creating a standard operation for a wsm enabled organization_spd
TRANSCRIPT
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
1/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Department
Responsibility/Role
File Name 27760459.doc
Revision
Document Generation Date 18/01/2010 09:39:00
Date Modified 1/18/2010 09:39:00 AM
Last Changed by
Status
Creating a Standard Operation for a WSM Enabled OrganizationTrigger:
Concept
Standard operations are commonly used operations you can define as a template for use in
defining future routing operations. If you assign the operation code of standard operation in a
routing, the standard operation information is copied into the operation you are currently
defining. You can then modify the operation information in your new operation.
The following fields in the Standard Operation page are enabled only for a Shop Floor
Management enabled organization:
Lowest Acceptable Yield.
Use Organization Settings.
Queue Mandatory Flag.
Run Mandatory Flag.
To Move Mandatory Flag.
Show Next Operation by Default.
Show Lot Attributes.
Show Scrap Codes.
In this topic, you will create a standard operation for a Shop Floor Management enabled
organization.
Required Field(s) Comments
Output - Result(s) Comments
Last changed on: 1/18/2010 09:39:00 AM Page 1
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
2/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Additional Information
Page 2 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
3/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Procedure
Step Action
1. Begin by navigating to the Standard Operations page.
Click the vertical scrollbar.
Last changed on: 1/18/2010 09:39:00 AM Page 3
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
4/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
2. Click the Manufacturing and Distribution Manager link.
Page 4 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
5/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Standard Operations link.
Last changed on: 1/18/2010 09:39:00 AM Page 5
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
6/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
5. Use the Organizations page to select a Shop Floor enabled Organization.
Page 6 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
7/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
6. Click the M4 Minneapolis Manufacturing list item.
Step Action
7. Click the OKbutton.
orPress [Alt+O].
Last changed on: 1/18/2010 09:39:00 AM Page 7
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
8/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
8. Use the Standard Operations page to create a standard operation for a Shop FloorManagement enabled organization.
Page 8 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
9/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
9. Click the New button.
Step Action
10. Enter the desired information into the Code field. Enter "RT10".
Last changed on: 1/18/2010 09:39:00 AM Page 9
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
10/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
11. Click in the Description field.
Page 10 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
11/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
12. Enter the desired information into the Description field. Enter "Load Laser Saw".
Step Action
13. Click in the Department field.
Last changed on: 1/18/2010 09:39:00 AM Page 11
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
12/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
14. Enter the desired information into the Department field. Enter "FAB".
Page 12 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
13/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
15. This option indicates whether the operation is dependant on the choice of an
optional component.
Click the Option Dependent option.
Step Action
16. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:39:00 AM Page 13
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
14/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
17. Click in the Yield field.
Page 14 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
15/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
18. Enter the desired information into the Yield field. Enter ".85".
Step Action
19. Click the Shop Floor Transaction tab.
Last changed on: 1/18/2010 09:39:00 AM Page 15
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
16/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
20. All the fields that you see when you click the Shop Floor Transaction tab areenabled only for Shop Floor Management enabled organizations.
Page 16 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
17/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
21. Low Yield is a situation when the actual scrap quantity in an operation is higher
than the quantity derived from the Lowest Acceptable Yield. You can put a job onhold by defining the lowest acceptable yield for a given standard operation.
Click in the Lowest Acceptable Yield field.
Step Action
22. Enter the desired information into the Lowest Acceptable Yield field. Enter
".313".
Last changed on: 1/18/2010 09:39:00 AM Page 17
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
18/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
23. Click the Queue Mandatory option.
Page 18 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
19/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
24. Click the Run Mandatory option.
Step Action
25. Click the To Move Mandatory option.
Last changed on: 1/18/2010 09:39:00 AM Page 19
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
20/21
System Process DocumentCreating a Standard Operation for a WSM EnabledOrganization
Step Action
26. Click the horizontal scrollbar.
Page 20 Last changed on: 1/18/2010 09:39:00 AM
-
8/14/2019 Creating a Standard Operation for a WSM Enabled Organization_SPD
21/21
System Process DocumentCreating a Standard Operation for a WSM Enabled
Organization
Step Action
27. Click the Save button.
Step Action
28. You have completed the Creating a Standard Operation for a WSM EnabledOrganization procedure.
End of Procedure.
Last changed on: 1/18/2010 09:39:00 AM Page 21