![Page 1: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/1.jpg)
Daniel SuterDaniel Suter Construction ManagementAE Senior Thesis PresentationThe Pennsylvania State University
Unknown Data CenterSomewhere, USA
4.12.2011
![Page 2: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/2.jpg)
Daniel SuterDaniel Suter Construction ManagementAE Senior Thesis PresentationThe Pennsylvania State University
Unknown Data CenterSomewhere, USA
4.12.2011
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Electrical Breadth
Tablet PC’s for Commissioning
Acknowledgements
Questions
Presentation Outline:
![Page 3: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/3.jpg)
Presentation Outline: PROJECT OVERVIEWo Owner – Anonymous
o Occupancy Type - Business
o Size - 17,445 SF South Expansion
o Cost - $ 50 Million (Design+Construction)
o Construction Duration - December 2008 – August 2010
o Delivery Method - Design-Bid-Build
oProject TeamCM – Turner Construction Architect/Engineers – Sigma 7 Design GroupCivil – Birdsall Services GroupStructural – Goldstein Associates
3
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USA
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Conclusions
Acknowledgements
Questions
![Page 4: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/4.jpg)
Presentation Outline: PROJECT OVERVIEW
4
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USA
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Conclusions
Acknowledgements
Questions
o Building Enclosure
• Architectural Precast Panels
• Total of 33 Panels to enclose the building
• Penthouse enclosed with EIFS
o Existing Roof Structure:
• Primary Roof - Composite, EPDM w/ Concrete Pavers
• Penthouse Roof – Composite, Standing Seam Metal
Roof
![Page 5: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/5.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o Opportunity
• Redesigning the 20’ Parapet Wall
• Tilt-up vs. Precast
o Objective
• Lower Material/Labor Cost
• Accelerate Schedule
5
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 6: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/6.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o Conceptual Design:
o Deduction of 10’
o Design Criteria:
o Line of Sight
o Penthouse vs. Building Enclosure
6
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 7: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/7.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o Sequence
o Follow the same sequence as Precast (33)
o Panels are formed and stacked onsite
o Site Layout
o Need to Revise Site Layout Plan
o Tilt-up Increases Site Congestion
7
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 8: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/8.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o RS Means:
o $41.5/ SF – Precast
o $15/ SF – Tilt-up
o Total Savings
o $160,000 – Includes design
o $327,000 – Includes design and method
8
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 9: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/9.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o Schedule Impact:
o Precast – 3.3 panels / day
o Tilt-up – 4 panels / hour
o 33 panels in a nine hour work day
o 9 days cut off cut from the critical path
9
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 10: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/10.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAFaçade Redesign/Tilt-Up
Construction
o Conclusion:
o Total Savings of 327,000
o 9 Days off the Critical Path
o Recommendations:
o The owner should pursue Tilt-up Method, but take note
on the safety issues and quality concerns.
o Highly recommended for the Redesign – Savings of
$160,000
o Money could pay for PV system10
Project Overview
Façade Redesign/Tilt-Up Construction
• Area of Potential Improvement
• Proposed Design
• Tilt-Up Sequence
• Cost Analysis
• Schedule Impact
• Conclusion
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 11: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/11.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o Opportunity
o Building is Oriented South
o Opportunity to utilize the Penthouse roof for design
o Objective
o Design a Preliminary Photovoltaic System
o Perform a Financial Feasibility Study
o Reduce Energy Cost of the Building
11
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 12: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/12.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o What will the power from the panels essentially
replace?
o Conclusion:
o The design will be able to power all of the lighting
fixtures in the building.
