d&d planning and execution approaches

14
Wendy Cain ETTP Portfolio Federal Project Director DOE-Oak Ridge Environmental Management D&D Planning and Execution Approaches

Upload: others

Post on 24-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: D&D Planning and Execution Approaches

Wendy Cain ETTP Portfolio Federal Project Director

DOE-Oak Ridge Environmental Management

D&D Planning and Execution Approaches

Page 2: D&D Planning and Execution Approaches

Current Cleanup Status

2

Page 3: D&D Planning and Execution Approaches

• Target Zero • Integrated Safety Management System and Work

Control • Stop Work Responsibility • Continuous Improvement • Conservative Decision Making • Safety Conscious Work Environment • Communicate • Do Less Work

Safety – It’s Foundational

3

Page 4: D&D Planning and Execution Approaches

• December 2013 - Structural demolition complete

• March 2014 – Final debris shipment to EMWMF

• June 24, 2014 – All contract scope complete

• January 9, 2015 – CD-4 approved

K-25 Building Demolition Complete

4

Page 5: D&D Planning and Execution Approaches

K-31 “Before”

Accelerating K-31 Demolition was enabled by: • Completing K-25 ahead of schedule • Avoiding K-25 costs associated with later

completion • Having trained, efficient work crews available

Productive progress toward ETTP vision while awaiting K-27 to be demolition-ready • CD-2/3 Approved April 28, 2014 • Structural demolition began October 8, 2014

K-31 Building Demolition

~50% complete

5

Page 6: D&D Planning and Execution Approaches

• Accelerate Characterization activities for hazard identification, regulatory process, and waste acceptance

• Perform Deactivation activities in parallel with demolition planning • Complete “Cold and Dark” • Attain Criticality Incredible • Demolition Ready

• Complete DOE Order 413.3B activities for CD-2/3 approval

Accelerating K-27 Building Activities

6

Page 7: D&D Planning and Execution Approaches

• Isolate utilities and remove energy sources

• Install temporary power and lighting

• Install life lines and grip strut • Perform asbestos abatement • Drain oil • Remove listed waste

Life Line Installation

Grip Strut Installation

Asbestos Abatement

Deactivation Approach – Cold & Dark

7

Page 8: D&D Planning and Execution Approaches

• Duct Cutting - Access process piping • Vent, Purge, Drain, and Inspect – Document visual

inspection of all ≥ 3” diameter PGE/piping • NDA measurement and sampling

Vent, Purge, Drain,

& Inspect

NDA Measurement Duct Cutting

Deactivation Approach - Crit Incredible

8

Page 9: D&D Planning and Execution Approaches

• High risk equipment removal and mining • Foaming

– Meets WAC subsidence requirements – Physical security – Immobilizes contaminants – Prevents water infiltration

• Criticality Safety independent verification • Criticality Incredibility determination documented

Deactivation Approach - Crit Incredible

Foaming

9

Page 10: D&D Planning and Execution Approaches

• “Go Orange” marking – Easy identification for segregation during demolition

• Tabbing and unbolting of equipment – Cleaner piping cuts and easier equipment handling during

demolition

Unbolting Compressors & Converters

“Go Orange” Marking

Deactivation Approach – Demo Ready

10

Page 11: D&D Planning and Execution Approaches

Demolition Approach

Demolition

Truck Loading Hauling Survey Slab

Converter Handled With Grapple

11

Page 12: D&D Planning and Execution Approaches

• Onsite disposal facility received 86% of the K-25 waste generated • Haul Road – reduced risk and increased efficiency with non-commerce transport • Eliminate double handling • Shipped waste is better than stored waste • Converter disposal approach • Reusable Compressor volute shipping containers

Converter Packaged To Be Shipped

Waste Disposition Approach

Dump Trucks Lined Up

Haul Road

12

Page 13: D&D Planning and Execution Approaches

• Formal Federal Facility Agreement (Tri-Party Agreement) review/approval process is implemented

• EPA and TDEC approval is required at each step • Collaborative Regulatory Project Teams

13

Remedial Activity

Siting Design/ Construction/ Expansion

Waste Acceptance & Operations Closure

Approval Process

Remedial Investigation/ Feasibility Study, Record

of Decision

Remedial Design Report; RDR Addenda, Phased

Construction Completion Report

Waste Acceptance Criteria Attainment Plan;

Remedial Action Work Plan

Remedial Design Report; Remedial

Action Report

Regulatory Approach

Page 14: D&D Planning and Execution Approaches

Maintaining Momentum

• Continue to build on the success of completing the K-25 Project and progress on the K-31 Project

• Performance Excellence – Safety – Schedule – Cost – Incorporate

lessons learned • Partnering

– Goal Alignment – Building Trust

14