Debriefing OCHA/IASC GenevaNovember 2008
Inter-Agency Real Time Evaluation of the Response to
Cyclone Nargis
![Page 2: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/2.jpg)
2
Path of Cyclone Nargis
![Page 3: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/3.jpg)
3
Introduction
• Objectives of the RTE
• Methodology
![Page 4: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/4.jpg)
4
Overall Findings
The Humanitarian Response has generally gone very well…but the international community can only take limited credit for the quality & timeliness of the response
There are two areas that require particular focus in “real time”:– Livelihoods– Disaster Risk Reduction
![Page 5: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/5.jpg)
5
Bogalay Township: “Who-What-Where”
![Page 6: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/6.jpg)
6
Thayaw Chaung Village
![Page 7: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/7.jpg)
7
Sar Phu Su Village
![Page 8: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/8.jpg)
8
Bogalay Township:
RTE Team Itinerary
![Page 9: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/9.jpg)
9
Accountability
Level of beneficiary participation?• Some efforts have been made (e.g. FAO
HH surveys);• Communication remains one-way;• Much more could be done, particularly
for recovery planning.
![Page 10: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/10.jpg)
10
Accountability
Effectiveness of AccountabilityMechanisms?• Good efforts by a number of actors (e.g.
WFP, Care, WVI, ActionAid, NCV);• What was ‘good enough’ during the
response phase should be strengthened;
• Check list initiatives.
![Page 11: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/11.jpg)
11
Accountability
Are funding levels adequate?
• Humanitarian funding has been adequate;
• There are serious concerns about funding for continuing humanitarian needs and recovery.
![Page 12: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/12.jpg)
12
Predictability
Are the clusters effective at mobilization and setting direction?
• Clusters at the central level have performed relatively well;
• Some unmet relief needs (water, psychosocial)
• More effort must be made to better link with the field, local organizations and beneficiaries.
![Page 13: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/13.jpg)
13
Predictability
How effective has strategic planningbeen:• Humanitarian? Not very strong;• Recovery? Lots of activity now but
concerns about the level or beneficiary consultation.
![Page 14: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/14.jpg)
14
Predictability
What has been the role of nationalentities? Extensive and critical;
• Capacity Building? Much more is required;
• Sustainability? Issues of legal status, funding and capacity.
![Page 15: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/15.jpg)
15
Predictability
What was the effect on restrictions to deploying international staff?
• Affected populations did not receive assistance as quickly as they would have.
![Page 16: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/16.jpg)
16
Coordination and Planning
How can we improve the clusters?• Fewer meetings, more outreach
activities;
• Strengthen linkages and consultation with the field and beneficiaries;
• Improve inter-cluster coordination on specific issues (e.g. dry season water)
• Rationalize the clusters.
![Page 17: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/17.jpg)
17
Coordination and Planning
What was the effect of partnerships?
• The role of ASEAN was critical to access;
• The TCG has played an invaluable role in facilitating humanitarian activities.
![Page 18: Debriefing OCHA/IASC Geneva November 2008 Inter-Agency Real Time Evaluation of the Response to Cyclone Nargis](https://reader036.vdocuments.mx/reader036/viewer/2022062404/551b8fe8550346a6148b5f06/html5/thumbnails/18.jpg)
18
Conclusions
A generally effective Humanitarian response, but…
• Some remaining humanitarian needs (DRR, dry season water, psychosocial);
• Need to strengthen linkages with field, beneficiary consultation; and
• Coherent recovery planning and adequate funding.