demolition feb 04

Upload: ajaipurushothaman

Post on 03-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Demolition Feb 04

    1/107

    Demolition within UrbanDemolition within Urban

    EnvironmentEnvironment

    Lecture Notes prepared byRaymond Wong

  • 8/12/2019 Demolition Feb 04

    2/107

    Demolition work is one of the mostDemolition work is one of the mostdangerous operations in construction.dangerous operations in construction.

    Reasons/causes:Easy to cause injury to human workers due to thedifficulty of accessing into or working inside a

    building which is under demolition.Falling of smaller objects or debris from thedemolishing building.

    Falling of partially demolished structure.Collapse of unstable structure due to originalstructure being disturbed.

    Employing inappropriate methods to demolsih

  • 8/12/2019 Demolition Feb 04

    3/107

    Reasons/causes (continued):Collapse of heavy demolition equipment due toinadequate support of the partially demolishedstructure.Collapse of the partially demolished structure due to

    the accommodation of large amount of uncleareddebris.Congested site environment that easily cause

    damages to human workers, or to the third partiesand their properties that are situated nearby thedemo1ition site.

  • 8/12/2019 Demolition Feb 04

    4/107

    Difficultaccess for

    workersentering intoa building

    underdemolition

  • 8/12/2019 Demolition Feb 04

    5/107

    Further examplesof difficult accessin demolition jobs

  • 8/12/2019 Demolition Feb 04

    6/107

    Partially demolished structure

    is hazardous and may easilycollapse and create accident

  • 8/12/2019 Demolition Feb 04

    7/107

    Heavy machinery used indemolition may have riskof collapse due toinsufficient support.

  • 8/12/2019 Demolition Feb 04

    8/107

    Accommodation of toomuch debris duringdemolition can imposeintolerable loading tothe disturbed structure

  • 8/12/2019 Demolition Feb 04

    9/107

    Typical congesting neighbour-hood condition for demolishingsmall buildings within urbanenvironment

  • 8/12/2019 Demolition Feb 04

    10/107

    HK Building Department has imposed very strictHK Building Department has imposed very strict

    control to any form of demolition works by thecontrol to any form of demolition works by theuse of approval & consent procedure.use of approval & consent procedure.

    1. Authorized person (AP) should be appointed tosubmit application for approval of the demolition,which includes an appraisal report with a methodstatement proposed for the demolition.

    2. Building Department will approve the work subjectto the satisfying of all precautionary measures

    pursuant to the Building (Demolition works)Regulations, hoarding and covered walkways or any

    other conditions as required.

  • 8/12/2019 Demolition Feb 04

    11/107

    3. After approva1 is obtained, another 2 stageconsent procedure are still required before startingthe actual demolition.

    4. Stage 1 is to obtain the consent for carrying out all precautionary/temporary works which include thehoardings, covered walkways, scaffolding, catch

    fans, dust screens and shoring etc.5. In case the provisions in Stage 1 is completed and

    to the satisfaction of the Building Department,Stage 2 of consent for the actual demolition can beapplied.

  • 8/12/2019 Demolition Feb 04

    12/107

    In the appraisal report, the followingIn the appraisal report, the followinginformation should be includedinformation should be included

    1. Structural survey of the building to be demolished2. Photographic record of the site and its adjacent

    buildings, slopes and retaining structures.

    3. The overall height of the structure above groundlevel and the proximity to adjoining buildings.

    4. Information on the type of building, its strudura1support system, the principal materials of itsconstruction, the degree of deterioration and theeffect of demolition etc.

  • 8/12/2019 Demolition Feb 04

    13/107

    Demolition PlanDemolition Plan

    Forming part of the submission information, theDemolition Plan should include:

    a) A set of drawings showing :- the location of the building to be demolished

    - other existing structures and facilities in vicinity b) Proposed methods of demolition.

