![Page 1: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/1.jpg)
Sub Project
Status Report
KC NCDDP Canaman
Cycle 1
![Page 2: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/2.jpg)
Barangay Fundado
SP: Desilting of Flood Control Canal
Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
764,787.50 100% Completed
![Page 3: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/3.jpg)
Barangay Sta. Teresita
SP: Construction of Foot Bridge
Total Project Cost/ KC
Grant
Physical
Accomplishment
Remarks
436,934.00 100% Completed
![Page 4: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/4.jpg)
Barangay Iquin
SP: Construction of One Unit Day Care
Center Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
832,422.58 100% Completed
![Page 5: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/5.jpg)
Barangay Dinaga
SP: Improvement of Drainage Canal Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
465,062.50 100% Completed
![Page 6: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/6.jpg)
Barangay PangPang
SP: Improvement of Drainage Canal Total Project Cost /
KC Grant
Physical
Accomplishment
Remarks
624,878.00 100% Completed
![Page 7: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/7.jpg)
Barangay San Roque
SP: Improvement of Drainage System Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
1,501,306.20 100% Completed
![Page 8: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/8.jpg)
Barangay San Jose West
SP: Construction of Drainage Canal Total Project Cost Physical
Accomplishment
Remarks
506,429.22 100% Completed
![Page 9: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/9.jpg)
Barangay San Jose East
SP: Construction of Drainage Canal Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
526,504.63 100% Completed
![Page 10: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/10.jpg)
Barangay San Francisco
SP: Construction of Footbridge Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
297,189.50 100% Completed
![Page 11: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/11.jpg)
Barangay San Nicolas
SP: Improvement of Drainage System Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
2,608,476.50 100% Completed
![Page 12: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/12.jpg)
Barangay Liñaga
SP: Construction of One (1) Unit Three (3) Classroom
School Building Total Project Cost Physical
Accomplishment
Remarks
2,864,349.80 100% Completed
![Page 13: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/13.jpg)
Barangay Sua
SP: Construction of One Unit One
Classroom School Building Total Project Cost / KC
Grant
Physical
Accomplishmet
Remarks
1,099,675.15 100% Completed
![Page 14: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/14.jpg)
Barangay Tibgao
SP: Construction of Evacuation and
Training Center
Total Project Cost / KC
Grant
Physical
Accomplishment
Remarks
2,169,225.18 100% Completed
![Page 15: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/15.jpg)
Barangay SP Name Disbursement FA PA Variance
Palo Rehabilitation of Wharf
With Riverbank Protection
1,034,429.50 100% 100% 0%
![Page 16: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/16.jpg)
Barangay
SP Name Disbursement FA PA Variance
San Juan
CONSTRUCTION OF ONE
UNIT TWO CLASSROOM
ELEMENTARY SCHOOL BUILDING
2,344,844.00 100%
100% 0%
![Page 17: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/17.jpg)
Barangay
SP Name Disbursement FA PA Variance
Sta. Cruz Construction of Slope
Protection
2,294,810.00 100% 100% 0%
![Page 18: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/18.jpg)
Barangay
SP Name Disbursement FA PA Variance
Talidtid CONSTRUCTION OF DRAINAGE SYSTEM
1,280,409.20 100% 100% 0%
![Page 19: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/19.jpg)
Barangay SP Name Disbursement FA PA Variance
Poro 2,819,399.58 100%
100% 0%
![Page 20: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/20.jpg)
Sub Project
Status Report
KC NCDDP Canaman
Cycle 2
![Page 21: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/21.jpg)
Barangay SP Name Disbursement FA PA Variance
Baras Construction of Drainage
Canal
996,906.36 47.67% 34.83% 25.17%
![Page 22: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/22.jpg)
Barangay SP Name Disbursement FA PA Variance
Del
Rosario
Construction of Slope
Protection
1,956,459.93 75% 74.14% -14.14%
![Page 23: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/23.jpg)
Barangay SP Name Disbursement FA PA Variance
San
Vicente
Construction of
Evacuation Cum Training
Center
761,649.00 41.92%
36.36% 23.64%
![Page 24: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/24.jpg)
Barangay SP Name Disbursement FA PA Variance
Mangayaw
an
Improvementof
Drainage Canal
1,254,969.00 80.41% 80.15% -20.15%
![Page 25: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/25.jpg)
Barangay SP Name Disbursement FA PA Variance
San Agustin Improvement of
Drainage Canal
1,290,545.45 83.67% 61.26% -1.26%
![Page 26: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/26.jpg)
Barangay SP Name Disbursement FA PA Variance
Tibgao Construction of Health
Station
230,492.00 29.89% 40.15 19.85%
![Page 27: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/27.jpg)
Community Volunteers Trained Regular Cycle
Cycle 2
Total
Attendee
s Male Male % Female
Female
% 4Ps
MO 57 32 56.14035 25 43.85965 11
MPSA 49 10 20.40816 39 79.59184 10
CSW 137 40 29.19708 97 70.80292 24
PDW 127 39 30.70866 88 69.29134 31
MTDR 86 31 36.04651 55 63.95349 5
MIBF 175 58 33.14286 117 66.85714 16
PIW Proc 86 17 19.76744 69 80.23256 14
PIW Finance 78 27 34.61538 51 65.38462 16
ODM 96 31 32.29167 65 67.70833 35
CMT 60 15 25 45 75 12
![Page 28: Cycle 1 - canaman.gov.ph · Barangay Iquin SP: Construction of One Unit Day Care Center Total Project Cost / KC Grant Physical Accomplishment Remarks 832,422.58 100% Completed](https://reader034.vdocuments.mx/reader034/viewer/2022050107/5f44f23c141a8a728f42e625/html5/thumbnails/28.jpg)
Cycle 2 Total
Attendees Male Male % Female
Female
% 4Ps
MAR 107 40 37.38318 67 62.61682 16
MFW 1 113 39 34.51327 74 65.48673 17
MFW 2 46 14 30.43478 32 69.56522 3
MFW 3 55 16 29.09091 39 70.90909 3
MFW 4 46 8 17.3913 38 82.6087 4
Cycle 3
MO 80 33 41.25 47 58.75
MIBF 37 22 59.45946 15 40.54054 10
PIW Proc 55 14 25.45455 41 74.54545 11
PIW Finance 57 13 22.80702 44 77.19298 8
TOTAL 1547 499 32.25598 1048 67.74402 246