in the pouches
provided by the manufacturers or brand owners of these products or in a suitable wrapping
material as instructed by the local authorities and shall place the same in the bin meant for
dry waste or non- bio-degradable waste;
(c) store separately construction and demolition waste, as and when generated, in his
own premises and shall dispose off as per the Construction and Demolition Waste
Management Rules, 2016; and
(d) Store horticulture waste and garden waste generated from his premises separately in
his own premises and dispose of as per the directions of the local body from time to time.
(2) No waste generator shall throw, burn or burry the solid waste generated by him, on
streets, open public spaces outside his premises or in the drain or water bodies.
(3) All waste generators shall pay such user fee for solid waste management, as specified
in the bye-laws of the local bodies.
(4) No person shall organize an event or gathering of more than one hundred persons at
any unlicensed place without intimating the local body, at least three working days in
advance and such person or the organizer of such event shall ensure segregation of waste at
source and handing over of segregated waste to waste collector or agency as specified by
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
181
the local body.
(5) Every street vendor shall keep suitable containers for storage of waste generated
during the course of his activity such as food waste, disposable plates, cups, cans, wrappers,
coconut shells, leftover food, vegetables, fruits, etc., and shall deposit such waste at waste
storage depot or container or vehicle as notified by the local body.
(6) All resident welfare and market associations shall, within one year from the date of
notification of these rules and in partnership with the local body ensure segregation of
waste at source by the generators as prescribed in these rules, facilitate collection of
segregated waste in separate streams, handover recyclable material to either the
authorized waste pickers or the authorized recyclers. The bio-degradable waste shall be
processed, treated and disposed off through composting or bio-methanation within the
premises as far as possible. The residual waste shall be given to the waste collectors or
agency as directed by the local body.
(7) All gated communities and institutions with more than 5,000 sqm area shall, within one
year from the date of notification of these rules and in partnership with the local body,
ensure segregation of waste at source by the generators as prescribed in these rules,
facilitate collection of segregated waste in separate streams, handover recyclable material
to either the authorised waste pickers or the authorized recyclers. The bio-degradable
waste shall be processed, treated and disposed off through composting or bio-methanation
within the premises as far as possible. The residual waste shall be given to the waste
collectors or agency as directed by the local body.
(8) All hotels and restaurants shall, within one year from the date of notification of these
rules and in partnership with the local body ensure segregation of waste at source as
prescribed in these rules, facilitate collection of segregated waste in separate streams,
handover recyclable material to either the authorised waste pickers or the authorised
recyclers. The bio-degradable waste shall be processed, treated and disposed off through
composting or bio-methanation within the premises as far as possible. The residual waste
shall be given to the waste collectors or agency as directed by the local body.
Duties and responsibilities of local authorities and village Panchayats of census towns and
urban agglomerations.-
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
182
The local authorities and Panchayats shall,-
(a) prepare a solid waste management plan as per state policy and strategy on solid
waste management within six months from the date of notification of state policy and
strategy and submit a copy to respective departments of State Government or Union
territory Administration or agency authorised by the State Government or Union territory
Administration;
(b) arrange for door to door collection of segregated solid waste from all households
including slums and informal settlements, commercial, institutional and other non
residential premises. From multi-storage buildings, large commercial complexes, malls,
housing complexes, etc., this may be collected from the entry gate or any other designated
location;
(c) establish a system to recognise organisations of waste pickers or informal waste
collectors and promote and establish a system for integration of these authorised waste-
pickers and waste collectors to facilitate their participation in solid waste management
including door to door collection of waste;
(d) facilitate formation of Self Help Groups, provide identity cards and thereafter
encourage integration in solid waste management including door to door collection of
waste;
(e) frame bye-laws incorporating the provisions of these rules within one year from the
date of notification of these rules and ensure timely implementation;
(f) prescribe from time to time user fee as deemed appropriate and collect the fee from
the waste generators on its own or through authorised agency;
(g) direct waste generators not to litter i.e throw or dispose of any waste such as paper,
water bottles, liquor bottles, soft drink canes, tetra packs, fruit peel, wrappers, etc., or burn
or burry waste on streets, open public spaces, drains, waste bodies and to segregate the
waste at source as prescribed under these rules and hand over the segregated waste to
authorised the waste pickers or waste collectors authorised by the local body;
(h) setup material recovery facilities or secondary storage facilities with sufficient space
for sorting of recyclable materials to enable informal or authorised waste pickers and waste
collectors to separate recyclables from the waste and provide easy access to waste pickers
and recyclers for collection of segregated recyclable waste such as paper, plastic, metal,
glass, textile from the source of generation or from material recovery facilities; Bins for
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
183
storage of bio-degradable wastes shall be painted green, those for storage of recyclable
wastes shall be printed white and those for storage of other wastes shall be printed black;
(i) direct street sweepers not to burn tree leaves collected from street sweeping and
store them separately and handover to the waste collectors or agency authorised by local
body;
(j) provide training on solid waste management to waste-pickers and waste collectors;
(k) collect waste from vegetable, fruit, flower, meat, poultry and fish market on day to
day basis and promote setting up of decentralised compost plant or bio-methanation plant
at suitable locations in the markets or in the vicinity of markets ensuring hygienic
conditions;
(l) collect separately waste from sweeping of streets, lanes and by-lanes daily, or on
alternate days or twice a week depending on the density of population, commercial activity
and local situation;
(m) transport segregated bio-degradable waste to the processing facilities like compost
plant, bio-methanation plant or any such facility. Preference shall be given for on site
processing of such waste;
(n) transport non-bio-degradable waste to the respective processing facility or material
recovery facilities or secondary storage facility;
(o) involve communities in waste management and promotion of home composting, bio-
gas generation, decentralised processing of waste at community level subject to control of
odour and maintenance of hygienic conditions around the facility;
(p) educate workers including contract workers and supervisors for door to door
collection of segregated waste and
transporting the unmixed waste during primary and secondary transportation to processing
or disposal facility;
(q) ensure that the operator of a facility provides personal protection equipment
including uniform, fluorescent
jacket, hand gloves, raincoats, appropriate foot wear and masks to all workers handling solid
waste and the same are used by the workforce;
(r) frame bye-laws and prescribe criteria for levying of spot fine for persons who litters or
fails to comply with the provisions of these rules and delegate powers to officers or local
bodies to levy spot fines as per the bye laws framed; and
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
184
(s) create public awareness through information, education and communication campaign
and educate the waste generators on the following; namely:-
(i) not to litter
(ii) minimise generation of waste;
(iii) reuse the waste to the extent possible;
(iv) practice segregation of waste into bio–degradable, non-biodegradable (recyclable
and combustible),
(v) practice home composting, vermi-composting, bio-gas generation or community
level composting;
(vi) wrap securely used sanitary waste as and when generated in the pouches provided
by the brand owners or a suitable wrapping as prescribed by the local body and
place the same in the bin meant for non- biodegradable waste;
(vii) storage of segregated waste at source in different bins;
(viii) handover segregated waste to waste pickers, waste collectors, recyclers or
waste collection agencies;and
(ix) pay monthly user fee or charges to waste collectors or local bodies or any other
person authorised by the local body for sustainability of solid waste management.
