cronograma de obra edificio

32
CRONOGRAMA DE EJECUCION DE OBRA : PABELLON DE IDIOMAS 1ERA ETAPA DIAGRAMA DE GANTT (TIEMPO DE EJECUCION = 210 DÍAS CALENDARIOS) FASE ACTIVIDAD 1° MES 2° MES 3° MES 4° MES 5° MES 6° MES 7° MES 8° MES PTO SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA 2° SEMANA 3° SEMANA 4° SEMANA SEMANA S/ L M M JV S D LM M J VS D L MM J VS D L MM J V SD L M MJ V S DL M M JV S D LM M JV S D LM M J VS D L MM J V SD L M MJ V S DL M MJ V S DL M M JV S D LM M J VS D L MM J V SD L MM J V SD L M MJ V S DL M M JV S D LM M J VS D LM M J VS D L MM J V SD L M MJ V S DL M M JV S DL M M JV S D LM M J VS D L MM J V SD L M MJ V SD L M MJ V S DL M M JV S D LM M J VS D L M ESTRUCTURAS OBRAS PROVISIONALES CASETA P/GUARDIANIA Y/O DEPOSITO DE MAT. 2,237.40 2,237.40 CERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE E 2,118.00 2,118.00 INSTALACION PROVISIONAL DE ENERGIA ELECTRICA 250.00 250.00 INSTALACION PROVISIONAL DE AGUA 250.00 250.00 CARTELDE OBRA 399.25 399.25 TRABAJOS PRELIMINARES TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTI 3,715.46 3,715.46 MOVIMIENTO DE TIERRAS EXCAVACION MASIVA A MAQUINA EN TERRENO NORMAL"C 19,250.18 19,250.18 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO 45,593.60 45,593.60 DEMOLICION DE ALBAÑILERIA 1,105.77 1,105.77 DEMOLICION DE VEREDAS 2,385.08 2,385.08 RELLENO CON MATERIAL PROPIO SELECCIONADO 22,283.37 22,283.37 RELLENO Y APISONADO CON MATERIAL SELECCIONADO 6,061.75 6,061.75 PERFILADO E=0.15 M 2,801.87 2,801.87 CONCRETO SIMPLE SOLADO PARA LOSA DE FUNDACION MEZCAL 1:12 7,289.88 7,289.88 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS 1,488.34 1,488.34 ENCOFRADO PARA CIMENTACIONES RENDIMIENTO=15 M2/ 1,083.31 1,083.31 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS 823.31 823.31 ENCOFRADO Y DESENCOF. SOBRECIMIENTO DE 0.30 A 0 706.20 706.20 OBRAS DE CONCRETO ARMADO VIGAS DE CIMENTACION Y PLATEA DE CIMENTACION CONCRETO EN VIGAS PLATEA DE CIMENTACION F'C= 21 129,716.94 ### ENCOFRADO Y DESENCOFRADO VIGA Y PLATEA DE CIME 23,487.96 23,487.96 ACERO EN VIGA Y PLATEA DE CIMENTACION GRADO 60 202,280.65 101,140.33 ### TECNOPORT EN JUNTAS 2" 1,031.21 ### MUROS DE CONTENCION REFORZADO CONCRETO EN MURO DE CONTENCION F'C= 210 KG/CM2 17,729.15 17,729.15 ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION 13,872.59 13,872.59 ACERO EN MURO DE CONTENCION GRADO 60 15,940.71 15,940.71 TECNOPORT EN JUNTAS 2" 1,828.02 1,828.02 COLUMNAS CONCRETO EN COLUMNAS F'C=210 KG/CM2 40,557.26 27,038.17 13,519.09 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 22,665.67 15,110.45 7,555.22 ACERO GRADO 60 EN COLUMNAS 211,499.10 140,999.40 70,499.70 COLUMNAS DE AMARRE CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 2,403.37 600.84 ### ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS DE 1,723.16 430.79 ### ACERO GRADO 60 EN COLUMNAS DE AMARRE 2,733.50 683.37 2,050.12 TECNOPORT EN JUNTAS 2" EN COLUMNAS 2,329.45 776.48 1,552.96 VIGAS VIGAS PRINCIPALES Y SECUNDARIAS CONCRETO EN VIGAS F'C=210 KG/CM2 68,086.57 34,043.28 34,043.28 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 43,107.32 21,553.66 21,553.66 ACERO GRADO 60 EN VIGAS 79,313.86 39,656.93 39,656.93 VIGAS DE AMARRE CONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2 1,616.56 808.28 808.28 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AMA 1,342.67 671.34 671.34 ACERO GRADO 60 EN VIGAS DE AMARRE 1,811.71 905.85 905.85 VIGAS DE ESCALERA CONCRETO EN VIGAS DE ESCALERA F'C=210 KG/CM2 473.21 473.21 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 347.53 347.53 ACERO GRADO 60 EN VIGAS 550.79 550.79 VIGAS CHATAS CONCRETO EN VIGAS CHATAS F'C=210 KG/CM2 1,019.90 509.95 509.95 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 467.81 233.90 233.90 ACERO GRADO 60 EN VIGAS 1,942.63 971.32 971.32 VIGAS DE BORDE CONCRETO EN VIGAS DE BORDE F'C=210 KG/CM2 1,404.94 1,404.94 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 1,821.96 ### ACERO GRADO 60 EN VIGAS 2,677.56 2,677.56 LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 54,468.76 27,234.38 27,234.38 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGER 41,177.67 20,588.84 20,588.84 ACERO GRADO 60 EN LOSAS ALIGERADAS 28,059.78 14,029.89 14,029.89 BLOQUE HUECO/CONCRETO 20X15X30 CM PARA TECHO AL 30,512.22 15,256.11 15,256.11 LOSAS MACISAS CONCRETO EN LOSAS SOLIDAS F'C=210 KG/CM2 UNSAAC 4,394.60 2,197.30 2,197.30 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZA 2,379.15 1,189.57 1,189.57 ACERO GRADO 60 EN LOSAS MACIZAS 5,437.02 2,718.51 2,718.51 ESCALERAS CONCRETO EN ESCALERAS F'C=210 KG/CM2 11,132.37 11,132.37 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 10,757.20 10,757.20 ACERO GRADO 60 EN ESCALERAS 21,797.57 21,797.57 PLACAS CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 210 KG 40,760.27 20,380.14 20,380.14 ENCOFRADO Y DESENCOFRADO MUROS TABIQUES Y PLACA 27,476.64 13,738.32 13,738.32 ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS 62,074.35 31,037.18 31,037.18 MUROS Y TABIQUES 1,356,054.13 MURO SOGA LADRILLO DE ARCILLA C/M 1:4 X 1.5C 2,829.69 1,414.84 1,414.84 MURO CABEZA LADRILLO DE ARCILLA C/M 1:5 X 1. 19,622.46 9,811.23 9,811.23 MURO SOGA LADRILLO DE ARCILLA C/M 1:4 X 1.5C 666.14 333.07 333.07 MUROS DE COSTILLA LADRILLO CORRIENTE 393.74 196.87 196.87 REVOQUES ENLUCIDOS Y CIELO RASOS TARRAJEO DEL TIPO RAYADO O PRIMARIO EN INTERIOR 747.72 373.86 373.86 TARRAJEO DEL TIPO RAYADO O PRIMARIO EN EXTERIOR 525.28 262.64 262.64 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-AREN 8,139.27 4,069.63 4,069.63 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 3,363.21 1,681.61 ### TARRAJEO DE SUPERF.VIGAS PERALTADAS-INDEPEND.(E 4,388.92 2,194.46 2,194.46 TARRAJEO DE SUPERF. VIGAS PERALTADAS-INDEPEND.( 10,637.63 ### 5,318.81 TARRAJEO COLUMNAS EXTERIOR C/MORTERO 1:5 X 1.5C 1,776.65 888.32 888.32 TARRAJEO DE COLUMNAS INTERIORES INDEPENDIENTES 4,936.61 2,468.30 2,468.30 TARRAJEO DE PLACAS EN EXTERIORES C:M 1:5 E=2cm 2,912.46 ### ### TARRAJEO DE PLACAS INTERIORES C:M 1:5 E=2cm 10,992.74 5,496.37 5,496.37

Upload: beni-del-toro-gonzales

Post on 27-Oct-2014

1.468 views

Category:

Documents


150 download

DESCRIPTION

Cronograma de edificio en el cusco

TRANSCRIPT

Page 1: Cronograma de Obra Edificio

CRONOGRAMA DE EJECUCION DE OBRA : PABELLON DE IDIOMAS 1ERA ETAPADIAGRAMA DE GANTT (TIEMPO DE EJECUCION = 210 DÍAS CALENDARIOS)

