Thursday, August 20, 2015
Briefing
for:
Briefing
on:
DC CLEAN RIVERS PROJECT
First
Street
Tunnel
Construction
Update
and
Community
Mitigation
Measures
First
Street
Tunnel
Forum/Community
Group
District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
2/40
Tunnel ForumRepresentatives and Alternates
Location/Group Representative Alternate
First Street NW Dr. Marilyn Lashley Tomas Encaracion
Bryant / Channing Streets Renee Peres Philomena FritzFlagler Place Victoria Leonard Pia Brown
Adams Street Shelly Parker Dianne Barnes
W Street Joe Levesque Neal Herman
First and V Streets Angela Ray Theodore Bush and Derrick Jones
U Street Serita Sanders Jean Marie Thomas
Thomas St / Rhode Island Ave Chris Von Ferro Vacant
Local Blogs Scott Roberts Betsy McDaniel
Government Austin Pearl, ANC 5E Teri Janine Quinn, ANC 5E
Bertha Holliday, ANC 5E
Laisha Dougherty, Councilmember
McDuffie’s office, Ward 5
Civic Associations Sherry Howard John MacNeil
All meetings are open to the public. 2
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
3/40
Welcome and Introductions
Meeting Dates for 2015 and 2016
Two-Month Construction Update at
Construction Staging Areas (CSAs) Channing Street CSA
Adams and Flagler CSA First and V CSA
First and Thomas CSA (Pumping Station)
Long-Range Construction Schedule
and Progress
3
Update on CommunityMitigation Measures
Responses to Residents’
Concerns
Saturday Work
Security and Safety withinConstruction Staging Areas
First and V Streets CSA
published
Tree Planting Initiative Project Display Boards at Two
CSAs
FEMS Doorway Mural Project
Next Steps/Save the Date
Agenda
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
4/40
MEETING
DATES
FOR
2015
AND
2016
Tom Lindberg and John Kennedy, DC Water
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
5/40
Meeting Dates for 2015 and 2016
Discussion Topic Meeting Date* Location
First Street Tunnel (FST) Project Update January 22, 2015 St. George’s Episcopal Church
Naming of the Tunnel Boring Machine (TBM) February 26, 2015 First Street Tunnel Project Office
FST update, TBM Naming Process and Ceremony March 26, 2015 St. George’s Episcopal Church
TBM Naming Ceremony April 14, 2015 Channing Street CSA
FST update, TBM naming ceremony, small diameter
water main project, Doors of Perception murals at
Adams St CSA
May 28, 2015 St. George’s Episcopal Church
Construction Update for Adams Street and Flagler
Place Residents
June 10, 2015 Adams Street Construction
Staging Area
Proposal to Extend Construction Work Hours June 27, 2015 St. George’s Episcopal Church
FST Project Update August 20, 2015 St. George’s Episcopal Church
FST Update and Landscaping and Restoration Plans October 22, 2015 St. George’s Episcopal Church
FST Hard Hat Site Tour October 24, 2015 Assembly location TBD
FST Update and Landscaping and Restoration Plans January 22, 2016 St. George’s Episcopal Church
FST Update and Landscaping and Restoration Plans March 24, 2016 St. George’s Episcopal Church
5
* Meeting dates are subject to change.
There will be no Tunnel Forum meetings in November and December 2015.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
6/40
TWO‐
MONTH
CONSTRUCTION
UPDATE
AT CONSTRUCTION STAGING AREAS
Scott Hoffman and Thomas March, SKJD
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
7/40
Channing StreetConstruction Staging Area
MiningShaft
ExcavationStockpile
Electrical/Mechanical
Site Office
7
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
8/40
Channing StreetConstruction Staging Area
Launch Tunnel Boring Machine, July 2015
Hard Hat Tour, October 24, 2015 Mining in progress, ongoing – November 2015
8
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
9/40
Lucy’s Progress (shown in purple)
9
First Street Tunnel
Channing Street NW
F i r s t S t r e e t NW
Channing
Street CSA
McMillan
Reservoir
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
10/40
Adams and Flagler IntersectionConstruction Staging Area
Building entrance
Construction traffic entrance and exit
CSA
CWZ
Road Closed ‒ No thru
traffic. Local access onlyat intersection of FirstStreet and Adams Street).