(x) Legal Provisions related to Solid Waste Management and Sanitation under
Karnataka Municipal Act 1964
Clause Sub clause Provision
75
Compulsory acquisition of land -Whenever a municipal council requires any immovable property for the purposes of this Act, the Government may, at the request of the municipal council procure the acquisition thereof under the Land Acquisition Act, 1894, and the immovable property shall be transferred to the municipal council and shall thereafter vest in such council.
Chapter V Obligatory and Discretionary Functions of Municipal Councils Obligatory functions of municipal councils related to Sanitation – Clause Sub clause Provision
87 C
cleansing public streets, places and sewers, and all spaces not being private property, which are open to the enjoyment of the public, whether such spaces are vested in the municipal council or not, removing noxious vegetation and abating all public nuisances
e regulating or abating offensive or dangerous trades or practices
r
providing covered metallic receptacles and covered metallic receptacles mounted on wheels for use by servants employed by the municipal council for the removal of night soil and rubbish and disposing of night-soil and rubbish and, if so required by the
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
185
Clause Sub clause Provision Government, preparation of compost manure from such night-soil and rubbish
Discretionary functions of municipal councils related to Sanitation – Clause Sub clause Provision
91 k
Supplying, constructing and maintaining receptacles, fittings, pipes and other appliances whatsoever on or for the use of private premises for receiving and conducting the sewage thereof into a sewer under the control of the municipal council
Chapter IX Powers and Offences Powers connected with Drainage and Water Works Clause Sub clause Provision 193 Municipal control over drains, etc. 194 Powers for making drains 195 Sufficient drainage of houses
196 Power of owners and occupiers of 1[buildings or vacant lands]1 to drain into municipal drains
197 Right to carry drain through land or into drain belonging to other persons
199 Provision of privies, etc 201 Power to close existing private drains 203 Encroachment on municipal drains, etc 206 Power of carrying water mains, etc Powers for the prevention of nuisance
224 1
Depositing dust, etc. - Whoever deposits or causes or suffers any member of his family or household to deposit any dust, dirt, dung or ashes, or garden, kitchen or stable refuse, or filth of any kind, or any animal matter or any broken glass or earthenware or other rubbish or any other thing that is or may be a nuisance, shall be punished with fine which may extend to twenty-five rupees.
2
Except with the permission of the municipal council, disposal of any nightsoil into any sewer, drain, culvert, tunnel, gutter or water-course, same, shall be punished with fine which may extend to twenty-five rupees.
225
Discharging sewage, etc - Whoever causes or allows the water of any sink or sewer or any other liquid or other matter which is or which is likely to become offensive, or causes or allows any offensive matter from any sewer or privy to run, drain or be thrown into a surface drain in any street, without the permission in writing of the municipal council or who fails to comply with any condition prescribed in such permission, shall be punished with fine which may extend to twenty-five rupees.
227 1
Removal of nightsoil The municipal council may from time to time fix the hours during which only it shall be lawful to remove any night-soil or other such offensive matter. (b) at any time, whether such hours have been fixed by the
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
186
Clause Sub clause Provision municipal council or not,- (i) uses for any such purpose any cart, carriage, receptacle or vessel not having a covering proper for preventing the escape of the contents thereof and of the stench therefrom, or (ii) wilfully or negligently slops or spills any such offensive matter in the removal thereof, or (iii) does not carefully sweep and clean every place in which any such offensive matter has been slopped or spilled, or (iv) places or sets down in any public place any vessel containing such offensive matter, or (v) drives or takes or causes to be driven or taken any cart, carriage, receptacle or vessel used for any such purpose as aforesaid through any street or by any route, other than such as shall from time to time be appointed for that purpose by the municipal council by public notice, shall be punished with fine which may extend to twenty-five rupees.
233 1 Provision of bathing facilities -The municipal council may set apart sufficient public places for the purpose of being used as bathing places
234
Fouling water.—Whoever, bathes in any stream, pool, tank, reservoir, well, cistern, conduit and aqueduct belonging to the municipal council, or washes, or causes to be washed therein any animal or anything whatever, or throws, puts or casts or causes to enter therein any animal or anything, shall be punished with fine which may extend to fifty rupees.
235 1
Regulation of washing of clothes by washermen.— The municipal council may, by public notice, prohibit the washing of clothes by washermen in the exercise of their calling, except at such places as it shall appoint for this purpose;
2 The municipal council shall provide suitable places for the exercise
236 1
Abatement of nuisances from wells, etc.— If, in the opinion of the municipal council, any pool, ditch, quarry excavation is or is likely to become a breeding place of mosquitoes or in any other respect a nuisance, the municipal council may, by notice in writing, require the owner thereof to fill up, cover over or drain off
238
Using offensive manure, etc - Whoever, except with the written permission of the municipal council, and in the manner, if any, enjoined in such permission stores or uses nightsoil or other manure or substance emitting an offensive smell shall be punished with fine which may extend to twenty-five rupees.
