Oracle Production Cutover Strategy
06.30.16
![Page 2: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/2.jpg)
2
Cutover Definition
What is Cutover?• Cutover is the execution of activities required to successfully
migrate the business operations from Legacy Systems to the new Production system
How is Cutover executed?• Cutover will be executed as per the ‘Cutover Plan’ - a set of
detailed, sequenced tasks to build the new Production system, convert and migrate data, configure the new system and decommission legacy systems
• Validate the Cutover Plan prior to Go-Live and make revisions prior to the actual. It is a way of fine-tuning the process and minimize risks prior to full production cutover
![Page 3: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/3.jpg)
3
Cutover Overview
Project Command Center
Site Readiness
Team
Cut-over Team
Cut-over activities
• Single Cutover Plan• Other teams report milestone status• Cutover team directly drives execution of
build, conversions & interfaces directly with resources responsible for execution
• “Check-In / Check-Out” communication as activities Enterprise & end
• Run status meetings• Maintains Contact List
Go-live Support
Team
Site readiness activities
Go-live activities
Master Data team
Functional Teams
Technical Team
![Page 4: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/4.jpg)
4
Cutover Objectives
• To successfully migrate business data and business operations from the Legacy systems to the new Production system
• A successful cutover is achieved through:
• Execution of the Go-Live Cutover plan in the Production environment with minimal impact to daily business activity
• Coordination with several key areas (e.g. Go-Live Support) to ensure a successful transition to the new operating support structure
• Execution of the Cutover Plan within the established timeframe
DeploymentDeployment
CommunicationsEnd User Training ChangeCutoverSite
Readiness
Preparing individual sites for cutover to production by focusing on people, process, and technology readiness.Involving people from outside of the core project team to complete readiness activities.
Go-Live Support
Creating and executing a cutover plan to build the production system and carry out all conversion activities for Go Live.
Supporting end-users after the production system goes live. Includes details such as Help Desk and crisis management
Training employees and managers on the new production system.
Helping employees and managers transition to new roles.
Delivering messages about production system deployment activities.
![Page 5: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/5.jpg)
5
Cutover Plan Components
Activities performed in the sites to ensure business preparation for go-live.
Process performed at periodic checkpoints to ensure completion of all critical tasks prior to go live
Activities to build the technical environment including infrastructure build, configuration & security
Configuration that cannot be transported and needs to be done manually in the system e. g. Number ranges
Master data and Historical data brought from existing systems to Production e.g. Customer Master.
Transactional data brought from existing systems to Production e.g. Open Orders.
Setup of stabilization and ongoing Production Support processes & procedures
Steps required to perform interfaces which are being run for the first time.
Activities to “turn-off” systems being replaced by new Production system.
Activities to monitor/track performance across key baseline metric readings and target measures
Site Readiness Checklist Activities
Production Support Strategy
Go / No-Go
Production Build
Manual configuration
Master Data and Historical Data Conversions
Open Transaction Data Conversions
System Decommission
Production Metrics
First Run Interfaces
Various components are essential for execution of a successful system cutover
![Page 6: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/6.jpg)
6
Executing Production Cutover Tasks
Execute Permit to Run
Progress / Issues
Complet
e
Process
• Report to Cutover Team to assess readiness to Enterprise task
• Review predecessor / successor dependencies
• Review turnover documentation for completeness and quality
Notes
• Enterprise cutover task once you’ve received approval
• Attend daily meeting• Validate resource requirements
• Daily meeting is to review status (task scheduled to be completed is not complete, etc)
• Update Cutover Team on
progress and delays• Log issues/bugs
• When logging issues use the “cutover” category• These issues are reviewed in daily meeting
• Update Cutover Team when task
ends.• Details required; actual duration,
effort of task, and end dates
• If Cutover Coordinators are not in room update workplan status on wall
![Page 7: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/7.jpg)
7
Cutover Deliverables
Cutover Plan (MS Project Plan)
Business Transaction Freeze
Document (excel)
I nterim Business Process Document
(excel)Site Coordinators
Checklist
Legacy System Coordinators List
(excel)
Integrated system and business transition activities by threads:
Infrastructure/system build Data conversion Legacy systems Security Business/System activities by functional area
Accountable: Cutover Team
List of system cutover data (master and transactional), associated business transactions and freeze dates Accountable:Cutover Team
Interim business process activities to be executed during cutover period Accountable: Functional Area Cutover Leads
