cta capital construction update august 9, 20061. capital construction update agenda • red line/dan...

16
Red Line Blue Line Randolph Washington Subsurface Station at Block 37 Tracks Block 37 Red Line/Dan Ryan Brown Line Howard CTA Capital Construction Update August 9, 2006 1

Upload: others

Post on 08-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Block 37

Red Line

Blue Line

Ran

dolp

h

Was

hing

ton

Subsurface Station at Block 37

Tracks

Block 37

Red Line/Dan Ryan

Brown Line Howard

CTA Capital Construction UpdateAugust 9, 2006 1

Page 2: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Capital Construction Update Agenda

• Red Line/Dan Ryan Rehabilitation Project

• Howard Station Reconstruction

• Brown Line Capacity Expansion Project

2

Page 3: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Red Line/ Dan Ryan Rehabilitation ProjectProject Summary

BUDGET • $282.6 million total budget

SCHEDULE• Phase I: Completed April 20, 2005• Phase II: Completed May 24, 2006• Phase III: NTP April 11, 2005, Completion December 31, 2006

PROJECT GOALS• Eliminate slow zones• Upgrade to bidirectional signal system • Upgrade power delivery system including commissioning of two new

substations at Pershing and 50th Street, and decommissioning of 42nd

substation • Upgrade communications system including installation of new fiber optic

cable throughout the project• Enhance stations’ appearance• Install new elevators at 47th and 69th• Improve bus connections

3

Page 4: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Red Line/ Dan Ryan Rehabilitation ProjectProject Activities

SUBSTATIONS• 50th/Wells substation and 39th/Pershing placed into service April 29,

2006

STATIONS• New platform storage units continue to be installed• New skylight canopy domes are being installed at all locations and

are substantially complete at 55th and 63rd

• Completed Escalator installation at 35th• Completed platform lighting installation at 63rd

• Completed steel erection at 69th Street and construction of staircase• Continued elevator construction at 47th and 69th Street

4

Page 5: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Red Line/ Dan Ryan Rehabilitation Project

Stair installation at 69th Street station 5

Page 6: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

6

Red Line/ Dan Ryan Rehabilitation Project

New staircase steel at 69th Street station

Page 7: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

7

Red Line/ Dan Ryan Rehabilitation Project

Elevator shaft construction at 69th Street station

Page 8: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Howard Station ReconstructionProject Summary

BUDGET • Total CTA budget: $87 million

SCHEDULE• NTP: February 27, 2006• Completion: Spring 2009

PROJECT GOALS• Key station to be made accessible in compliance with the

Americans with Disabilities Act Accessibility Guidelines by December 31, 2010

• Reconstruct Howard station, Rail Operations and Facilities Maintenance facilities

• Infrastructure upgrades will include newly-installed precastconcrete platforms, viaduct repairs, track work, new elevators, and escalators.

8

Page 9: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Howard Station ReconstructionProject Activities

• Completed reconstruction of tracks 1 thru 4

• Completed the installation of South Boulevard crossover

• Continued signalizing the South Boulevard crossover

9

Page 10: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Howard Station Reconstruction

10Reconstruction of tracks 2 and 3

Page 11: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Howard Station Reconstruction

11Reconstruction of track 4

Page 12: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Howard Station Reconstruction

Installation of South Boulevard Crossover 12

Page 13: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Brown Line Capacity Expansion ProjectProject Summary

BUDGET• Total project budget: $529.9 million

SCHEDULE• Project Completion: December 31, 2009• Fullerton ADA Completion: December 31, 2008

PROJECT GOALS• Extend platforms to allow 8-car operations• Make stations ADA compliant• Add elevators to 13 stations• Rehabilitate 18 stations• Restore 8 historic stations• Upgrade signal, communications and power delivery system

13

Page 14: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Brown Line Capacity Expansion Project

Kedzie station glass installation 14

Page 15: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Brown Line Capacity Expansion Project

Rockwell station signal installation 15

Page 16: CTA Capital Construction Update August 9, 20061. Capital Construction Update Agenda • Red Line/Dan Ryan Rehabilitation Project • Howard Station Reconstruction • Brown Line Capacity

Block 37

Red Line

Blue Line

Ran

dolp

h

Was

hing

ton

Subsurface Station at Block 37

Tracks

Block 37

Red Line/Dan Ryan

Brown Line Howard

CTA Capital Construction UpdateAugust 9, 2006 16