cse404 - week 2 guidance
TRANSCRIPT
-
8/9/2019 CSE404 - Week 2 Guidance
1/38
The Hong Kong Polytechnic UniversityDepartment of Civil & Environmental Engineering
CSE404 Design Project Session 2014-2015
Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
2/38
2
Q&A Summary of the Previous Lecture
1. Available space between basement footprint
& site boundary?
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
2. Design Ground Water Table?
- Basement footprintat 1.5m from site
boundary
- Hoarding outsidesite boundary
permitted
- D.G.W.T at +3.5mPD (i.e. 1.5m below ground)
- Typical features of a site on reclaimed land
Basement
footprint
Site
Boundary
-
8/9/2019 CSE404 - Week 2 Guidance
3/38
3
Progress Report by Group Project Managers (Task E)
• Concise summary of team’s work within TWO slides for
presentation within THREE minutes• Submit by e-mail by Monday 12:00
• Late submission is NOT ENTERTAINED!!
• To be consolidated in lecture slides (for marking & record)
• Welcome drawings / sketches / diagrams.
• Avoid leeeeeeeeeengthy text.
• Starting next week (26th Jan submission for 27th Jan Workshop)
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
4/38
Scheme Design Guidance
Superstructure
-
8/9/2019 CSE404 - Week 2 Guidance
5/38
BUILDING EXAMPLE
Design ‘Triangle’
ideas
scheme
Full design
-
8/9/2019 CSE404 - Week 2 Guidance
6/38
Lets take a quick look at a building
• Check stability
• Use span-depth ratios
• Estimate vertical forces
• Use N/A , M/Z
• Learn some ‘checking stresses’
• Use design aids – charts and tables
-
8/9/2019 CSE404 - Week 2 Guidance
7/38
Brief
• Hospital block
• 7.2 - 8m column grid
• ~Plan area 75m x 50m
• 5 storeys high
-
8/9/2019 CSE404 - Week 2 Guidance
8/38
Stability •Hospital block •8m column grid
•Plan area 70m x 50m
•5 storeys high• Core aspect ratio - 1:7 – 1:12
We may consider to provide movement joints at 70m spacing
Each side of movement joint needs a stability system
-
8/9/2019 CSE404 - Week 2 Guidance
9/38
Stability
MJ
-
8/9/2019 CSE404 - Week 2 Guidance
10/38
Loading?
Live Load? General usage 3.0kN/m2
Partitions 1.0kN/m2
Services & finishes 0.6kN/m2
-
8/9/2019 CSE404 - Week 2 Guidance
11/38
Floor system?
Suitable systems?
Depth?
Self weight?
RC flat slab
RC ribbed floor
Steel/concrete composite floor
Steel/precast composite floor
300 – 680mm
3.5 - 7.2
-
8/9/2019 CSE404 - Week 2 Guidance
12/38
Span/Depth Ratios
• RC flat slab 24
• RC ribbed slab 18
• Steel/concrete composite slab 18
•
Steel beams 15
• Precast slab (inc topping) 33
-
8/9/2019 CSE404 - Week 2 Guidance
13/38
So lets have a quick look at the columns
What are the loads?
Live load
Dead load + Superimposed
Dead Load
4.0kN/m2
17.0 kN/m2
-
8/9/2019 CSE404 - Week 2 Guidance
14/38
Load Take-Down
ELEMENT DEAD LIVE AREA DEAD LIVE
Roof 17 2 52 884 104General floor 17 4 52 884 208
General floor 17 4 52 884 208
General floor 17 4 52 884 208
General floor 17 4 52 884 208
4420 936
Approximate LOAD TAKE DOWN:
-
8/9/2019 CSE404 - Week 2 Guidance
15/38
Concrete Columns
‘Danish Method’
•
Factor axial force to take account of moments from the beams of the floorabove
• Internal columns: Factor 1
• Edge columns : Factor 1.25
• Corner columns : Factor 1.5
• So our basic internal column load is
1.4x4420 +1.6x936 = 7685kN ~ 8000kN
• Edge Column supports half the area, but has to take the effect of frame:
= 8000/2 x 1.25 = 5000kN
• Remember penultimate columns actually support 1.2 x typical internal columnload
-
8/9/2019 CSE404 - Week 2 Guidance
16/38
Learn ‘Checking Stresses’
• ‘Design Checking stresses’:
e.g. 23N/mm2 = Design checking stress for C45
concrete columns with 2%
• e.g.~ f cu/2 for f cu
-
8/9/2019 CSE404 - Week 2 Guidance
17/38
Scheming: Summary
•
We just had a quick look at scheming. The principles applyto other systems
• STABILITY
• PROPORTIONS
• ESTIMATE FORCES IN KEY ELEMENTS
• APPROXIMATE STRESS CHECKS
• DESIGN AIDS AND TABLES
-
8/9/2019 CSE404 - Week 2 Guidance
18/38
Span/Depth Ratios
• Steel beams 15-20
20-24
12-15
20-30
20-25
18-22
• Steel girders
• Space frames
• Composite
• Concrete floors
• Timber joisted floors
So knowing this can we estimate span:depth ratios for:
•Single span RC bridge?