Abbreviations
CSA ‒ Construction Staging AreaCWZ ‒ Construction Work Zone
FEMS ‒ Fire and EMS Department
CSA
CWZ
FEMS Access Zone
4’-wide Pedestrian Sidewalk
Local Traffic
10
14 feet
55 feet
Fire department
ladder truck clearances
Legend
F l a g l e r P l
Adams St
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
11/40
Adams and Flagler IntersectionConstruction Staging Area
Shaft excavation completed
Construction of sewer flume completed Adams shaft liner 50% complete, finish early
September
Construct near surface structures, started April2015 – ongoing
Adit excavation and lining, starting September
2015 Micro Tunnel Boring Machine setup and lining,
starting November 2015
11
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
12/40
Adams and First IntersectionConstruction Work Zone
Concrete barrier
with 6-foot-highchain link fence
8-foot-high chain linkfence all around
Traffic sand drum
Adams Street NW
12
N
Freeze pipes installed at the corner ofFirst and Adams where adit tunnelwill connect to First Street Tunnel.
Concrete barrier with6-foot-high chain link fence
Open North-Southsidewalk to pedestrians
F i r s t S t r e e t N W
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
13/40
This page intentionally left blank.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
14/40
First and V IntersectionConstruction Staging Area
V Street
F i r s t
S t r e e t
Legend
CSA
CLC
CSA
CLC
4'-wide pedestrian walkway
FEMS access zone
Building entrance
Construction traffic entrance & exit
CSA ‒ Construction Staging Area
CLC ‒ Construction Lane ClosureFEMS ‒ Fire and EMS Department
Abbreviations
Sidewalk at
V Street has
been shiftedto allow FST
access to
storm drains
14 feet
55 feet
Fire department
ladder truck clearances
Local Traffic
14
Currentlyfenced
Securityfencingin place
Will notbefenced
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
15/40
First and V IntersectionConstruction Staging Area
Completed shaft cast-in-place liner
Construction of sewer flume has started Verizon support work completed
Freeze system and formation completed, adit
mining started Construct near surface structures, started in
May 2015 – ongoing
Continued closure of First and V Streetsintersection
15
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
16/40
Plan View of First and V StreetsConstruction Staging Area
Alley
Shaft
Adit
Chiller Unit for Freeze
Adit
A A
N
16
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
17/40
V Street Profile View Adit Construction
Section B-B
B
B
TBM Tunnel
Connection to be made after
TBM tunnel complete
AlleyStreet Level
Ventilation Fan 75 HP
17
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
18/40
Adit Excavation Cycle (Section A–A)
Freeze Pipes
Roadheader Small Loader
MuckBox
Re-establish Freeze Pipe
Shotcrete support as
soon as lattice girdersand mesh installed
Excavation Steps:
1. Excavation maximum 6 feet, remove freeze pipes
2. Erect lattice girder and wire mesh
3. Shotcrete
4. Re-establish freeze pipe in invert
Current
CycleNext
Cycle
18
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
19/40
Equipment to be Used
Roadheaderbeing fabricated .
Roadheader finished product.
Shotcrete plant setup. Roadheader excavating V Street adit.
