CONSTRUCTION PROGRESS
PHOTO JOURNAL
Department of Recreation, Parks, and Cultural Activities Department of General Services City of Alexandria, Virginia
![Page 2: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/2.jpg)
June 17, 2013
Demo Work Begins:
Floor protection in-place
Security fence installed
Ceiling removal begins
HVAC Contractor:
![Page 3: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/3.jpg)
June 17th through 26th
Demo Work Continues:
Preparing mechanical room Removal of old equipment
Ceiling demo continues Dumpster in place
![Page 4: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/4.jpg)
June 27th through July 12th
Demo Work Continues:
Admin. offices ceiling demo Demolition debris
Demo material at dumpster Mechanical room cleared
![Page 5: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/5.jpg)
July 13th through July 23rd
Demo Work Continues:
Removal of wall in conflict with new construction
Demo nearing completion
Ready to receive new ductwork Locker room ceiling demo
![Page 6: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/6.jpg)
July 13th through July 23rd
New Construction Work:
New ductwork installation begins Pouring new concrete pads for new equipment
New pipe-work installation begins Preparing ducts for installation
![Page 7: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/7.jpg)
July 24th through August 2nd
New Construction Work:
New copper piping and duct work to lower level
Locations of new RTU-1 and RTU-2, ductwork and piping
Duct work and piping at the Mezzanine level
Duct installation at Programming and Admin areas
![Page 8: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/8.jpg)
July 24th through August 2nd
New Construction Work:
Duct and piping at locker rooms Locations of new RTU-1 and RTU-2, ductwork and piping
Mechanical room: New equipment Pad/layout boilers
Piping and duct at Mezzanine level continuing.
![Page 9: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/9.jpg)
August 3rd through August 9nd
New Construction Work:
Programming Suite new piping ductwork installed.
Swimming Pool is maintained throughout construction.
New pipe and ductwork over Locker Rooms.
Typical floor protection throughout building.
![Page 10: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/10.jpg)
August 3rd through August 9nd
New Construction Work:
Mechanical Room new piping installed.
Demolition and removal of existing lockers.
Temporary toilets installed near Tennis Courts.
New ceiling work in mezzanine area corridor.
![Page 11: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/11.jpg)
August 3rd through August 9nd
New Construction Work:
Exposed structural system for complete mechanical change out.
Intricacies of electrical and mechanical work.
Work up-close on piping between major ducts.
Handling and preparation of cylindrical metal ductwork.
![Page 12: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/12.jpg)
August 3rd through August 9nd
New Construction Work:
Ductwork installation continues in Ladies’ Locker-room.
Stock of mechanical appurtenances ready for installation.
New piping in Gentlemen’s Locker-room.
Demolition and removal in Locker-rooms.
![Page 13: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/13.jpg)
August 10rd through August 23nd
New Construction Work:
Relocate hand dryer in Men’s Room.
Removal of existing damaged solar screening.
Relocate hand dryers in Women’s Room.
Hair-dryers in conflict with new Mech. Closet to be relocated.
![Page 14: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/14.jpg)
August 10rd through August 23nd
New Construction Work:
Demo and removal completed in Gentlemen’s Locker Room.
Demo and removal completed in Ladies Locker Room.
Gentlemen’s Locker Room to receive new lockers.
Over-head in the Mechanical Room.
![Page 15: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/15.jpg)
August 10rd through August 23nd
New Construction Work:
New pump pad installed ready for new equipment.
Equipment upgrade in Mechanical Room.
New pumps ready for installation.
Over-head in Mezzanine area.
![Page 16: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/16.jpg)
August 10rd through August 23nd
New Construction Work:
Duct through shaft to roof above Locker Room.
Equipment upgrade in Mechanical Room.
New ductwork above Gentlemen’s Locker Room.
Testing new pipes.
![Page 17: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/17.jpg)
August 10rd through August 23nd
New Construction Work:
Insulated ductwork installed. New pumps installed on new pads in Mechanical Room.
Installing new damper in duct.
New duct installed in shaft.
![Page 18: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/18.jpg)
August 23rd through September 11th
New Construction Work:
New pumps in mechanical room over new concrete pads.
Open area at Mezzanine: new VAVs, duct, and piping.
Pipe cutting.
Portable electrical generator providing temporary power.
![Page 19: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/19.jpg)
August 23rd through September 11th
New Construction Work:
Dominion Power disconnects service for electrical upgrades.
Demolition and removal of existing electrical panels.
Work above ceiling in Programming Room.
VAVs installed in open Mezzanine area.
![Page 20: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/20.jpg)
August 23rd through September 11th
New Construction Work:
New Aaon air-handlers to serve locker rooms (one of two).
New electrical switchgear system.
Removal of existing natatorium units and RTU #3.
Electrical connections in progress.
![Page 21: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/21.jpg)
August 23rd through September 11th
New Construction Work:
Refrigeration lines installation and new ductwork at Locker Rm.
Insulting ductwork to Administration Office.
Fan coil refrigerant lines and pipe insulation work.
Connecting new pumps to new boilers.
![Page 22: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/22.jpg)
August 23rd through September 11th
New Construction Work:
New power service. Insulting new ERUs and RTU #3 curbs.
Skylight-screens ready to be removed.
Removal of natatorium units and RTU#3. .
