Live DCUSA Change Proposals 15 February | Energy Networks Association – DCMF DCP 081 – Authority decision making process –Presenting to Panel 16 February –Issue for voting 17 February x 5WD –Proposed implementation 01 April 2011 DCP 078 – Reciprocal DUoS payment arrangements –Issued for consultation 14 February x 10 WD –Proposed implementation 01 April 2011 DCP 077 – Rate of Return % –Approved implementation 01 April 2011 DCP 066A – Enhanced provision of cost information –Implemented 26 January 2011 –Post implementation review meeting 01 March 2011TRANSCRIPT
DCUSA Change Proposals
Elizabeth LawlorDCUSA Panel Secretary
15 February 20111 | Energy Networks Association - DCMF
Live DCUSA Change Proposals
15 February 20112 | Energy Networks Association – DCMF
• DCP 082 – Consideration of wider industry developments…(Smart)
• DCP 081 – Authority decision making process• DCP 080 - Theft in Conveyance
• DCP 079 – Statutory application of NTC
• DCP 078 – Reciprocal DUoS payment arrangements• DCP 077 – Rate of Return %• DCP 075 – Voting arrangements for a party category with few members
• DCP 066A – Enhanced provision of cost information• DCP 062 – Grid Code Compliance
• DCP 054 – Revenue Protection / Unrecorded units in to Settlement
Live DCUSA Change Proposals
15 February 20113 | Energy Networks Association – DCMF
• DCP 081 – Authority decision making process– Presenting to Panel 16 February
– Issue for voting 17 February x 5WD
– Proposed implementation 01 April 2011
• DCP 078 – Reciprocal DUoS payment arrangements– Issued for consultation 14 February x 10 WD
– Proposed implementation 01 April 2011
• DCP 077 – Rate of Return %– Approved implementation 01 April 2011
• DCP 066A – Enhanced provision of cost information– Implemented 26 January 2011