FASE ACTIVIDAD1° MES 2° MES 3° MES 4° MES 5° MES 6° MES 7° MES 8° MES

PTO 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA

S/ L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

ES

TR

UC

TU

RA

S

OBRAS PROVISIONALESCASETA P/GUARDIANIA Y/O DEPOSITO DE MAT. 2,237.40 2,237.40

CERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE EUCALIPT 2,118.00 2,118.00

INSTALACION PROVISIONAL DE ENERGIA ELECTRICA 250.00 250.00

INSTALACION PROVISIONAL DE AGUA 250.00 250.00

CARTELDE OBRA 399.25 399.25

TRABAJOS PRELIMINARESTRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO 3,715.46 3,715.46

MOVIMIENTO DE TIERRASEXCAVACION MASIVA A MAQUINA EN TERRENO NORMAL"C"/RET 19,250.18 19,250.18

ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO NORMA 45,593.60 45,593.60

DEMOLICION DE ALBAÑILERIA 1,105.77 1,105.77

DEMOLICION DE VEREDAS 2,385.08 2,385.08

RELLENO CON MATERIAL PROPIO SELECCIONADO 22,283.37 22,283.37

RELLENO Y APISONADO CON MATERIAL SELECCIONADO 6,061.75 6,061.75

PERFILADO E=0.15 M 2,801.87 2,801.87

CONCRETO SIMPLESOLADO PARA LOSA DE FUNDACION MEZCAL 1:12 7,289.88 7,289.88

CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS 1,488.34 1,488.34

ENCOFRADO PARA CIMENTACIONES RENDIMIENTO=15 M2/DIA 1,083.31 1,083.31

CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS 823.31 823.31

ENCOFRADO Y DESENCOF. SOBRECIMIENTO DE 0.30 A 0.60 MT 706.20 706.20

OBRAS DE CONCRETO ARMADOVIGAS DE CIMENTACION Y PLATEA DE CIMENTACIONCONCRETO EN VIGAS PLATEA DE CIMENTACION F'C= 210 KG/CM 129,716.94 129,716.94

ENCOFRADO Y DESENCOFRADO VIGA Y PLATEA DE CIMENTACI 23,487.96 23,487.96

ACERO EN VIGA Y PLATEA DE CIMENTACION GRADO 60 202,280.65 101,140.33 101,140.33

TECNOPORT EN JUNTAS 2" 1,031.21 1,031.21

MUROS DE CONTENCION REFORZADOCONCRETO EN MURO DE CONTENCION F'C= 210 KG/CM2 17,729.15 17,729.15

ENCOFRADO Y DESENCOFRADO EN MURO DE CONTENCION 13,872.59 13,872.59

ACERO EN MURO DE CONTENCION GRADO 60 15,940.71 15,940.71

TECNOPORT EN JUNTAS 2" 1,828.02 1,828.02

COLUMNAS CONCRETO EN COLUMNAS F'C=210 KG/CM2 40,557.26 27,038.17 13,519.09

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUM 22,665.67 15,110.45 7,555.22

ACERO GRADO 60 EN COLUMNAS 211,499.10 140,999.40 70,499.70

COLUMNAS DE AMARRE CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 2,403.37 600.84 1,802.53

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS DE AM 1,723.16 430.79 1,292.37

ACERO GRADO 60 EN COLUMNAS DE AMARRE 2,733.50 683.37 2,050.12

TECNOPORT EN JUNTAS 2" EN COLUMNAS 2,329.45 776.48 1,552.96

VIGASVIGAS PRINCIPALES Y SECUNDARIASCONCRETO EN VIGAS F'C=210 KG/CM2 68,086.57 34,043.28 34,043.28

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 43,107.32 21,553.66 21,553.66

ACERO GRADO 60 EN VIGAS 79,313.86 39,656.93 39,656.93

VIGAS DE AMARRECONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2 1,616.56 808.28 808.28

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AMARRE 1,342.67 671.34 671.34

ACERO GRADO 60 EN VIGAS DE AMARRE 1,811.71 905.85 905.85

VIGAS DE ESCALERACONCRETO EN VIGAS DE ESCALERA F'C=210 KG/CM2 473.21 473.21

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 347.53 347.53

ACERO GRADO 60 EN VIGAS 550.79 550.79

VIGAS CHATASCONCRETO EN VIGAS CHATAS F'C=210 KG/CM2 1,019.90 509.95 509.95

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 467.81 233.90 233.90

ACERO GRADO 60 EN VIGAS 1,942.63 971.32 971.32

VIGAS DE BORDECONCRETO EN VIGAS DE BORDE F'C=210 KG/CM2 1,404.94 1,404.94

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 1,821.96 1,821.96

ACERO GRADO 60 EN VIGAS 2,677.56 2,677.56

LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 54,468.76 27,234.38 27,234.38

ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADA 41,177.67 20,588.84 20,588.84

ACERO GRADO 60 EN LOSAS ALIGERADAS 28,059.78 14,029.89 14,029.89

BLOQUE HUECO/CONCRETO 20X15X30 CM PARA TECHO ALIGER 30,512.22 15,256.11 15,256.11

LOSAS MACISASCONCRETO EN LOSAS SOLIDAS F'C=210 KG/CM2 UNSAAC 4,394.60 2,197.30 2,197.30

ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZAS 2,379.15 1,189.57 1,189.57

ACERO GRADO 60 EN LOSAS MACIZAS 5,437.02 2,718.51 2,718.51

ESCALERASCONCRETO EN ESCALERAS F'C=210 KG/CM2 11,132.37 11,132.37

ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 10,757.20 10,757.20

ACERO GRADO 60 EN ESCALERAS 21,797.57 21,797.57

PLACAS CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 210 KG/CM2 40,760.27 20,380.14 20,380.14

ENCOFRADO Y DESENCOFRADO MUROS TABIQUES Y PLACAS 27,476.64 13,738.32 13,738.32

ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS 62,074.35 31,037.18 31,037.18

AR

QU

ITE

CT

UR

A

MUROS Y TABIQUES 1,356,054.13MURO SOGA LADRILLO DE ARCILLA C/M 1:4 X 1.5CM. 2,829.69 1,414.84 1,414.84

MURO CABEZA LADRILLO DE ARCILLA C/M 1:5 X 1.5CM. 19,622.46 9,811.23 9,811.23

MURO SOGA LADRILLO DE ARCILLA C/M 1:4 X 1.5CM PARA MU 666.14 333.07 333.07

MUROS DE COSTILLA LADRILLO CORRIENTE 393.74 196.87 196.87

REVOQUES ENLUCIDOS Y CIELO RASOSTARRAJEO DEL TIPO RAYADO O PRIMARIO EN INTERIORES C/MO 747.72 373.86 373.86

TARRAJEO DEL TIPO RAYADO O PRIMARIO EN EXTERIORES 525.28 262.64 262.64

TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA 8,139.27 4,069.63 4,069.63

TARRAJEO EN EXTERIORES CON CEMENTO-ARENA 3,363.21 1,681.61 1,681.61

TARRAJEO DE SUPERF.VIGAS PERALTADAS-INDEPEND.(EN EXTE 4,388.92 2,194.46 2,194.46

TARRAJEO DE SUPERF. VIGAS PERALTADAS-INDEPEND.(EN INTE 10,637.63 5,318.81 5,318.81

TARRAJEO COLUMNAS EXTERIOR C/MORTERO 1:5 X 1.5CM. 1,776.65 888.32 888.32

TARRAJEO DE COLUMNAS INTERIORES INDEPENDIENTES 4,936.61 2,468.30 2,468.30

TARRAJEO DE PLACAS EN EXTERIORES C:M 1:5 E=2cm 2,912.46 1,456.23 1,456.23

TARRAJEO DE PLACAS INTERIORES C:M 1:5 E=2cm 10,992.74 5,496.37 5,496.37

Page 2: Cronograma de Obra Edificio

AR

QU

ITE

CT

UR

ATARRAJEO DE MUROS REFORZADOS C:M 1:5 E=2cm 3,618.55 1,809.28 1,809.28

TARRAJEO DE MURETES EN BARANDAS Y ESCALERAS C:M 1:5 E 762.78 381.39 381.39

TARRAJEO FINO PARA REVESTIMIENTO DE FONDO Y CARAS LATE 2,178.94 726.31 1,452.62

TARRAJEO FINO PARA PIZARRAS UNSAAC 860.03 430.01 430.01

ACTIVIDAD1° MES 2° MES 3° MES 4° MES 5° MES 6° MES 7° MES 8° MES

PTO 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA

S/ L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

VESTIDURA DE DERRAMES 4,699.33 783.22 1,566.44 1,174.83 1,174.83

BRUÑAS DE 1/2" 1,452.12 726.06 726.06

CIELORRASOS EN INTERIOR CON MEZCLA DE CEMENTO-AREN 16,077.19 8,038.60 8,038.60

PISOS Y PAVIMENTOSCONTRAPISO DE 48 MM. 19,119.24 19,119.24

FALSO PISO 4" INCLUYE ENRROCADO 29,026.53 29,026.53

PISO DE TERRAZO CON ESTRIAS DE ALUMINIO 22,708.97 11,354.49 11,354.49

PISO CERAMICO 0.30X0.30 SERIE ORIGENES 1,693.40 1,693.40

PISO CERAMICO SUPERFORTE ALTO TRANSITO 0.30X0.30 16,457.70 16,457.70

VEREDAS DE CONCRETOFC=140 KG/CM2 E=10CM CON EMPEDR 892.31 892.31

SARDINELES FC=175 KG/CM2 DE 15*30 M 546.20 546.20

TAPAJUNTAS METALICO 421.17 421.17

CONTRAZOCALOSCONTRAZOCALO DE TERRAZO E=1CM, H=0.15m 3,586.50 3,586.50

CONTRAZOCALO DE CERAMICO H=0.15m COLOR 4,231.47 4,231.47

ZOCALOSZOCALO DE CERAMICO 20X30 cm 2,329.44 1,164.72 1,164.72

LISTELOS DE 7.5 X 20 cm 1,247.01 623.51 623.51

CARPINTERIA DE MADERAPUERTA DE MELAMINA CON BORDES DE MADERA CEDRO (1 HOJ 6,543.69 6,543.69

PUERTA DE MELAMINA CON BORDES DE MADERA CEDRO Y JAMB 10,140.12 10,140.12

CLOSETS EMPOTRADOS CON MELAMINA DE18MM CORREDIZO 2,138.94 2,138.94

CLOSETS- ESTANTE EMPOTRADOS CON MELAMINA DE18MM C 1,809.48 1,809.48

MAMPARA DE MELAMINA CON MARCOS DE CEDRO Y VIDRIOS 6 5,147.48 5,147.48

BARANDA DE MADERA D=3" CON TUBO ELECTROSOLDADO 1 1/2" 1,588.22 1,588.22

PASAMANO DE MADERA D=3" CON TUBO ELECTROSOLDADO 1 1/2 1,002.80 1,002.80

SEPARADORES DE URINARIOS CON MELAMINA INC INSTALACIO 124.08 124.08

TAPAJUNTAS DE MADERA CEDRO DE 10" X 1/2" 33.54 33.54

CARPINTERIA METALICASEPARADORES DE BAÑO CON MELAMINA CON FIERRO CUADRAD 2,091.68 2,091.68

PUERTAS EN SEPARADORES DE BAÑO CON MELAMINA 469.30 469.30

PUERTA METALICA DE INSPECCION A DUCTOS 195.84 195.84

PIZARRA ACRILICA 7,292.00 7,292.00

REJA METALICA DE PROTECCION VENTANAS ICL. PINT. ANTICO 8,750.28 8,750.28

CERRAJERIABISAGRA CAPUCHINA BRONCEADA DE 3 1/2" X 3 1/2" UNSAAC 980.10 980.10

CERRADURA PARA PUERTAS DE VIDRIO O CRITAL 210.00 210.00

CERRADURA PTA.BAÑO TIPO PERILLAS UNSAAC 782.88 782.88

CERRADURA PARA PUERTA PRINCIPAL UNSAAC 167.22 167.22

CIERRAPUERTAS FRENO HIDRAULICO PUERTAS VIDRIO 2,730.00 2,730.00

PICAPORTES DE FIERRO REDONDO DE 4" 222.32 222.32

VIDRIOS, CRISTALES Y SIMILARESVENTANA VIDRIO CRUDO COLOR GRISS 6mm CON PERFILES DE 2,621.59 2,621.59

VENTANA VIDRIO CRUDO COLOR GRISS 8mm CON PERFILES DE 597.19 597.19

PUERTA DE VIDRIO CRUDO COLOR BRONCE 10mm CON TUBO E 6,006.97 6,006.97

VIDRIOS 6mm 340.06 340.06

VITROVENT 1,913.98 1,913.98

VIDRIO CATEDRAL INCOLORO 47.02 47.02

ESPEJO BISELADO CORRIDO ICL. ARMASON DE MADERA Y SUJ 487.73 487.73

PINTURAPINTURA LATEX EN MUROS INTERIORES UNSAAC 14,127.89 14,127.89

PINTURALATEX EN DERRAMES 939.00 939.00

PINTURA ESMALTE EN PIZARRAS COLOR VERDE 280.71 280.71

INS

TA

LA

CIO

NE

S S

AN

ITA

RIA

S

APARATOS Y ACCESORIOS SANITARIOS 283,623.51INODORO BLANCO CON GRIFERIA Y ACCESORIOS UNSAAC 1,379.00 1,379.00

LAVATORIOS TIPO OVALIN BLANCO INC. MESA DE CONCRETO 1,400.00 1,400.00

LAVATORIOS TIPO MALIBU BLANCO C/P 70.00 70.00

URINARIOS DE LOZA DE PICO BLANCO UNSAAC 218.79 218.79

GRIFERIA DE URINARIOS UNSAAC 120.00 120.00

GRIFERIA DE LAVATORIOS UNSAAC 522.00 522.00

COLOCACION DE APARATOS SANITARIOS UNSAAC 619.68 619.68

GABINETE CONTRAINCENDIOS 1,100.29 1,100.29

RED DE CONEXION A TANQUE E INSTALACION PROVISIONAL AL EDIFICIOSISTEMA DE ALIMENTACIONTUBERIA DE 3" PVC-SAP 864.05 864.05

TEE PVC-SAP 3" * 3/4" 19.92 19.92

CODO PVC SAP 3" 53.44 53.44

TUBERIA PVC SAP C-10 R 3/4" 622.69 622.69

CODO PVC-SAP3/4" 36.64 36.64

SISTEMAS DE CONDUCCIÓN AGUA POTABLE A T. ELEVADO Y CONTRAINCENDIOTUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEBA 108.70 108.70

CODO PVC SAP 2" 26.58 26.58

CODO PVC SAP 2"X45° 13.65 13.65

SISTEMA DE CONTRAINCENDIOTUBERIA FIERRO GALVANIZADO 2 " INSTAL.INC.PRUEBA HIDR. 1,236.38 1,236.38

CODO PVC SAP 2" 93.03 93.03

SISTEMA DE AGUA Y DESAGUESISTEMA DE AGUA FRIASALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" 1,897.50 1,897.50

SISTEMA DE DESAGUE Y VENTILACIONSALIDA DE DESAGÜE DE 2" 2,232.00 1,116.00 1,116.00

SALIDA DE DESAGÜE DE 4" 1,764.37 882.19 882.19

PROVISION E INSTALACION TUBERIA PVC-SAL D=4" + PRUEB.HID 344.03 172.01 172.01

PROVISION E INSTALACION TUBERIA PVC-SAL D=3" + PRUEB.HID 212.26 106.13 106.13

PROVISION E INSTALACION TUBERIA PVC-SAL D=2" + PRUEB.HID 86.13 43.07 43.07

REGISTRO DE BRONCE CROMADO DE 4" 49.71 49.71

REGISTRO DE BRONCE CROMADO DE 3" 81.80 81.80

REGISTRO DE BRONCE 2" 10.53 10.53

SUMIDERO DE BRONCE 2" 60.18 60.18

CODO PVC SAL 4"X45° 65.46 65.46

CODO PVC SAL 3"X45° 147.84 147.84

YEE DE P.V.C. SAL SP,RAMAL CON REDUCCION DE 4"-3" 40.32 40.32

YEE PVC SAL 4" 84.30 84.30

TEE PVC-SAL 3"* 2" 145.20 145.20

COLECTOR DE AGUAS SERVIDAS TRAZO Y REPLANTEO 162.30 162.30

EXCAVACION DE TERRENO P/TUB COLECTOR AGUAS SERVIDAS ( 4,939.19 4,939.19

Page 3: Cronograma de Obra Edificio

INS

TA

LA

CIO

NE

S S

AN

ITA

RIA

SELIMINACION DE EXCESO DE CORTE CON VOLQUETE, CARGUIO 2,358.03 2,358.03

RELLENO CON MATERIAL PROPIO SELECCIONADO 7,091.48 7,091.48

PERFILADO E=0.15 M 127.73 127.73

DEMOLICION DE VEREDAS 46.20 46.20

DEMOLICION DE PAVIMENTO ASFALTICO DE 2" 98.22 98.22

TUBERIA PVC SAL3" 56.82 56.82

TUBERIA PVC SAL4" 38.88 38.88

ACTIVIDAD1° MES 2° MES 3° MES 4° MES 5° MES 6° MES 7° MES 8° MES

PTO 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA 3° SEMANA 4° SEMANA 1° SEMANA 2° SEMANA

S/ L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

TUBERIA PVC SAL 6" 1,342.05 1,342.05

TUBERIA PVC SAL10" 3,691.74 3,691.74

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 10"X20" 172.32 172.32

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 18"X24" 144.01 144.01

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 28"X28" 526.94 526.94

BUZON TIPO I TERR.NORMAL E.D. C/CARG.+VOLQ.HASTA 3.00M 4,881.72 4,881.72

SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 3"- 4" 522.99 522.99

SISTEMA DEDESAGUE DE AGUAS PLUVIALESTUBERIA PVC SAL3" 56.82 56.82

TUBERIA PVC SAL4" 38.88 38.88

ACCESORIOS DE FIJACION DE RECUBRIMIENTO DE MONTANTES 557.16 ###

TARRAJEO DE RECUBRIMIENTO DE MONTANTES C:M 1:5 E=1.5c 1,924.91 1,924.91

CODO PVC SAL 4"X45° 10.91 10.91

CODO PVC SAL 3"X45° 24.64 24.64

TEE PVC SAL 4" 15.17 15.17

TEE PVC-SAL 3" 10.42 10.42

SISTEMA COLECTOR DE AGUAS DE PLUVIALESTRAZO Y REPLANTEO 239.17 239.17

EXCAVACION DE TERRENO P/TUB COLECTOR AGUAS SERVIDAS ( 3,974.06 3,974.06

ELIMINACION DE EXCESO DE CORTE CON VOLQUETE, CARGUIO 1,459.35 1,459.35

RELLENO CON MATERIAL PROPIO SELECCIONADO 5,705.79 5,705.79

PERFILADO E=0.15 M 231.54 231.54

TUBERIA PVC SAL3" 44.60 44.60

TUBERIA PVC SAL4" 378.43 378.43

TUBERIA PVC SAL 6" 1,369.51 1,369.51

TUBERIA PVC SAL10" 5,856.89 5,856.89

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 10"X20" 258.48 258.48

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 12"X24" 121.20 121.20

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 18"X24" 144.01 144.01

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 24"X24" 579.39 579.39

CAJA DE REGISTRO DE DESAGUE C/TAPA Cº 28"X28" 263.47 263.47

BUZON TIPO I TERR.NORMAL E.D. C/CARG.+VOLQ.HASTA 2.00M 1,030.20 1,030.20

BUZON TIPO I TERR.NORMAL E.D. C/CARG.+VOLQ.HASTA 3.00M 1,220.43 1,220.43

SALIDA DE DESAGÜE DE 3" 149.40 149.40

INS

TA

LA

CIO

NE

S E

LE

CT

RIC

AS

INSTALACIONES ELECTRICAS 67,591.92LINEA DE ALIMENTACION PRINCIPAL Y A TABLEROS DE DISTRIBUCION

TUBERIAS PVC SAP (ELECTRICAS) D=2" 636.23 636.23

TUBERIAS PVC SAP (ELECTRICAS) D=3" - ALIMENTACION 2,004.62 2,004.62

CABLE ELECTRICO NYY 3 X 70 MM2. 2,562.00 2,562.00

CABLE ELECTRICO NYY 3 X 6 MM2. 258.45 258.45

CABLE NYY 3 X 10 MM2 - ALIMENTACION 1,036.21 1,036.21

CABLE ELECTRICO NYY 3X25 MM2. A TABL. DIST. 1,334.34 1,334.34

CABLE ELECTRICO NYY 1X16 MM2 A TABL. DISTRIB. 718.62 718.62

CABLE ELECTRICO NYY 3X16 MM2. A TABL. DISTRIB. 790.16 790.16

TUBERIAS PVC SAP (ELECTRICAS) D=2" 1,168.16 1,168.16

TUBERIAS PVC SAP (ELECTRICAS) D=3" 2,373.61 2,373.61

EXCAVACION PARA POZO DE TIERRA 101.75 101.75

POZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB, 1,829.88 1,829.88

EXCAVACION 138.03 138.03

RELLENO CON MAT FILTRANTE 45.30 45.30

RELLENO COMPACTADO A MANO 107.94 107.94

LADRILLO DE ARCILLA CORRIENTE 239.20 239.20

TABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y C 1,154.79 1,154.79

INTERRUPTORES TERMOMAGNETICOS 2,406.83 2,406.83

SISTEMA DE DISTRIBUCIONSALIDA DE TOMACORRIENTE CON PUESTA TIERRA 4,327.68 2,163.84 2,163.84

SALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRA sin ca 3,760.00 1,880.00 1,880.00

SALIDA PARA TOMACORRIENTES MONOFASICO EN PISO 455.40 227.70 227.70

SALIDA PARA TOMACORRIENTES MONOFASICO EN PISO sin cablead 274.20 137.10 137.10

SALIDA PARA TOMACORRIENTE AH=1.80 m 60.72 30.36 30.36

SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC sin cable 109.68 54.84 54.84

SALIDA DE TECHO TW 4.0mmUNSAAC 3,817.80 1,908.90 1,908.90

SALIDA DE TECHO TW 4.0mmUNSAAC sin cableado ni acces. 3,887.84 1,943.92 1,943.92

SALIDA DE PARED (BRAQUETES) CON PVC 1,271.51 635.76 635.76

SALIDA DE PARED (BRAQUETES) CON PVC sin cableado ni acces. 1,106.84 553.42 553.42

CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA 159.00 79.50 79.50

LUMINARIASLAMPARA FLUORESCENTE SIMPLE ADOSADA A PARED 684.00 684.00

LAMPARA FLUORESCENTE SIMPLE ADOSADA A CIELO RASO 205.20 205.20

LAMPARA FLUORESCENTE DOBLE CON REJILLA ADOSADA A CIE 3,242.40 3,242.40

LUMINARIA CEILING LIGTH CLR 304 DE 60 W O EQUIVALENTE 1,937.60 1,937.60

LUMINARIA WALL SPOTLIGTH 1*50 W O EQUIVALENTE 574.20 574.20

LUMINARIA WALL SPOTLIGTH 3*50 W O EQUIVALENTE 477.60 477.60

REFLEXTOR LAMPARA HALOGENA DE 150 W PISO 636.80 636.80

LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A° 1,356.80 1,356.80

LAMPARA INCANDECENTE DE 50w 59.40 59.40

FOTOCELULAS RELOJ 111.53 ###

INSTALACIONES ESPECIALESINTERNETSALIDA PARA RED INFORMATICA 2,519.20 1,259.60 1,259.60

CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA INTERN 37.20 18.60 18.60

TUBERIAS PVC SAP (ELECTRICAS) D=1 1/2" 608.61 304.30 304.30

TV CABLESALIDA PARA TELEVISION - CABLE 464.52 232.26 232.26

CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA TV-CAB 43.40 21.70 21.70

TUBERIAS PVC SAP (ELECTRICAS) D=2" 774.11 387.06 387.06

TELEFONO DIRECTO E INTERNOSALIDA PARA TELEFONIA INTERNA 66.96 33.48 33.48

TUBERIAS PVC SAP (ELECTRICAS) D=1" 126.17 63.09 63.09

TUBERIAS PVC SAP (ELECTRICAS) D=2" 357.12 178.56 178.56

CAJA DE PASO METALICA DE 400X250X50 MM. INC. TAPA TELEFO 63.86 31.93 31.93

LUZ DE EMERGENCIA

Page 4: Cronograma de Obra Edificio

INS

TA

LA

CIO

NE

S E

LE

CT

RIC

AS

SALIDA DE PARED (BRAQUETES) CON PVC PARA EMERGENCIA 147.85 73.93 73.93

TUBERIAS PVC SAP (ELECTRICAS) D=1 1/2" PARA EMERGENCIA 702.24 351.12 351.12

CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA EMERGENCIA 159.00 79.50 79.50

ALARMA CONTRAINCENDIOSALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMA 239.04 ### ###

TUBERIAS PVC SAP (ELECTRICAS) D=1 1/2" PARA EMERGENCIA 147.90 73.95 73.95

53,879.50

1,761,149.06 188,638.56 451,121.07 395,825.12 230,491.88 295,038.43 118,624.78 58,728.14 22,681.07

Page 5: Cronograma de Obra Edificio

2,237.402,118.00

250.00250.00399.25

3,715.46

19,250.1845,593.60

1,105.772,385.08

22,283.376,061.752,801.87

7,289.881,488.341,083.31

823.31706.20

129,716.9423,487.96

202,280.651,031.21

17,729.1513,872.5915,940.71

1,828.02

40,557.2622,665.67

211,499.10

2,403.371,723.162,733.502,329.45

68,086.5743,107.3279,313.86

1,616.561,342.671,811.71

473.21347.53550.79

1,019.90467.81

1,942.63

1,404.941,821.962,677.56

54,468.7641,177.6728,059.7830,512.22

4,394.602,379.155,437.02

11,132.3710,757.2021,797.57

40,760.2727,476.6462,074.35

2,829.6919,622.46

666.14393.74

747.72525.28

8,139.273,363.214,388.92

10,637.631,776.654,936.612,912.46

10,992.74

Page 6: Cronograma de Obra Edificio

3,618.55762.78

2,178.94860.03

4,699.331,452.12

16,077.19

19,119.2429,026.5322,708.97

1,693.4016,457.70

892.31546.20421.17

3,586.504,231.47

2,329.441,247.01

6,543.6910,140.12

2,138.941,809.485,147.481,588.221,002.80

124.0833.54

2,091.68469.30195.84

7,292.008,750.28

980.10210.00782.88167.22

2,730.00222.32

2,621.59597.19

6,006.97340.06

1,913.9847.02

487.73

14,127.89939.00280.71

1,379.001,400.00

70.00218.79120.00522.00619.68

1,100.29

864.0519.9253.44

622.6936.64

108.7026.5813.65

1,236.3893.03

1,897.50

2,232.001,764.37

344.03212.26

86.1349.7181.8010.5360.1865.46

147.8440.3284.30

145.20

162.304,939.19

Page 7: Cronograma de Obra Edificio

2,358.037,091.48

127.7346.2098.2256.8238.88

1,342.053,691.74

172.32144.01526.94

4,881.72522.99

56.8238.88

557.161,924.91

10.9124.6415.1710.42

239.173,974.061,459.355,705.79

231.5444.60

378.431,369.515,856.89

258.48121.20144.01579.39263.47

1,030.201,220.43

149.40

636.232,004.622,562.00

258.451,036.211,334.34

718.62790.16

1,168.162,373.61

101.751,829.88

138.0345.30

107.94239.20

1,154.792,406.83

4,327.683,760.00

455.40274.20

60.72109.68

3,817.803,887.841,271.511,106.84

159.00

684.00205.20

3,242.401,937.60

574.20477.60636.80

1,356.8059.40

111.53

2,519.2037.20

608.61

464.5243.40

774.11

66.96126.17357.12

63.86

Page 8: Cronograma de Obra Edificio

147.85702.24159.00

239.04147.90

1,761,149.06

1,761,149.06

Page 9: Cronograma de Obra Edificio

FASE ACTIVIDAD1° MES 2° MES 3° MES 4° MES

LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2

ES

TR

UC

TU

RA

S

OBRAS PROVISIONALESCERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE EUCA 0.50INSTALACION PROVISIONAL DE AGUA 0.50INSTALACION PROVISIONAL DE ENERGIA ELECTRICA 1.00CARTELDE OBRA 1.00ENCOFRADO Y DESENCOFRADO PARA PROTECCION DE DUC 1.00TRABAJOS PRELIMINARESTRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTI 4.00OBRAS DE CONCRETO ARMADOCOLUMNAS CONCRETO EN COLUMNAS F'C=210 KG/CM2 4.00ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 16.00ACERO GRADO 60 EN COLUMNAS 12.00 TECNOPORT EN JUNTAS 2" EN COLUMNAS 2.00COLUMNAS DE AMARRE CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 4.00ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS D 4.00ACERO GRADO 60 EN COLUMNAS DE AMARRE 4.00VIGAS CONCRETO EN VIGAS F'C=210 KG/CM2 4.00ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 40.00ACERO GRADO 60 EN VIGAS 25.00VIGAS DE AMARRE CONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2 4.00ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AM 4.00ACERO GRADO 60 EN VIGAS DE AMARRE 4.00PLACAS CONCRETO EN PLACAS F'C= 210 KG/CM2 2.00ENCOFRADO Y DESENCOFRADO EN PLACAS 4.00ACERO GRADO 60 EN PLACAS 4.00LOSAS ALIGERADAS CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 5.00ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGE 27.00ACERO GRADO 60 EN LOSAS ALIGERADAS 20.00BLOQUE HUECO/CONCRETO 15X20X30 CM PARA TECHO AL 7.00LOSAS SOLIDAS PLEGADAS CONCRETO EN LOSAS SOLIDAS PLEGADAS F'C=210 KG/CM2 4.00ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS SOLIDA 4.00ACERO GRADO 60 EN LOSAS SOLIDAS PLEGADAS 4.00ESCALERAS CONCRETO EN ESCALERAS F'C=210 KG/CM2 1.00ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 3.00ACERO GRADO 60 EN ESCALERAS 2.00RAMPACONCRETO EN RAMPAS F'C=210 KG/CM2 2.00ENCOFRADO Y DESENCOFRADO EN RAMPAS 6.00ACERO GRADO 60 EN RAMPAS 6.00PARAPETOSCONCRETO EN PARAPETO F'C= 210 KG/CM2 2.00ENCOFRADO Y DESENCOFRADO ENPARAPETO 8.00ACERO ENPARAPETO GRADO 60 4.00

AR

QU

ITE

CT

UR

A

MUROS Y TABIQUES DE ALBAÑILERIAMURO DE BLOQUE HUECO DE CONCRETO e=15 cm, mezcla 1:5 12.00MURO DE BLOQUE HUECO DE CONCRETO e=30 cm, mezcla 1:5 30.00REVOQUES, ENLUCIDOS Y MOLDURASTARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5 6.00TARRAJEO FINO unsaac 42.00TARRAJEO FROTACHADO CON CEMENTO-ARENA UNSAAC 30.00TARRAJEO DE COLUMNAS C:M 1:5 E=2cm 42.00TARRAJEO DE VIGAS PERALTADAS 48.00TARRAJEO DE PLACAS INT. C:M 1:5 E=2cm 3.00TARRAJEO DE ESCALERAS C:A 1:5 20.00TARRAJEO DE PARAPETOS EN RAMPAS Y ESCALERASC:M 1: 27.00VESTIDURA DE DERRAMES 24.00BRUÑAS 24.00TARRAJEO FINO EN CIELORRASOS CON MEZCLA DE CEME 54.00TARRAJEO FROTACHADO EN CIELORRASOS CON MEZCLA D 24.00PISOS Y PAVIMENTOSCONTRAPISO DE 48 MM. 24.00PISO DE TERRAZO CON ESTRIAS DE ALUMINIO E= 2.50 cm 54.00PISO DE PARQUET HUAYACAN 6 X 30 CM VETEADO 60.00PISO CERAMICO 0.30X0.30 12.00PISO CERAMICO VITRIFICADO ALTO TRANSITO ANTIDESLIZAN 10.00REVESTIMIENTO DE GRADAS CON TERRAZO ICL. CANTONER 11.00TAPAJUNTAS METALICO 12.00CONTRAZOCALOSCONTRAZOCALO DE TERRAZO C/PERFILES DE ALUMINIO 48.00CONTRAZOCALO DE MADERA AGUANO DE 4" x 3/4" C/RODON DE 3/4" 12.00CONTRAZOCALO DE MADERA AGUANO DE 6" x 3/4" C/RODON DE 3/4" 2.00CONTRAZOCALO CERAMICO 1.00ZOCALOSZOCALO DE CERAMICO DE 30x30cm. 18.00LISTELO TIPO CINTILLO DE 0.015x0.30m. 2.00CUBIERTASCOBERTURA DE TEJAS SOBRE TIJERALES DE MADERA Y CORREAS 14.00COBERTURA DE POLICARBONATO SOBRE ESTRUCT METALICA 5.00MURO LADRILLO SOGA 9.00TARRAJEO DE PARAPETOS DE TECHO 14.00TARRAJEO CON IMPERMEABILIZANTE EN CANALES DE TECHO 6.00CANALETA DE LATON 2.00SUMIDERO DE BRONCE DE 6" 2.00CARPINTERIA DE MADERAPUERTA DE MELAMINA CON BORDES DE MADERA AGUANO e=45mm. 12.00ASIENTOS DE MADERA SOBRE TUBO DE 2" Y PERFILES DE 12.00CARPINTERIA METALICAPUERTA DE VIDRIO CRUDO 8mm CON BORDES DE TUBO DE 6.00SEPARADORES METALICOS DE BAÑO e= 2.50MM 6.00SEPARADORES DE URINARIOS METALICO e= 6MM INC INST 6.00BARANDAS METALICAS DE TUBO 2" CON FIERRO LISO DE 5/ 12.00TUBO DECORATIVO DE FIERRO DE 4" PINTADO DE COLOR A 12.00ANCLADO CON ANGULAR ESTRIADO DE 1 1/2" X 1 1/2" X 1/ 12.00PLATAFORMAS DE DESCANSO TIPO CANASTILLA 1.00ESCALERA DE GATO METALICA 5.00PIZARRA ACRILICA 2.00CERRAJERIACERRADURA TIPO PERILLAS TIPO FORTE 12.00CERRADURA DE POMO PARA PUERTAS DE VIDRIO O CRITAL 12.00CERRADURA PARA PISO EN PUERTAS DE VIDRIO SIMILAR A 12.00BISAGRA CAPUCHINA ALUMINIZADA DE 4" X 4" UNSAAC 12.00CERROJO DE FIERRO REDONDO DE 5/8" X 0.60 M. 1.00CERROJO DE FIERRO REDONDO DE 5/8" X 0.35 M. 1.00PICAPORTES DE FIERRO REDONDO DE 4" 1.00VIDRIOS, CRISTALES Y SIMILARESVENTANA VIDRIO CRUDO TRASLUCIDO 8mm INCL ACCESOR 8.00VENTANA VIDRIO PAVONADO 8mm INCL ACCESORIOS 1.00VIDRIOS PAVONADO DE 8mm EN PUERTAS 1.00

