www.spenergynetworks.co.uk 1 Write here the title of the presentation
SWS Developer
Forum
3rd December 2015
www.spenergynetworks.co.uk 2 Write here the title of the presentation
Introduction
Agenda
Overview
Next Steps
www.spenergynetworks.co.uk 3 Write here the title of the presentation
SWS Consenting Update
Update
Next Steps
www.spenergynetworks.co.uk 4 Write here the title of the presentation
SWS Programme Update
Update
Next Steps
www.spenergynetworks.co.uk 5 Write here the title of the presentation
Project Progress Stage 1: Coylton-New Cumnock
• Circa £50m investment undertaken
• All works now substantially complete at Coylton, New
Cumnock and overhead line between Coylton and New
Cumnock
• Energisation planned for Q1 2016
www.spenergynetworks.co.uk 6 Write here the title of the presentation
Construction of New Cumnock 275/132kV Substation
INSERT VIDEO OF TIME LAPSE
PHOTOGRAPHY
www.spenergynetworks.co.uk 7 Write here the title of the presentation
Coylton-New Cumnock 275kV Overhead Line
14.4km of new line
46 towers, platforms and working areas
Circa 18km of stone roads
Circa 19km fencing
Circa 240,000 tonnes of stone
www.spenergynetworks.co.uk 8 Write here the title of the presentation
SP-RI-142 Kilmarnock South – Coylton 275kV (XY Route) Uprating
• Uprating of Coylton to Kilmarnock Cumnock Circuits • Current rating 600MVA • New rating 1600MVA • New twin Drake ACCR Conductor • Initial conductor replacement undertaken in 2015 • Works at new Chipperlagan GIB compound to
commence early 2016 • Programme completion planned end of 2016
www.spenergynetworks.co.uk 9 Write here the title of the presentation
Stage 2 New Cumnock – Blackhill
Stage 3 Blackhill - Glenglass
Stage 4 New Cumnock - Margree
SWS Project Progress (Stages 2 – 4)
Network Overview Diagram
• Steel tower overhead line construction contract
awarded, pre-construction site investigations and
detailed design works in progress.
• Tree cutting contract awarded, site works
commenced by SP contractor and landowners.
• Manufacture of 275 and 132kV transformers in
progress.
• Manufacture of 132kV GIS and 33kV switchgear
in progress.
• Platform construction contracts awarded for
Dunhill / Blackhill and Glenglass substations.
www.spenergynetworks.co.uk 10 Write here the title of the presentation
SWS Project Progress (Stages 2 – 4)
• Platform construction contracts in final stages of tender process for Margree and Blackcraig
substations.
• Tender evaluation in progress substation building, cable, electrical and civil works packages for
Blackhill and Glenglass Substation.
• Tendering commenced for wood pole overhead line Margree – Blackcraig.
• Initial site clearance works target to commence Dec 15 at Blackhill substations.
• Main overhead line construction works including quarry operations to commence Jan 16.
• Main substation platform works at Blackhill and Glenglass to commence Jan 16.
• Main substation platform works at Margree and Blackcraig to commence Apr 16.
• Detailed electrical design complete for all collector substations.
• Q1 of 2017 for completion of SP-RI-114 infrastructure to Dunhill.
• Q2 of 2017 for completion of SP-RI-116 / 022 infrastructure to Blackhill and Glenglass
substations.
• Q2 of 2017 for completion of SP-R1-111 / 034 infrastructure to Margree substations.
www.spenergynetworks.co.uk 11 Write here the title of the presentation
SWS Project (Stages 2 – 4) Key Risks
• Discharge conditions Stages 2 and 3:
• D&G good progress made - All conditions discharged
• EAC progress has remained slow 3 conditions outstanding – Target Dec 2015
• Discharge Conditions Stage 4
• D&G good progress made - All conditions discharged
• EAC progress has remained slow 3 conditions outstanding – Target Dec 2015
• Conclusion of land agreements with 3 x remaining landowners for overhead line routes
(potential impact to Stages 2, 3 and 4) agreements in principle reached.
• Secure rights to widen access road at Glenglass and Margree S/S.
• Conclude Mineral Leases for 5 x quarry locations.
• Planning permission granted for 4 x quarries in D&G area / 1 x EAC to committee in Dec 2015.
• Major construction activities through 2 x winter periods.
www.spenergynetworks.co.uk 12 Write here the title of the presentation
SWS Project Tree Cutting Overview Map
www.spenergynetworks.co.uk 13 Write here the title of the presentation
SWS Project Blackhill Substation Layout