Takashi KawabataMETI, Japan May, 2017
産業技術環境局 環境調和産業・技術室03-3501-9271Background
2
Oct 2016 @CSLF Tokyo meeting:Japan proposed to establish Regulation Task Force, and agreed to show the detail at 2017 spring meeting
Aug 2016:CO2 injection must be stopped under the regulation of Marine Pollution Prevention Act (=regulations on the offshore CCS)
To define “REASONABLE” regulations on CCSPurpose of this TF
1.Tomakomai Project Overview2.Marine Pollution Prevention Act3.What happened in Tomakomai4.Purpose of the TF
産業技術環境局 環境調和産業・技術室03-3501-9271Tomakomai Demonstration Project - Schedule
The first large scale CCS demonstration project in Japan has started from April,2016 in Tomakomai, Hokkaido
Approx. 100,000 tons of captured CO2 from gas emissions at an oil refinery will beinjected annually, and demonstration will be conducted on such technologies asstored CO2 monitoring technologies.
4
~2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
SiteSurvey
Preparation- Capture Facility EPC- Drilling Wells- Test Operation etc.
Injection(100,000 tons/y)
MonitoringBaseline
Monitoring
産業技術環境局 環境調和産業・技術室03-3501-9271Capture Facility (Outlook)
5
6
Information Disclosure
Project information (e.g. Total injected CO2 amount) is disclosed at Tomakomai City Hall and on the website of Japan CCS Co. Ltd.
http://www.jccs-tomakomai-monitoring.com/JCCS/index.php/top/
Natural earthquakes and micro seismic events are detected by monitoring, and these results are disclosed.Micro seismic events have been detected regardless CO2
injection, by pre-injection monitoring.
1.Tomakomai Project Overview2.Marine Pollution Prevention Act3.What happened in Tomakomai4.Purpose of the TF
産業技術環境局 環境調和産業・技術室03-3501-9271Regulation
8(Source: Ministry of Environment, @SG40 for LP/LC)
Prohibition of disposal of oils, noxious liquid substances and wastes under seabed (Article 18-7)
Permit issued by Minister of the Environment
be required. (Article 18-8)
1. Oily matter resulting from exploration of mineral resources in seabed and sub-seabed
2.Gases consisting overwhelmingly of CO2over 99% (hydrogen production: over 98%)
Except for
産業技術環境局 環境調和産業・技術室03-3501-9271Application
9(Source: Ministry of Environment, @SG40 for LP/LC)
1. Application form for a disposal permit– Information on the representative of the applicant– Project execution plan– Monitoring plan
2. Attached documents1. Prior assessment on marine environment 2. Site selection3. Explanation for no reasonable measure other than storing in a
formation under seabed4. Financial capability to proceed CCS and monitoring5. Technical capability to proceed CCS and monitoring6. Outline of the project
産業技術環境局 環境調和産業・技術室03-3501-9271Monitoring Phase
10(Source: Ministry of Environment, @SG40 for LP/LC)
Phase 1 : Regular monitoringMonitoring to be normally implemented during the injection phase of CO2 streams
Phase 2 : Precautionary MonitoringMonitoring to judge whether or not a (potential) negative effect on the marine environment have occurred/would occur
Phase 3 : Contingency monitoringContinuous monitoring to watch the event until no negative effect on the marine environment caused by CO2 streams is confirmed.
Exceed the threshold
Exceed the threshold
An applicant must report the monitoring result in each phase to MOE.The threshold for monitoring phase transition should be set by an applicant in the monitoring plan.
Monitoring Programme in Japanese law
1.Tomakomai Project Overview2.Marine Pollution Prevention Act3.What happened in Tomakomai4.Purpose of the TF
産業技術環境局 環境調和産業・技術室03-3501-9271Setting the threshold (1)
12(Source: Ministry of Environment, @SG40 for LP/LC)
According to the survey under operated by MOE…
y = 2E+06x-1.863
R² = 0.7498
150
200
250
300
350
400
450
500
550
600
650
75 80 85 90 95 100 105 110 115
pCO
2(μatm)
DO(%)
monitoring data
累乗 (monitoring data)
Field monitoring data in Tomakomai area (4 years) and fitted curve
The values are stable throughout a year.pCO2 is inversely correlated with DO. Monitoring data for several years can be used for curve fitting.
fitted curve
250
300
350
400
450
500
550
75.0 80.0 85.0 90.0 95.0 100.0 105.0
pCO
2(μatm)
DO (%)
Fitted Curve
Threshold Line (95%prediction interval)
○ monitoring data
産業技術環境局 環境調和産業・技術室03-3501-9271Setting the threshold (2)
13
As the result of the consultation of MOE:
Threshold was set by background monitoring data for 1 year periodin accordance with MOE guideline(8 points, 4 seasons = 32 data)
産業技術環境局 環境調和産業・技術室03-3501-9271Actual Monitored Data
14
The fact is … :
Injection Suspended (under the regulation by the Act);even no CO2 leakage
250
300
350
400
450
500
550
75.0 80.0 85.0 90.0 95.0 100.0 105.0
PCO
2(μatm)
DO (%)
2016 spring survey
2016 spring resurvey
July 2016 Precautionaly Monitoring
Baseline Data
Fitted Curve (Baseline)
Threshold Line
Precautionary Monitoring
産業技術環境局 環境調和産業・技術室03-3501-9271Lessons Learned
15
It’s too difficult to detect CO2 leakage accurately from offshore storage site, from only the marine water environmental data.
Regulators do not always have enough knowledge of CCS.
Too conservative regulations have negative effect on CCS project, as well as its economic performance.
Regulators may have no concern about CCS project itself; only considering about regulation target. (e.g. marine environment)
1.Tomakomai Project Overview2.Marine Pollution Prevention Act3.What happened in Tomakomai4.Purpose of the TF
産業技術環境局 環境調和産業・技術室03-3501-9271Objectives & Outcomes
17
Objectives:To explore practical CCS regulations which contributes to smooth planning, development and operation of CCS projects
Outcomes:A report of case studies, findings and recommendations
産業技術環境局 環境調和産業・技術室03-3501-9271Contents
18
Case studies of- Flexible CCS regulations or flexible enforcement of CCS regulations which resulted in smooth project planning, development or operation, and- Rigid CCS regulations or rigid enforcement of CCS regulations which hindered smooth project planning, development or operation.
Contents of a case study- An outline of the project to be discussed,- A description of regulations to be discussed,- What was happened?- Lessons learned
産業技術環境局 環境調和産業・技術室03-3501-9271Timeline
19
Timeline:
May- early June: to finalize contents of case studies and to identify projects to request submission of a case study
Mid June: to request the identified projects to submit a case study
Early September: to compile case studies
Late October: to finalize a draft findings and recommendations
Early November: to circulate the draft findings and recommendations for comments in the Policy and Technical Groups
Late November: to finalize the report
産業技術環境局 環境調和産業・技術室03-3501-9271