Balfour Bea~y Construction
Page 1 of 20
Staffordshire University Academy
Demolition & Construction Method Statement
The following has been prepared as part of the planning submission as detailed below:
Programme
The planned programme of works is included within Appendix 1.
Within appendix 4 we enclose site phasing diagrams indicating the following:
• Site entrance.
• Site Accommodation/Compound.
• Academy/Construction Vehicular access (No Pedestrian Access to School)
• Material and plant storage areas.
• Sequence of decant by the school.
• Sequence of demolition.
• Sequence of Construction.
Considerate Constructor Scheme
The project will be registered and audited against the above scheme. As part of the CCS protocol we will undertake regular contact with the local residents through regular newsletter advising of site activities. In
addition contact numbers will be displayed at the site entrance to provide residents with means to contact the project management team should the need arise.
In addition Balfour Beatty Construction Northern Limited are an environmentally accredited company to ISO14001 and will operate a full environmental management system for the project.
Dust Suppression Measures
In terms of avoidance of prevention of dust nuisance measures we will work in accordance with the ‘CIRIA Environmental good practice site guide’. Attached is the Balfour Beatty Environmental Standard for
Nuisance Prevention – Appendix 2.
In terms of the monitoring of dust nuisance issues site activities will be monitored as a minimum weekly through the Environmental Coordinators check sheet. Any issues noted during these inspections will be
subject to immediate corrective actions.
Our approach to the project will be to install base coat tarmacadam at the earliest practical opportunity which will be kept clean an free from dust accumulation with vacuum road sweepers.
Noise Suppression Measures
In terms of noise suppression we will work in accordance with Ciria’s Environmental Good Practice site guide. In each instance selection of lower noise methods and plant will be the first mitigation. Beyond this
we will ensure that static plant is located away from sensitive receptors and locally screened to reduce noise nuisance. In selecting our main compound location we have chosen a position with our site boundary
that provides the greatest distance from adjoining properties.
Working Hours
It is intended that the working hours will be 07.30-19.00 hours Monday- Friday. Due to the nature of maintaining a live school it will be necessary to extend these hours, to perform such activities as diversions.
The option of working Saturday 07.30-16.00 and Sunday 07.30-14.00 would also be requested for added opportunity to perform key interface works, within the school
![Page 2: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/2.jpg)
Balfour Bea~y Construction
Page 2 of 20
Material Storage
These will be stored within the secure compound area.
Waste
Waste will be segregated on site into various skips ie metal, timber, plasterboard. Attached is the Balfour Beatty Environmental Standard for Project Start Up Controls – Appendix 3.
Vibro-Piling Operations
Piling is programmed to commence in week 29 and continue for 4 weeks.
Due to the nature of the build, the vibro-piling operation will be screened by the remaining school buildings. No activity will take place outside of the working hours requested to avoid nuisance.
Fire
This will be developed in the Project Management Plan (PMP), with the
Fire Risk Assessment.
![Page 3: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/3.jpg)
Balfour Bea~y Construction
Page 3 of 20
APPENDIX 1-PROGRAMME
![Page 4: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/4.jpg)
Balfour Bea~y Construction
Page 4 of 20
Not Applicable
![Page 5: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/5.jpg)
Balfour Bea~y Construction
Page 5 of 20
![Page 6: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/6.jpg)
Balfour Bea~y Construction
Page 6 of 20
APPENDIX 2- NUISANCE PREVENTION
![Page 7: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/7.jpg)
Balfour Bea~y Construction
Page 7 of 20
APPENDIX 3-PROJECT START UP CONTROLS
![Page 8: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/8.jpg)
Balfour Bea~y Construction
Page 8 of 20
APPENDIX 4-PHASING PLANS
![Page 9: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/9.jpg)
Balfour Bea~y Construction
Page 9 of 20
![Page 10: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/10.jpg)
Balfour Bea~y Construction
Page 10 of 20
![Page 11: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/11.jpg)
Balfour Bea~y Construction
Page 11 of 20
![Page 12: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/12.jpg)
Balfour Bea~y Construction
Page 12 of 20
![Page 13: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/13.jpg)
Balfour Bea~y Construction
Page 13 of 20
![Page 14: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/14.jpg)
Balfour Bea~y Construction
Page 14 of 20
![Page 15: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/15.jpg)
Balfour Bea~y Construction
Page 15 of 20
![Page 16: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/16.jpg)
Balfour Bea~y Construction
Page 16 of 20
![Page 17: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/17.jpg)
Balfour Bea~y Construction
Page 17 of 20
![Page 18: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/18.jpg)
Balfour Bea~y Construction
Page 18 of 20
![Page 19: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/19.jpg)
Balfour Bea~y Construction
Page 19 of 20
![Page 20: Demolition Planning Method Statement for Staffordshire](https://reader030.vdocuments.mx/reader030/viewer/2022012803/61bd236d61276e740b0fbff9/html5/thumbnails/20.jpg)
Balfour Bea~y Construction
Page 20 of 20