ddugjy part-i sr. previous month during month cumulative
TRANSCRIPT
Comm Comp Comm Comp Comm Comp
1 20 20 19 20 16 0 1 0 17 0 2 0
2 4 3 3 3 3 0 0 0 3 0 0 0
3 4 4 4 4 4 0 0 0 4 0 0 0
4 211.45 170 164 170 125.3 17.873 5.527 0 130.81 17.87 13 2.32
5 238.57 171.34 91 171.34 67.8 3.1 0 0 67.8 20.9 2 0.3
6 0 2 4 2 4 0 0 0 4 0 0 0
7 0 1.05 1.05 1.05 0 1.05 0 0 0 1.05 0 0
8 2 6 6 6 2 1 0 0 2 4 0 0
9 1 0 0 0 0 0 0 0 0 0 0 0
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
2nd Freezing
Status
7. Issues
0 0 0 0 0
Dec-17
DDUGJY PART-I
Monthly Progress Report for the month of July 2020
Circle- Aurangabad DDUGJY PART-I Zone- Aurangabad Back
Land H/O Date
Milestone Date
% Rate quote:-
33 KV Feeder Bay (Nos)
11 KV Feeder Bay (Nos)
Aug.of PTR (Nos)
Additional PTR (Nos)
New Substation (Nos)
33 KV Line (km)
11 KV Line (km)
33 KV 3Cx300 sqmm XLPE U/G
11 KV 3Cx300 sqmm XLPE U/G
Kannad
Aurangabad Rural-I
Aurangabad Rural-II
LOA Scope Balance
New S/stn Name PAL
Activity WIP
JAYAKWADI MODHA AGRKANADGAON AGATHAN
Commissioned on Dtd.13.04.2018 Commissioned on Dtd. 02.02.2018 Commissioned on Dtd. 15.08.2018 Commissioned on Dtd. 27.08.2018 Commissioned on Dtd. 15.08.2018
24.01.2017 30.01.2017 17.02.2017 25.01.2017 25.1.2017
Oct-17 Oct-17 Oct-17 Nov-17
6798.36 Lakhs LOA Date:- 06.01.2017
Milestone
Division-Tender Amount:- 6294.78 Lakhs Contract Period- 18 Months
Freezed Scope
Date of Agreement:- 07/04/2017
Name of Agency : M/s Bharat Electricals Tender No. 18R
8%
LOA Amount: -
During Month CumulativePrevious MonthSr.No.
c Status
1. Land development & Fencing
3. Equipment Erection
4. Power T/f
5. Lines 33/11 KV
6. Manpower at Site
33 Kv line/Feeder (220 Kv Phulambri) = 4.733 KM Comm11 Kv Feeders:-1. Jining Ag (0.3) :- 0.3 Km Comm2. Pal Ag (3.7):- 3.7 Km Comm3. Pal gao (2.3) :- 2.3 Km Comm
33 Kv line ( (132 KV Paithan) :- 0.05 KM Comm (Tapping from existing 33 Kv Niranjan feeder) 11 Kv Fedders:-1.Panthewadi (0.24):-0.24 Km Comm2.Muddalwadi(0.16):-0.16 Km Comm3. Balangar Ag (0.47):-0.47 Km Comm
2. Control room & Equipment foundation
33 Kv line (Tapping at Khodkai) = 3.85KM Comm11 Kv Feeders:-1. Moha Kh(1.5):- 1.5 Comm2. Modha Bk (1.5):- 1.5 Comm3. Wannjoda (1.2):- 1.2 Comm4.Wanjona Ag Link(1) Comm
33 Kv line (132 Kv Gangapur) = 11.00 KM Comm11 Kv line Feeders:-1. Nevargaon :-2 Km comp2. Kanadgaon :-1 Km Comm3. Mamdapur :- 0.5 Km Comm
33 Kv line ( 33 kv Siddhenath wadgaon LILO) = 5 Km Comm, on tapping from 33 kv Lasur S/stn. due to ROW near Sidhnath (W) village & Due to PWD Dept.11 Kv Feeders:-1. Shirasgaon AG(6.5) :- 7.2 Km Comm2. Katepimpalgaon AG(0.18) :-0.15Comm3.Katepimpalgaon Gav (0.18) :- 0.15 Comm
33KV- 3.76 KM 11 KV - 5.41 KM
33KV- 0 KM 11 KV - 0.71 KM
33KV- 3.76 KM 11 KV - 2.53 KM
33KV- 10.71 KM 11 KV - 1.41 KM
33KV- 12 KM 11 KV - 7.12 KM
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
Milestone Date
Status
2. Control room & Equipment foundation
7. Issues
Source change from 220 KV Sawngi to 132 Kv Harsool. Tapping proposed to Himayat
Bagh feeder is Awaited.& in Jatwada Line 12 pole ROW near Ovar
village,Everest collage & tapping point.
27.01.2017 28.02.2017 27.01.2017
New S/stn Name CHITTE PIMPALGAON JATWADA ZARI FATA
Feb-18 Feb-18
Status
1. Land development & Fencing
3. Equipment Erection
4. Power T/f
5. Lines 33/11 KV
6. Manpower at Site
33KV- 13.12 KM 11 KV - 02 KM
33KV- 6.53 KM 11 KV - 0.47 KM
Commissioned on 31.10.2018Commissioned on Dtd. 25.05.2018
ADGAON JAWALE
Commissioned on 15.07.2020
Forest perimission is recived on dated 12.02.2020
0
March-18
Commissioned on 31.10.2018
WIP
Land devlopment Completed
UCR wall, Barbed wire Completed. Control room slab Completed. & Store room completed upto
lintel level.
