december 2015 sws developer forum - …...sws project progress (stages 2 – 4) • platform...

13
www.spenergynetworks.co.uk 1 Write here the title of the presentation SWS Developer Forum 3 rd December 2015

Upload: others

Post on 21-May-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 1 Write here the title of the presentation

SWS Developer

Forum

3rd December 2015

Page 2: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 2 Write here the title of the presentation

Introduction

Agenda

Overview

Next Steps

Page 3: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 3 Write here the title of the presentation

SWS Consenting Update

Update

Next Steps

Page 4: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 4 Write here the title of the presentation

SWS Programme Update

Update

Next Steps

Page 5: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 5 Write here the title of the presentation

Project Progress Stage 1: Coylton-New Cumnock

• Circa £50m investment undertaken

• All works now substantially complete at Coylton, New

Cumnock and overhead line between Coylton and New

Cumnock

• Energisation planned for Q1 2016

Page 6: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 6 Write here the title of the presentation

Construction of New Cumnock 275/132kV Substation

INSERT VIDEO OF TIME LAPSE

PHOTOGRAPHY

Page 7: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 7 Write here the title of the presentation

Coylton-New Cumnock 275kV Overhead Line

14.4km of new line

46 towers, platforms and working areas

Circa 18km of stone roads

Circa 19km fencing

Circa 240,000 tonnes of stone

Page 8: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 8 Write here the title of the presentation

SP-RI-142 Kilmarnock South – Coylton 275kV (XY Route) Uprating

• Uprating of Coylton to Kilmarnock Cumnock Circuits • Current rating 600MVA • New rating 1600MVA • New twin Drake ACCR Conductor • Initial conductor replacement undertaken in 2015 • Works at new Chipperlagan GIB compound to

commence early 2016 • Programme completion planned end of 2016

Page 9: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 9 Write here the title of the presentation

Stage 2 New Cumnock – Blackhill

Stage 3 Blackhill - Glenglass

Stage 4 New Cumnock - Margree

SWS Project Progress (Stages 2 – 4)

Network Overview Diagram

• Steel tower overhead line construction contract

awarded, pre-construction site investigations and

detailed design works in progress.

• Tree cutting contract awarded, site works

commenced by SP contractor and landowners.

• Manufacture of 275 and 132kV transformers in

progress.

• Manufacture of 132kV GIS and 33kV switchgear

in progress.

• Platform construction contracts awarded for

Dunhill / Blackhill and Glenglass substations.

Page 10: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 10 Write here the title of the presentation

SWS Project Progress (Stages 2 – 4)

• Platform construction contracts in final stages of tender process for Margree and Blackcraig

substations.

• Tender evaluation in progress substation building, cable, electrical and civil works packages for

Blackhill and Glenglass Substation.

• Tendering commenced for wood pole overhead line Margree – Blackcraig.

• Initial site clearance works target to commence Dec 15 at Blackhill substations.

• Main overhead line construction works including quarry operations to commence Jan 16.

• Main substation platform works at Blackhill and Glenglass to commence Jan 16.

• Main substation platform works at Margree and Blackcraig to commence Apr 16.

• Detailed electrical design complete for all collector substations.

• Q1 of 2017 for completion of SP-RI-114 infrastructure to Dunhill.

• Q2 of 2017 for completion of SP-RI-116 / 022 infrastructure to Blackhill and Glenglass

substations.

• Q2 of 2017 for completion of SP-R1-111 / 034 infrastructure to Margree substations.

Page 11: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 11 Write here the title of the presentation

SWS Project (Stages 2 – 4) Key Risks

• Discharge conditions Stages 2 and 3:

• D&G good progress made - All conditions discharged

• EAC progress has remained slow 3 conditions outstanding – Target Dec 2015

• Discharge Conditions Stage 4

• D&G good progress made - All conditions discharged

• EAC progress has remained slow 3 conditions outstanding – Target Dec 2015

• Conclusion of land agreements with 3 x remaining landowners for overhead line routes

(potential impact to Stages 2, 3 and 4) agreements in principle reached.

• Secure rights to widen access road at Glenglass and Margree S/S.

• Conclude Mineral Leases for 5 x quarry locations.

• Planning permission granted for 4 x quarries in D&G area / 1 x EAC to committee in Dec 2015.

• Major construction activities through 2 x winter periods.

Page 12: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 12 Write here the title of the presentation

SWS Project Tree Cutting Overview Map

Page 13: December 2015 SWS Developer Forum - …...SWS Project Progress (Stages 2 – 4) • Platform construction contracts in final stages of tender process for Margree and Blackcraig substations

www.spenergynetworks.co.uk 13 Write here the title of the presentation

SWS Project Blackhill Substation Layout