239
Tethering cattle, etc.—Whoever tethers cattle or other animals, or causes or suffers them to be tethered by any member of his family or household, in any public street or place so as to obstruct or endanger the public traffic therein, or to cause a nuisance, or who causes or suffers such animals to stray about without a keeper, shall be punished with fine which may extend to twenty-five rupees.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
187
Clause Sub clause Provision
240
Feeding animals on filth.—Whoever feeds any animal which is kept for dairy purposes or is intended for human food on excrementitious matter, stable refuse, filth, or other offensive matter, or permits such animal to feed or to be fed on such matter, shall be punished with fine which may extend to fifty rupees.
241 2
Consumption of smoke - (2) If any person shall, after such direction, use or permit to be used, any such furnace not so constructed, supplemented, or altered, or shall so negligently use, or permit to be used, any such furnace that the smoke arising there from shall not be effectually consumed or burnt as far as may be practicable, every person so offending being the owner or occupier of the said works or buildings or being an agent or other person employed by such owner or occupier for managing the same, shall be punished with fine which may extend to fifty rupees and upon any subsequent conviction with fine which may extend to five hundred rupees:
242 iv Prohibition of nuisance.—Whoever, carries meat exposed to public view, shall, be punished with fine which may extend to one hundred rupees
Regulation of markets, sale of goods, etc. Clause Sub clause Provision
243 2
Licensing markets, slaughter houses and certain businesses - Whoever uses or permits the use of any place contraty to the direction, or without the licence required by sub-section (1), or in contravention of any of the conditions or during the suspension of the licence shall be punished with fine which may extend to twenty-five rupees
244 2
Opening, closing and letting of markets and slaughter houses - Any person who, without the permission or licence of the municipal council, sells or exposes for sale any articles in the said markets, or uses the said slaughter houses, shall be punished with fine which may extend to twenty-five rupees.
246
Slaughter houses, etc., beyond municipal limits.—It shall be lawful for the municipal council with the sanction of the Deputy Commissioner, to establish slaughter houses, or places for the disposal of carcasses of animals beyond the limits of the 1[municipal area]1 and all provisions of this Act and of bye-laws in force thereunder relating to such places within municipal limits shall have full force therein, as if such places were within the municipal limits.
Chapter XIII Rules and Bye - Laws Clause Sub clause Provision
324 1
Power to make bye-laws - Subject to the provisions of this Act and the rules made thereunder, every municipal council may from time to time make, alter or rescind bye-laws – (a) for the regulation and inspection of markets, all public places used for the sale of articles, and slaughter houses and all places used by or for animals which are for sale or hire or the produce of which
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
188
Clause Sub clause Provision is sold, and for the proper and clean conduct of business therein, for regulating the sale of fruits, flowers and vegetables, or meat, fish, eggs and animals in the municipal markets or other specified places, and for fixing the rents and other charges to be levied for the use of any of them which belong to the municipal council (l) for the regulation of advertisements and their display
2 In making any bye-laws under sub-section (1), the municipal council may provide that a contravention thereof shall be punishable,—
5
Every bye-law made by a municipal council under this section shall not have effect until it has been approved by the Government; and every such bye-law shall be submitted to the Government along with a copy of the notice published under sub-section (4) and of every objection or suggestion received with respect to the draft bye-law.
7
Every bye-law as approved by the Government shall be published in the prescribed manner and shall come into force from such date as may be specified by the municipal council and where no date is specified on the date of such publication.
325 1
Power of Government to make model bye-laws and adoption of such bye-laws by municipal councils. – (1) In respect of any of the matters specified in section 324 the Government may, after previous publication of the draft for not less than one month, make model bye-laws, and such bye-laws may be different for different classes of 1[municipal areas]1. 1. Substituted by Act 36 of 1994 w.e.f. 1.6.1994.
2
A municipal council may by resolution adopt the model bye-laws in respect of any matter, and such bye-laws shall come into force in such 1[municipal area]1 from such date as the municipal council may specify in a notice published in the prescribed manner. 1. Substituted by Act 36 of 1994 w.e.f. 1.6.1994.
3
If a municipal council proposes to adopt the model bye-laws in respect of any matter subject to any modifications, the procedure specified in sub-sections (4), (5) and (6) of section 324 shall be followed as if the modifications were bye-laws proposed to be made by the municipal council. The modifications as approved by the Government shall be published in the prescribed manner and the model bye-laws shall subject to such modifications come into force from such date as may be specified by the municipal council and where no date is specified on the date of such publication.
4
a) The Government may by order direct any municipal council to adopt the model bye-laws in respect of any matter, within such period not being less than three months from the date of receipt of the direction by the municipal council. (b) If the municipal council fails to take any action for adopting the model bye-laws with or without modifications, the Government may by notification declare that the said model bye-laws shall come into force in the said 1[municipal area]1 from such date as may be specified in such
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
189
Clause Sub clause Provision notification, and such bye-laws shall come into force accordingly. 1. Substituted by Act 36 of 1994 w.e.f. 1.6.1994.