19
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
20/40
Legend CSA
CLC
CSA FEMS accesszone
Building entrance
Construction traffic entrance and exit
CSA ‒ Construction Staging AreaCLC ‒ Construction Lane Closure
FEMS – Fire and EMS Department
Abbreviations
First and Thomas IntersectionConstruction Staging Area (Pumping Station)
14 feet
55 feet
Fire department
ladder truck clearances
Local Traffic
20
30-inch sewer line replaced
mid-September; restrictedto one lane with flaggers.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
21/40
First and Thomas IntersectionConstruction Staging Area (Pumping Station)
Construct shaft cast-in-placeliner, July 2015 – August 2015
Freeze system completed andadit formation in progress
Construct near surface
structures, started inMay 2015 – ongoing
Adit excavation and lining,
starting September 2015
21
Excavation of the pumping station dropshaft is complete. Installation of the
cast-in-place liner is 60% complete.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
22/40
Production, Delivery, andPlacement of Concrete
SKJD makes every effort to schedule concrete pours
during regular work hours:
Monday thru Friday, 7 AM to 7 PM; on Saturdays, 9 AM to 5 PM
However, there have been times at all First Street Tunnel
construction sites when concrete pours must continue
beyond normal work hours:
Concrete plants are independent suppliers and there can be
problems at the plant, causing delays
Concrete trucks are independent suppliers traveling on publicroads; traffic congestion and detours can cause delays
Concrete placement requires all SKJD equipment to be
completely functioning and fully staffed
22
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
23/40
Reported Incident on August 14at Adams Street CSA
The contractor experienced an equipment problem with the main cranelast Friday evening at the Adams and Flagler Construction Staging Area
The contractor then mobilized its secondary crane to access the shaft
The crew in the shaft were detained while the second crane was putinto position
The main crane began working and the work wrapped up
These types of activities can and do occur with complex construction
projects. They are not uncommon, and contingency plans and actionsare in place to address equipment issues, interruptions, and otherdisturbances.
23
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
24/40
LONG‐
RANGE
CONSTRUCTION
SCHEDULE AND PROGRESS
Scott Hoffman, SKJD and John Kennedy, DC Water
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
25/40
25
Long-Range Construction Schedule
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
26/40
Division P – First Street Tunnel
Progress at-a-Glance as of July 31, 2015; 63% complete
TBM Mining and Lining
• Installed temporary ringsand launch frame
• Started mining throughshaft wall
• Installed Ring No. 8
V Street NCS-DC
• Continue excavating
• Installing bracingLevels 1 and 2
• Exposed sewer line
V Street Adit Tunnel
• Started Sequential
Excavation Method(SEM)
Pump Station – Drop Shaft
• Continue freeze
formation at drop shaftand adit
• Installed rebar, concreteforms and poured invertslab
• Installed rebar, concrete
forms and pouredconcrete for CIP LiftNo. 1
Adams Street – Drop Shaft
• Finished shaft excavation
• Installed rebar, concreteforms and poured invertslab
AS – Diversion Chamber
• Continue installing andwelding wales forbracing Levels 1 and 2
• Demo existing sewer
pipe and installed flumepipe
26
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
27/40
UPDATE
ON
COMMUNITY MITIGATION MEASURES
John Kennedy, DC Water
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
28/40
Responses to Residents’ Concerns
Employee parking outside of designated areas
Ticketed and towed vehicles when identified
Loud equipment backup alarms and air horns
Replaced some equipment/vehicle with static alarms and reduced air horn
usage with buzzer (OSHA requirement)
Queuing concrete and dump trucks at Construction Staging Areas
(CSAs)
Increased awareness to stage trucks at Channing Street CSA
Loud noise from First and V Streets CSA at night
Insulated cylinder pressure relief to avoid venting from temperature
changes
28
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
29/40
Responses to Residents’ Concerns
Metropolitan Police Department officer stationary in patrol vehicle
Directed officer to periodically foot patrol around CSAs
Obstructed view around First and V Streets CSA due to sound
blankets
Removed some blankets on First Street at the north end of CSA Increased speeding in east alleyway
Installed collapsible fence, bollards, and additional signage to reduce traffic
Inadequate lighting at First and V Streets and Adams Street andFlagler Place Construction Staging Areas
Installed additional perimeter lighting around CSAs
29
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
30/40
Saturday work efforts at each of the Construction Staging
Areas (CSAs) will continue
Saturday work hours are from 9 AM to 5 PM, and occur as
weather and the contractor’s schedule allows
The additional work day is necessary to make up for timelost during delays in the construction schedule (i.e., utility
relocations, inclement weather conditions, extensive water
main replacement at Adams Street and Flagler Place)
If you have questions, please call the First Street Tunnel
Hotline at 1-844-FST-INFO (1-844-378-4636)
Saturday Work
30
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
31/40
Security and Safety withinConstruction Staging Areas
The Construction Staging Areas
(CSAs) house large trucks, construc-
tion equipment, and tools and havedeep, open excavations
The CSAs are closed to the public
Security personnel are onsite duringoff hours
SKJD has installed security lighting and cameras
31
To better ensure your safety and the
safety of your children and pets, donot enter a Construction Staging Area.