![Page 23: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/23.jpg)
September 12th through October 4th
New Construction Work:
Ladies locker room mechanical equipment in place.
All new roof curbs completed; roof work prep completed.
Locker room new roof top equipment in place.
Mezzanine area pipe and insulated duct installation.
![Page 24: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/24.jpg)
September 12th through October 4th
New Construction Work:
2 x 2 acoustical ceiling installation in progress at admin. area.
Siemens company’s systems control technician on site.
Ceiling tiles delivered and stored on site.
Ceiling grid system completed in admin area.
![Page 25: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/25.jpg)
September 12th through October 4th
New Construction Work:
Large ducts in place with piping, con-trol wiring and power installation.
Duct to underside of natatorium ERUs.
RTU#3 rooftop curb in place. Locker room rooftop unit in- place with piping.
![Page 26: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/26.jpg)
September 12th through October 4th
New Construction Work:
Piping to ERUs in progress.
Gentlemen’s locker room unit.
Mechanical room work nearing completion. Pipe-fitting in progress.
![Page 27: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/27.jpg)
September 12th through October 4th
New Construction Work:
Moving back into Admin; #2
Moving back into Admin; #1
Pool mechanical room: Remove existing sand filter tanks.
Moving back into Prog. Suite.
![Page 28: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/28.jpg)
September 12th through October 4th
New Construction Work:
Roof top unit connected. Restoring manager’s office.
New 2x2 acoustical ceiling tiles in-place at lower level corridor.
New rooftop unit RTU#3 in-place; connections in progress.
![Page 29: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/29.jpg)
September 12th through October 4th
New Construction Work:
Boiler pipe-work completed.
New boilers in place.
Wall patching prior to new paint finish.
![Page 30: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/30.jpg)
October 4th through October 18th
New Construction Work:
New filter tank in place and connected to system.
New filter tank for swimming pool mechanical room.
Cleaning and preparation of Infants Soft Play Room.
Swimming pool re-caulked, refilled, and ready for use.
![Page 31: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/31.jpg)
October 4th through October 18th
New Construction Work:
Testing of new boilers. Typical testing at Locker Rooms’ new air-handlers.
Repairing pool mechanical room ceiling; adding new exhaust unit.
Humidity resistant ceiling tiles at Locker Rooms.
![Page 32: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/32.jpg)
October 4th through October 18th
New Construction Work:
Completing work in Pool Staff Office.
New pumps in-place and functional.
Completing work in Ladies’ Locker Room (includes refinishing of sauna exterior).
![Page 33: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/33.jpg)
October 4th through October 18th
New Construction Work:
Contractor’s crew putting in final touches.
Preparing for installation of exterior louvers.
New 2x2 ceiling tiles in Mezzanine Area.
![Page 34: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/34.jpg)
Preparing to Reopen, October 19th to November 2nd
Work Completion:
Swimming Pool, ready for swimmers.
Preparing Soft Play room.
Installation of new lockers. New filter-tank for swimming pool.
![Page 35: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/35.jpg)
Preparing to Reopen, October 19th to November 2nd
Work Completion:
New solar film over skylights.
Video surveillance cameras in fitness room.
New storefront at pool staff office and pool-side lockers entrances.
Close up of new video camera.
![Page 36: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/36.jpg)
Preparing to Reopen, October 19th to November 2nd
Work Completion:
New storefront at main entrance. New ceiling system and paint finish at mezzanine.
New finish at sauna exterior. New sign on King Street.
![Page 37: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/37.jpg)
Preparing to Reopen, October 19th to November 2nd
Work Completion:
New heating, ventilation, and air-conditioning system
Soft Play up and ready for use.
![Page 38: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/38.jpg)
November 2nd
Grand Reopening:
Celebrating Chinquapin’s reopening.
Kayakers having fun in the pool.
Patrons and their guests enjoying the water.
Soft play room up and in use.
![Page 39: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/39.jpg)
New heating, ventilation, and air-conditioning system
![Page 40: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/40.jpg)
Project Costs and Scope of Work:
Chinquapin Recreation Center’s HVAC Renovations and Upgrades is actually two projects within one!
I. HVAC Work: This concerns replacement of major mechanical components,
equipment, ductwork, piping, and roof top units with new. The new system will increase patron comfort throughout the center. Additionally, completed work will allow remote control system access for immediate adjustment of settings.
II. Architectural Work: This concerns replacement and improvement of various architectural systems. New work includes installation of new storefront for the pool office, new south entrance, storefront system for compliance with Americans with Disabilities Act (ADA), new vented all-metal lockers at men’s and women’s locker rooms, and other miscellaneous improvements such as new ceilings, new paint finish, and new signage.
Total HVAC Work ………………………….………..…………………………….$1.5 million dollars Total Architectural Work ………………….………………………………$465 thousand dollars Project Budget……………….…………….…………………………………….…$2.0 million dollars.
![Page 41: Department of Recreation, Parks, and Cultural Activities ... · Siemens company’s systems control technician on site. Ceiling tiles delivered and ... Moving back into Admin; #2](https://reader034.vdocuments.mx/reader034/viewer/2022051905/5ff740de802e986a114e46ae/html5/thumbnails/41.jpg)
Welcome Back!
Department of Recreation, Parks, and Cultural Activities
Department of General Services
City of Alexandria, Virginia
On behalf of the Directors and staff of RPCA and DGS,
City of Alexandria: