    Los Angeles CountyMetropolitan Transportation Authority

    Hollywood/West Hollywood Transit

    Corridor Connection to Crenshaw/LAXTransit Corridor-

    Initial ReviewMeasure R Project Delivery Committee (Item #__)

    November 18, 2010

  • 8/7/2019 Crenshaw-LAX Line Extensions

    2/7

    Recommendation

    Receive and File Report

    on Issues, AlignmentOptions and Costs toConduct an InitialReview

    These extensions areincluded in Strategic(Unfunded) Element of

    the Long RangeTransportation Plan

    2

  • 8/7/2019 Crenshaw-LAX Line Extensions

    3/7

    West Hollywood Alternative - Westside Subway Draft EIS/EIR

    4.5 mile Heavy Rail subway from Hollywood/Highland (Metro Red Line) toWilshire Boulevard

    High ridership potential identified, high cost did not meet federal cost-effectiveness criteria

    Not Recommended as part of Locally Preferred Alternative

    3

    Potential for4,000 to 5,000boardings permileHigher thanany existing orplanned LRTCorridor, butless than MetroRed/PurpleLine Corridors

  • 8/7/2019 Crenshaw-LAX Line Extensions

    4/7

    Alternatives Identified in Crenshaw/LAX Corridor Northern ExtensionFeasibility Study (June 2009)

    Crenshaw Blvdterminates atWilshire

    Riders propensity totravel towards west.

    LaBrea, Fairfax LaCienaga betterconnection points

    with WestsideSubway

    Possible secondphase extensionnorth to West

    Hollywood andHollywood

    4

  • 8/7/2019 Crenshaw-LAX Line Extensions

    5/7

    Harbor Subdivision Alternatives Analysis

    Approved December2009, precursor to

    South Bay MetroGreen Line Extension

    Examined possibleextensions of SouthBay Metro Green Lineto San Pedro and/or

    Long Beach

    5

  • 8/7/2019 Crenshaw-LAX Line Extensions

    6/7

    Potential North/South LRT Corridor Connection

    Hollywood/West Hollywood Connector toExposition/Crenshaw would be 6.5 to 9.5 miles in lengthdepending on alignment

    Would be more cost-effective than heavy rail if portions ofalignment could be above ground

    6

    Potential toConnect five northsouth lines withfive east-west linesMetro Red LineMetro Purple LineExposition LineMetro Green LineLAX Connector

    Project Segment(Assumes LRT Mode)

    Phase

    OfDevelopment

    Length(Miles)

    Cumulative

    Length(Miles)

    1 Crenshaw/LAX Corridor FEIS/FEIR/PE 8.5 8.5

    2 South Bay Metro GreenLine Extension AA/DEIS/DEIR

    4.0 12.5

    3 Hollywood/WestHollywood Connection Initial Review 6.5 - 9.5 19.0-22.0

    4 Long Beach Extension AA Study 10.0 29.0-32.0

    5 San Pedro Extension AA Study 5.0 34.0-37.0

  • 8/7/2019 Crenshaw-LAX Line Extensions

    7/7

    Westwood/West Hollywood to Crenshaw/LAX Initial Review

    Study Scope Conceptual Alignments, stationlocations, connections to existing andplanned transit lines, ridershipforecasts and costs

    Study Time 12 Months (Following NTP)

    Study Cost $1.5 million (est.)

    Issues No staffing or budget currently

    assigned or planned in near future

    7