Fencing signage at First and V Streets CSA.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
32/40
First and V Streets CSA published!
32
The First Street Tunnel project
was shown in an advertisement
in the August 2015 geotechnical
magazine, Geostrata
First and V Streets Construction Staging Areashown in geotechnical periodical, Geostrata.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
33/40
DC Water and District Department ofTransportation Tree Planting Initiative
33Chinese PistacheCrepe Myrtle Magnolia
Community requested tree planting plan
DC Water is ready to provide funds to DDOT
DDOT will work with community members to coordinate plan and determineplanting locations
DC Water and SKJD will present landscaping and restoration plans in
October 2015 and will continue discussions through March 2016
35 native trees to be planted in Bloomingdale
P j t Di l B d t T
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
34/40
Project Display Boards at TwoConstruction Staging Areas
There are currently 17 display boards that provide information
on the DC Clean Rivers Project and First Street Tunnel
On Tuesday, August 18, the DC Clean Rivers team installed
two sets of the display boards on the outer facing fences of
the Construction Staging Areas. One set each at:
First and V Streets Construction Staging Area
First and Thomas Streets Construction Staging Area
The following pages show where the display boards werepositioned along the fences at both Construction Staging
Areas
34
Di l t Fi t d V St t
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
35/40
Displays at First and V StreetsConstruction Staging Area (1 of 3)
35
V StreetNW
First Street and V Street NWLooking South
First Street NW
Di l t Fi t d V St t
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
36/40
Displays at First and V StreetsConstruction Staging Area (2 of 3)
36
First Street and V Street NWLooking West
V StreetNW
First Street NW
Di l t Fi t d V St t
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
37/40
Displays at First and V StreetsConstruction Staging Area (3 of 3)
37
First Street and V Street NWLooking Northwest
V StreetNW
First Street NW
Displays at First and Thomas Streets
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
38/40
Displays at First and Thomas StreetsConstruction Staging Area
38
First Street and Thomas Street NWLooking West
Thomas Street NW
sidewalk
patio house
FEMS Doorway Mural Project at
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
39/40
FEMS Doorway Mural Project atAdams and Flagler CSA
39
The mural painting ofthe doors at Adams and
Flagler CSA is currentlyunderway
The first ten doors will becompleted in September
The remaining doors, 11thru 31, will be deliveredin October/November
Nessar paints a tribute to the environment (left) andDC Water’s Clean Rivers Project logo.
-
8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20
40/40
Next Steps/Save the Date
Next Tunnel Forum Meeting on Thursday, October 22 at
7 PM, at St. George’s Episcopal Church
Save the date: First Street Tunnel hard hat tour day on
Saturday, October 24 at 10 AM. (Rain date is Saturday,
November 7). Logistic details to come.
Topics for next meeting: Landscaping and restoration of
disturbed areas
For updates, go to
www.dcwater.com/firststreettunnel or
call 1-844-FST-INFO (1-844-378-4636)for First Street Tunnel Construction Issues