5 The provisions of this section shall have effect notwithstanding anything contained in section 324.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
190
Annexure 2. Solid Waste Chemical Analysis
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
191
Annexure 3. Waste Generation Estimation
Waste Generation from Households Samples
Daily Survey Report Survey Location Residential (Household)
Sr.No Ward No. Street Name Name of the
respondent Weight in kg Average
Day 1 Day 2 Day 3 Average
1 4 station road shahunagar Irfan khan 1.0 1.2 0.8 1.0
2 3 Station Road Shavu Nagar Shakhib mulla 0.9 0.4 0.8 0.7
3 3 station road Santos dodamani 0.7 0.5 0.9 0.7
4 3 station road shahunagar Malik khan 1.5 0.7 1.0 1.1
5 3 Station Road Shavu Nagar Anjawwa kumta 1.0 1.0 1.2 1.1
6 3 Station Road Shavu Nagar Mk khadir 0.5 0.9 0.9 0.8
7 3 station road shahunagar mustak khan 0.6 1.0 0.7 0.8
8 3 station road shahunagar Ramchandar kodan 1.1 0.6 1.2 1.0
9 3 station road punshik solkar 1.5 0.7 0.9 1.0
10 3 station road shahunagar Jagannath solkar 0.4 1.2 0.7 0.8
11 3 station road shahunagar babalu khaji 0.7 1.3 0.9 1.0
12 3 station road shahunagar Irfan khaji 0.8 0.5 0.7 0.7
13 4 station road kempanna 1.2 0.7 0.6 0.8
14 4 station road maruti madar 1.0 0.9 1.2 1.0
15 3 station road shahunagar gangavva sathnayak 1.5 1.0 0.9 1.1
16 3 station road shahunagar magdum Ainapure 1.3 1.2 1.5 1.3
17 3 station road shahunagar Bhimappa baloanage 1.5 0.6 1.4 1.2
18 3 station road shahunagar Dileep janwekar 0.8 0.8 0.9 0.8
19 3 station road shahunagar Harish lokalkar 1.0 0.4 1.2 0.9
20 3 station road shahunagar Mahadev gojalar 1.6 1.2 1.3 1.4
Total 20.6 16.8 19.7 1.0
Waste Generation from Slum Households Samples
Daily Survey Report Survey Location Residential (Household)
Sr.No. Ward No. Street Name Name of the
respondent Weight in kg
Day 1 Day 2 Day 3 Average
1 Station Road Shavu Nagar Saidabhi mulla 1.2 0.9 1.0 1.0
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
192
Waste Generation from Slum Households Samples
Daily Survey Report Survey Location Residential (Household)
Sr.No. Ward No. Street Name Name of the
respondent Weight in kg
2 Station Road Shavu Nagar Sulochana ogle 0.8 1.5 1.2 1.2
3 station road shahu nagar sanju man 1.2 1.2 0.6 1.0
4 Station Road Shavu Nagar Eucharist gounkar 0.8 1.0 0.8 0.9
5 station road shah nagar sahadev kolkar 0.9 0.6 0.7 0.7
4.9 5.2 4.3 1.0
Waste Generation from Commercial Establishments Samples
Daily Survey Report Survey Location Residential (Household)
Sr.No. Ward No. Street Name Name of the
respondent Weight in kg
Day 1 Day 2 Day 3 Average
1 station road shahu nagar devendra karennavar 1 1.2 1.2 1.1
2 station road shahunagar Ameer shek 0.6 2.5 1.2 1.4
3 Station Road Shavu Nagar Raju kamble 0.8 1.9 1.3 1.3
4 station road shahu nagar Abdul mulla 0.7 0.9 1 0.9
5 station road shahunagar kashim shek 0.9 1 1.2 1.0
6 Station Road Shavu Nagar Ashid mulla 0.6 2 2.3 1.6
7 station road sukhesh davane 0.7 2.5 2.4 1.9
8 Station Road Shavu Nagar Rajesh patil 0.9 0.5 0.7 0.7
9 station sameer shek 1 0.8 0.9 0.9
10 Station Road Shavu Nagar Sujatha kale 1.2 2 1.7 1.6
11 station road anand dumadi 1 0.5 0.6 0.7
12 station road shahu nagar bismills aboobkar 1.2 2.2 2 1.8
13 Station Road Shavu Nagar Rashid kamlapur 0.5 1.4 1.4 1.1
14 station road shahunagar Ganesh shetti 0.6 0.9 0.9 0.8
15 station road shahunagar parsharam patil 0.7 2.8 2.3 1.9
12.4 23.1 21.1 1.3
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
193
Annexure 4. Survey Analysis
HOUSEHOLD SURVEY
KHANAPUR TP
Questionnaire Format
1. City 2. Name of Surveyor
3. Name of City
Nippani CMCGokak CMCSankeshw ar TMCChikkodi TMCBailhongal TMCSaundatti TMCRamdurg TMCMudalgi TMCAthani TMCKhanapur TP
4. Ward Number
5. Locality
6. Date
7. Location of City
Latitude (decimal degrees, e.g. -42.454):
Longitude (decimal degrees, e.g. 115.55):
Personal Information
8. Name of Respondent
9. Age 10. Highest Educational Qualification of the Family head
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
194
Primary EducationSecondary EducationHigher SecondaryGraduatePost Graduate
11. No of members in the House 12. Who gives the waste in your house?
MaleFemaleAny
13. Age of Person Giving waste 14. At What time are most people at home
in Afternoon from 10am to 1 pmMorning up to 10 Am
15. Daily Waste Generated in kg 16. Frequency of Door to Door Waste collection
DailyWeeklyOnce in 2 DaysNot Collected
17. Reasons for Door to Door Waste collection not Happening No one is coming for D2D connectionOur area is not accesible for D2D collection vehicleI am not at home w hen they come, time does not matchThey do not come at a f ixed timeDid not know about the systemNot Applicable
18. Do you know what is wet waste and dry waste YesNo
19. Do you segregate waste as wet waste & dry waste YesNo
20. Why don't you segregated Waste No timeDo not w ant to /or have separate binsGet confused on w hat to throw w here
21. If given separate bins will you segregate YesNo
22. Do you think your neighborhood is kept clean by the municipality Yesthey do not collect w aste regularlythey do not sw eep roads properlyPeople throw garbage on road
23. Are there adequate Municipality container bins in the locality YesNo
24. Frequency of Waste Collection from Municipality Container Bin
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
195
Tw ice a DayDailyOnce in 2 DaysWeeklyRandomly
25. Willingness to Pay & Contributions 26. Do you pay for Solid Waste Management System
YesNo
27. How much do you pay / month 28. If not paying are you willing to pay for improved Services
YesNo
29. How much you are willing to pay for improved SWM system / Month Up to 2021 to 3031 to 5051 to 70
30. Exposure to IEC 31. Do You Own A TV
YesNo
32. Do you take daily newspaper YesNo
33. What Kind of Awareness program do you prefer Community meetingPamphletStreet playsAnnouncementsAdvertisements
34. Save Response
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
196
1. The following pie chart depicts the highest educational qualification of the family head and the percentage.
This chart shows that 36% of the population (family heads) have basic primary
education; many have secondary education (36%) and are graduates (6%)
2. This pie chart depicts the percentage of who in the family gives waste to waste collectors
This chart shows that in majority of the households, the waste is given by the
females (62%).