Duración(días)

Page 10: Cronograma de Obra Edificio

AR

QU

ITE

CT

UR

AVIDRIO CRUDO 8mm TRASLUCIDO EN PUERTAS 1.00MAMPARA DE VIDRIO CRUDO 8mm C/TUBO ELECTROSOLDADO10.00PUERTA DE VIDRIO CRUDO 8mm 3.00ESPEJO BISELADO CON MARCO DE ALUMINIO 3.00PINTURAPINTURA LATEX EN MUROS INTERIORES UNSAAC 30.00PINTURALATEX EN MUROS EXTERIORES 24.00PINTURA VINILICA EN COLUMNAS , VIGAS Y/O PLACAS 30.00PINTURA VINILICA EN ESCALERAS, RAMPAS Y PARAPETOS 24.00PINTURA LATEX EN CIELORRASOS UNSAAC 21.00PINTURALATEX EN DERRAMES 3.00

INS

TA

LA

CIO

NE

S S

AN

ITA

RIA

S

APARATOS Y ACCESORIOS SANITARIOSINODORO BLANCO CON ACCESORIOS 6.00LAVATORIOS TIPO OVALIN BLANCO SOBRE MESA DE CONCRETO 6.00URINARIOS DE LOZA DE PICO BLANCO 6.00GRIFERIA DE URINARIOS UNSAAC 4.00GRIFERIA DE LAVATORIOS UNSAAC 1.00COLOCACION DE APARATOS SANITARIOS 1.00PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO 1.00GABINETE CONTRAINCENDIOS 1.00SISTEMA DE AGUA FRIA Y CONTRA INCENDIOREDES DE DISTRIBUCION DE AGUA FRIA Y CONTRAINCENDIOTUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEBA HIDR 1.00VALVULA DE COMPUERTA 1 1/2" 2.00REDUCCION PVC SAP DE 2" A 1 1/2" 2.00REDUCCION PVC SAP DE 1 1/2" A 3/4"TEE PVC-SAP 1 1/2" 2.00CODO PVC SAP 2" 2.00CODO PVC-SAP 1 1/2" 2.00TUBERIA DE AGUA PVC. DE 2"(50MM) ISIST CONTRAINCENDIO 2.00TEE PVC-SAP 2"* 2" 2.00SISTEMA DE AGUA FRIASALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 3/4" 1.00SISTEMA DE DESAGUE Y VENTILACIONREDES DE DISTRIBUCION DE DESAGUE Y VENTILACIONSALIDA DE DESAGÜE DE 2" 4.00SALIDA DE DESAGÜE DE 4" 1.00PROVISION E INSTALACION TUBERIA PVC-SAL D=4" + PRUEB.HIDRPROVISION E INSTALACION TUBERIA PVC-SAL D=2" + PRUEB.HIDR 2.00TEE PVC SAL 4" 2.00TEE PVC SAL 2" 2.00CODO DE PVC SAL SP DE 4" 2.00SOMBRERO PARA VENTILACION DE P.V.C. DE 2" 2.00REGISTRO DE BRONCE CROMADO DE 4" 2.00REGISTROS DE BRONCE DE 2" 2.00SUMIDERO DE BRONCE 2" 2.00SISTEMA DE AGUAS PLUVIALESRED DE DISTRIBUCION DE AGUAS PLUVIALESSALIDA SUMIDERO REJILLA 0.10m x 0.10m EN TECHO 14.00SALIDA DE DESAGÜE DE 4"TUBERIA PVC SAL4" 1.00CONCRETO EN FALSA COLUMNA F'C=140 KG/CM2 RECUBRIMIENTO DE 1.00ENCOFRADO EN COLUMNAS RECUBRIMIENTO DE MONTANTES 1.00TARRAJEO DE RECUBRIMIENTO DE MONTANTES C:M 1:5 E=1.5cm 4.00CONFORMACIÓN DE FONDOS EN CANALES DE TECHOCODO PVC SAL 4" 5.00TEE PVC SAL 4" 6.00EQUIPOHIDRONEUMATICO DE 120 GLN DE 20-40 LB DE PRESIONELECTROBOMBA DE 1.5 HP

INS

TA

LA

CIO

NE

S E

LE

CT

RIC

AS

INSTALACIONES ELECTRICASLINEA DE ALIMENTACIONTUBERIAS PVC SAP (ELECTRICAS) D=3/4"CABLE ELECTRICO TW AWG NO. 12CABLE ELECTRICO TW AWG-MCM NO. 14 -2.5 MM2.EXCAVACIONPOZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB,TOMACORRTABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y CERRADURA PARA 8TERMOMAGNETICOS TIPO ENGRAMPEINTERRUPTOR TERMOMAGNETICO 2X20ASISTEMA DE DISTRIBUCIONSALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRASALIDA DE TECHO TW 4.0mmUNSAACCAJA DEPASO F°G° 200X200X30 MM. INC. TAPACAJA DE PASO CUADRADO CAJA DE PASO CIRCULAR LUMINARIASLAMPARA FLUORESCENTE DOBLE PARA EMPOTRAR DE 40WLAMPARA FLUORESCENTE DOBLE CON REJILLA ADOSADA A CIELORASOLAMPARA FLUORESCENTE CIRCULAR PARA DOSAR CON DIFUSORLAMPARA FLUORESCENTE DOBLE PARA ADOSAR 40WLAMPARA HALOGENA FLOOD LIGTH DE 150 W O EQUIVALENTEREFLEXTOR LAMPARA HALOGENA DE 75 W CIELO RASOLAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A°INSTALACIONES ESPECIALESINTERNETSALIDA PARA RED INFORMATICACAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA INTERNETTELECONFERENCIASSALIDA PARA TELECONFERENCIASCAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA TV-CABLEALARMA CONTRAINCENDIOSALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMACAJA DE PASO CUADRADO PARLANTESSALIDA DE PARLANTESCAJA DE PASO CUADRADO

OB

RA

S E

XT

ER

IOR

ES

OBRAS PRELIMINARESTRAZO Y REPLANTEO DURANTE UNSAACREUBICACION DE ESTRUCTURAS DE CONCRETOELIMINACION DE ARBOLESREUBICACION DE POSTES DE LUZMOVIMIENTO DE TIERRASEXCAVACION MASIVA A MAQUINA CORTE Y EXCAVACION MANUAL DEMOLICION ESTRUCTURA DE CONCRETOPICADO DE MURO DE CONCRETO (JARDINERA)REMOSION DE PAVIMENTO- VEREDASPICADO DE PAVIMENTO PARA NUEVO VACIADORELLENO CON MATERIAL PROPIO SELECCIONADOELIMINACION DE DESMONTE,COMPACTADO Y APISONADO CON MAT. SELECCIONADOPERFILADO E=0.15 MCONCRETO SIMPLEMURO-SARDINEL FC=140 KG/CM2 DE 0.30*1.20 MSARDINELES FC=175 KG/CM2 DE H= 15 E=30 MSARDINELES FC=175 KG/CM2 DE 15*10 M