Equipement Foundation completed
Equipment erection completed except Power T/F.
PTF Plinth completed
PTF is awaited ( Make- National Electrical ,Final Inspection Done)
March-18
commissioned on tapping from 33 kv Adul S/stn.33 Kv line (220 Kv Shendra) = 13.74 Km Comp.Railway crossing work Completed.11 Kv Feeders:-1. Power grid Expess(0.18):- 0.18 Km Comm2. Pachod (1.12):-1.12 Km Comm3. Chittegaon(0.71):-0.71 Km Comm
33 Kv line (220 Kv Sawangi) =1.5 km Comp 11 Kv Feeders:-
1. Jatwada Ag:-0.49 Km Comp2. Ohar Ag:- 0.36 Km Comp
3.Jatwada Gaothan :-0.12 Km Comp
33 Kv line (132 KV Kagzipua) = From 33 kv Gadana S/stn. 21 KM Comp
11 Kv Feeders:-1. Bazarsawngi AG(4):-3.5 Km Comp
2. Bodkha Ag (0.5):- 0.5 Km Comp3. Bodkha Gaonthan - 0.12 Km Comp
33 Kv line (132 Kv Mahakala) =18 Km Completed11 KV Line :- 1 .Dabhrul Ag- 5 KM Completed 2.ADGAON Ag - 0.18 KM Completed 3.ADGAON gavthan- 2.5 KM Completed
Jan-18
33KV- 10 KM 11 KV - 4.71 KM
33 Kv Line (33 Kv Chikaltan LILO) :- 7 km WIP11 KV Line :-
1. Wadali Gaothan = 4 Km pole erection completed & stringing is balance and 0.5 Km pole erection near substation is balance which require
forest permission. 2. Jaitkheda Gaothan = Work not Started
3. Jaitkheda AG = Work not Started
812 0 5
33KV- 23.59 KM 11 KV - 3.88 KM
33KV- 31.24 KM 11 KV - 2.94 KM
15.02.2017 24.01.2017
WADALI
Land H/O Date
c
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
Land H/O Date
Milestone Date
24.01.2017
New S/stn Name MANGRUL WADODCHATHA TAKALI GONDHEGAON KHAMBALA
24.01.2017 27.01.2017 07.02.2017 25.01.2017
April-18 April-18 May-18 May-18 June-18
33KV- 0.29 KM 11 KV - 0.76 KM
PTF is awaited ( Make- National Electrical , Final Inspection Done)
PTF plinth Excavation Work In Progress
33 Kv line ( Tap to 33 KV Purangaon feeder) = 0.21 km Comm.11 Kv Feeders:-1. Surala(0.18):- 0.18 Km Comm2. Khambala (0.18):- 0.18 KM Comm3. Ghaigaon (0.4):- 0.4 Km Comm
10
WIP
2. Control room & Equipment foundation
Control room Completed uptom lintel level & store room Completed upto Plinth leve
UCR work Wip & Area fencing Completed
Commissioned on Dtd.1.12.2018 Commissioned on Dtd.16.08.2018 Commissioned on Dtd. 07.09.2018 Commissioned on Dtd. 27.07.2018
All material reached at site
Equipement erection completed
Status
7. Issues
cStatus
1. Land development & Fencing
3. Equipment Erection
4. Power T/f
5. Lines 33/11 KV
6. Manpower at Site 0 0 0 0
33 Kv line (33 Kv anvi tapping) = 5.4 KM Comm11 Kv Feeders:-
1. Mangrul (0.25):- 0.25 Km Comm2. Palod (4.5):- 4.5 Km Comm
3. Chandpur (0.24):- 0.24 Comm
33 Kv Line (33 Kv Bharadi LILO)- 9 KM Completed
11 Kv Feeders:-1. Vadala -:-0.18 KM WIP
2. Wadodhchata Gaothan:- 0.12 Km WIP3.Wadoodh AG :-0.18 Km WIP
33 Kv line(220 Kv Deonala) =13 KM Comm.11 KV Feeders:-1. Takli (0.46):- 0.46 Km Comm2. Vaisapur (0.87):- 0.87 Km Comm3. Kesapur (1.1):- 1.1 Km Comm
33 Kv Line is Commissioned by LILO arrangement at new Gondegaon SS. 1.2 Km 11 Kv Line - 1.Gondegaon Ag-0.75 Km- Comm2.Gondegaon Gaothan-1.95 Km - Comm3.Upalkheda Ag- 2.15 Km Comm
33KV- 10.06 KM 11 KV - 0.24 KM
33KV- 5.94 KM 11 KV - 6.41 KM
33KV- 6.47 KM 11 KV - 1.71 KM
33KV- 22.94 KM 11 KV - 6.47 KM
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
2 Siddhenath wadgaon Limbe jalgaon Waluj Devgaon Rangari Nagapur Gadana Shelgaona 06.08.2017 06.11.2017 06.07.2018 06.07.2017 06.08.2017 06.07.2018 06.07.2018
Work StatusCommisioned on Dtd.17.10.2017
Commissioned on 17.04.2018
Foundation Complete.
Foundation Complete.
Foundation Completed
Foundation Completed
Material Status
PTF Erected PTF Erected Work StatusCommissioned on
19.01.2018Commissioned on
01.02.2018Commissioned on 29.11.2018
Commissioning scheduled
on 28.12.2018.
Work StatusCommissioned on Dtd.
20.08.2017Commissioned on
17.04.2018Material Status
5 MVA Power T/F erected.
5 MVA Power T/F erected.
5 MVA Power T/F erected.
5 MVA Power T/F
erected.
Material Status
Commissioned on Dtd. 20.08.2017
Commissioned on 17.04.2018
Work StatusCommissioned on
19.01.2018Commissioned on
01.02.2018Commissioned on 29.11.2018
Commissioning scheduled
on 28.12.2018.
Material Status
Commissioned on Dtd. 20.08.2017
PTF Erected
Commissioned on Dtd. 20.08.2017
Commissioned on Dtd. 20.08.2017
06.07.2017Ranjangaon Pol
5
33KV- 12.1KM 11 KV - 2.2 KM
33 Kv line(132 Kv Vaijapur) = 14.5Km Comp.11 Kv line = 1.4 km Comp
Feeders:-1. Wadaji :-1.2 Km Comp2. Parala - 0.1 km Comp3Bhadali - .1 km Comp
20.11.2017
June-18 Jul-18 Jul-18 Jul-18
0 0 8
Commissioned on Dtd.18.10.2019Commissioned on dtd. 30.08.2019
15.04.2017 26.07.2017 23.02.2018 15.07.2017
Jul-18
Test Charged on Dtd. 30.07.2019
Land H/O Date
Milestone Date
New S/stn Name PATEGAON PALASWADI ISARWADI BAJTHANA BHADLI
cStatus
1. Land development & Fencing
Work Not Started
2. Control room & Equipment foundation
Work Not Started
3. Equipment Erection
Work Not Started
No material reached at site
4. Power T/f
Work Not Started
No material reached at site
Commissioned on 31.10.2018
Status Untouched
6. Manpower at Site
7. IssuesLand demarkation is pending & instructed
Civil Dept. for the same.
8
5. Lines 33/11 KV
33KV- 2.47 KM 11 KV - 14.82 KM
33KV- 2.7 KM 11 KV - 2.1 KM
33KV- 2.92 KM
11 KV - 1.58 KM
33KV- 18 KM 11 KV - 5.5 KM
33 Kv line (Tapping from 33 kv Wadwali) =3.5Km Comm.11 KV line= 1. Chanakwadi Gaonthan- 0.89 Km Comp.
2. Open Gale Feeder- 3.5 Km comp 3. Gharifata Feeder- 0 Km
Work Not Started.33 Kv Line ((33 KV Ellero LILO)
33 Kv line(Paithan) = 5.5Km Comp.
11 Kv line = 2.5 km Comp
Feeders:-
1. Walegaon Gaonthan :-1.2 Km Comp
2. Walegaon AG - 0.1 km Comp
3. Dhorkin AG - 0.3 km Comp
33 Kv line= Completed & Lilo at 33/11 kv mhalgaon S/s 5 Km Comp & 17 poles
stringing balanced.11 Kv line = 4.7 km Comp
Feeders:-1. Bhamthana (1.7):-1.7 Km Comp
2. Chendufal(2):- 2 km comp3.Gadipimpalgao(1.2):-1 km Comp
Sign Board/Bill Board - 23Nos --New s/s -Pal S/S,Jayakwadi S/S, Jatwada S/S, Agathan S/S, Chitte- Pimpalgaon S/s, Mangrool S/s, Khambala S/s , Agarkanadgaon S/s, Zari Phata S/S & Takli S/s, Modha S/s., PATEGAON S/s, ISARWADI s/s, BAJTHANA s/s, BHADLI s/s, GONDHEGAON s/s, ADGAON JAWALE s/s , Additional power Transformer-Devgaon Gangari , Nagapur ,
Issues if any-
Aug.of PTR Additional PTRMilestone Date Milestone Date
b Status
1. Equipment erection
Already Executed in other scheme hence deleted in freezing. Status
1. Civil work details
2. Equipment erection
2. Power T/f
3. Power T/f
3. Manpower at Site4. Manpower at Site
Tender Amount:- 9.68 Crs
% Rate quote:- 8 %
LOA Amount: - 10.4544 Crs.
Previous Month During Month Cumulative WIP
Comm Comp Comm Comp Comm Comp
1 8 0 0 0 0 1 1 5 1
2 24 0 0 0 0 0.02 10.48 8 5.5
3 25 0 0 0 0 13 0 0 12
1 Additional PTR
2 Material Status
3 Work status
1 Additional PTR
2 Material Status
3 Work status
Activity Additional scope Qty Balance
Additional PTR (Nos)
11 KV Line (km)
Replacement of Relay
33/11 KV Chittegaon 33/11 KV Jayakwadi 33/11 KV Amrapurwadi Waghundi 33/11 KV Bidkin
earthing paipe , rsj pole & foundation boult
material recived at storeC.I .earthing paipe , rsj pole & foundation boult material recived atSite C.I .earthing paipe , rsj pole & foundation boult material recived at Site
11 KV Feeder Line shifiting issue excavation of equipement foundation & PTF plinth work wip Excavation of equipement foundation wip & UCR wall work Wip
Commissioned on Dtd.27.07.2020
33/11 KV Patoda 33/11 KV Karodi 33/11 KV Hiwara 33/11 KV Bhambarda
C.I .earthing paipe , rsj pole & foundation boult
material recived at StoreC.I .earthing paipe , rsj pole & foundation boult material recived at Site C.I .earthing paipe , rsj pole & foundation boult material recived at Site C.I .earthing paipe , rsj pole & foundation boult material recived at store
Work not Started & Change of Location Requried excavation of equipement foundation wip EQuipement foundation Excavation Completed & casting wip Work Not Started
Comm Comp Comm Comp Comm Comp
1 New DTC (Nos) 861 811 811 460 4 11 5 471 9 83 248
2 Aug. DTC (Nos) 0 0 0 0 0 0 0 0 0 0 0
3 SDT (Nos) 92 80 80 38 11 0 0 38 11 10 21
4Feeder separation
(Nos)75 74 74 50 10 2 0 52 10 7 5
5 HT line (Km) 1063.11 949.41 949.41 555.85 155 34.61 0 590.46 155 96 107.95
6 LT Line (Km) 449.05 241.95 241.95 137.3 35 7.2 0 144.5 35 20 42.45
7No. of BPL connection
(Nos)20707 3900 3900 2906 0 0 0 2906 0 0 994
Work Status
Material Status
Status
APL
BPL
2. SDT
4. LT line
DDUGJY PART-II
Monthly Progress Report for the month of July 2020
Circle- Aurangabad Rural DDUGJY PART-II Zone- Aurangabad Back
LOA Date:- 06.01.2017
BalanceSr.No. Milestone WIPActivity LOA Scope2nd Freezed
Scope
3. HT line
Aurangabad Rural-I/II & Kannad
Previous Month During Month Cumulative
Name of Agency : M/S Bharat Electrical Contractor & Mfrs. Tender No. DD-112
Division- Tender Amount:-8399.46 Lakhs Contract Period- 18 Months
% Rate quote:- 8 % Above Date of Agreement:- 24.04.17
LOA Amount: - 9071.42 Lakhs
2906 Nos of connection released
Issues if any-
7. No. of Connections released
Sign Board/Bill Board - Not Installed
Status
6. Sagy
Village wise Scope
5. Feeder Separation
1. New/ Aug. DTC
Commissioned Feeders- Hathmali,Golatgaon , Dudhad , Sayyadpur , Gadiwat , Pimpalkhutta , Ladsavangi , Nevpur, Takali, Chincholi, Malisagar, panavi, Jategaon,Shirasgaon,Koradgaon, Dhanora (W), Mahalpimpri, Garaj, Gadhejalgaon, Kachner, Dhakpimpalgaon, Manoor, Bhadli, Wadali, Manegaon,Mahalgaon, Shelkewadi. Pimpaldari, Shivna,Ghatnandra,Jambhai,Shendra, Bhalgaon, Gandheli., Adgaon, Bharadi, Hiwerkheda, Wadodh, Upali Gav, Khadi Cenre, Pokhari Gav, Halda , Digiraj, Khandala,Bhagaon,Palod,Anvi, Jalki Bajar, Ganeshpur, Daulatabad,Bangaon,amathana. Completed Feeders- Rotegaon, Asegaon, Anjandoh, Shindon, Andhari,Gevrai,Mahankalwadgaon, Parsoda, Anchalgaon, Kelgaon
1) Verul Village:- 100 KVA DTC= 10, 25 KVA DTC= 8, HT Line=8.41 Km, LT Line= 2.34 Km, AB Cable: 3.5 Km & BPL Connection = 50 Nos.
2) Aadgaon Village:- 100 KVA DTC= 3 , HT Line= 5 Km, LT Line= 0.48 Km, AB Cable=1.5 Km & BPL Connection = 29 Nos. All work completed
Total:- 100 KVA DTC= 13, 25 KVA DTC= 8, HT Line=13.41 Km, LT Line= 2.82 Km, AB Cable :-5 Km & BPL Connection = 79 Nos.1) Verul Village:- 10 nos 100 KVA DTC Commissioned & 4 Nos 25 KVA DTC Commissioned, HT line 3.07 & LT Line 1.632 commissioned ,28 Nos BPL connections are Released. All work completed2) Aadgaon Village:- 3 Nos 100 KVA DTC commissioned , 0.33 Km 11 kv line completed & 0.18 LT line completed & 29 BPL consumer are Released.-(all work is Completed)
(Feeder Separation allied DTC = 397 Nos Commissioned, 9 Nos Completed & 80 Nos WIP ) RHH DTC = 57 Nos Commissioned & 3 Nos WIP & SAGY DTC = 17 Nos Commissioned (25 KVA- 5 Nos (3Phase) , 100 KVA- 466 Nos Commissioned) (100 KVA- 9 Nos Completed) (100 KVA- 83 NOS WIP)
Material received at store :- DTC = 25 Nos 100 KVA , Poles= 60 Nos (9 M) ,40 nos (11 M) , Insulator= 1200 nos & Conductor= 80 Kms (55 sqmm) ,25 km ( 50 sqmm),15 km ( 25 Sqmm)
38 Nos SDT commissioned, 11 Nos Completed & 10 Nos in WIP
Feeder Separation : (Commissioned line - 565 Km, Completed- 153 Km & WIP - 94.33 Km) RHH:- (Commissioned:-17.93 Km, Completed:-2 KM WIP:-1.7 Km)SAGY : ( Commissioned line -3.07 Km )
Feeder Sepration:- 134 Km- Comm, Completed line -33 Km , WIP-19 WIP RHH : (Commissioned line - 5.7 Km, Completed line -1 Km & WIP - 1 Km) SAGY : ( Commissioned line -1.812 Km, )
Tender Amount:- 6.33 Crs
% Rate quote:- 8 %
LOA Amount: - 6.8364 Crs.
