CS Faculty Lunch, March 10, 2008CS Faculty Lunch, March 10, 2008
Status of Sutardja Dai Hall
Tentative CITRIS Occupancy Plan
Projected Impact on Soda Hall
Proposed Occupancy Plan for Oct. 08
Proposal: How to Handle Surge Phase
Page 2
Level 1: Computer RoomLevel 1: Computer Room
Page 3
Level 1: CorridorLevel 1: Corridor
Page 4
Level 1: Future “Macro-Lab”Level 1: Future “Macro-Lab”
Page 5
Level 1: Utilities under Marvell LabLevel 1: Utilities under Marvell Lab
Page 6
Level 2: Machinery under Marvell LabLevel 2: Machinery under Marvell Lab
Page 7
Level 2: Pete’s CyberCafeLevel 2: Pete’s CyberCafe
Page 8
Level 2: Atrium StairsLevel 2: Atrium Stairs
Page 9
Level 3: AtriumLevel 3: Atrium
Page 10
Level 3: AuditoriumLevel 3: Auditorium
Page 11
Level 3.5: Lower Marvell Lab Level 3.5: Lower Marvell Lab
(Photolithography)
Page 12
Level 3.5: Marvel Lab (Air Filtration)Level 3.5: Marvel Lab (Air Filtration)
Page 13
Level 4: Carrel Space (W)Level 4: Carrel Space (W)
Page 14
Level 4: Office CorridorLevel 4: Office Corridor
Page 15
Level 5: Carrel Space (E)Level 5: Carrel Space (E)
Page 16
Level 5: Lab AdministrationLevel 5: Lab Administration
Page 17
Level 5: Entry to Marvell LabLevel 5: Entry to Marvell Lab
Page 18
Level 5: Upper Marvell LabLevel 5: Upper Marvell Lab (Diffusion Furnaces)
Page 19
Level 6: TerraceLevel 6: Terrace
Page 20
Level 6: Bridge to CoryLevel 6: Bridge to Cory
Page 21
Level 6: LoungeLevel 6: Lounge
Page 22
Level 6: Carrel Space (E)Level 6: Carrel Space (E)
Page 23
Level 7: Carrel Space (E)Level 7: Carrel Space (E)
Page 24
Level 7: Carrel Space (W)Level 7: Carrel Space (W)
Page 25
Level 7: Elevator ShaftLevel 7: Elevator Shaft
Page 26
Level 7: LoungeLevel 7: Lounge
Page 27
Level 8: Roof with Air HandlersLevel 8: Roof with Air Handlers
Page 28
Level 9: Roof of Elevator PenthouseLevel 9: Roof of Elevator Penthouse
Page 29
Level 9: View of Marvell Lab RoofLevel 9: View of Marvell Lab Roof
Page 30
Street Level: Corner of Marvell LabStreet Level: Corner of Marvell Lab
Page 31
Sutardja-Dai Hall: Status SummarySutardja-Dai Hall: Status Summary
It is real
It is on schedule
Move-in starts January 2009
Grand opening on March 6, 2009
Initial occupancy is being finalized now ...
Page 32
Initial Occupancy -- Phase 1 Move-inInitial Occupancy -- Phase 1 Move-in(tentative)(tentative)
F7: 3 AI-robotics projects: Malik, Fearing, ...
F6: MEMS, sensor appl.: Glaser (CEE), Boser, ...
F5: Lab-proj.: King Liu, Bokor, Majumdar (ME), ...
F4: BID, CNM, TIER, ... : Canny, Niemeyer (AP), Goldberg, Brewer, ...
F3: CITRIS & GLOBE administration; Auditorium.
F2: CyberCafe, Seminar rooms, 24-7 IT room.
F1: Computer room, MacroLab, Motion Capture.
Page 33
Impact on Soda HallImpact on Soda Hall
AI-group (6 Faculty) will move.
TIER (Brewer + 6-8 students) will move.
UNKNOWNS:
Where will “Cyber-Security” end up ?(Tygar, Samuelson (IS), Saxenian (IS) ...)
Where will “Quantum-Computing” reside ?(Vazirani, Kubiatowicz, ...)
Page 36
Minimal-Perturbation Goal-StatesMinimal-Perturbation Goal-States
Trying to consolidate Theory (faculty and students) on Floor 6
Potential to consolidate Security(faculty and students) on Floor 7 or 5
Page 39
How Do We Approach Goal-States ?How Do We Approach Goal-States ?
Discuss more detailed surge plan by Scott McNally.
Discussion about most desirable goal-state should continue through the next weeks and through Spring Retreat.