BSBPMG502A Manage Project Scope Project Scope is – the work that must be performed to deliver a product, service or result as per the specifications or requirements concerned with what is included in the project and what is excluded from the project determined at a high level during the project initiation phase and expanded in the planning phase generally determined by the Project Sponsor, expanded by the Project Manager and then reconfirmed with the Project Sponsor defined by the boundaries or range for the project including constraints, assumptions and dependencies related to the objectives, outcomes, requirements Definition of Project Scope Adapated from PMBOK 4 th Edition

Upload: kieran-silva

Post on 01-Jan-2016

82 views

Category:

Documents


6 download

DESCRIPTION

Definition of Project Scope. Project Scope is – the work that must be performed to deliver a product, service or result as per the specifications or requirements concerned with what is included in the project and what is excluded from the project - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope is –the work that must be performed to deliver a product, service

or result as per the specifications or requirementsconcerned with what is included in the project and what is

excluded from the projectdetermined at a high level during the project initiation phase

and expanded in the planning phase generally determined by the Project Sponsor, expanded by

the Project Manager and then reconfirmed with the Project Sponsor

defined by the boundaries or range for the project including constraints, assumptions and dependencies

related to the objectives, outcomes, requirements

Definition of Project Scope

Adapated from PMBOK 4th Edition

Page 2: Definition of Project Scope

BSBPMG502A Manage Project Scope

What is a Project Sponsor?

• The Project Sponsor is critical during the development of project scope and has a key role to play during project execution.

• They are the person for whom the project is being undertaken and they will directly benefit from the deliverables and outcomes of the project.

• The Project Manager needs to ensure that the Project Sponsor has approved the Project Scope so that there are no misunderstandings about the breadth and outcomes of the project.

• The Project Sponsor is often a senior manager, customer or external client.

Page 3: Definition of Project Scope

BSBPMG502A Manage Project Scope

Importance of Project Scope

Why is it important?Gives the Project Manager concrete goalsEnsures the objectives of the Project Sponsor are

metProvides the basis for expectation management,

monitoring and reportingDetermines the baseline against which project

success can be measured

Page 4: Definition of Project Scope

BSBPMG502A Manage Project Scope

Characteristics of Project Scope

• Poor control over project scope is one of the common reasons for project failure

• Projects that never seem to finish are normally suffering from a failure to control scope

• Project scope is defined at a high level during the early stages of the project and then progressively refined

Changesneed to bemonitored

Assumptionsoften

requiredHigh levelbecoming detailed

Constraintswill beapplied

Measuresproject

success

Refined during

the project

Page 5: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope Interrelationships

• Scope is related to Project Time, Project Cost and project Quality

• Sometimes referred to as the ‘triple constraint’

• Scope expansion and contraction has flow on impacts to Time, Cost and Quality

• Trade offs between all four relationships are possible

Cost

Scope Time

Quality

Page 6: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope Interrelationships

• If the project scope is increased when the project timeframe must remain fixed then normally the overall cost will need to increase as more resources are added in order to complete the additional work

Scope Increases

Increased Cost

Additional Resources

Time Fixedwhen leads to and/or

Page 7: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope Interrelationships

Scope Increases Cost Fixedwhen leads to

Reduced Quality

Extra Time

and/or

• If the project scope is increased and the project cost must remain fixed then normally the overall timeframe will need to be extended to allow extra time for the additional work to be undertaken (this assumes that there is no cost involved in extending the resources for a longer period). It may also be possible to compromise on quality in order to speed up execution so that no additional time is required, thereby reducing pressure on the budget.

Page 8: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope Interrelationships

• When scope is decreased then it may be possible to reduce both the project cost and timeframe. Scope reduction is a common reaction to overall budget cuts within an organisation.

Scope Decreases lead to

Reduced Cost

Reduced Time

and/or

Page 9: Definition of Project Scope

BSBPMG502A Manage Project Scope

Project Scope Management Processes

PMBOK Project Scope Management Processes -5.1 Collect Requirements

5.2 Define Scope

5.3 Create Work Breakdown Structure

5.4 Verify Scope

5.5 Control Scope

Related processes from Project Integration Management –

4.1 Develop Project Charter

4.2 Develop Project Management Plan

4.5 Perform Integrated Change Control

PMBOK 4th Edition