3. This pie chart depicts the percentage of people who are at home at particular time periods.
6%
22%
36%
36%
Highest Educational Qualification of Family Head
Graduate
Higher Secondary
Primary Education
Secondary Education
38%
62%
0% Who Gives Waste in your House
Any
Female
Male
1%
99%
Time when people are at home
in Afternoon from 10am to 1 pm
Morning up to 10 Am
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
197
In this chart, it is seen that 99% of the population are available up to 10 am to give the
waste, whereas 1% are available between 10 am to 1 pm.
4. The following chart shows the frequency of door to door waste collection
In majority of the households, namely 88%, the waste is collected on a daily basis and 1% of
the households exists whose waste is not collected via door to door collection.
5. Frequency of people knowing the difference between wet waste and dry waste is shown in this chart.
It is seen in this chart that 97% of the city’s population know the difference between
dry waste and wet waste.
6. This chart shows the frequency of people who segregate dry and wet waste at household level.
88%
1%7%
4% Frequency of door to door collection
Daily
Not Collected
Once in 2 Days
Weekly
3%
97%
Do you know what is wet waste and dry waste
No
Yes
31%
69%
Segregation of wet waste and dry waste
No
Yes
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
198
Out of the above 94% population, 69% people carry out segregation of wet and dry waste
whereas 31% does not segregate the household waste.
7. This pie chart depicts the reasons for not segregating waste at household level and the frequency thence.
Out of the above 31%, when asked the reason for not segregating their household
waste, 82% of the people said that they do not have time for segregation while the
remaining either do not have separate bins or are not fully aware of the difference
between dry and wet waste.
8. This chart shows the frequency of people who are willing to segregate waste if given separate bins for dry and wet waste.
Of the above population, 99% of the people are willing to segregate wet and dry waste if
provided with separate bins by the municipal council.
9. This chart shows the frequency of people who think that their neighborhood is kept clean by municipality.
10%8%
82%
Reasons for not segregating waste
Do not want to /or have separate binsGet confused on what to throw whereNo time
1%
99%
Count of HH who will segregate if given separate bins
No
Yes
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
199
When asked if their respective neighborhoods were kept clean by the municipality,
74% said that it was and 12% said that waste is not regularly collected.
10. Following pie chart depicts the frequency of waste collection from collection bins in Khanapur.
64% of the population is of the opinion that the waste from container bins is collected in a
weekly basis, 27% said it was collected daily.
11. Whether people pay for SWM system is shown in the following pie chart.
7%
12%
7%
74%
Is your neighborhood kept clean by municipality
People throw garbage on road
they do not collect waste regularly
they do not sweep roads properly
Yes
27%
5%
2%2%
64%
Frequency of Waste Collection from Municipality Container bin
Daily
Once in 2 Days
Randomly
Twice a Day
Weekly
3%
97%
Do you pay for SWM system
No
Yes
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
200
The above chart shows that 97% of the population pays for the current solid waste
management system, whereas 3% do not.
12. This pie chart depicts the amount paid by people for SWM system.
The above chart shows that majority of the people paying for SWM system pay 20
rupees (90%) for the current SWM system.
13. This chart shows the frequency of people who are willing to pay (if not already paying) for improved services.
Out of the people not currently paying for SWM system, 99% are willing to pay,
whereas 1% is not.
14. This chart shows the amount of money that people are willing to pay for improved services.
1%
90%
0%2% 1%
4% 1% 1%
How much do you pay per month
2 20
21 25
28 30
208 203
1%
99%
Are you willing to pay for improved services (if not paying)
No
Yes
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
201
Out of the above 99%, 62% of the people are willing to pay up to 20 rupees, 38% are willing
to pay 21 to 30.
15. This chart depicts the frequency of people who receive daily newspapers.
53% of the total population receives daily newspaper, whereas 47% do not.
38%
0%
62%
Amount willing to pay
21 to 30
31 to 50
Up to 20
47%
53%
Do you take daily newspaper
No
Yes
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
202
16. This chart depicts the preferred mode of awareness regarding SWM system and its importance.
The above chart shows that 17% of the people prefer community
meetings/advertisements/announcements as a medium of awareness whereas the others
prefer an assortment of ways such as pamphlets, street plays, etc.
2% 2%
14%
12%
5%
17%
2%2%1%
4%
0%
1%2%2%
4%
3%
9%
2% 1%
3% 3%2%
1%
4%
1%
Preferred awareness programme
Advertisements
Announcements
Community meeting
Community meeting|Advertisements
Community meeting|Announcements
Community meeting|Announcements|Advertisements
Community meeting|Pamphlet
Community meeting|Pamphlet|Advertisements
Community meeting|Pamphlet|Announcements
Community meeting|Pamphlet|Announcements|Advertisements Community meeting|Pamphlet|Street plays|Advertisements
Community meeting|Pamphlet|Street plays|Announcements
Community meeting|Pamphlet|Street plays|Announcements|Advertisements Community meeting|Street plays
Community meeting|Street plays|Advertisements
Community meeting|Street plays|Announcements
Community meeting|Street plays|Announcements|Advertisements Pamphlet
Pamphlet|Advertisements
Pamphlet|Announcements
Pamphlet|Street plays
Pamphlet|Street plays|Announcements|Advertisements
Street plays|Advertisements
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
203
Annexure 5. Existing and Proposed Route
Map for Collection and Transport Vehicles
GIS Based Route Optimization
In the MSWM DPR the digital base map are prepared. The roads are depicted as road centerlines and respective road flanks as per their widths. The actual physical marking of the routes of the vehicles is done on the base maps. These digital basemap are used as the input and optimum routes have been identified for Solid Waste collection for door to door household level.
