System Process DocumentCreating a Bill of Material
Department
Responsibility/Role
File Name 27760369.docRevision
Document Generation Date 18/01/2010 09:36:00
Date Modified 1/18/2010 09:36:00 AM
Last Changed by
Status
Creating a Bill of Material
Trigger:
Concept
A bill of material contains information on the parent item, components, attachments, and
descriptive elements. Each standard component on a bill can have multiple reference designators
and substitute components. You can create an engineering, manufacturing, or asset (maintenance)
bill, copy an existing bill, or reference a common bill. When you create a bill, it exists only in the
current organization. To use a bill in another organization, you must either copy it or reference it
as a common one.
As a prerequisite to this topic, you must define the parent item and all components as inventory
items and set the BOM Allowed attribute to Yes and BOM Item Type to model, option class,
planning or standard.
In this topic, you will create a bill of material.
Required Field(s) Comments
Output - Result(s) Comments
Additional Information
Last changed on: 1/18/2010 09:36:00 AM Page 1
-
8/14/2019 Creating a Bill of Material_SPD
2/58
System Process DocumentCreating a Bill of Material
Procedure
Step Action
1. Begin by navigating to the Bills of Material page.
Click the vertical scrollbar.
Page 2 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
3/58
System Process DocumentCreating a Bill of Material
Step Action
2. Click the Manufacturing and Distribution Manager link.
Last changed on: 1/18/2010 09:36:00 AM Page 3
-
8/14/2019 Creating a Bill of Material_SPD
4/58
System Process DocumentCreating a Bill of Material
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Bills link.
Page 4 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
5/58
System Process DocumentCreating a Bill of Material
Step Action
5. Use the Organization page to select your organization.
Last changed on: 1/18/2010 09:36:00 AM Page 5
-
8/14/2019 Creating a Bill of Material_SPD
6/58
System Process DocumentCreating a Bill of Material
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OKbutton.
orPress [Alt+O].
Page 6 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
7/58
System Process DocumentCreating a Bill of Material
Step Action
8. Use the Bills of Material page to create a bill. You can create an engineering,
manufacturing, or asset bill, copy an existing bill, or reference a common bill.