    c) Proposed shoring and precautionary measures foradjacent buildings

    d) Proposed shoring and protection for the buildingto be demolished

  • 8/12/2019 Demolition Feb 04

    14/107

  • 8/12/2019 Demolition Feb 04

    15/107

    Catch fan

    Typical dust screen and fans provision to protect buildingand minimize disturbance to

    public during demolition

  • 8/12/2019 Demolition Feb 04

    16/107

    Provision of Hoarding as a

    protection to public

  • 8/12/2019 Demolition Feb 04

    17/107

    Provision of Hoarding as a protection to public

  • 8/12/2019 Demolition Feb 04

    18/107

    Provision of Fence

    and screen to preventfalling of debris andgetting out of dust

  • 8/12/2019 Demolition Feb 04

    19/107

    Detail of protectionscaffold, screen and

    catch fan

  • 8/12/2019 Demolition Feb 04

    20/107

    Common ways to get rid of thedemolished debris to controlthe falling of the debris into a

    pre-determined vertical shaft

    formed on the floor slabs

    Shaft for fallingof debris

  • 8/12/2019 Demolition Feb 04

    21/107

    Temporary props erected tosupport heavy equipment

  • 8/12/2019 Demolition Feb 04

    22/107

  • 8/12/2019 Demolition Feb 04

    23/107

    Typical sectioning/sequencing arrangementof work duringdemolition demolishfrom exterior inward

  • 8/12/2019 Demolition Feb 04

    24/107

    Typical sectioning/

    sequencing arrangementof work duringdemolition demolish

    from one side to theother side of building

  • 8/12/2019 Demolition Feb 04

    25/107

    Protection measures to publicProtection measures to publicduring demolition processduring demolition process

    The following concerns related to the protectionand safety of general public or their propertiesshould be provided in the demolition process

    1. Overall structure of the adjacent buildings

    (stability).2. Party walls and external walls of adjacent

    buildings (sealing and waterproofing)3. Foundations of other buildings which may be

    affected.

    4. Public roadway and traffic.

  • 8/12/2019 Demolition Feb 04

    26/107

  • 8/12/2019 Demolition Feb 04

    27/107

    Stiffening frame to strengthenan exposed party wall

    Strengthening of party wall ofadjoining building after demolition

  • 8/12/2019 Demolition Feb 04

    28/107

    Timber raking shore as a temporarysupport to adjacent building

    Shoring support to adjoining building after demolition

  • 8/12/2019 Demolition Feb 04

    29/107

    Method of demolitionMethod of demolition

    General ConcernsThe choice of choosing a demolition method depends

    on a number of factors such as the projectconditions, site constraints, sensitivity of the

    neighbourhood and availability of equipment etc.In general, top-down methods are applicable for most

    sites, particularly for those situated in busy urban

    areas. Other mechanical methods applied from theoutside of a building may be suitable for projectsthat have sufficient clear spaces.

  • 8/12/2019 Demolition Feb 04

    30/107

    Method of demolitionMethod of demolition

    General Concerns (continue)For structural projections such as balconies, canopies

    and verandahs extending beyond the building lines,demolition by hand held tools or the cut and lift

    process may be a safe solution.Each site has its specific features and conditions. The

    method, including detail procedures, shall be

    designed to accommodate the specific projectrequirements. In general, demolition should bedone in the reverse order of construction.

  • 8/12/2019 Demolition Feb 04

    31/107

    Method of demolitionMethod of demolition

    Demolition by human operatives

    This method particularly suitable for use in smallersite with congested space where larger machinecannot be employed.

    In this case, human operatives are used in thedemolition process using simple electrically or

    pneumatically powered tools such as picks,hammers, wire cutters, welding cutters or handdriven hydraulic jacks etc. to carry out the

    demolition of individual elements.

  • 8/12/2019 Demolition Feb 04

    32/107

    Typical demolitionarrangement done byhuman operatives

    Typical demolition

  • 8/12/2019 Demolition Feb 04

    33/107

    Typical demolitionarrangement done by

    human operatives

    Slab with the sidesdisconnected readyfor dismantle

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    34/107

    Method of demolitionMethod of demolition

    Deliberate collapse method

    Demolition by deliberate collapse consists ofsystematic removal, or weakening of the keystructural elements to induce the collapse of thestructure.

    However, when applying this method, several precautions should be observed, such as:Sufficient distance of collapse should be providedCollapse procedure should be carefully designedso that there is no pre-mature collapse or collapseout of the anticipated area.

    Control height of building structure to becollapsed

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    35/107

    Method of demolitionMethod of demolition

    Using of applied pulling/pushing forcesConnecting structural members are disconnected first

    allowing part of the remaining structure to bedragged down by the use of some pulling/pushingequipments such as powered jack, winchingmachine, pulley systems, pushing arms, powered

    blocks or from the pull/push of a hydraulicexcavator.

    However, a firm base in the demolishing building isrequired such as basing on an undisturbed corewall or a strong column section for the applyingof the pulling/pushing force.