The digital base map of TP shows the road network, building footprints, waste dumping site, and location of bulk generators. The road network comprises of road centerlines and the road flanks (marked as per the road widths).
For the purpose of optimum route identification, initially all the road junctions (nodes, to be treated as garbage collection points) are marked. This was followed by manual selection of nodes to be retained as garbage collection point and discarding the others. The selection of nodes was based upon the density of buildings in the zone under consideration.
Optimum route for Solid Waste collection was identified using ESRI’s Network Analyst extension of ArcView GIS. This extension helps the user to use the networks more efficiently. It gives the facility to find the best route to get from one location to another, or the best way to visit several locations. It allows the user to either decide the order in which the locations are to be visited, or the Network Analyst can find the best visiting sequence.
Network Analyst used Direction and Resistance as the minimum parameters for finding the optimum route. As of now, all the roads have been marked as one way roads or Bidirectional roads on basis of actual site scenario and the length of individual road segment as the resistance. Thus, for given source and destination with intermediate nodes to be visited, Network Analyst finds the existing connectivity and selects the geometrically shortest route as the ‘Optimum Path’.
Garbage collection typically follows the sequence: from node to dumping site. The optimum route is identified for Solid Waste collection from nodes. The existing routes and proposed optimized routes for Solid Waste Collection are presented in the annexure volume
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
204
Annexure 6. Designs for proposed Waste
Processing facility
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
205
Annexure 7. Machine Specifications at
Processing Facility
Machine and Equipment Specifications
Municipal Solid waste Processing plant
Coarse Segregation Trommel 35
This is a rotary screen which separates material on the basis of overall size. Trommel-35 rejects all material having overall size above 35 mm and all undersized material is forwarded to next equipment.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC150, ISMC125,
ISMC100, ISMC75 ISA50, etc.
Covers : M.S. sheet 10 , 12 & 14 SWG
Drive: Friction Drive ( Tyre type)
Motor : Hydraulic ( Radial Piston type)
Tyre: Specially made , Heavy duty , Roller type
Screen : M.S.- 7 SWG with punched hole of 35 mm
Ring: Fabricated, Heavy duty.
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 4.5 m
Width – W – 1.8 m
Height – H – 4.5 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 9 RPM
Capacity : 6.5 TPH (Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Fully covered with heavy duty dust covers. (2) Easily replaceable screens. (3) Spiral flights to move material faster and prevent choking.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
206
Municipal Solid waste Processing plant
Coarse Segregation Conveyor - Process 35
This special conveyor is meant to take material coming through the screens of Trommel-35 and feed that material to Trommel - 14. This conveyor is of Chain belt type & is specially designed to meet requirements of MSW management’s plants.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC125, ISMC100,
ISMC75, ISA50, etc.
Covers : M.S. sheet 14 SWG
Gear Box : Worm reduction Gearbox
Motor : Hydraulic ( G-Rotor type)
Chain : Specially made , Heavy duty , Roller type 3” pitch
Belt : 450 mm wide, 3 ply
8mm thick Rubberized
Sprockets: 3” pitch. Hardened
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 6.6 m
Width – W – 0.8 m
Height – H – 3 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 12 MPM
Capacity : 6.5 TPH(Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Typical ‘Z’ shaped Design. (2) All steel used in manufacturing of equipment confirms to IS: 2062.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
207
Municipal Solid waste Processing plant
Coarse Segregation Conveyor -reject 35
Reject – 35 serves the purpose of removing all oversize refuge of Trommel – 35, off the process line. This conveyor is of chain belt type and is especially designed to handle bulky and irregular shaped material.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC125, ISMC100,
ISMC75, ISA50, etc.
Covers : M.S. sheet 12 & 14 SWG
Gear Box : Shaft mounted( SGR)
Motor : Hydraulic ( G-Rotor type)
Chain : Specially made , Heavy duty , Roller type 3” pitch
Belt : 450 mm wide, 3 ply
8mm thick Rubberized
Sprockets: 3” pitch. Hardened
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 6.6 m
Width – W – 0.8 m
Height – H – 3 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 12 MPM
Capacity : 3 TPH(Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
Speed variation is possible.
(1) Shaft mounted gearbox eliminates chances of misalignment. (2) All steel used in manufacturing of equipment confirms to IS: 2062.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
208
Municipal Solid waste Processing plant
Coarse Segregation Trommel 14
This is a rotary screen which separates material on the basis of overall size. Trommel-14 rejects all material having overall size above 14 mm and all undersized material is forwarded to next equipment. The output of Trommel-14 is semi furnished organic manure.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC150, ISMC125,
ISMC100, ISMC75 ISA50, etc.
Covers : M.S. sheet 10 , 12 & 14 SWG
Drive: Friction Drive ( Tyre type)
Motor : Hydraulic ( Radial Piston type)
Tyre: Specially made , Heavy duty , Roller type
Screen : M.S.- 7 SWG with punched hole of 35 mm
Ring: Fabricated, Heavy duty.
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 4.5 m
Width – W – 1.8 m
Height – H – 4.5 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 9 RPM
Capacity : 6.5 TPH (Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Fully covered with heavy duty dust covers. (2) Easily replaceable screens. (3) Spiral flights to move material faster and prevent choking.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
209
Municipal Solid waste Processing plant
Coarse Segregation Transfer Conveyor
Transfer conveyor is meant to take material coming through screens of Trommel – 14 and drop the material in Semi-finish godown. This conveyor is of Chain belt type & is specifically designed to meet requirements of MSW management plants.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC125, ISMC100,
ISMC75, ISA50, etc.
