cse404 - week 2 guidance

Upload: lee-tin-yan

Post on 01-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 CSE404 - Week 2 Guidance

    1/38

    The Hong Kong Polytechnic UniversityDepartment of Civil & Environmental Engineering

    CSE404 Design Project Session 2014-2015

    Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    2/38

    2

    Q&A Summary of the Previous Lecture

    1. Available space between basement footprint

    & site boundary?

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    2. Design Ground Water Table?

    - Basement footprintat 1.5m from site

     boundary

    - Hoarding outsidesite boundary

     permitted

    - D.G.W.T at +3.5mPD (i.e. 1.5m below ground)

    - Typical features of a site on reclaimed land

    Basement

    footprint

    Site

    Boundary

  • 8/9/2019 CSE404 - Week 2 Guidance

    3/38

    3

    Progress Report by Group Project Managers (Task E)

    • Concise summary of team’s work within TWO slides for

     presentation within THREE minutes• Submit by e-mail by Monday 12:00

    • Late submission is NOT ENTERTAINED!!

    • To be consolidated in lecture slides (for marking & record)

    • Welcome drawings / sketches / diagrams.

    • Avoid leeeeeeeeeengthy text.

    • Starting next week (26th Jan submission for 27th Jan Workshop)

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    4/38

    Scheme Design Guidance

    Superstructure

  • 8/9/2019 CSE404 - Week 2 Guidance

    5/38

    BUILDING EXAMPLE

    Design ‘Triangle’

    ideas

    scheme

    Full design

  • 8/9/2019 CSE404 - Week 2 Guidance

    6/38

    Lets take a quick look at a building

    • Check stability

    • Use span-depth ratios

    • Estimate vertical forces

    • Use N/A , M/Z

    • Learn some ‘checking stresses’

    • Use design aids – charts and tables

  • 8/9/2019 CSE404 - Week 2 Guidance

    7/38

    Brief 

    • Hospital block 

    • 7.2 - 8m column grid

    • ~Plan area 75m x 50m

    • 5 storeys high

  • 8/9/2019 CSE404 - Week 2 Guidance

    8/38

    Stability •Hospital block •8m column grid

    •Plan area 70m x 50m

    •5 storeys high• Core aspect ratio - 1:7 – 1:12

    We may consider to provide movement joints at 70m spacing

    Each side of movement joint needs a stability system

  • 8/9/2019 CSE404 - Week 2 Guidance

    9/38

    Stability

    MJ

  • 8/9/2019 CSE404 - Week 2 Guidance

    10/38

    Loading?

    Live Load? General usage 3.0kN/m2

    Partitions 1.0kN/m2

    Services & finishes 0.6kN/m2

  • 8/9/2019 CSE404 - Week 2 Guidance

    11/38

    Floor system?

    Suitable systems?

    Depth?

    Self weight?

    RC flat slab

    RC ribbed floor 

    Steel/concrete composite floor 

    Steel/precast composite floor 

    300 – 680mm

    3.5 - 7.2

  • 8/9/2019 CSE404 - Week 2 Guidance

    12/38

    Span/Depth Ratios

    • RC flat slab 24

    • RC ribbed slab 18

    • Steel/concrete composite slab 18

    Steel beams 15

    • Precast slab (inc topping) 33

  • 8/9/2019 CSE404 - Week 2 Guidance

    13/38

    So lets have a quick look at the columns

    What are the loads?

    Live load

    Dead load + Superimposed

    Dead Load

    4.0kN/m2

    17.0 kN/m2

  • 8/9/2019 CSE404 - Week 2 Guidance

    14/38

    Load Take-Down

    ELEMENT DEAD LIVE AREA DEAD LIVE

    Roof 17 2 52 884 104General floor 17 4 52 884 208

    General floor 17 4 52 884 208

    General floor 17 4 52 884 208

    General floor 17 4 52   884 208

    4420 936

    Approximate LOAD TAKE DOWN:

  • 8/9/2019 CSE404 - Week 2 Guidance

    15/38

    Concrete Columns

    ‘Danish Method’

    Factor axial force to take account of moments from the beams of the floorabove

    • Internal columns: Factor 1

    • Edge columns : Factor 1.25

    • Corner columns : Factor 1.5

    • So our basic internal column load is

    1.4x4420 +1.6x936 = 7685kN ~ 8000kN

    • Edge Column supports half the area, but has to take the effect of frame:

    = 8000/2 x 1.25 = 5000kN

    • Remember penultimate columns actually support 1.2 x typical internal columnload

  • 8/9/2019 CSE404 - Week 2 Guidance

    16/38

    Learn ‘Checking Stresses’

    • ‘Design Checking stresses’:

    e.g. 23N/mm2 = Design checking stress for C45

    concrete columns with 2%

    • e.g.~ f cu/2 for f cu

  • 8/9/2019 CSE404 - Week 2 Guidance

    17/38

    Scheming: Summary

    We just had a quick look at scheming. The principles applyto other systems

    • STABILITY

    • PROPORTIONS

    • ESTIMATE FORCES IN KEY ELEMENTS

    • APPROXIMATE STRESS CHECKS

    • DESIGN AIDS AND TABLES

  • 8/9/2019 CSE404 - Week 2 Guidance

    18/38

    Span/Depth Ratios

    • Steel beams 15-20

    20-24

    12-15

    20-30

    20-25

    18-22

    • Steel girders

    • Space frames

    • Composite

    • Concrete floors

    • Timber joisted floors

    So knowing this can we estimate span:depth ratios for:

    •Single span RC bridge?

