Denver Public Schools

2012 Bond and Mill Levy Planning

Technology Investment Scenarios

April 25, 2012

Technology Bond “Envelopes”

Using the criteria previously outlined, DPS conducted a prioritization exercise to allocate funds to the different investment scenarios

- 2 -

As the scenarios increase in value, additional funds are prioritized towards Educational Technology and the Infrastructure requirements needed to support the classroom

$30M $40M $45M

Educational Technology $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Operational Improvement $5.0M 17% $6.0M 15% $6.0M 13%

Key Observations

$30M Investment Scenario

- 3 -

What is funded What is not funded

Educational Technology

Minimum necessary funding investment in all critical and high priority to provide additional devices for student use, additional software tools, and improved data analysis

Ability to bring classrooms to base-level standard for technology

Ability to deliver a significant number of technology devices beyond the baseline standard for each classroom

Investment in educational technology innovation Assistive technology funded at less than

necessary to meet current need Investment in additional/new online assessment

tools

Safety & Security

Limited building access control; limited video surveillance upgrades; and minimal investment in emergency notification

Complete building access control Complete video surveillance

Infrastructure Critical infrastructure and Wireless Network

replacements with minor improvement needed to support new systems

Infrastructure and wireless network upgrades necessary for supporting significant device and video growth

Operational Improvement

Minimal investment in high priority projects to enhance HR, document and information sharing systems for staff use

Interactive parent tools Enterprise systems for Learning Management,

Contract Management, HR Knowledge base, and Building Automation systems

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%

$40M Investment Scenario

- 4 -

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%

What is funded What is not funded

Educational Technology

Minimum investment in all critical and high priority projects to provide additional devices for student use, additional software tools, and improved data analysis capabilities

Increased investment in Computers & Devices Increased investment for Assistive Tech for

Special Needs students Moderate investment in educational technology

innovation

Significant investment in educational technology innovation

Assistive technology funded at less than necessary to meet known need and anticipated growth

Investment in additional/new online assessment tools

Safety & Security

Moderate building access control; moderate video surveillance upgrades; and minimal investment in emergency notification

Complete building access control Complete video surveillance

Infrastructure

Critical infrastructure replacements with minor improvement needed to support new systems

Significant wireless capacity improvements to support video streaming and “Bring your own device” models

Infrastructure and wireless network upgrades necessary for supporting significant / outside device growth

Operational Improvement

Interactive parent tools Minimal investment in high priority projects to

enhance HR, document and information sharing systems for staff use

Enterprise systems for Learning Management, Contract Management, HR Knowledge base, and Building Automation systems

$45M Investment Scenario

- 5 -

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%

What is funded What is not funded

Educational Technology

Minimum investment in most critical and high priority projects to provide additional devices for student use, additional software tools, and improved data analysis capabilities

Significant investment in Computer & Devices Additional investment in educational technology

innovation

Significant investment in educational technology innovation

Investment in additional/new online assessment tools

Safety & Security

Moderate building access control; moderate video surveillance upgrades; and minimal investment in emergency notification

Complete building access control Complete video surveillance

Infrastructure

Critical infrastructure replacements with minor improvement needed to support new systems

Significant wireless capacity improvements to support video streaming and “Bring your own device” models

Remaining infrastructure requirements will be funded through individual projects or E-Rate

Operational Improvement

Interactive parent tools Minimal investment in high priority projects to

enhance HR, document and information sharing systems for staff use

Enterprise systems for Learning Management, Contract Management, HR Knowledge base, and Building Automation systems

$30M Investment Scenario

- 6 -

Critical High Medium

Educational Technology

Computers & Devices for student and teacher use

Educational Software Tools

Data Analysis Tools

Collaboration Tools

Investments in Innovation

IT InfrastructureEnterprise Infrastructure refresh

Wireless network upgrade

Cyber security Improvements

Tech Safety & Security

Access Control

Emergency Notification

Video Surveillance

Student Access

Operational Improvement

HR System ImprovementsFacilities System Implementation

Interactive Parent Tool

Adequately funded

Minimally funded

Not funded

No investments

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%

$40M Investment Scenario

- 7 -

Critical High Medium

Educational Technology

Computers & Devices for student and teacher use

Educational Software Tools

Data Analysis Tools

Collaboration ToolsInvestments in Innovation

IT InfrastructureEnterprise Infrastructure refresh

Wireless network upgrade

Cyber security Improvements

Tech Safety & Security

Access Control

Emergency Notification

Video Surveillance

Student Access

Operational Improvement

HR System ImprovementsFacilities System Implementation

Interactive Parent Tool

Adequately funded

Minimally funded

Not funded

No investments

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%

$45M Investment Scenario

- 8 -

Critical High Medium

Educational Technology

Computers & Devices for student and teacher use

Educational Software Tools

Data Analysis Tools

Collaboration ToolsInvestments in Innovation

IT InfrastructureEnterprise Infrastructure refresh

Wireless network upgrade

Cyber security Improvements

Tech Safety & Security

Access Control

Emergency Notification

Video Surveillance

Student Access

Operational Improvement

HR System ImprovementsFacilities System Implementation

Interactive Parent Tool

Adequately funded

Minimally funded

Not funded

No investments

$30M $40M $45M

Educational Tech $10.1M 33% $13.9M 35% $16.6M 37%

Safety & Security $6.5M 21% $8.3M 20% $8.3M 18%

Infrastructure $8.7M 29% $12.2M 30% $14.6M 32%

Ops Improvement $5.0M 17% $6.0M 15% $6.0M 13%