Page 11: Cronograma de Obra Edificio

OB

RA

S E

XT

ER

IOR

ES

MURO DE C° C° REVESTIDO CON LAJA GRADA DE CONCRETO 175 KG/CM2BANCAS DE CONCRETO CICLOPEO TARRAJEADAS MURO DE CONTENCION C° C° TIPO BANCA REVESTIDOCUNETAS REVESTIDAS EVAC. PLUVIAL OBRAS DE ARTE CONCRETO ARMADO MURO DE CONTENCION CONCRETO ARMADO TIPO 1 H=2.50 MURO DE CONTENCION CONCRETO ARMADO TIPO2 H=1.20TAPA DE CANAL CONCRETO ARMADO ANCHO=0.70MRAMPA TAPA DE CANAL CONCRETO ARMADO BANCAS MADERA C/SOPORTE DE C° A° INCL PINTADOREJILLA FIERRO ANGULAR 3/4" Y FIERRO DE 1/2" PAVIMENTO Y VEREDASASENTADO DE BLOCK GRASS DE CONCRETO PISO SEMIRIGIDO BLOQUES DE CONCRETO S/ CAMA ARENAPISO DE TERRAZO CON ESTRIAS DE ALUMINIOPAVIMENTO/VEREDAS DE C° FC=175 KG/CM2 REPOSICION DE PISOS CONCRETO E=2" C:A 1:2 UNSAACBRUÑAS JARDINESNIVELACION CON TIERRA AGRICOLA Y ARENASEMBRADOD E GRASSPLANTACION DE ARBOLESVARIOSLAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A°LIMPIEZA DE OBRA UNSAAC

Page 12: Cronograma de Obra Edificio

4° MES 5° MES 6° MESMI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Page 13: Cronograma de Obra Edificio
Page 14: Cronograma de Obra Edificio
Page 15: Cronograma de Obra Edificio

