data capture of the phc 2002 (uganda) experiences and lessons leant

8
Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Upload: helen-charles

Post on 23-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Data capture of the PHC 2002 (Uganda)

Experiences and lessons leant

Page 2: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Introduction•6 population censuses in 1948.1959, 1969, 1980, 1991 and the 2002 (most recent)

•Planning for the PHC 2002 started in 1997 with the development of the Census Master Plan •The plan also included strategy for data processing

•PHC 2002 Results showed that Uganda population size then was 24.2 millions

Page 3: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

• Preparations for Data processing started in 2001 (Challenges, successes, technology to use)– A study tour to SA, Kenya, and Zambia

After the tour, UBOS opted for the traditional mode of data capture using keyboards.

Data ProcessingThe 1991 PHC software used was

- imps for capture- CONCOR for editing- TPL for tabulation

The 2002 PHC software used was - CsPro for capture- CONCOR for editing- CsPro for tabulation

Page 4: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Why manual data Entry?

Time left was little (only 12 months)

The budget for the equipment and technical expertise

The pilot census had used data entry.

Needed to redesign the tools which had already been piloted

Available expertise to manage traditional data entry method

No local technology available to print papers for scanning technology, International procurement for this would be very slow.

Page 5: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Data processing personnel

•It involved about 527, 330 of whom were DEOs (some become supervisors, shift leader and team leaders)

•The center was headed by a data processing officer and an assistant DPO (permanent UBOS staff).

•60 extra data entry operators to capture the post enumeration data were recruited.

•Data processing took place in a site away from the UBOS premises.

•A team had 10 people and one was a team leader

There was four sections•Stores --------- Normal working hours•Coding --------- Three shifts•Data entry --------- Three shifts•Editing and tabulation -----Normal working hours

Questionnaire was pre-coded, coders coded only occupation and verified the geo-information

Page 6: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Working shifts

Three shifts a day for 6 days a week

Shift A (from 7.30 am to 2.30 pm); Shift B (from 3.00 pm to 10.00 pm); and Shift C (from 11.30 pm to 6.30 am).

Page 7: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

Data Entry

•Started with a summary sheet in October 2002- took one month•Then captured the agricultural module (100% verification)•Then the Household Module (100% verification and later 20%

verification) started in July 2003, Net work was then laid ended in October 2004

•Then the The Hotel, MSE and Community questionnaires. (different DEO for this).

Training•All new data entry clerks were subjected to a one month training toperfect their keyboard skills.

•Focus of the training was speed and accuracy

Page 8: Data capture of the PHC 2002 (Uganda) Experiences and lessons leant

9.12 Technical Assistance

The US Census Bureau on census planning which included data processing

An independent consultant for data processing

The US Census Bureau on developing edits and implementing edits, plus tabulation