o 125 panels required – Design consist of 129 panels
o 105 panels located on west penthouse
o 24 panels located on east penthouse12
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 13: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/13.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o Calculate Optimal Tilt in Panels
o West Penthouse – 40°
o East Penthouse - 32°
o Determine Most Efficient Panel:
o Sanyo Electric, HIP-200BA19/20
13
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 14: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/14.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o PV Watts Calculations:
o System Produces 31,000 kWh / Year
o Yearly Savings of $3900
14
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 15: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/15.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o Energy Distribution:
o DC – Inverter – AC – Grid system
o Inverter:
o Sunny Tower ST 36
o Easy mount
o Includes all DC/AC connections
o Voltage Drop:
o DC - Use #8 AWG Wire 15
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 16: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/16.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
System
o Total System Cost:
o $250,000
o W/ Rebates and Incentives: = $160,000
o Potential Buy back – 17-18 years 16
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
o Schedule Impact:
o Once the penthouses are constructed, the PV
contractor can start
o Main Concern is Crane Usage
o Should not affect the critical path
![Page 17: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/17.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAlternate Roof Type – Photovoltaic
Systemo Conclusion :
o Up front cost - $160,000
o Potential Buyback of 17-18 years
o Does not affect schedule’s critical path
o Recommendation:
o Highly recommended for the owner to consider this
preliminary design.
o Owner has potential to pay for the whole up front cost
of this system 17
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
• Area of Improvement
• Proposed PV System
• Electrical Breadth
• Cost Analysis/Schedule Impact
• Conclusion
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 18: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/18.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USATablet PCs for Commissioning
o Tablet PC Use:
o Quality Control
o Punch List Management
o Production Tracking
o Materials Management
o Safety
o Commissioning
o BIM in the Field
o Visual Reporting
18
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
• Introduction
• Potential Benefits/Challenges
• Case Study
• Conclusion
Acknowledgements
Questions
![Page 19: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/19.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USATablet PCs for Commissioning
o Potential Benefits:
o Store PDF and paper forms of the budget, schedule,
and specs.
o Easier to organize and manage while onsite
o Record performance of mechanical equipment
o Record issues during the commissioning process
o Reference the data on future projects
19
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
• Introduction
• Potential Benefits/ Challenges
• Case Study
• Conclusion
Acknowledgements
Questions
o Challenges:
o Tablet are exposed to hazards on the construction
jobsites
o Weather may affect the life of the tablet
o Lack of knowledge in this industry
oUsing the tablets to it’s full advantage
![Page 20: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/20.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USATablet PCs for Commissioning
o Case Study (Maryland General Hospital)
o Barton Malow – CM
o $57 Million renovation
o Includes an array of indoor AHU
o 650 –ton electric chillers/cooling towers
o Tablets for commissioning
o Collected data and documents as one integrated unit
with their 3D model.
o Eliminated all data re-entry
o Commissioning and their BIM Model totally in synched 20
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
• Introduction
• Potential Benefits/Challenges
• Case Study
• Conclusion
Acknowledgements
Questions
“The same tasks that used to take us days to manage and track, now take just hours”
![Page 21: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/21.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USATablet PCs for Commissioning
o Recommendations:
o All CM firms to use tablet PCs for the whole
construction process
o For commissioning – highly recommended for complex
MEP projects (hospitals, data centers)
o Conclusion:
o Hard to determine actual value in cost and schedule
acceleration.21
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
• Introduction
• Potential Benefits/Challenges
• Case Study
• Conclusion
Acknowledgements
Questions
![Page 22: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/22.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAAcknowledgements
o Academic Acknowledgments
o Penn State AE Faculty
o Dr. Rob Leicht
o Industry Acknowledgements:
o Turner Construction
o Sigma 7 Design Group
o Special Thanks to:
o Frank Forcino @ Turner Construction
o Tom Atrens @ Turner Construction
o Family and Friends22
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions
![Page 23: Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011](https://reader034.vdocuments.mx/reader034/viewer/2022051315/56649e2a5503460f94b18208/html5/thumbnails/23.jpg)
Presentation Outline:
Daniel Suter | Construction Management | 4.12.2011
Unknown Data CenterSomewhere, USAQuestions
23
Project Overview
Façade Redesign/Tilt-Up Construction
Alternate Roof Type – Photovoltaic System
Tablet PC’s for Commissioning
Acknowledgements
Questions