Los Angeles CountyMetropolitan Transportation Authority
Hollywood/West Hollywood Transit
Corridor Connection to Crenshaw/LAXTransit Corridor-
Initial ReviewMeasure R Project Delivery Committee (Item #__)
November 18, 2010
-
8/7/2019 Crenshaw-LAX Line Extensions
2/7
Recommendation
Receive and File Report
on Issues, AlignmentOptions and Costs toConduct an InitialReview
These extensions areincluded in Strategic(Unfunded) Element of
the Long RangeTransportation Plan
2
-
8/7/2019 Crenshaw-LAX Line Extensions
3/7
West Hollywood Alternative - Westside Subway Draft EIS/EIR
4.5 mile Heavy Rail subway from Hollywood/Highland (Metro Red Line) toWilshire Boulevard
High ridership potential identified, high cost did not meet federal cost-effectiveness criteria
Not Recommended as part of Locally Preferred Alternative
3
Potential for4,000 to 5,000boardings permileHigher thanany existing orplanned LRTCorridor, butless than MetroRed/PurpleLine Corridors
-
8/7/2019 Crenshaw-LAX Line Extensions
4/7
Alternatives Identified in Crenshaw/LAX Corridor Northern ExtensionFeasibility Study (June 2009)
Crenshaw Blvdterminates atWilshire
Riders propensity totravel towards west.
LaBrea, Fairfax LaCienaga betterconnection points
with WestsideSubway
Possible secondphase extensionnorth to West
Hollywood andHollywood
4
-
8/7/2019 Crenshaw-LAX Line Extensions
5/7
Harbor Subdivision Alternatives Analysis
Approved December2009, precursor to
South Bay MetroGreen Line Extension
Examined possibleextensions of SouthBay Metro Green Lineto San Pedro and/or
Long Beach
5
-
8/7/2019 Crenshaw-LAX Line Extensions
6/7
Potential North/South LRT Corridor Connection
Hollywood/West Hollywood Connector toExposition/Crenshaw would be 6.5 to 9.5 miles in lengthdepending on alignment
Would be more cost-effective than heavy rail if portions ofalignment could be above ground
6
Potential toConnect five northsouth lines withfive east-west linesMetro Red LineMetro Purple LineExposition LineMetro Green LineLAX Connector
Project Segment(Assumes LRT Mode)
Phase
OfDevelopment
Length(Miles)
Cumulative
Length(Miles)
1 Crenshaw/LAX Corridor FEIS/FEIR/PE 8.5 8.5
2 South Bay Metro GreenLine Extension AA/DEIS/DEIR
4.0 12.5
3 Hollywood/WestHollywood Connection Initial Review 6.5 - 9.5 19.0-22.0
4 Long Beach Extension AA Study 10.0 29.0-32.0
5 San Pedro Extension AA Study 5.0 34.0-37.0
-
8/7/2019 Crenshaw-LAX Line Extensions
7/7
Westwood/West Hollywood to Crenshaw/LAX Initial Review
Study Scope Conceptual Alignments, stationlocations, connections to existing andplanned transit lines, ridershipforecasts and costs
Study Time 12 Months (Following NTP)
Study Cost $1.5 million (est.)
Issues No staffing or budget currently
assigned or planned in near future