Last changed on: 1/18/2010 09:36:00 AM Page 7
-
8/14/2019 Creating a Bill of Material_SPD
8/58
System Process DocumentCreating a Bill of Material
Step Action
9. Click in the Item field.
Step Action
10. Enter the desired information into the Item field. Enter "RT1000".
Page 8 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
9/58
System Process DocumentCreating a Bill of Material
Step Action
11. Click in the Revision field.
Last changed on: 1/18/2010 09:36:00 AM Page 9
-
8/14/2019 Creating a Bill of Material_SPD
10/58
System Process DocumentCreating a Bill of Material
Step Action
12. Click in the Component field.
Step Action
13. Enter the desired information into the Component field. Enter "CM38060".
Page 10 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
11/58
System Process DocumentCreating a Bill of Material
Step Action
14. Click in the Item Description field.
Last changed on: 1/18/2010 09:36:00 AM Page 11
-
8/14/2019 Creating a Bill of Material_SPD
12/58
System Process DocumentCreating a Bill of Material
Step Action
15. Click the horizontal scrollbar.
Step Action
16. Click in the Quantity field.
Page 12 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
13/58
System Process DocumentCreating a Bill of Material
Step Action
17. Enter the desired information into the Quantity field. Enter "10".
Last changed on: 1/18/2010 09:36:00 AM Page 13
-
8/14/2019 Creating a Bill of Material_SPD
14/58
System Process DocumentCreating a Bill of Material
Step Action
18. Click in the Inverse Usage field.
Step Action
19. Click in the Item Seq field.
Page 14 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
15/58
System Process DocumentCreating a Bill of Material
Step Action
20. Click in the Component field.
Last changed on: 1/18/2010 09:36:00 AM Page 15
-
8/14/2019 Creating a Bill of Material_SPD
16/58
System Process DocumentCreating a Bill of Material
Step Action
21. Enter the desired information into the Component field. Enter "CM08830".
Step Action
22. Click in the Item Description field.
Page 16 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
17/58
System Process DocumentCreating a Bill of Material
Step Action
23. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:36:00 AM Page 17
-
8/14/2019 Creating a Bill of Material_SPD
18/58
System Process DocumentCreating a Bill of Material
Step Action
24. Click in the Quantity field.
Step Action
25. Enter the desired information into the Quantity field. Enter "100".
Page 18 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
19/58
System Process DocumentCreating a Bill of Material
Step Action
26. Click in the Inverse Usage field.
Last changed on: 1/18/2010 09:36:00 AM Page 19
-
8/14/2019 Creating a Bill of Material_SPD
20/58
System Process DocumentCreating a Bill of Material
Step Action
27. Click in the Item Seq field.
Step Action
28. Click in the Component field.
Page 20 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
21/58
System Process DocumentCreating a Bill of Material
Step Action
29. Enter the desired information into the Component field. Enter "CM00043".
Last changed on: 1/18/2010 09:36:00 AM Page 21
-
8/14/2019 Creating a Bill of Material_SPD
22/58
System Process DocumentCreating a Bill of Material
Step Action
30. Click the horizontal scrollbar.
Step Action
31. Click in the Item Description field.
Page 22 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
23/58
System Process DocumentCreating a Bill of Material
Step Action
32. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:36:00 AM Page 23
-
8/14/2019 Creating a Bill of Material_SPD
24/58
System Process DocumentCreating a Bill of Material
Step Action
33. Click in the Quantity field.
Step Action
34. Enter the desired information into the Quantity field. Enter "100".
Page 24 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
25/58
System Process DocumentCreating a Bill of Material
Step Action
35. Click in the Inverse Usage field.
Last changed on: 1/18/2010 09:36:00 AM Page 25
-
8/14/2019 Creating a Bill of Material_SPD
26/58
System Process DocumentCreating a Bill of Material
Step Action
36. Click in the Item Seq field.
Step Action
37. Click in the Component field.
Page 26 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
27/58
System Process DocumentCreating a Bill of Material
Step Action
38. Enter the desired information into the Component field. Enter "CM67433".
Last changed on: 1/18/2010 09:36:00 AM Page 27
-
8/14/2019 Creating a Bill of Material_SPD
28/58
System Process DocumentCreating a Bill of Material
Step Action
39. Click the horizontal scrollbar.
Step Action
40. Click in the Item Description field.
Page 28 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
29/58
System Process DocumentCreating a Bill of Material
Step Action
41. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:36:00 AM Page 29
-
8/14/2019 Creating a Bill of Material_SPD
30/58
System Process DocumentCreating a Bill of Material
Step Action
42. Click in the Quantity field.
Step Action
43. Enter the desired information into the Quantity field. Enter "100".
Page 30 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
31/58
System Process DocumentCreating a Bill of Material
Step Action
44. Click in the Inverse Usage field.
Last changed on: 1/18/2010 09:36:00 AM Page 31
-
8/14/2019 Creating a Bill of Material_SPD
32/58
System Process DocumentCreating a Bill of Material
Step Action
45. Click the horizontal scrollbar.
Step Action
46. Click the Date Effectivity tab.
Page 32 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
33/58
System Process DocumentCreating a Bill of Material
Step Action
47. Click in the To field.
Last changed on: 1/18/2010 09:36:00 AM Page 33
-
8/14/2019 Creating a Bill of Material_SPD
34/58
System Process DocumentCreating a Bill of Material
Step Action
48. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".
Step Action
49. Click in the To field.
Page 34 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
35/58
System Process DocumentCreating a Bill of Material
Step Action
50. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".
Last changed on: 1/18/2010 09:36:00 AM Page 35
-
8/14/2019 Creating a Bill of Material_SPD
36/58
System Process DocumentCreating a Bill of Material
Step Action
51. Click in the To field.
Step Action
52. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".
Page 36 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
37/58
System Process DocumentCreating a Bill of Material
Step Action
53. Click in the To field.
Last changed on: 1/18/2010 09:36:00 AM Page 37
-
8/14/2019 Creating a Bill of Material_SPD
38/58
System Process DocumentCreating a Bill of Material
Step Action
54. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".
Step Action
55. You can use the ECO tab to enable the Implemented check box to indicate
whether the component is implemented.
Unchecked: Component is on a pending Engineering Change Order (ECO).
Checked: Component is on an implemented ECO or was added directly to the bill.
If the component is part of a pending or implemented ECO, the ECO field displays
this ECO.
Page 38 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
39/58
System Process DocumentCreating a Bill of Material
Step Action
56. Click the Component Details tab.
Last changed on: 1/18/2010 09:36:00 AM Page 39
-
8/14/2019 Creating a Bill of Material_SPD
40/58
System Process DocumentCreating a Bill of Material
Step Action
57. Use the Components Details tab to enter the planning percent, the yield, and the
Enforce Integer Requirement.