Comm Comp Comm Comp Comm Comp
111 kv feeder
bay (Nos)16 0 0 0 3 8 3 1 4
2 HT line (Km) 8 0 0 0 0 1.5 1 3.1 2.4
3 LT AB Cable 50 0 0 0 0 0 0 5 45
4DB
Replacement
100kva
500 0 0 70 0 350 0 50 100
Sr.N0 ActivityAdditional
scope Qty
Previous Month During Month
Remark 1) 33 KV NAGAMTHAN -2 Nos Bays work Completed 2) Maliwada-1 Nos Bays work WIP 3) Wadwali -2 Nos Bays work completed 4) Vihamandva- 1 Nos Bays work
completed 5) Solegon- 3 Nos Bays work Completed 6) Vijapur-2 nos bay WiP
Cumulative
WIP Balance
Matrial Status Conductor = 15 Km, Dist box-170 , switch gear material of 12 nos feeder bay Recived at store
Comm Comp Comm Comp Comm Comp
1 16 16 16 13 0 1 0 14 0 2 0
2 0 0 0 0 0 0 0 0 0 0 0
3 0 0 0 0 0 0 0 0 0 0 0
4 251 251 251 164.49 11.38 1.05 0 165.54 11.38 5.66 68.42
5 218.42 218.42 218.42 38.57 46.75 11.05 0 49.62 46.75 3.92 118.13
6 0 1.5 1.5 1.17 0 0.31 0 1.48 0 0 0.02
7 0 0 0 0 0 0 0 0 0 0 0
8 15 15 15 0 0 0 0 0 0 0 15
9 2 2 2 0 0 0 0 0 0 0 2
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
DDUGJY PART-I
Monthly Progress Report for the month of July 2020
Circle- Jalna Circle DDUGJY PART-I Zone- Aurangabad BackName of Agency : M/S Shreem Electric Limited Tender No. DD-20
Division-Tender Amount:- 5119.97 lakhs Contract Period- 18 Months% Rate quote:- 9.75% above Date of Agreement:- 05.06.2017
LOA Amount: - 5619.167075 lakhs LOA Date:- 21.03.2017
Aurangabad Rural-IIAurangabad Rural-I
Kannad
During Month CumulativeWIP Balance
Previous Month
33 KV 3Cx300 sqmm XLPE U/G (Km)
Remark-
11 KV 3Cx300 sqmm XLPE U/G (Km)
33 KV Feeder Bay (Nos)
11 KV Feeder Bay (Nos)
New Substation (Nos)
Aug.of PTR (Nos)
Additional PTR (Nos)
33 KV Line (km)
11 KV Line (km)
Sr.No.
Activity LOA Scope Freezed Scope Milestone
Walsadawargaon Rohilaghad Rammurthy Shahapur Bhakarwadi KarhalaNew S/stn Name
Land H/O Date
Milestone Date
1. Land development & Fencing
Staus
3. Equipment Erection
4. Power T/f
5. Lines 33/11 KV
19.04.2017
Oct-17 Nov-17 Dec-17 Dec-17 Feb-18 Feb-18
17.04.2017 18.04.2017 15.04.2017 18.04.2017 15.04.2017
Commissioned on Dtd 11.09.2019
c Status
Land development work in Completed.metal spreading Completed.
S/s Charged on 08.03.2018 Charged on 21.12.2017S/s Charged on 22.05.2018
S/s Charged on 24.08.2018
Barbed wire fencing work completed. Chainlink fencing completed & BBM Completed & Carpet road work in WIP.
2. Control room & Equipment foundation
Control room finishing works Completed & Cable Trench work completed.
S/s Charged on 08.03.2018 Charged on 21.12.2017S/s Charged on 22.05.2018
S/s Charged on 24.08.2018
Control room Finishing works in Completed & cable trench completed.
Commissioned on Dtd 06.09.2019 Commission on Dtd.08.03.2018 Commission on Dtd.21.012.2018 Commission on Dtd.22.05.2018 Commission on Dtd.24.08.2018
33 kv & 11 kv Equipment foundations completed.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments reached at site & Power T/F. Erected .
All Electrical equipments with Power T/F. reached at site
33 & 11 KV VCB, Isolatros, CTs & PTs erection completed.gantry poles erection completed.
33 kv & 11 kv Equipment foundations completed.
S/s Charged on 08.03.2018 Charged on 21.12.2017S/s Charged on 22.05.2018
S/s Charged on 24.08.2018
5 MVA Power Transformer erected
33 KV & 11 KV VCB,CT,PT,Isolators erection completed
Final Inspection Done Final Inspection Done Final Inspection Done Final Inspection Done Final Inspection done
Power Transformer erection work completed.
5 MVA Power T/F Charged on 08.03.2018 5 MVA Power T/F Charged on 21.12.2017 5 MVA Power Transformer Charged on 22.05.2018
5 MVA Power Transformer erection works completed
33 Kv Line=14 Km 11 Kv Line=25 Km
33 Kv Liine (220 Kv Bhokardan)(14 KM) :-11.06 km Completed & 1.11 Km WIP.11 Kv Line(10.5):- 3.1 KM Comp &0.7 Km WIP.Feeders:1. Walsadaawargaon Ag(2):- 1.1 comp 2. Walsadawargaon Gav (2):-1 Km Comp.3.Kumbhari Ag(7):- 1 km Comp & 0.7 WIP
33 KV Line (132 Kv Ambad):- 25.53 Km Comm.11 KV line (6.95) :-6.95 Km CommFeeders:1. Deshgavan (4.78):-4.78 Km Comm.2. Rohilagad Ag(1.17):- 1.17 Km Comm.3. Rohilagad Gav (1):- 1 Km Comm.
33 KV Line (132 Kv Kanhiya Nagr):-10.15 Km Comm.11 KV line(3.04):-3.04 Km CommFeeders:1. MIDC Indus(1.3):-1.3 Km Comm.2. Choudhri Nagar(1.11):1.11 Km Comm3. Rammurthi Gav (0.63):- 0.63 Km Comm.