Covers : M.S. sheet12 &14 SWG
Gear Box : Worm reduction Gearbox
Motor : Hydraulic ( Radial Piston type)
Chain : Specially made , Heavy duty , Roller type 3” pitch
Belt : 650 mm wide, 3 ply
8mm thick Rubberized
Sprockets: 3” pitch. Hardened
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 10 m
Width – W – 0.8 m
Height – H – 3 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 12 MPM
Capacity : 6.5 TPH(Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Typical ‘L’ shaped Design with special guide to prevent side shift. (2) Length & discharge height can be altered as per site conditions.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
210
Municipal Solid waste Processing plant
Coarse Segregation Conveyor -reject 14
Reject – 14 serves the purpose of removing all oversize refuge of Trommel – 14, off the process line. This conveyor is of chain belt type and is especially designed to handle bulky and irregular shaped material.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC150, ISMC125,
ISMC100, ISMC75 ISA50, etc.
Covers : M.S. sheet 10 , 12 & 14 SWG
Drive: Friction Drive ( Tyre type)
Motor : Hydraulic ( G rotor type)
Chain: Specially made , Heavy duty , Roller type with 3” pitch
Screen : M.S.- 7 SWG with punched hole of 35 mm
Ring: Fabricated, Heavy duty.
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Hyd. Line : 20mm, High Pressure
Length – L – 4.5 m
Width – W – 1.8 m
Height – H – 4.5 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Hydraulic *
Power Reqd : (PP- II) ^
Speed : 12 MPM
Capacity : 2 TPH (Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Fully covered with heavy duty dust covers. (2) Easily replaceable screens. (3) Spiral flights to move material faster and prevent choking.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
211
Municipal Solid waste Processing plant
Refinement Section Finishing Reject Conveyor
This conveyor serves the purpose of removing all oversize refuge of Rotary screen, off the process line. This conveyor is of chain belt type and is especially designed for handling MSW Handling Plant.
Technical Data
Structure : Various rolled steel sections
Viz. ISMC150, ISMC125,
ISMC100, ISMC75 ISA50, etc.
Covers: M.S. sheet. 12 & 14 SWG
Gear Box: Worn Reduction Gearbox
Motor : Electrical
Chain : Specially made , Heavy duty , Roller type with 3”pitch
Belt : 450 mm, Wide, 2Ply
8mm thick, Rubberized
Sprockets: 3” pitch.
Surface : Blasting & Pickling
Primer : Epoxy Primer
Paint : Epoxy Paint
Length – L – 6 m
Width – W – 0.8 m
Height – H – 2.3 m
[ These are broad specifications & may vary with the technological advancements]
DYNAMICS
Drive mode : Electrical
Power Reqd. : 3HP
Speed : 12 MPM
Capacity : 2 TPH (Intake)
* Taking Bulk density to be 1 Tons/m3
^ Connected to Power Pack II (15 HP)
Salient Features :
(1) Length and Discharge height can be varied, depending on site conditions. (2) All steel used in manufacturing of equipment confirms to IS:2062
Trommel 04
a) Process To rotate the dry waste into Screening Compartment. Screening & Dropping the items below 4 mm on the Discharge Conveyor for processing Rejecting and Dropping the oversized material more than 4 mm on Rejecting Conveyor
b) Capacity 6.5 tons per hour c) Material of Construction M.S. Fabricated body.
Corrosion resistant paint. d) Electric Drive 10 HP Electric Motor, 3 phase,
With suitable Reduction Gear Box. e)
Drive Fiction Drive (Tyre Type) Heavy Duty Chain Sprocket Heavy Duty Support Rollers 4 Nos. and
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
212
Thrust Rollers 2 Nos.
f) Screen Holes M.S. Screen 3 mm thick (10 SWG) with Punched holes Dia 4 mm g) Screen Size Screen Size Dia 1000 mm x 3500 mm h) Screening Compartment Spiral Flights to move material faster and prevent chocking. i) Control Panel On / Off with suitable Dual Contactors
Municipal Solid waste Processing plant
Hydraulic System
Hydraulic system is meant to run all Hydraulic motor driven equipment’s. It consists of Power Pack which convert electrical energy into Hydraulic energy, which in turn is connected to all the equipment’s. Hydraulically driven equipment’s supersede electrical driven performance, speed control and hazard management.
Technical Data
Power Packs Two
(a) P.P. I – 15 H.P. (b) P.P. II – 15 H.P.
Drive: Electrical
Manifold: Specially designed, MS
Pump : Twin Stage, Heavy Duty (3090 / 3070)
Motors : Radial Piston & Orbit
Line : Heavy Duty 20 mm
Cooling : Forced water circulation in
Cooling tank through radiator.
Controls: Local push button type control panel for each 20 H.P unit
Reservoir: M.S. fabricated, 400lt oil capacity
Working : Servo system 68
fluid
Salient Features :
(1) Cooling coil made from Cu to give better cooling. (2) All controls at push button type control panel. (3) All steel used in manufacturing of equipment confirms to IS:2062
Municipal Solid waste Processing plant Control System This is a rotary screen which separates material on the basis of overall size. Trommel-14 rejects all material having overall size above 14 mm and all undersized material is forwarded to next equipment. The output of Trommel-14 is semi furnished organic manure.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
213
Technical Data Body : All MS as per IS : 2062
Sheet 12 & 14 swg, ISMC100, ISMC75 ISA50, etc.
Control element : All Standard as L&T Siemen etc & electrical accessories Primer: Epoxy Primer Color: Epoxy Paint Enclosure: As per IPSS Display : Temp, Voltage , On ,
Off Mimic display
[ These are broad specifications & may vary with the technological advancements]
Salient Features : (1) All Switches / relays of standard & reputed make. (2) Rigid enclosure as per specifications with facility of cabinet light. (3) Emergency shut off switch at various locations.