Integrated system and business activities to be executed during cutover period at sites(Excel template) Accountable: Site Readiness Team
List of legacy system activities (Excel template – similar to site coordinators checklist)Accountable: Deployment Team
![Page 8: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/8.jpg)
8
Cutover Plan Template
The cutover workplan will provide a detailed minute by minute, step by step account of all activities involved with the production cutover
![Page 9: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/9.jpg)
9
Interim Business Transaction Template
Use this template to track the interim steps for execution of tasks/processes/ transactions between the time they are frozen and final production cutover
Task ID Task Details Transaction Volume(volumne by period to estimate resource requirements)
Inputs (Information inputs required for carrying out tasks)
Outputs(Information outputs captured from the task)
Information Capture(Manual Entry: Provide link or embed formsSystem Capture: Provide Transaction code)
Associated Risks & Contingency Plan(Outline risks with external and internal impacts involving process, people, or systemsProvide link or reference to contingency plan)
1.1 During Inventory, extracts a snapshot of catalyst system at that in time is uploaded to Production
N/A Inventory snapshot from each warehouse (all sub inventories and locators)
Inventory updates in Production
Enabled by conversion program
Accuracy of inventory snapshot from each warehouse at that point in time
Corruption of data extracts
1.2 Production is stopped in this period and changes from Production will be updated manually after cutover
N/A N/A N/A N/A N/A
![Page 10: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/10.jpg)
10
Cutover Timeline
Production Build
Apply Transport
Deltas
Validate system
PRD system
ready
Data Extracts
Master Data Loads
Delta LoadsPre-Data Load Activities Post-Data Load Activities
+ 2 Weeks (6/13)+3 Weeks (6/7) + 1 Weeks (6/20) + 1 Week (7/4) + 3 WeeksFriday – Sunday (7/1-7/4)
Final Go/No-GoDecision
Trans. Data Loads
4 Build Production System using restore, backup method (see above)4 Finalize legacy data extracts and preparation; ensure cleansing is
completed4 Perform all pre-data load activities including configurations, moving
transports, custom tables4 Begin capturing delta processing transactions for identified delta
processing areas4 Convert all master data (Materials, Customers, Employee, Vendors, etc)
4 Legacy system ‘lockdown’ at pre-designated time at the Enterpriset of Cutover weekend
4 Transactional data extracts4 Transactional data loads to new
Enterprise system4 Execute automated delta loads and
enter manual ‘catch up’ transactions4 Validate all loads to confirm go/no-go4 Reconciliations/Report runs4 Execute Enterpriset-up procedures4 Periodic go/no-go decision points4 Coordinate sequence and execution
of relevant Site Readiness Activities
4 Go-Live support processes fully operational
4 Week 1 processes, reports4 Monitor system infrastructure
performance
Pre-Cutover Weekend Activities Cutover Weekend Activities Post-Cutover Activities
Post-Cutover WeekendCutover WeekendPre-Cutover Weekend
Transactional Data ExtractsDelta ExtractsInitial data Extracts
The schedule provides key milestones and activities related to pre-cutover through cutover
![Page 11: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/11.jpg)
11
Name Role Office Phone Mobile Phone Email
Bill Francis ENTAPPS Operations 650.610.5192 650.888.4980 [email protected]
![Page 12: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/12.jpg)
12
Cutover Coordination
• Coordination with Business/Departmental Readiness Testing• Collaboration through periodic meetings• Synching of entrance and exit criteria• Communication and synching of project plans
• Coordination with Stress Testing• Collaboration through periodic meetings• Synching of entrance and exit criteria• Communication and synching of project plans
• Coordination with Site Readiness• Consolidation of project plan during the last 2 weeks prior to
Cutover• Communication and synching of project plans
• Coordination with Go-Live Support• Go-live support involvement in Cutover• Command center will be set up and run for Cutover• Communication and synching of project plans • Synching of entrance and exit criteria• Virtual ‘merging’ of Cutover and Go-Live Support teams during
cutover (function as a single team)
![Page 13: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/13.jpg)
13
Next Steps
Task
Assemble the Cutover Core Team and Cutover coordinators
Solicit preliminary cutover task list from each of the Cutover Support Team representatives
Kickoff Meeting with Cutover coordinatorsBuild Draft Cutover PlanConduct Cross Team review of Draft Cutover PlanComplete Draft Cutover plan in preparation for Mock Cutover - 1Execute Cutover Mock Cutover - 1Update plan based on the experiences/findings during Cutover Trial Run
Conduct Cross-Team review of draft Mock Cutover planComplete Draft Cutover plan in preparation for Mock Cutover - 2
Execute Mock Cutover - 2
Update plan based on the experiences/findings during Mock Cutover - 2
Conduct Cross Team review of Final Cutover Plan
Finalize Mock Cutover Plan in preparation for Production Cutover
Execute Production Cutover
![Page 14: Cutover Strategy 063016](https://reader036.vdocuments.mx/reader036/viewer/2022082321/5880fae41a28abc3368b626f/html5/thumbnails/14.jpg)
14
Contact Information