You can also indicate whether the component should be included in cost rollups. If
enabled, the material cost of this component, but not the routing cost, is included inthe cost of the parent item.
Step Action
58. Use the Material Control tab to enter the supply type.
Click the Material Control tab.
Page 40 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
41/58
System Process DocumentCreating a Bill of Material
Step Action
59. Click in the Subinventory field.
Last changed on: 1/18/2010 09:36:00 AM Page 41
-
8/14/2019 Creating a Bill of Material_SPD
42/58
System Process DocumentCreating a Bill of Material
Step Action
60. Enter the desired information into the Subinventory field. Enter "Stores".
Step Action
61. Click in the Subinventory field.
Page 42 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
43/58
System Process DocumentCreating a Bill of Material
Step Action
62. Enter the desired information into the Subinventory field. Enter "Stores".
Last changed on: 1/18/2010 09:36:00 AM Page 43
-
8/14/2019 Creating a Bill of Material_SPD
44/58
System Process DocumentCreating a Bill of Material
Step Action
63. Click in the Subinventory field.
Step Action
64. Enter the desired information into the Subinventory field. Enter "Stores".
Page 44 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
45/58
System Process DocumentCreating a Bill of Material
Step Action
65. Click in the Subinventory field.
Last changed on: 1/18/2010 09:36:00 AM Page 45
-
8/14/2019 Creating a Bill of Material_SPD
46/58
System Process DocumentCreating a Bill of Material
Step Action
66. Enter the desired information into the Subinventory field. Enter "Stores".
Step Action
67. Use the Order Management tab to enter the minimum and maximum sales order
quantities.
Click the Order Management tab.
Page 46 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
47/58
System Process DocumentCreating a Bill of Material
Step Action
68. Click in the Minimum field.
Last changed on: 1/18/2010 09:36:00 AM Page 47
-
8/14/2019 Creating a Bill of Material_SPD
48/58
System Process DocumentCreating a Bill of Material
Step Action
69. Enter the desired information into the Minimum field. Enter "1".
Step Action
70. Click in the Maximum field.
Page 48 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
49/58
System Process DocumentCreating a Bill of Material
Step Action
71. Click the Check ATP option.
Last changed on: 1/18/2010 09:36:00 AM Page 49
-
8/14/2019 Creating a Bill of Material_SPD
50/58
System Process DocumentCreating a Bill of Material
Step Action
72. Click in the Minimum field.
Step Action
73. Enter the desired information into the Minimum field. Enter "1".
Page 50 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
51/58
System Process DocumentCreating a Bill of Material
Step Action
74. Click in the Maximum field.
Last changed on: 1/18/2010 09:36:00 AM Page 51
-
8/14/2019 Creating a Bill of Material_SPD
52/58
System Process DocumentCreating a Bill of Material
Step Action
75. Click the horizontal scrollbar.
Step Action
76. Use the Check ATP check box to indicate whether the component is Available to
Promise.
Click the Check ATP option.
Page 52 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
53/58
System Process DocumentCreating a Bill of Material
Step Action
77. Click in the Minimum field.
Last changed on: 1/18/2010 09:36:00 AM Page 53
-
8/14/2019 Creating a Bill of Material_SPD
54/58
System Process DocumentCreating a Bill of Material
Step Action
78. Enter the desired information into the Minimum field. Enter "10".
Step Action
79. Click in the Maximum field.
Page 54 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
55/58
System Process DocumentCreating a Bill of Material
Step Action
80. Click the horizontal scrollbar.
Last changed on: 1/18/2010 09:36:00 AM Page 55
-
8/14/2019 Creating a Bill of Material_SPD
56/58
System Process DocumentCreating a Bill of Material
Step Action
81. Click in the Minimum field.
Step Action
82. Enter the desired information into the Minimum field. Enter "10".
Page 56 Last changed on: 1/18/2010 09:36:00 AM
-
8/14/2019 Creating a Bill of Material_SPD
57/58
System Process DocumentCreating a Bill of Material
Step Action
83. Click in the Maximum field.
Last changed on: 1/18/2010 09:36:00 AM Page 57
-
8/14/2019 Creating a Bill of Material_SPD
58/58
System Process DocumentCreating a Bill of Material
Step Action
84. Click the Save button.
Step Action
85. You have completed the Creating a Bill of Material procedure.
End of Procedure.