Front Wheel Loader (Back Hoe Loader) Pallet Trucks
Bag stitching machine Weight Machine (100 kg)
40 ft Conveyor System for output of 4mm compost Technical Specification: For 40 ft. Conveyor system
Sr. No. Particulars Details 1 Motor 2 HP Geared Motor, Foot Mounted, O/p RPM: 51 RPM
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
214
2 Conveyor Belt 600X3plyX3mm Top X1.5 mm Bottom X5mm Nominal X CMR Grade.
3 Idlers 8 No’s 4 Return Rolls 4 No’s 5 Side Guides 4 No’s or as needed. 6 Height of Conveyor Stand 24 Inches.
Bailing Machine Technical Specification: Bailing Machine Double box
Capacity 25 Ton (Double Box) Bale Size 30 (L) x 27 (W)x 14 (H) Inch Bale Weight 50 to 80 kg Platform Size 30 (L) x 27 (W)x 25 (H) Inch No. of Cylinder 1 Nos. Cylinder Size 140*90*1000 (Stroke) mm Oil Tank Capacity 80 Liters. (oil is to be Brought by Buyer) Production Rates 10 min. per Bale Hydraulic System 32 Liters. (B series Gear pump) Day Light Gap 47 Inch Operation Hand lever operate Electric Motor 7.5 HP (3 Phase) Machine Weight (Approx.) Approx 1700 Kgs Overall Dimension 96x36x105 Inch Body Plate 9 + 35 mm
HDPE SMOOTH GEOMEMBRANE LINER OF 1500 MICRONS
PROPERTY TEST METHOD VALUES
Minimum average values Thickness - mm ASTM D 5199 1.5 Density - g/cm3 ASTM D 1505 0.94 Tensile Properties ( Each direction ) ASTM D 6693 Strength at yield - N/mm width Type IV Specimen 25 Strength at break- N/mm width @ 50 mm /min 52 Elongation at yield - % G.L. 33 mm 15 Elongation at break - % G.L. 50 mm 800 Tear Resistance - N ASTM D 1004 222 Puncture Resistance – N ASTM D 4833 400 Carbon Black Content - % ASTM D 1603 2.3 Carbon Black Dispersion ASTM D 3015 A1 / A2
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
215
Vehicle Specifications –
1. TATA Ace Twin Compartment Tipper 2.0 Cum ACE Box Tipper BS4 Tipper with
compartments
2. Jeep Tipper – 40HP Tractor with 3 Ton trailer
3. Backhoe loader– ACE AX130, 2WD, 76 HP Engine, Standard Tyre, Excv Bucket : 0.24
Cum, loader Bucket : 1.00 Cum
4. Jetting & Suction Machine - Chassis Mounted 3000L sucking cum jetting machine.
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
216
Annexure 8. Normative Standards for
Municipal Solid Waste Management Government of Karnataka
Directorate of Municipal Administration
Normative standards for Municipal Solid Waste Management
Name of the SWM Tools, Equipment
and Vehicles Unit requirements per annum Unit Manpower required
Door to door collection One command area = 1000 households / shops Push carts with 6 bins 1 no. for 200 households / Shops 1 per pushcart
Tricycle with 8 bins 1 no. for 250 households / Shops 1 per tricycle
Auto Tipper 1 no. for 1000 households / Shops 1 driver + 1 helper per auto tipper
Street Sweeping Brooms 4 nos for each sweeper 1 sweeper for every 1000 m
of road length Pushcarts 1 no for every 2 workers Metal Tray/ Metal plate
2 nos for every sweeper
Ghamela 1 no for every loaders/sweepers Hand gloves 4 sets for every loader/sweeper Face mask 2 nos for every worker Gum boots 1 set for every worker Uniforms 2 sets for each worker Tractor trailers 1 no. for every 25 Kms of street
sweeping with 7 years of life 1 driver + 3 loaders (2 to 3 trips/day, 2.0-2.5 tons per trip, 200 Kgs to 300 Kgs of waste / Km )
Tipper Trucks 1 no. for every 40 Kms of street sweeping with 7 years of life
1 Driver+ 4 loaders (2 to 3 trips/day, 4.0-4.5 tons per trip, 200 Kgs to 300 Kgs of waste / Km)
Secondary Collection & Transportation 3.0 cum Containers (1.2 Tons Cap.)
1 Container for every 1000 households or approx. for 1.0 ton of waste which ever is higher
4.5 cum Containers (1.8 Tons Cap.)
1 Container for every 1500 households or approx. 1.6 tons of
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
217
waste which ever is higher Twin Container Dumper Placer
1 no. for every 10 to 14 nos of 3.0 / 4.5 Cum Containers – 5 to 7 trips a day
1 Driver + 1 Helper
Cleaning of Markets/Slaughter Houses Tools & Equipment as same as street sweeping
Requirements are as same as street sweeping
1 worker / 400 m2 area, for two time cleaning everyday
Tractor trailers 1 no. for every 6 to 8 tons of waste, 3 to 4 trips a day
1 driver + 3 loaders Unloading distance is less than 10 Kms,
Tipper Truck 1 no. for every 10 to 14 tons of waste, 3 to 4 trips a day
1 driver + 4 loaders Unloading distance is more than 10 Kms,
Cleaning of Office premises, Parks, Public grounds etc Tools & Equipment as same as street sweeping
Requirements as same as street sweeping
2 workers for every 7500 m2
Tractor trailers 1 no. for every 6 to 8 tons of waste, 3 to 4 trips a day
1 driver + 3 loaders Unloading distance is less than 10 Kms,
Tipper Truck (Big) 1 no. for every 8 to 12 tons of waste, 3 to 4 trips a day
1 driver + 4 loaders Unloading distance is more than 10 Kms,
Cleaning of Public Toilets Brooms/Brushes 4 nos for each worker / year 1 worker for every 2 toilet
blocks consisting 10 WCs, with three time cleaning
Gloves 4 sets for every worker / year Boots 1 set for every worker / year Uniforms 2 sets for every worker / year
Commissioner
Directorate of Municipal Administration
Bangalore
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
218
Annexure 9. Office Memorandum for GOI
share
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
219
Annexure 10. Minimum Wages Act GOK 2016
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
220
D E T A I L E D P R O J E C T R E P O R T O F M U N I C I P A L S O L I D W A S T E M A N A G E M E N T
Prepared by: AIILSG Pune
Prepared For: Town Panchayath Khanapur
221
Annexure 11. Quotation