  • 8/12/2019 Demolition Feb 04

    36/107

    Demolition of an

    external wall by pull-down methodusing pully

  • 8/12/2019 Demolition Feb 04

    37/107

    Demolition of anexternal wall by pull-down method using

    excavator arm

  • 8/12/2019 Demolition Feb 04

    38/107

    Disconnectedexternal wall readyto be pulled down

    by an applied force

    Demolition done byapplying a pulling force toa portion of structure

    Remain fragments from pulled-down structure to be removed afterward

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    39/107

    Method of demolitionMethod of demolition

    Using of wrecking ball -The use of wrecking ball method requires a craneequipped with a steel ball. The destruction of the

    building is caused by the impact energy of thesteel ball suspended from a crawler crane.The wrecking ball can be operated outside or inside a

    building. In case the process is operated inside a building, sufficient clearance from the buildinginterior should be made first (by having the

    interior portion of the building demolished)This method also demands experienced operators in

    order to handle the wrecking ball and control the

    demolition sequence in a safe manner.

  • 8/12/2019 Demolition Feb 04

    40/107

    Swing action ofwrecking ball

    Vertical drop ofwrecking ball

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    41/107

    Method of demolitionMethod of demolition

    Use of powered plant or demolition machine -The principle of demolition by machine is typicallythe same as the top-down manual method, except thatmost of the demolition begins with the lifting of themechanical plant on to the building top floor.

    Powered plant such as crawler mounted breakinghammer are used in the demolition process andexcavating machines with bucket are used in theremova1 or handling of the demolished materials.However, due to the weight of these machines, theyshould be properly supported such as by the use ofsteel props no matter in still or in operating condition.

  • 8/12/2019 Demolition Feb 04

    42/107

    Demolition by the help ofmechanical plant pneumatic

    breaker and bucketedexcavator

    Lifting the

  • 8/12/2019 Demolition Feb 04

    43/107

    Lifting themechanical

    equipment to topof building

    Building before demolition

    Demolition using top-down method using machines

    Demolition using properly proppedexcavating/breaking machine

  • 8/12/2019 Demolition Feb 04

    44/107

    excavating/breaking machine

    Demolition using top-down method using machines

  • 8/12/2019 Demolition Feb 04

    45/107

    Demolition using top-downmethod using machines

    typical floor cycle andmachine movement

    Moving down of the breakingmachine to the lower floor

  • 8/12/2019 Demolition Feb 04

    46/107

    Demolition using top-down

    method using machines typical floor cycle and

    machine movement

  • 8/12/2019 Demolition Feb 04

    47/107

    Demolition using top-downmethod using machines

    typical floor cycle and

    machine movement

    Demolition of 2-way

  • 8/12/2019 Demolition Feb 04

    48/107

    floor slab using

    mechanical breaker

    Demolition of floor should be started from the middle

    Safe practice Demolition

  • 8/12/2019 Demolition Feb 04

    49/107

    Using manual method

    Safe practice Demolitionof cantilever slab

    Using cut and remove method

  • 8/12/2019 Demolition Feb 04

    50/107

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    51/107

    Method of demolitionMethod of demolition

    Using saw cut method

    This method is suitable for alteration and additionalworks where accuracy is important and restrictionon noise and vibration is required.

    It can be used to cut concrete slab and wall elementsinto segments or for the forming of openings,

    breaking into existing structure like a basement,servicing tunnel, flyover, or other part of aninhabited building in the process of alteration orrenovation works.

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    52/107

    Method of demolitionMethod of demolition

    Using saw cut method (continue)

    Saw cutting can be done using the followingmethods:

    wire saw cutting

    diamond core stitch drilling

    disc saw

    Set-up and mounting of the

  • 8/12/2019 Demolition Feb 04

    53/107

    Set up and mounting of thesaw dis on wall

    Demolition using dis saw cutting

  • 8/12/2019 Demolition Feb 04

    54/107

    An openingformed on floorfor the insertionof a steel prop

    Demolition using diamond core

  • 8/12/2019 Demolition Feb 04

    55/107

    Demolition using wire sawing

  • 8/12/2019 Demolition Feb 04

    56/107

    Disc saw

    Demolition using saw-cut and drill method forthe diversion of a storm water discharge culvert

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    57/107

    Using cut and lifting method

    Cut and lifting involves the initial cuttingof the structure into individual pieces or

    segments, and then lifting the pieces bycrane onto the ground for furtherdemolition or hauling away.

