day2 session3 pcm milestones
TRANSCRIPT
INTRODUCTION TO PROJECT CYCLE
MANAGEMENT: MAJOR STAGES AND
MILESTONES OF PCM PROCESS
David SimekOECD
Promoting Clean Urban Public Transport in Kazakhstan: Designing a Green Investment Programme
14 December 2016, Astana
Policy: response to perceived problem or set of issues.
Statement of approach or decision-making procedure to
obtain an objective. Public policy is the course of action,
including laws, regulatory measures and funding
priorities, to address a given objective
Programme: broad areas of work required to
implement policy decisions and priorities. Group of
activities intended to contribute to an
identifiable set of government objectives with a
clearly defined budget and a timeframe for achieving
these objectives
Projects, Programmes, Policies (1)
Project: "series of activities aimed at bringing about
clearly specified objectives within a defined time-period
and with a defined budget."
Project should have:
– Clearly identified stakeholders, including the primary target group
and the final beneficiaries
– Clearly defined coordination, management and financing
arrangements
– Monitoring and evaluation system (to support performance
management)
– appropriate level of financial and economic analysis, which
indicates that the project’s benefits will exceed its costs
Projects, Programmes, Policies (2)
PCM tries to ensure that:
1. Projects contribute to overarching policy objectives
2. Projects are relevant to the agreed strategy & the
target groups / beneficiaries
3. Projects are feasible (i.e. within the possibilities and
scope of action of implementing agencies)
4. Project results are sustainable (in medium / long
term)
Key Principles of Project Cycle
Managament (PCM)
Programming; Establishing Funding Priorities
Identification of Projects
Formulation of Projects
(Pre-selection of Potential Projects)
(Complete Appraisal of Pre-selected Projects)
(Selection of Projects for Financing)
Negotiations and Contracting
Project Implementation and Monitoring
Project Evaluation
Stages of PCM (1)
Stages of PCM (2)
Strategic and Programme Considerations
Feedback loops
Process flow
Implementation
Planning
Programming
Identification
FormulationImplementation
Evaluation and
Audit
Financing???
Project
Start-up
Project
Execution
Project
Sustainability
Project
Identification
Project
Preparation
During the Programming phase, the situation at national
and sectoral level is analysed:
To identify problems, constraints and opportunities which
cooperation could address
To identify the main objectives and sectoral priorities for
cooperation, taking into account national as well as donor
objectives
I. Project Programming (1)
National Policy Statements
National Programmes: specify overall policy
directions and funding priorities
Establish Funding Priorities: based on overall policy
directions and programme priorities
Based on this, the Implementing Agency publishes
written guidelines:
– on use of funds, types of projects financed, type of assistance
available for each type of project, maximum funding amount,
etc.
– Sometimes, priority investments are even listed by name
I. Project Programming (2)
Analysis of relevance of project ideas within the
framework of sectoral, thematic or “pre-feasibility”
studies
Analysis of relevant stakeholders / target groups /
beneficiaries (in terms of gender, socio-economic groups,
etc.)
Identification of their problems and feasible options to
address them
Implementation schedule (with proposals of main
milestones)
Brief outline of M&E (objectives/results,
assumptions/risks etc.)
II. Project Identification (1)
II. Project Identification (2)
Implementing Agency
Applicant Competition Winner
Distribute information
Call for projects - competitive;
aimed at specific
environmental problem
Project Concept Project
FACILITATING INITIATING
Relevant project ideas are developed into project
plans
Preparatory studies that outline feasible (i.e. likely to
succeed) and sustainable (i.e. will generate long-term
benefits) aspects of the project (technical, economic /
financial, institutional / management, socio/cultural,
environmental, etc.)
