creating dedicated renewable hydrogen supply...creating dedicated renewable hydrogen supply...
TRANSCRIPT
![Page 1: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/1.jpg)
Creating Dedicated Renewable Hydrogen Supply
California Fuel Cell Partnership
Executive Board Meeting
Phil Cazel
October 17, 2018
California Energy Commission
![Page 2: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/2.jpg)
Energy Commission Support
GFO-17-602: Renewable Hydrogen Transportation Fuel Production Facilities and Systems
• 100 percent renewable hydrogen production of at least 1,000 kg/day capacity for public stations
• Solicitation released in December 2017
• One facility funded in June 2018
• Notice of Proposed Award (NOPA) for two more facilities in October 2018
![Page 3: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/3.jpg)
Hydrogen Production Facility Map
![Page 4: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/4.jpg)
StratosFuel, Inc.
• Grant Award: $3,965,665
• Energy Commission approved in June 2018 with CEQA process complete
• Location: Moreno Valley, Riverside County
• Production Capacity: 2,000 kg/day in addition to 3,000 kg/day already planned
• Completion Date: Estimated Q4/2019
• Renewable Hydrogen: Electricity from wind farm PPA
• Electrolyzer equipment from Hydrogenics
![Page 5: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/5.jpg)
StratosFuel – Moreno Valley Site
![Page 6: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/6.jpg)
Shell-Equilon
• Grant Award: $3,965,665
• Energy Commission NOPA October 2018
• Location: Bay Point, Contra Costa County
• Production Capacity: 1,000 kg/day
• Completion Date: Estimated Q4/2020
• Renewable Hydrogen: On-site Solar Photovoltaic
• Partnering with other companies within the Shell Group for site (existing industrial plant) and solar development
![Page 7: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/7.jpg)
Shell – Bay Point Site
![Page 8: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/8.jpg)
H2B2, USA LLC
• Grant Award: $3,965,000
• Energy Commission NOPA October 2018
• Location: Unincorporated Kings County
• Production Capacity: 1,000 kg/day
• Completion Date: Estimated Q4/2020
• Renewable Hydrogen: On-site Solar Photovoltaic
• Giner ELX is equipment partner
![Page 9: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/9.jpg)
H2B2 – King’s County Site
![Page 10: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/10.jpg)
Funding
• Alternative and Renewable Fuel and Vehicle Technology Program (ARFVTP)
• $3,965,665 from Emerging Opportunities Fund
• $7,930,665 from Alternative Fuel Production and Supply
• Does not reduce the $20 million annual allocation for hydrogen refueling infrastructure
![Page 11: Creating Dedicated Renewable Hydrogen Supply...Creating Dedicated Renewable Hydrogen Supply California Fuel Cell Partnership Executive Board Meeting Phil Cazel October 17, 2018 California](https://reader036.vdocuments.mx/reader036/viewer/2022071605/6141b992d64cc55ff0755a85/html5/thumbnails/11.jpg)
Questions?
Thank you!