33 KV Line (132 KV Ambad):- 6 Km comm & 6.30 Km Comp. .11 KV line (11.5):-4.02 Km Comm.Feeders:1. Dhakalgaon AG(3.5):- 0.50Km Comm2. Shahpur AG (3):-0.68 Km Comm3. Shahpur Gav (5):- 2.84 Comm
33 KV Line ( 33 Kv Ghansawngi LILO):-15.64Km Comm 11 Kv line (5.16):- 5.3 Km Comm.Feeders:1. Nankheda (4):-3.94 Km Comm2. Rajewadi (0.8) :-1.04 Km Comm3.Bhakarwadi (0.36):- 0.33 Km Comm
33 KV Line(220 Kv Partur)(40KM):-38.50 Km Comp & 1.80 WIP.11 Kv line(10): 5 Km Comp & 1. WIP.Feeders:1. Karhala Gavthan (6):-4Km Comp & 1 KM WIP2. Lingasa Ag(2):-1.0KM Comp 3. Akali Brhamanwadi(2):-0
33 Kv Line=15 Km11 Kv Line=26 Km
33 Kv Line=30 Km11 Kv Line=12 Km
33 Kv Line=9 Km &11 Kv Line=12.5 Km
33 Kv Line=20 Km11 Kv Line=9.5 Km
33 Kv Line=6 Km11 Kv Line=6 Km
48 (S/S-15 & Line-33)
17(S/S-10 & Line-7
6. Manpower at Site20 (S/S-10 & Line-10)
0 0 0
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
New S/stn Name
Land H/O Date
Kokate Hadgaon Akoladeo Nagewadi Saste Pimpalgaon Walsawangi Gadesawargaon
Status Commissionedon Dtd.06.09.08 Commissioned on Dtd 19.12.2019 Commissionedon Dtd.21.09.18 Commissioned on Dtd.27.11.2018
20.04.2017
Milestone Date Mar-18 Mar-18 May-18 May-18 Jun-18 Jun-18
19.04.2017 17.04.2017 15.04.2017 18.04.2017 17.04.2017
WIP Commissioned on Dtd.12.12.2018
c Status
1. Land development & Fencing
Charged on Dtd .06.09.2018Land development work in WIP & chain link UCR works completed.
Charged on Dtd.21.09.18 Charged on Dtd.27.11.2018
chainlink UCR pointing works Completed & cable trench,septic tank works completed & Control cable termination works in WIP.
charged on Dtd.12.12.2018
2. Control room & Equipment foundation
Charged on Dtd .06.09.2018
Control room external Painting work & tiles work in WIP. Plumbing & Metal spreading work balance. BBM road work wip.
Charged on Dtd.21.09.18 Charged on Dtd.27.11.2018
3. Equipment Erection
4. Power T/f
Metal spreading & control room colouring work & Finishing works in WIP. BBM road balance.
charged on Dtd.12.12.2018
Charged on Dtd .06.09.2018Equipment foundation 33 & 11 KV Completed .
Charged on Dtd.21.09.18 Charged on Dtd.27.11.2018All Electrical equipments with Power T/F. Erected.
charged on Dtd.12.12.2018
All Electrical equipments with Power T/F. Erected.
5 MVA Power Transformer erected Power Transformer erection work completed.
5 MVA Power Transformer erected 5 MVA Power Transformer erected Power Transformer erection work completed.
5 MVA Power Transformer erected.
All Electrical equipments with Power T/F. reached at site
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. reached at site .
Final Inspection Done, T/F Make:-CTR Manufacturing T/F Sr No.:-1729757
5. Lines 33/11 KV
33 Kv Line=15 Km11 Kv Line=12.5 Km
34 Kv Line=20 Km 11 Kv Line=10.92 Km
33 Kv Line=7 Km 11 Kv Line=12 Km
33 Kv Line=10 Km 11 Kv Line=12 Km
33 Kv Line=25 Km11 Kv Line=16 Km
33 Kv Line=2 Km11 Kv Line=10.5 Km
33 KV Line (132 Kv Partur):-10.70 Km Comp11 Kv line (12.5):-0.15 Km Comm, 7.04 Km Comp. & 1.10 Km WIP.Feeders:1. Kokate H Gaothan (3.5):- 7.04 KM Comp & 1.10 Km WIP2. Pandey Pokhri(4.5):-0.2 Km Comp3. Assangaon AG(4.5):-0.15 Km Comm
33 Kv Line (132 Kv D.Raja) (13KM):-16.45 km comp11 Kv Line(11):-5.47 Comp
33 Kv line (220 Kv MIDC Jalna):- 3.32 km Comm11 Kv line(11):-2.5 Km Comp.Feeders:1. Indusrtial (3):-1 Km comp2. Chganzara Ag(4):-1comp3. NagewadiGav(4): 0.5 comp
33 Kv line (132 Kv Mahakala):- 9.94 Km Comm.11 Kv Line(9):-2.26 Km Comp.Feeders:1. Aapegaon Ag(3):-1.17 Km Comp2. Sastepimpalgaon Ag(4):-0.51 Comp3. Sastepimpalgao (2):-0.15 Comp.