    •Continuous span, prestressed concrete bridge?

    18:1

    25:1

    30 - 40• Post tensioned slab

  • 8/9/2019 CSE404 - Week 2 Guidance

    19/38

    Scheme Design Guidance

    Foundation Design

  • 8/9/2019 CSE404 - Week 2 Guidance

    20/38

    20

    Foundation Design – Key Issues

    • Loading

    - Gravity- Water (Buoyancy, Flood)

    - Wind

    - Soil

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    21/38

    21

    Foundation Design – Selection

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    22/38

    22

    Foundation Design - Classifications

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    23/38

    23

    Foundation Design – Common Pile types

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    24/38

    24

    Foundation Design – Typical Pile Capacity

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    25/38

    25

    Foundation Design – Basics

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    • Presumed end-bearing capacities / rock friction of bedrock 

    - Foundation CoP 2004, BD

    • Strength of steel / concrete section

    - Concrete CoP 2013, BD

    - Steel CoP 2011, BD

    • Individual Piles vs Pile Group (reduction factor for friction piles)- GEO Publication No. 1/2006

    • Lateral Load Resistance

    - Subgrade vs. raking piles

    - Pile group vs. individual piles- GEO Publication No. 1/2006

    • Testing Method (Dynamic test, proof loading test, proof drilling test)

    - GEO Publication No. 1/2006

  • 8/9/2019 CSE404 - Week 2 Guidance

    26/38

    Scheme Design Guidance

    Excavation and Lateral Support Design

  • 8/9/2019 CSE404 - Week 2 Guidance

    27/38

    27

    ELS Design – Design Consideration

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    • Technical Considerations

    - Location / Ground Condition / Ground Water Condition- Development History --> Obstructions?

    - Adjacent structures / utilities --> risks

    - Ground movement criteria

    • Other Considerations

    - Constructability

    - Time and Cost

    - Flexibility for Basement / Superstructure Design

    - Matching with foundation type

  • 8/9/2019 CSE404 - Week 2 Guidance

    28/38

    28

    ELS Design – Design Consideration

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    29/38

    29

    ELS Design – Building / Ground Movement Control

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    30/38

    30

    ELS Design – Common Wall Types

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    • Steel – Usually Temporary

    - Channel Planking- Sheet Pile Wall

    - Pipe Pile Wall

    - Soldier Pile Wall

    RC – may be permanent- Secant pile wall

    - Bored pile wall

    - Diaphragm wall

    • Water cut-off 

    - Grout Curtain

    - Temporary Wall

    - Pumping Test

  • 8/9/2019 CSE404 - Week 2 Guidance

    31/38

    31

    ELS Design – Common Wall Types

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    32/38

    32

    ELS Design – Systems

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    • Bottom-up construction

    - Cantilevered wall- Braced (cross-lot shoring / raking struts)

    - Tie-back 

    - Hoop action

    • Top-down construction

    - Permanent Slab

    • Hybrid construction method

    - Semi Top-down construction

  • 8/9/2019 CSE404 - Week 2 Guidance

    33/38

    33

    ELS Design – Top-Down / Semi Top-Down

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    34/38

    34

    ELS Design – Difference in Approach

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

  • 8/9/2019 CSE404 - Week 2 Guidance

    35/38

    Scheme Design Guidance

    Recommending a Scheme to the Client

  • 8/9/2019 CSE404 - Week 2 Guidance

    36/38

    36

    Scheme Design – Making a Recommendation

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    Distinct and Viable

    Options!!!

  • 8/9/2019 CSE404 - Week 2 Guidance

    37/38

    37

    Scheme Design – Making a Recommendation

    CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)

    • Features / Flexibility Allowed

    - Benefits to the Client

    • Load Transfer Path

    - Performance of product

    • Ease of Construction

    - Sophisticated temporary works?- Available working Space?

    • Availability of Materials / Skilled Labour 

    • Cost & Time

    • Associated Risk (and their resolution!!!)

  • 8/9/2019 CSE404 - Week 2 Guidance

    38/38

    Scheme Design – Making a Recommendation

    CSE404 D i P j t W k N 2 20th J 2015 (C lt ti )

    Tools: A sketch is more powerful

    than a thousand words

    Tools: Traffic Lights