    Special precaution should be made whenapplying this method for demolition suchas:

    weight of the cut segment may causeextra loading to the remaining structure

    lowering of the segment can bedangerous Lowering of segment from a

    footbridge after dismantled by saw-cut

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    58/107

    Method of demolition

    Using of hydraulic clamp or robotic breaker

    S pecially designed breaking/cutting machines,usually track mounted, are used to demolish

    some smaller structural elements such as thinwalls, stairs, slab or parapet etc. when usingthis kind of equipment, planning for accessingthe machines into the working spot is essential.

  • 8/12/2019 Demolition Feb 04

    59/107

    Demolition usinghydraulic clamp or

    robotic breaker

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    60/107

    By implosion (explosive)

    If using this method to demolish a building, contractorshould carry out a comprehensive risk andenvironmental assessment on the effect of implosionon the neighbourhood.

    A detail demolition design is also important, whichshould cover:Method to pre-weaken the structure (e.g. demolish someload taking structures)Placement of explosiveTime-delay design to allow the building to collapseunder control director and location

    Method of demolitionMethod of demolition

  • 8/12/2019 Demolition Feb 04

    61/107

    By implosion (continue)charges of explosive are placed within the fabric ofstructure and detonated to cause partial orcomplete collapse. Competent explosivespecialist is required when demolition is to bedone by using explosive.

    There are numerous types of explosives for use forvarious types of demolition (sometimes includingnon-explosive agent). Consideration such as thespacing and depth of explosive to be located, the

    amount of explosive to be used, or the degree offragmentation required in order to control the boundary of demolition etc., are requiredthroughout the planning and operation process.

    Removal of demolished material or debrisRemoval of demolished material or debris

  • 8/12/2019 Demolition Feb 04

    62/107

    Demolition will generate huge amount of debris. Thesafe and effective removal of such constructionremains will be a prime concern in the operation.

    In this case, before and during demolition, thefollowing provision should thus be provided:

    Overall debris disposal planningTraffic routing for debris handling and vehicularaccess etc.Adequate number of chutes for debris disposalSorting of non-structural materials such as

    timber and metal for recycling.

    Removal of demolished material & debrisRemoval of demolished material & debris

  • 8/12/2019 Demolition Feb 04

    63/107

    Debris created by demolition is usually collected toone or two pre-arranged shafts in the building andthe debris are allowed to fall or drop freely from

    the shafts, by the push of a bulldozer or alike,down to a safe debris collecting areas for furtherdeposal. Since the accommodation of a certain

    amount of debris is expected, the areas around theshaft should be properly fenced or propped so thatthe extra weight of the debris can be taken up.

    Accommodation of debris is often dangerous for theymay impose extra load to the floor or wall (ifleaned against onto). Debris should be cleared

    away the structure at the earliest possible.

    F l d li h d t i l h ti

  • 8/12/2019 Demolition Feb 04

    64/107

    For larger demolished materials, such as a sectionof a beam or column member, they can behoisted down using steel rope, lifting arms orwinch etc.

    If the site area is large enough or where situationallows, a section of building may be demolished

    first. The area vacated can be used for thehandling of the debris. In this case, a mobilecrane may be employed to lower the debrisusing a bucket or skip.

  • 8/12/2019 Demolition Feb 04

    65/107

    Portion of the buildinginterior being cleared out fordebris handling purposes

    Collected metal and other

  • 8/12/2019 Demolition Feb 04

    66/107

    Collected metal and other

    valuable scrape for recycle

    Demolition for special structureDemolition for special structure

  • 8/12/2019 Demolition Feb 04

    67/107

    The following structure should require veryspecial attention during demolition:

    Precast elementsPrestressed elementsCantilever structureHigh headroom or Large-spanned elementsStructural elements under special jointing

    arrangement (e.g. hinged or pin-jointed)Composite or steel structure

    Demolition for special structureDemolition for special structure

  • 8/12/2019 Demolition Feb 04

    68/107

    pp

    The following structure should require veryspecial attention during demolition (continue):Hanging structuresTransfer plate and deep beams

    Special floor structures - waffle floor, flat slabArches, trusses or girders structures

    Cladding or curtain wall

    Demolition for special structureDemolition for special structure

  • 8/12/2019 Demolition Feb 04

    69/107

    The following facilities or buildings should requirevery special attention during demolition:

    Buildings located in contaminated siteBuildings used as oil or dangerous goods storage

    Marine structuresUnderground structures (tunnel, basement orfoundation)Soil retaining structures

    Disconnection of utilities servicesDisconnection of utilities servicesbefore demolitionbefore demolition

  • 8/12/2019 Demolition Feb 04

    70/107

    before demolitionbefore demolitionThe following utilities should be properly sealed or

    disconnected before the commencement ofdemolition:Electricity and gasGas and water supply

    Vent shaft or any underground accessDrainage and sewage systems

    Majority of these utilities services are locatedunderground and can hardly be seen visually. Adetail survey should be done before hand to ensure

    they are found and disconnected.