Beneficiaries and other stakeholders participate in the
detailed specification of the project idea
Again, checks need to ensure that cross-cutting issues
and overarching policy objectives are adequately
considered in the project design and objectives
III. Project Formulation
Also referred to as feasibility study or ex ante evaluation
phase
Before a financing decision can be made, a submitted
project is reviewed for compliance with programme
objectives
It is recommended that the appraisal process comprise of
two stages:
i. Preliminary appraisal
ii. Project appraisal and selection
IV. Project Appraisal
V. Preliminary Appraisal (1)
Applicant completes short
application form
Short application:
Basic Applicant Data,
Project Objectives,
Expected Environmental Effects,
Basic Technical and Economic
Information
Implementing Agency:
Pre-appraisal
Application is
sent to Implementing Agency
Decision
V. Preliminary Appraisal (2)
Implementing Agency
determines whether project fulfills all of
the preliminary criteria
Implementing Agency
sends Applicant:
Invitation to submit
a full application
Implementing Agency
sends Applicant:
Rejection Letter
YES NO
Timeframe:
Maximum Several Weeks
VI. Project Application (1)
Implementing Agency
Applicant Competition Winner
Distribute information
Call for projects - competitive;
aimed at specific
environmental problem
Project Concept Project
FACILITATING INITIATING
VI. Project Application (2)
Compiles additional
documentation and permits
Completes full application
depending on investment
type, plus environmental
(technical) and financial
section
Evaluates application
accuracy and completeness
Technical and economic
experts evaluate project
Applicant Implementing Agency
Following documents should be part of the final
application
Feasibility study
Cost-benefit analysis
Design study / Technical design
Financing proposal
Financing application
VI. Project Application (3)
If all the required documentation is submitted,
Implementing Agency accepts the application
If the application is accepted, the project is subjected to
appraisal and ranking
In regular periods (for instance, quarterly, semi-annually,
annually), the Implementing Agency compiles the results of the
ranking
If the project ranks high, the Implementing Agency will invite
representatives of the best projects to negotiations, up to the pre-
set budget limit for that financing objective
VII. Project Appraisal and Selection (1)
In case of incomplete or unclear documentation,
the Implementing Agency may
⇒ reject the project
⇒ encourage the Applicant to further elaborate
certain aspects
VII. Project Appraisal and Selection (2)
The Implementing Agency and the Applicant enter into
negotiations on the conditions of the contract
– Form of Assistance (grant, loan, equity)
– Conditions of Assistance
– In case of loan: Grace Period, Interest Rate, Credit Period
The loan or grant agreement is signed and the
disbursements are sent to the Applicant as negotiated.
Equipment purchases are typically reimbursed after
delivery based on an invoice
The Applicant initiates bidding procedures in accordance
with Public Procurement Law
VIII. Negotiations, financing decision
and disbursement
Usually, projects and programmes are implemented over
several years
Main stages:
I. Inception phase
II. Implementation phase
III. Final period
Main principles:
A. Planning and pre-planning (implementation schedule)
B. Monitoring (internal: project management / external:
implementing agency)
C. Reporting (internal and external reports on progress, usually
on quarterly basis)
IX. Project Implementation
and Monitoring (1)
Internal monitoring and reporting: usually on quarterly
basis with a focus on:
- Efficiency (conducted activities + implemented finances = overall
performance), i.e. relation between inputs and outputs (results)
External monitoring and evaluation: once or twice per
project cycle with a focus on:
- Relevance (results are relevant to the objective)
- Effectiveness (results have an impact on the objective)
- Sustainability (results are of long-term nature)
IX. Project Implementation
and Monitoring (2)
IX. Project Implementation
and Monitoring (3)
Selects contractor
Manages own and
Implementing Agency
resources
Implements and monitors
project (if according to
schedule)
Maintains documentation,
invoices for Implementing
Agency inspection
May appoint an expert to
evaluate project
performance at a given
stage
May conduct on-site visits to
evaluate project
performance
Inspects and approves
invoices
Applicant Implementing Agency
Implementing Agency should conduct evaluation that is:
Impartial & independent (from the project management)
Credible (level of expertise)
Participatory (incorporating stakeholders’ views)
Possible evaluation stages:
i. Ex ante (feasibility)
ii. Mid-term (recommendations)
iii. Final (results / objectives)
iv. Ex post (impact / lessons learnt)
X. Evaluation