FASE ACTIVIDAD TOTAL

1° MES 2° MES

LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

ES

TR

UC

TU

RA

S

OBRAS PROVISIONALES

CERCO PROVISIONAL CON ARPILLERA Y ROLLIZOS DE EUCALIPTO 0.50

INSTALACION PROVISIONAL DE AGUA 0.50

INSTALACION PROVISIONAL DE ENERGIA ELECTRICA 1.00

CARTELDE OBRA 1.00

ENCOFRADO Y DESENCOFRADO PARA PROTECCION DE DUCTOS PASILLO 1.00

TRABAJOS PRELIMINARES

TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO 4.00

OBRAS DE CONCRETO ARMADO

COLUMNAS

CONCRETO EN COLUMNAS F'C=210 KG/CM2 4.00

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 16.00

ACERO GRADO 60 EN COLUMNAS 12.00

TECNOPORT EN JUNTAS 2" EN COLUMNAS 2.00

COLUMNAS DE AMARRE

CONCRETO EN COLUMNAS DE AMARRE F'C=175 KG/CM2 4.00

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS DE AMARRE 4.00

ACERO GRADO 60 EN COLUMNAS DE AMARRE 4.00

VIGAS

CONCRETO EN VIGAS F'C=210 KG/CM2 4.00

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 40.00

ACERO GRADO 60 EN VIGAS 25.00

VIGAS DE AMARRE

CONCRETO EN VIGAS DE AMARRE F'C=210 KG/CM2 4.00

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE AM ARRE 4.00

ACERO GRADO 60 EN VIGAS DE AMARRE 4.00

PLACAS

CONCRETO EN PLACAS F'C= 210 KG/CM2 2.00

ENCOFRADO Y DESENCOFRADO EN PLACAS 4.00

ACERO GRADO 60 EN PLACAS 4.00

LOSAS ALIGERADAS

CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 5.00

ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 27.00

Page 16: Cronograma de Obra Edificio

ES

TR

UC

TU

RA

S

ACERO GRADO 60 EN LOSAS ALIGERADAS 20.00

BLOQUE HUECO/CONCRETO 15X20X30 CM PARA TECHO ALIGERADO 7.00

LOSAS SOLIDAS PLEGADAS

CONCRETO EN LOSAS SOLIDAS PLEGADAS F'C=210 KG/CM2 4.00

ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS SOLIDAS PLEGADAS 4.00

ACERO GRADO 60 EN LOSAS SOLIDAS PLEGADAS 4.00

ESCALERAS

CONCRETO EN ESCALERAS F'C=210 KG/CM2 1.00

ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 3.00

ACERO GRADO 60 EN ESCALERAS 2.00

RAMPA

CONCRETO EN RAMPAS F'C=210 KG/CM2 2.00

ENCOFRADO Y DESENCOFRADO EN RAMPAS 6.00

ACERO GRADO 60 EN RAMPAS 6.00

PARAPETOS

CONCRETO EN PARAPETO F'C= 210 KG/CM2 2.00

ENCOFRADO Y DESENCOFRADO ENPARAPETO 8.00

ACERO ENPARAPETO GRADO 60 4.00

AR

QU

ITE

CT

UR

A

MUROS Y TABIQUES DE ALBAÑILERIA

MURO DE BLOQUE HUECO DE CONCRETO e=15 cm, mezcla 1:5 12.00

MURO DE BLOQUE HUECO DE CONCRETO e=30 cm, mezcla 1:5 30.00

REVOQUES, ENLUCIDOS Y MOLDURAS

TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5 UNSAAC 6.00

TARRAJEO FINO unsaac 42.00

TARRAJEO FROTACHADO CON CEMENTO-ARENA UNSAAC 30.00

TARRAJEO DE COLUMNAS C:M 1:5 E=2cm 42.00

TARRAJEO DE VIGAS PERALTADAS 48.00

TARRAJEO DE PLACAS INT. C:M 1:5 E=2cm 3.00

TARRAJEO DE ESCALERAS C:A 1:5 20.00

TARRAJEO DE PARAPETOS EN RAMPAS Y ESCALERASC:M 1:5 E=2cm 27.00

VESTIDURA DE DERRAMES 24.00

BRUÑAS 24.00

TARRAJEO FINO EN CIELORRASOS CON MEZCLA DE CEMENTO-ARENA UNSAAC 54.00

TARRAJEO FROTACHADO EN CIELORRASOS CON MEZCLA DE CEMENTO-ARENA U 24.00

PISOS Y PAVIMENTOS

CONTRAPISO DE 48 MM. 24.00

Page 17: Cronograma de Obra Edificio

AR

QU

ITE

CT

UR

A

PISO DE TERRAZO CON ESTRIAS DE ALUMINIO E= 2.50 cm 54.00

PISO DE PARQUET HUAYACAN 6 X 30 CM VETEADO 60.00

PISO CERAMICO 0.30X0.30 12.00

PISO CERAMICO VITRIFICADO ALTO TRANSITO ANTIDESLIZANTE DE 0.30X0.30 10.00

REVESTIMIENTO DE GRADAS CON TERRAZO ICL. CANTONERA ALUMINIO 11.00

TAPAJUNTAS METALICO 12.00

CONTRAZOCALOS

CONTRAZOCALO DE TERRAZO C/PERFILES DE ALUMINIO 48.00

CONTRAZOCALO DE MADERA AGUANO DE 4" x 3/4" C/RODON DE 3/4" 12.00

CONTRAZOCALO DE MADERA AGUANO DE 6" x 3/4" C/RODON DE 3/4" 2.00

CONTRAZOCALO CERAMICO 1.00

ZOCALOS

ZOCALO DE CERAMICO DE 30x30cm. 18.00

LISTELO TIPO CINTILLO DE 0.015x0.30m. 2.00

CUBIERTAS

COBERTURA DE TEJAS SOBRE TIJERALES DE MADERA Y CORREAS 14.00

COBERTURA DE POLICARBONATO SOBRE ESTRUCT METALICA 5.00

MURO LADRILLO SOGA 9.00

TARRAJEO DE PARAPETOS DE TECHO 14.00

TARRAJEO CON IMPERMEABILIZANTE EN CANALES DE TECHO 6.00

CANALETA DE LATON 2.00

SUMIDERO DE BRONCE DE 6" 2.00

CARPINTERIA DE MADERA

PUERTA DE MELAMINA CON BORDES DE MADERA AGUANO e=45mm. 12.00

ASIENTOS DE MADERA SOBRE TUBO DE 2" Y PERFILES DE FIERRO 8mm 12.00

CARPINTERIA METALICA

PUERTA DE VIDRIO CRUDO 8mm CON BORDES DE TUBO DE ACERO 6.00

SEPARADORES METALICOS DE BAÑO e= 2.50MM 6.00

SEPARADORES DE URINARIOS METALICO e= 6MM INC INSTALACION Y PINTURA 6.00

BARANDAS METALICAS DE TUBO 2" CON FIERRO LISO DE 5/8" SEGUN DISEÑO 12.00

TUBO DECORATIVO DE FIERRO DE 4" PINTADO DE COLOR ALUMINIO 110 12.00

ANCLADO CON ANGULAR ESTRIADO DE 1 1/2" X 1 1/2" X 1/8" EN GRADAS 12.00

PLATAFORMAS DE DESCANSO TIPO CANASTILLA 1.00

ESCALERA DE GATO METALICA 5.00

PIZARRA ACRILICA 2.00

CERRAJERIA

Page 18: Cronograma de Obra Edificio

AR

QU

ITE

CT

UR

A

CERRADURA TIPO PERILLAS TIPO FORTE 12.00

CERRADURA DE POMO PARA PUERTAS DE VIDRIO O CRITAL 12.00

CERRADURA PARA PISO EN PUERTAS DE VIDRIO SIMILAR A CISA 12.00

BISAGRA CAPUCHINA ALUMINIZADA DE 4" X 4" UNSAAC 12.00

CERROJO DE FIERRO REDONDO DE 5/8" X 0.60 M. 1.00

CERROJO DE FIERRO REDONDO DE 5/8" X 0.35 M. 1.00

PICAPORTES DE FIERRO REDONDO DE 4" 1.00

VIDRIOS, CRISTALES Y SIMILARES

VENTANA VIDRIO CRUDO TRASLUCIDO 8mm INCL ACCESORIOS 8.00

VENTANA VIDRIO PAVONADO 8mm INCL ACCESORIOS 1.00

VIDRIOS PAVONADO DE 8mm EN PUERTAS 1.00

VIDRIO CRUDO 8mm TRASLUCIDO EN PUERTAS 1.00

MAMPARA DE VIDRIO CRUDO 8mm C/TUBO ELECTROSOLDADO DE 2" X 1" 10.00

PUERTA DE VIDRIO CRUDO 8mm 3.00

ESPEJO BISELADO CON MARCO DE ALUMINIO 3.00

PINTURA

PINTURA LATEX EN MUROS INTERIORES UNSAAC 30.00

PINTURALATEX EN MUROS EXTERIORES 24.00

PINTURA VINILICA EN COLUMNAS , VIGAS Y/O PLACAS 30.00

PINTURA VINILICA EN ESCALERAS, RAMPAS Y PARAPETOS 24.00

PINTURA LATEX EN CIELORRASOS UNSAAC 21.00

PINTURALATEX EN DERRAMES 3.00

INS

TA

LA

CIO

NE

S S

AN

ITA

RIA

S

APARATOS Y ACCESORIOS SANITARIOS

INODORO BLANCO CON ACCESORIOS 6.00

LAVATORIOS TIPO OVALIN BLANCO SOBRE MESA DE CONCRETO 6.00

URINARIOS DE LOZA DE PICO BLANCO 6.00

GRIFERIA DE URINARIOS UNSAAC 4.00

GRIFERIA DE LAVATORIOS UNSAAC 1.00

COLOCACION DE APARATOS SANITARIOS 1.00

PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO 1.00

GABINETE CONTRAINCENDIOS 1.00

SISTEMA DE AGUA FRIA Y CONTRA INCENDIO

REDES DE DISTRIBUCION DE AGUA FRIA Y CONTRAINCENDIO

TUBERIA DE AGUA PVC. DE 2"(50MM).INSTALACION.INC.PRUEBA HIDR 1.00

VALVULA DE COMPUERTA 1 1/2" 2.00

REDUCCION PVC SAP DE 2" A 1 1/2" 2.00

Page 19: Cronograma de Obra Edificio

INS

TA

LA

CIO

NE

S S

AN

ITA

RIA

S

REDUCCION PVC SAP DE 1 1/2" A 3/4"

TEE PVC-SAP 1 1/2" 2.00

CODO PVC SAP 2" 2.00

CODO PVC-SAP 1 1/2" 2.00

TUBERIA DE AGUA PVC. DE 2"(50MM) ISIST CONTRAINCENDIO 2.00

TEE PVC-SAP 2"* 2" 2.00

SISTEMA DE AGUA FRIA

SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 3/4" 1.00

SISTEMA DE DESAGUE Y VENTILACION

REDES DE DISTRIBUCION DE DESAGUE Y VENTILACION

SALIDA DE DESAGÜE DE 2" 4.00

SALIDA DE DESAGÜE DE 4" 1.00

PROVISION E INSTALACION TUBERIA PVC-SAL D=4" + PRUEB.HIDR

PROVISION E INSTALACION TUBERIA PVC-SAL D=2" + PRUEB.HIDR 2.00

TEE PVC SAL 4" 2.00

TEE PVC SAL 2" 2.00

CODO DE PVC SAL SP DE 4" 2.00

SOMBRERO PARA VENTILACION DE P.V.C. DE 2" 2.00

REGISTRO DE BRONCE CROMADO DE 4" 2.00

REGISTROS DE BRONCE DE 2" 2.00

SUMIDERO DE BRONCE 2" 2.00

SISTEMA DE AGUAS PLUVIALES

RED DE DISTRIBUCION DE AGUAS PLUVIALES

SALIDA SUMIDERO REJILLA 0.10m x 0.10m EN TECHO 14.00

SALIDA DE DESAGÜE DE 4"

TUBERIA PVC SAL4" 1.00

CONCRETO EN FALSA COLUMNA F'C=140 KG/CM2 RECUBRIMIENTO DE MONTANTES 1.00

ENCOFRADO EN COLUMNAS RECUBRIMIENTO DE MONTANTES 1.00

TARRAJEO DE RECUBRIMIENTO DE MONTANTES C:M 1:5 E=1.5cm 4.00

CONFORMACIÓN DE FONDOS EN CANALES DE TECHO

CODO PVC SAL 4" 5.00

TEE PVC SAL 4" 6.00

EQUIPO

HIDRONEUMATICO DE 120 GLN DE 20-40 LB DE PRESION

ELECTROBOMBA DE 1.5 HP

Page 20: Cronograma de Obra Edificio

INS

TA

LA

CIO

NE

S E

LE

CT

RIC

AS

INSTALACIONES ELECTRICAS

LINEA DE ALIMENTACION

TUBERIAS PVC SAP (ELECTRICAS) D=3/4"

CABLE ELECTRICO TW AWG NO. 12

CABLE ELECTRICO TW AWG-MCM NO. 14 -2.5 MM2.

EXCAVACION

POZO-CONEXION A TIERRA EN SISTEMA C/EQ.BOMBEO,ALUMB,TOMACORR

TABLERO DE DISTRIBUCION CAJA METALICA CON PUERTA Y CERRADURA PARA 8TERMOMAGNETICOS TIPO ENGRAMPE

INTERRUPTOR TERMOMAGNETICO 2X20A

SISTEMA DE DISTRIBUCION

SALIDA DE TOMACORRIENTE TRIFASICO CON PUESTA TIERRA

SALIDA DE TECHO TW 4.0mmUNSAAC

CAJA DEPASO F°G° 200X200X30 MM. INC. TAPA

CAJA DE PASO CUADRADO

CAJA DE PASO CIRCULAR

LUMINARIAS

LAMPARA FLUORESCENTE DOBLE PARA EMPOTRAR DE 40W

LAMPARA FLUORESCENTE DOBLE CON REJILLA ADOSADA A CIELORASO

LAMPARA FLUORESCENTE CIRCULAR PARA DOSAR CON DIFUSOR

LAMPARA FLUORESCENTE DOBLE PARA ADOSAR 40W

LAMPARA HALOGENA FLOOD LIGTH DE 150 W O EQUIVALENTE

REFLEXTOR LAMPARA HALOGENA DE 75 W CIELO RASO

LAMPARA VAPOR DE SODIO DE 150W CON POSTE DE C°A°

INSTALACIONES ESPECIALES

INTERNET

SALIDA PARA RED INFORMATICA

CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA INTERNET

TELECONFERENCIAS

SALIDA PARA TELECONFERENCIAS

CAJA DE PASO METALICA DE 100X100X50 MM. INC. TAPA TV-CABLE

ALARMA CONTRAINCENDIO

SALIDA PARA ALARMA CONTRAINCENDIO INC. SISTEMA

CAJA DE PASO CUADRADO

PARLANTES

SALIDA DE PARLANTES

Page 21: Cronograma de Obra Edificio

OB

RA

S E

XT

ER

IOR

ES

OBRAS PRELIMINARES

TRAZO Y REPLANTEO DURANTE UNSAACREUBICACION DE ESTRUCTURAS DE CONCRETO

Page 22: Cronograma de Obra Edificio

2° MES 3° MES 4° MES 5° MES

MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI JU VI SA DO LU MA MI

21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Page 23: Cronograma de Obra Edificio
Page 24: Cronograma de Obra Edificio
Page 25: Cronograma de Obra Edificio
Page 26: Cronograma de Obra Edificio
Page 27: Cronograma de Obra Edificio
Page 28: Cronograma de Obra Edificio