    Environment concerns in demolitionEnvironment concerns in demolitionDemolition is a dirty and dangerous process In view

  • 8/12/2019 Demolition Feb 04

    71/107

    Demolition is a dirty and dangerous process. In viewof ensure such works are done properly withoutcausing any unnecessary interference to general

    public, the following areas of environmentalconcern should be noted.The proper recycle or disposal of the constructionwasteTreatment of harmful material (e.g. asbestos orcontaminated waste)

    Control of dust generationControl of noiseControl of waste water (including rain water

    carrying large amount of mud running out from site)

    Other precautions to be notedOther precautions to be noted

  • 8/12/2019 Demolition Feb 04

    72/107

    1. When handling the debris, continual spraying ofwater onto the debris can help suppressing thecreating of dust.

    2. Better work coordination should be maintained toensure no worker is working inside the building

    when the debris is being pushed down from thedebris shafts.3. Secure all the partially demolished structures by

    prop, wire or bracing etc. to ensure the areas aresave and will not fall down, at least temporary, andhurt the workers who is working around.

    4. When a building is attached to other buildings

  • 8/12/2019 Demolition Feb 04

    73/107

    4. When a building is attached to other buildingsnearby, the structure to be demolished should first

    be detached from the adjoining structure by handdemolition techniques.

    5. Very special attention should be made to anydemolition work that is carried out along the

    external perimeter of building for the falling ofobjects may cause great casualty to third party

    below.

    6. Maintain a safe emergency access all the timeduring demolition.

    Jetting water to the spotwhere demolition takes

  • 8/12/2019 Demolition Feb 04

    74/107

    place

    Protect by secure a freestanding external wallsection by steel ropes

    Steel rope

  • 8/12/2019 Demolition Feb 04

    75/107

    Fence off the vertical shaftfor the removal of debris

    Maintain a safe access forworker during demolition

  • 8/12/2019 Demolition Feb 04

    76/107

    Avoid letting along section of

  • 8/12/2019 Demolition Feb 04

    77/107

    wall free standingwithout support

    Free standingwall withoutsupport

  • 8/12/2019 Demolition Feb 04

    78/107

    Safe practice Demolition of an externalcolumn by pull-down method using pull rope

  • 8/12/2019 Demolition Feb 04

    79/107

    Some other very complicateddemolition cases

    The redevelopment

  • 8/12/2019 Demolition Feb 04

    80/107

    of the Lee GardensHotel

    Various phases of basementdemolition part of the

    basement being removed forconstruction of the pile capfor the future building

    Continual stages of the basement demolition with theincorporation of other substructure of the future building

  • 8/12/2019 Demolition Feb 04

    81/107

    The redevelopment of the Lee Gardens Hotel

  • 8/12/2019 Demolition Feb 04

    82/107

    The demolition of the basement structure working at the

    same time with the construction of the future building

    The redevelopment of the Lee Gardens Hotel

  • 8/12/2019 Demolition Feb 04

    83/107

    The redevelopment of the Hilton Hotel

  • 8/12/2019 Demolition Feb 04

    84/107

    Demolition of the basement structure of the previous Hilton Hotel the

    lower basement was backfilled to maintain stability of the disrupted basement structure before the commencement of the new basement

    The redevelopment of the Hilton Hotel

  • 8/12/2019 Demolition Feb 04

    85/107

    Demolition of the basement structure ofthe previous Garden Road Carpark

    The Millennium City in Kwun Tong

  • 8/12/2019 Demolition Feb 04

    86/107

    Demolition of the basement working at the same time with the building foundation

    Concerns when demolishing a basementConcerns when demolishing a basement

  • 8/12/2019 Demolition Feb 04

    87/107

    Basement is a soil retaining structure. If demolishednot in a proper manner, the basement and thesurrounding may collapse and cause seriousdamage both inside and outside the basement

    boundary. The following concerns should be takenwhen doing the demolition work:

    Careful planning of work is important (usual todemolish in smaller section and in coordinated

    phases)

    Proper shoring should be provided to the basementduring demolition

    Concerns when demolishing a basementConcerns when demolishing a basement

  • 8/12/2019 Demolition Feb 04

    88/107

    (continue)(continue)Because the upper structure has been remove, the

    basement (and the soil below) may have uplifting problem.

