PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
1
Project Background
National Energy PolicyNational Energy Mix 2025
1To increase the use of renewable
energy by total 23% of national energyin 2025, including the solar energy for
power plant
Decree of Ministry of Energy and Mineral Resources
No. 17 / 2013
2Feed in tariff for solar power plant.
Maximum at USD 25 cents per kWh with
additional incentive USD 5 cents forlocal solar module application
Decree of Director General of New and Renewable Energyand Energy Conservation No. 979 K/29/DJE/2013
3Capacity Quota for Solar Power Plant
80 Sites,140 MWp.Kupang 5 MW was included in the 7 first
sites to be tendered
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
3/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
2
Capacity Quota for PV Power Plant (2013)
80 LOCATIONS OF CAPACITY QUOTA FOR PV POWER PLANT2013
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
4/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
3
Why Len ?
PT Len Industri (Persero) is an Indonesian state owned company which develops business and products in electronics for industry andinfrastructure. As the highly competition in electronic technology based business, Len takes focus on 5 ( five) sectors : Railway Transportation,
ICT, Renewable Energy, Defense Electronics, and Navigation System. As for the solar energy business, Len is the most experienced company in
Indonesia with many success stories, both in manufacturing and EPC business.
2 x 1 MW On Grid PV Plant
Bali
Solar Street Lighting
Toll Road of Purbaleunyi
Airport BIPV/Rooftop
Lampung, Southern Sumatera
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
5/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
4
The First PPA in Solar Energy
MEMR designated Len as the winner for IPP PV Plant in Kupang 5 MW
(February 2014)1
Power Purchase Agreement (PPA) between Len and PLN 9th of January 20152Electricity Price
USD 0.25/kWh during20 years period
The PPA Agreement was signed by General Manager PLN of East Nusa Tenggara Area Richard Safkaur
and President Director of Len Abraham Mose,
in headquarter of PLN, Jakarta
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
6/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
5
Site Location
Location
CoordinateAvg. ESH
Desa Oelpuah, Kupang Regency, East Nusa Tenggara
123o 44’55” E | 10o8’58” S 6.38, lowest at 5.52 (kWh/m2/day)
Summer Season Approximately 8 months / year
Area Above 75.000 m2
ESH : Equivalent Sun HourENT : East Nusa Tenggara
Electrification Ratio of ENT 58.91%, the second lowest level in Indonesia
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
7/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
6
Site Position to the Grid (nearest feeder point)
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
8/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
7
Site Survey
Main Substation NaibonatThe Site
Some parts are plantation areas
Main Substation Maulafa
Middle voltage line near site
Express Feeder power lines on Jl.Timor RayaSite, forest
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
9/20
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
10/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
9
Construction Schedule
DecNovOctSep AugJulJunMay AprMarFebJan
Financial Closing
Procurement & Logistics
Land Clearing & Civil Works
Concrete Works
Metal Support Inst.
Water & Drainage System
Control Room
Road Works
CCTV
Solar Module Installation
Combiner & Inverter
Monitoring & Weather Inst.
Transformer & Switch Gear
Commissioning Certificate
COD
civil
mechanical & electrical
2015
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
11/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
10
General Block Diagram
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
12/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
11
General PV Arrays Design
PV Module
Tilt /Azimuth Orientation 10o/0o
Number of PV Modules 21.840
Nb. in series 21 modules
Nb. in parallel 1.040 strings
Unit Nominal Power 230 Wp
Module Area 36.614 m2
Inverter
Number of Inverter 260
Unit Nominal Power 17.0 kW
Operating Voltage 430 – 900 V
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
13/20
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
14/20
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
15/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
14
Pictures from Kupang
Metal Support Inst.
Water & Drainage System
Control Room
Road Works
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
16/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
15
Pictures from Kupang
Solar Module Installation
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
17/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
16
Pictures from Kupang
Combiner & Inverter
Monitoring & Weather Inst.
Transformer & Switch Gear
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
18/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
17
Pictures from Kupang
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
19/20
PT Len Industri (Persero)
Competitive Technological Independence
www.len.co.id
18
Pictures from Kupang
-
8/18/2019 Day 2 Solar 2 Developing the First Grid Connected Solar PV in Indonesia Abraham Mose
20/20
PT Len Industri (Persero)
Competitive Technological Independence19
Pictures from Kupang