•Continuous span, prestressed concrete bridge?
18:1
25:1
30 - 40• Post tensioned slab
-
8/9/2019 CSE404 - Week 2 Guidance
19/38
Scheme Design Guidance
Foundation Design
-
8/9/2019 CSE404 - Week 2 Guidance
20/38
20
Foundation Design – Key Issues
• Loading
- Gravity- Water (Buoyancy, Flood)
- Wind
- Soil
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
21/38
21
Foundation Design – Selection
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
22/38
22
Foundation Design - Classifications
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
23/38
23
Foundation Design – Common Pile types
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
24/38
24
Foundation Design – Typical Pile Capacity
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
25/38
25
Foundation Design – Basics
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
• Presumed end-bearing capacities / rock friction of bedrock
- Foundation CoP 2004, BD
• Strength of steel / concrete section
- Concrete CoP 2013, BD
- Steel CoP 2011, BD
• Individual Piles vs Pile Group (reduction factor for friction piles)- GEO Publication No. 1/2006
• Lateral Load Resistance
- Subgrade vs. raking piles
- Pile group vs. individual piles- GEO Publication No. 1/2006
• Testing Method (Dynamic test, proof loading test, proof drilling test)
- GEO Publication No. 1/2006
-
8/9/2019 CSE404 - Week 2 Guidance
26/38
Scheme Design Guidance
Excavation and Lateral Support Design
-
8/9/2019 CSE404 - Week 2 Guidance
27/38
27
ELS Design – Design Consideration
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
• Technical Considerations
- Location / Ground Condition / Ground Water Condition- Development History --> Obstructions?
- Adjacent structures / utilities --> risks
- Ground movement criteria
• Other Considerations
- Constructability
- Time and Cost
- Flexibility for Basement / Superstructure Design
- Matching with foundation type
-
8/9/2019 CSE404 - Week 2 Guidance
28/38
28
ELS Design – Design Consideration
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
29/38
29
ELS Design – Building / Ground Movement Control
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
30/38
30
ELS Design – Common Wall Types
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
• Steel – Usually Temporary
- Channel Planking- Sheet Pile Wall
- Pipe Pile Wall
- Soldier Pile Wall
•
RC – may be permanent- Secant pile wall
- Bored pile wall
- Diaphragm wall
• Water cut-off
- Grout Curtain
- Temporary Wall
- Pumping Test
-
8/9/2019 CSE404 - Week 2 Guidance
31/38
31
ELS Design – Common Wall Types
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
32/38
32
ELS Design – Systems
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
• Bottom-up construction
- Cantilevered wall- Braced (cross-lot shoring / raking struts)
- Tie-back
- Hoop action
• Top-down construction
- Permanent Slab
• Hybrid construction method
- Semi Top-down construction
-
8/9/2019 CSE404 - Week 2 Guidance
33/38
33
ELS Design – Top-Down / Semi Top-Down
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
34/38
34
ELS Design – Difference in Approach
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
-
8/9/2019 CSE404 - Week 2 Guidance
35/38
Scheme Design Guidance
Recommending a Scheme to the Client
-
8/9/2019 CSE404 - Week 2 Guidance
36/38
36
Scheme Design – Making a Recommendation
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
Distinct and Viable
Options!!!
-
8/9/2019 CSE404 - Week 2 Guidance
37/38
37
Scheme Design – Making a Recommendation
CSE404 Design Project – Week No. 2 – 20th January 2015 (Consultation)
• Features / Flexibility Allowed
- Benefits to the Client
• Load Transfer Path
- Performance of product
• Ease of Construction
- Sophisticated temporary works?- Available working Space?
• Availability of Materials / Skilled Labour
• Cost & Time
• Associated Risk (and their resolution!!!)
-
8/9/2019 CSE404 - Week 2 Guidance
38/38
Scheme Design – Making a Recommendation
CSE404 D i P j t W k N 2 20th J 2015 (C lt ti )
Tools: A sketch is more powerful
than a thousand words
Tools: Traffic Lights