    There may have ground water problem.

    Existence of old foundation structure (usuallyrequired to be removed)

    Accessibility into basement (and removal ofdebris) is difficult.

    An accident caseAn accident case the collapse of thethe collapse of theAsian Trade Centre atAsian Trade Centre at Yau Yau TongTong

  • 8/12/2019 Demolition Feb 04

    89/107

    The Asian TradeCentre before

    the collapse

    Existing structure of the Asian Trade Centre

    1 ld

  • 8/12/2019 Demolition Feb 04

    90/107

    1. Building size:about 45m by 50m on plan and 25m high

    2. Structural form:- flat slab structure with limited amount of beams on

    the building edges and corners- non-load bearing reinforced concrete external wall- arranged in approx. 8m span in 5 x 6 bay grid- strength of concrete 30 N/mm 2 (judge accordingto speaker s experience)

  • 8/12/2019 Demolition Feb 04

    91/107

    The site as seen after the collapse on 30.11.01 (viewing north)

  • 8/12/2019 Demolition Feb 04

    92/107

    The site as seen on 30.11.01 (viewing south)

  • 8/12/2019 Demolition Feb 04

    93/107

    The site as seen on 30.11.01 (viewing west)

  • 8/12/2019 Demolition Feb 04

    94/107

    The site as seen on 30.11.01(viewing at J/O Sze Shan Street and Shung Shun Street)

  • 8/12/2019 Demolition Feb 04

    95/107

    The damage the wreck of two out of the five breaking/excavating machines used for demolition

  • 8/12/2019 Demolition Feb 04

    96/107

    The damage the 6-storey building collapsed inwardforming a heap of debris about 6m high from ground

    Adjoining building Separating joint

  • 8/12/2019 Demolition Feb 04

    97/107

    The damage fortunately, the collapse does not damage

    the adjoining building which separated from the collapsed building by a separating joint only a few millimeter apart

  • 8/12/2019 Demolition Feb 04

    98/107

    The remain a section of the external wall onthe west side of the building

    The remain a portion of building

    structure at the

  • 8/12/2019 Demolition Feb 04

    99/107

    structure at thecorner at J/O SzeShan Street &

    Shung Shun Street

  • 8/12/2019 Demolition Feb 04

    100/107

    Party wall

    being pullinward

    Observation all the fallen columns centered inward indicatesthat the collapse orientated somewhat from the building center

  • 8/12/2019 Demolition Feb 04

    101/107

    Observation with the columns basically remain intact while no trace

    of floor slab can be observed in the remain indicates that the floorstructure in general is a weak source that may cause the collapse

  • 8/12/2019 Demolition Feb 04

    102/107

    Observation the exposed steel bars on the cut-edges indicates thecollapsing structure fell rapidly and produced tremendous pulling force thatfail to keep the floor in position. There is no trace of floor concrete adheredto the bar, again indicates that strength of concrete may be sub-standard

  • 8/12/2019 Demolition Feb 04

    103/107

    Observation further evidence of possible floor failure.

    More than 3 storeys of floor slab crushed to rubble anddetached completely from the columns

  • 8/12/2019 Demolition Feb 04

    104/107

    Steel prop

    Observation the steel props

    used as temporary support forthe positioning of the heavy breaker machines seeminsufficient for the purpose

    Props shouldrest on bearing

    plate rather

  • 8/12/2019 Demolition Feb 04

    105/107

    pthan directlyon floor to

    avoidconcentrationof loading

  • 8/12/2019 Demolition Feb 04

    106/107

    Observation the accommodation of large amount of debrisabove the floor impose great loads to the structure

  • 8/12/2019 Demolition Feb 04

    107/107

    End of Presentation

    Please refer to the Code of Practice forDemolition of Buildings published by the

    Buildings Department, HKSAR Government

    (can be downloaded from the homepage of BD athttp://www.info.gov.hk/bd/english/documents/index.html )