Defining a Reason for a Resource Capacity Change
Trigger:
Concept
The resource capacity change reasons list of values are defined as lookups. Lookup codes must be
decided upon and defined during the implementation process.
You can assign a reason for a resource capacity change in the Capacity Changes page by
selecting the reason from the list of values. You can define the reasons for this list of values in the
Resource Capacity Change Reasons page.
In this topic, you will define a reason for a resource capacity change.
Required Field(s) Comments
Output - Result(s) Comments
Additional Information
Last changed on: 1/18/2010 09:35:00 AM Page 1
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
2/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Procedure
Step Action
1. Begin by navigating to the Resource Capacity Change Reasons page.
Click the vertical scrollbar.
Page 2 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
3/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
2. Click the Manufacturing and Distribution Manager link.
Last changed on: 1/18/2010 09:35:00 AM Page 3
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
4/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Resource Capacity Change Reasons link.
Page 4 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
5/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
5. Use the Resource Capacity Change Reasons page to assign reasons for a resource
capacity change.
Last changed on: 1/18/2010 09:35:00 AM Page 5
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
6/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
6. Click in the Code field.
Step Action
7. Enter the desired information into the Code field. Enter "10".
Page 6 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
7/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
8. Click in the Lookup Code Meaning field.
Last changed on: 1/18/2010 09:35:00 AM Page 7
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
8/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
9. Enter the desired information into the Lookup Code Meaning field. Enter
"Mechanical Fault".
Step Action
10. Click in the Lookup Code Description field.
Page 8 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
9/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
11. Enter the desired information into the Lookup Code Description field. Enter
"Mechanical Fault".
Last changed on: 1/18/2010 09:35:00 AM Page 9
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
10/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
12. The Tag field enables you to categorize lookup values.
Click in the Tag field.
Step Action
13. Enter the desired information into the Tag field. Enter "101".
Page 10 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
11/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
14. The Effective From Date defaults as the system date, but you can update this date.
Last changed on: 1/18/2010 09:35:00 AM Page 11
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
12/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
15. Enter a Effective To Date to indicate an expiration of the code.
Click in the To field.
Step Action
16. Enter the desired information into the To field. Enter "31-OCT-2008".
Page 12 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
13/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
17. Use the Enabled check box to enable this code for Bills of Material.
Last changed on: 1/18/2010 09:35:00 AM Page 13
-
8/14/2019 Defining a Reason for a Resource Capacity Change_SPD
14/14
System Process DocumentDefining a Reason for a Resource Capacity Change
Step Action
18. Click the Save button.
Step Action
19. You have completed the Defining a Reason for a Resource Capacity Change
procedure.End of Procedure.
Page 14 Last changed on: 1/18/2010 09:35:00 AM