33 KV Line (132 KV Dhad S/s) (15KM):-8 .10 Km Completed & 4.66 KM WIP1. Sundri Agi(7):-1.20 Comp2. Walsawangi gav(4):-2.39 km Comp & 0.47 WIP3. Walssawngi Ag(8):-1.55 Comp
33 Kv line (132 Kv Ambad):- 0.82 Km comm11 Kv Line(9):-1.48KM Comp & 1.480 Km WIP.Feeders:1. Gadesawargaon Gav(1):-0.5 Comp & 1.08 wip2. Manepuri Ag(4):-0.9 Comp & 0.30 WIP3. Mundegaon(4):-0.08 Comp & 0.1 wip
Final Inspection Done, T/F Make:-CTR Manufacturing T/F Sr No.:-1729468
Power Transformer,33 KV & 11KV equipment foundation completed.
Final Inspection done Final Inspection done Final Inspection done
1210(S/S-10)
6. Manpower at Site25(S/S-14 & Line-11)
27(S/S-16 & Line-10)
16(S/S-8 & Line-8)
0
1
a
b
Work Status
Material Status
Work Status
Material Status
Scope
Status
Status Commissioned on Dtd 31.01.2020 Commissioned on Dtd 29.08.2019 Commissioned on Dtd 25.03.2019 WIP
New S/stn Name Devgaon Khavne Soinjana Warfal Kendhali
Milestone Date Aug-18 Aug-18 Sep-18 Sep-18
Land H/O Date 19.04.2017 04.04.2018 09.12.2017 19.05.2018
Chainlink fencing,cable trench & barbed wire works completed
Chain link UCR stone massonary 3 side work completed &Yard light poles erection Wip.
2. Control room & Equipment foundation
Control room internal & external Painting works WIP. Plumbing & Metal spreading work balance. BBM road balance.Station Transformer erection work completed & earth mat work & earth pits work in WIP.
Control room- finishing works WIP.& Road work BBM layers Completed.
Control room- internal tiles fitting WIP. Cable trench cover works completed
Control room internal plaster works WIP & outer plaster balance. Plumbing & Metal spreading work balance. BBM road balance.
c Status
1. Land development & Fencing
Land development work in WIP & Arial fencing work in completed.
Chainlink fencing,cable trench & barbed wire works completed.Bore well Completed.
3. Equipment Erection
33 KV & 11 KV equipments foundations works in Completed & erection done.
33 KV & 11 KV equipments foundations works in Completed.
4. Power T/f
Power Transformer erection work completed.
Power Transformer erection done.
5. Lines 33/11 KV
33 Kv Line=23 Km11 Kv Line=17.5 Km
33 Kv Line=0.6Km 11 Kv Line=18.1 Km As per survey
6. Manpower at Site 10
Power Transformer erected. 33 kv & 11 Kv VCB,isolator erection works completed.
33kv & 11 kv VCB,Isolator erection done, 11 kv CT ,PT erection WORK Completed.
32 kv &11 kv VCB erection completed,33 KV Gantry erection done and 11 KV Gantry erection in Completed.
33 kv &11 kv VCB erection completed,33 KV Gantry erection done and 11 KV Gantry erection in WIP.
Power Transformer,33 KV & 11KV equipment foundation completed.
33kv & 11 kv equipment foundations work completed.
33 KV & 11 KV equipments foundations works in Completed & erection done. 11 KV Gantry structure erection WIP.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
All Electrical equipments with Power T/F. Erected.
Issues if any-
0 0 6
33 Kv Line=15Km11 Kv Line=10.5 Km
33 Kv Line=17 Km11 Kv Line=16 Km
33 KV Line (132 Kv Mantha)(2.8km) :- 2.97Km Comp. 11 Kv line(10.3)- 7.60 Km Comp & 1.40km WIP.Feeders:1. Doksal (7.5):-5.50Km Comp & 1 km WIP2 Naigaon(4):-1.5 Km Comp 3. Khowrud Sawngi(4):-0.6 Comp & 0.1 wip
33 Kv Line(220 Kv Partur):-0.30 Km Comp11 Kv line(18.1):- 17.68 Km Comp & 1 WIP.Feeders:1. Soinjana AG (0.6):-0.40comp.2. Shingona AG (2.5):-1.98 comp 3. Gavthan (20):-15.30 Km Comp & 1 Wip
33 KV Line (132 33Kv Partur)(4.9 km);- 4.9 Km Comp.11 Kv line (1.2):- 1.2 Km CompFeeders:1. Koregaon AG(0.8):-0.9 Km Comp2. Chincoli gav(0.5):-0.1 Km Comp3. Mapegaon Ag(0.5): 0.2comp
33 Kv Line (132 KV Mantha) (13KM):1.80 Completed & 0.90 WIP11 Kv Line(6.8):0.82 WiP
Sign Board/Bill Board - 13 Nos. (Rohilaghad, Rammurthy , Shahapur, Bhakarwadi,Nagewadi, Kokte Hadgaon, Karhala, Soinjana, Warfal, Devgaon Khavne, Kendhali, Saste Pimpalgaon & Gadesawargaon Substaions)
Comm Comp Comm Comp Comm Comp
1 New DTC (Nos) 421 390 390 339 22 0 0 339 22 29 0
2 Aug. DTC (Nos) 0 0 0 0 0 0 0 0 0 0 0
3 SDT (Nos) 60 60 60 6 24 0 1 6 25 12 17
4 Feeder separation (Nos) 60 60 60 45 5 0 0 45 5 9 1
5 HT line (Km) 811.4 718.7 718.70 569 104 0 0 569 104 29.2 16.5
6 LT Line (Km) 382 179.56 179.56 115 10.28 0.5 0 115.5 10.28 31.5 22.28
7 11 Kv UG cable 8 8 8 3 0 0 0 3 0 1
8Conversion of Errection of Aerial
Bunched Cable (70 Sq.mm) 132 174 174 35 9 0 12 35 21 32 86
9 No. of BPL connection (Nos) 12877 3500 3500 2900 0 0 0 2900 0 0 600
Work Status
Material Status
Scope
Status
APL
BPL
DDUGJY PART-II
Monthly Progress Report for the month of July 2020
Circle- Jalna Circle DDUGJY PART-II Zone- Aurangabad Back
Jalna Division -I & II
Contract Period- 18 Months
Status
During Month CumulativeWIP
Tender Amount:- 6738.35 Lakhs
% Rate quote:- 8 % Above Date of Agreement:-9/8/2017
Tender No. 113RName of Agency : M/S Bharat Electrical Contractor & Mfrs.
Lakhs
1. New/ Aug. DTC
RHH DTC = 75 Nos DTC Commissioned , SAGY DTC = 5 Nos Commissioned. Feeder Sepration:- 259 Nos DTC Commissioned , 22 Nos Completed, WIP- 29 Nos(63
KVA-4 Nos,25 KVA- 33 Nos,25 Kva(Single Phase)-4 nos,100 KVA-298 Nos Commissioned) ( 25 kva -2 nos & 100 KVA- 20 Nos Comp )
Material received at store :- DTC = 22 Nos 100 KVA , Poles= 150 Nos (9 M) ,30 nos (11 M) , Insulator= 500 nos & Conductor= 135 Kms (55 sqmm) , 60 km ( 50
sqmm), 18 km ( 25 Sqmm) ,Aerial Bunched Cable (70 Sq.mm) -20 km
Previous Month
LOA Date:- 17-06-17
BalanceSr.No. Activity LOA ScopeFreezed
ScopeMilestone
Division-
LOA Amount: - 7277.43
2. SDT 6 No SDT Commissioned 25 Nos SDT Completed & 12 NOS WIP
3. HT lineFeeder Separation : (Commission:-546.878 Km Completed :-104 Km & WIP -18.85 Km) ; RHH :Commission:-20 Km, & WIP -1.15Km;SAGY :Commissioned:- 2.122
Km
4. LT lineRHH : Commissioned line -15 Km & Completed line -0.14 Km , WIP:- 0.25Km; SAGY : Commissioned line -1.233 ;Feeder Sepration:- 98.767 Km- Comm, Completed
line - 10.14 Km , WIP-28.25 KM
5. Feeder Separation
Commission Feeder :- 1) Konad -07.08.2018 2) Tadhadgaon-04.08.18 3) Usmanpur-12.08.2018 4) Liha Shelud-01.09.18 5) Rajala- 02.09.2018 6)Pimpalgaon R -
05.09.18 7) Ghansawngi-14.09.18 8) Jamkhed-26.10.2018 9) Rui-26.10.2018 10) Janephal- 12.10.2018 11) Rajegaon-23.10.2018 12)Paradh 13)Relgaon
14)Nimgaon 15)Gowli Pokhari 16)Pangarkheda 17) Dhakephal 18) Satoan Kh. 19) Kandari 20) Changatpuri 21) manegaon 22) Aland 23) Bharaj 24) sawangi
Awgh 25) Warud 26) Paregaon 27) Ujjainpuri 28) Dabhadi 29) Chikali 30) Wadhona Feeder, 31) Walha 32) sawangi 33)Khadakwadi 34) Latifpur 35) Nandi 36)
Pirkalyan 37) Khadaki 38)Dahegavhan 39) Dahifal Bhogane 40) Kolegaon 41) Rohilagadh 42) Bhodhalapuri 43) Asai 44) Tembhurni 45) Pangari Completed
Feeders- 1) Hanodi/ Shelgaon 2) Adha 3) Wankheda 4)Sipora Bajar 5) Loni
Total Manpower- 200
Notice to Correct Issued dtd. 03.01.2018 & 02.05.2018
Sign Board/Bill Board - Not Installed
Issues if any-
6. Sagy
Rajur Village:- 100 KVA DTC= 5, HT Line=2.75 Km, LT Line= 4.64 Km, Conversion of Errection of Aerial Bunched Cable= 2.79 Km ,AB cable (70 Sq mm)-1 km, LT
Rec-2 KM & BPL Connection = 17 Nos.
5 Nos DTC Commissioned , HT Line 2.122 Km, LT Line Commissioned 1.23 Km & Conversion of Errection of Aerial Bunched Cable- 2.79 KM comm & BPL
Connection = 17 Nos.( all work completed.)
7. No. of Connections released12877
2900 Nos connection released
Tender Amount:- 7.52 Crs
% Rate quote:- 8 %
LOA Amount: - 8.1216 Crs.
Comm Comp Comm Comp Comm Comp
1 New DTC (Nos) 150 50 0 6 22 107 5 18 20
2 Feeder Sepration (Nos) 5 0 0 0 0 0 0 0 5
3 Feeder Bay (Nos) 5 0 0 0 0 0 0 0 5
4 HT line (Km) 20 0 0 0 0 0 0 0 20
5 LT Line (Km) 3 phase 4 wire 20 0 0 5 3.28 0 0 0 20
6 LT AB Cable 10 0 0 0 0 0 0 0 10
7 DB Replacement 100kva 100 0 0 0 0 50 0 0 50
Work Status 100 KVA DTC- 107 Commissioned & 100 KVA DTC 5 Nos Completed
Matrial Status Dist. T/f = 42, Dist box 100 , RSJ pole -135 nos, AB Cable =10 Km & Conductor = 216 Km Received at store
During Month CumulativeWIP BalanceSr.No. Activity
Additional
scope Qty
Previous Month