  • 8/14/2019 Creating a Bill of Material_SPD

    1/58

    System Process DocumentCreating a Bill of Material

    Department

    Responsibility/Role

    File Name 27760369.docRevision

    Document Generation Date 18/01/2010 09:36:00

    Date Modified 1/18/2010 09:36:00 AM

    Last Changed by

    Status

    Creating a Bill of Material

    Trigger:

    Concept

    A bill of material contains information on the parent item, components, attachments, and

    descriptive elements. Each standard component on a bill can have multiple reference designators

    and substitute components. You can create an engineering, manufacturing, or asset (maintenance)

    bill, copy an existing bill, or reference a common bill. When you create a bill, it exists only in the

    current organization. To use a bill in another organization, you must either copy it or reference it

    as a common one.

    As a prerequisite to this topic, you must define the parent item and all components as inventory

    items and set the BOM Allowed attribute to Yes and BOM Item Type to model, option class,

    planning or standard.

    In this topic, you will create a bill of material.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:36:00 AM Page 1

  • 8/14/2019 Creating a Bill of Material_SPD

    2/58

    System Process DocumentCreating a Bill of Material

    Procedure

    Step Action

    1. Begin by navigating to the Bills of Material page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    3/58

    System Process DocumentCreating a Bill of Material

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:36:00 AM Page 3

  • 8/14/2019 Creating a Bill of Material_SPD

    4/58

    System Process DocumentCreating a Bill of Material

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Bills link.

    Page 4 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    5/58

    System Process DocumentCreating a Bill of Material

    Step Action

    5. Use the Organization page to select your organization.

    Last changed on: 1/18/2010 09:36:00 AM Page 5

  • 8/14/2019 Creating a Bill of Material_SPD

    6/58

    System Process DocumentCreating a Bill of Material

    Step Action

    6. Click the M1 Seattle Manufacturing list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    7/58

    System Process DocumentCreating a Bill of Material

    Step Action

    8. Use the Bills of Material page to create a bill. You can create an engineering,

    manufacturing, or asset bill, copy an existing bill, or reference a common bill.

    Last changed on: 1/18/2010 09:36:00 AM Page 7

  • 8/14/2019 Creating a Bill of Material_SPD

    8/58

    System Process DocumentCreating a Bill of Material

    Step Action

    9. Click in the Item field.

    Step Action

    10. Enter the desired information into the Item field. Enter "RT1000".

    Page 8 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    9/58

    System Process DocumentCreating a Bill of Material

    Step Action

    11. Click in the Revision field.

    Last changed on: 1/18/2010 09:36:00 AM Page 9

  • 8/14/2019 Creating a Bill of Material_SPD

    10/58

    System Process DocumentCreating a Bill of Material

    Step Action

    12. Click in the Component field.

    Step Action

    13. Enter the desired information into the Component field. Enter "CM38060".

    Page 10 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    11/58

    System Process DocumentCreating a Bill of Material

    Step Action

    14. Click in the Item Description field.

    Last changed on: 1/18/2010 09:36:00 AM Page 11

  • 8/14/2019 Creating a Bill of Material_SPD

    12/58

    System Process DocumentCreating a Bill of Material

    Step Action

    15. Click the horizontal scrollbar.

    Step Action

    16. Click in the Quantity field.

    Page 12 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    13/58

    System Process DocumentCreating a Bill of Material

    Step Action

    17. Enter the desired information into the Quantity field. Enter "10".

    Last changed on: 1/18/2010 09:36:00 AM Page 13

  • 8/14/2019 Creating a Bill of Material_SPD

    14/58

    System Process DocumentCreating a Bill of Material

    Step Action

    18. Click in the Inverse Usage field.

    Step Action

    19. Click in the Item Seq field.

    Page 14 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    15/58

    System Process DocumentCreating a Bill of Material

    Step Action

    20. Click in the Component field.

    Last changed on: 1/18/2010 09:36:00 AM Page 15

  • 8/14/2019 Creating a Bill of Material_SPD

    16/58

    System Process DocumentCreating a Bill of Material

    Step Action

    21. Enter the desired information into the Component field. Enter "CM08830".

    Step Action

    22. Click in the Item Description field.

    Page 16 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    17/58

    System Process DocumentCreating a Bill of Material

    Step Action

    23. Click the horizontal scrollbar.

    Last changed on: 1/18/2010 09:36:00 AM Page 17

  • 8/14/2019 Creating a Bill of Material_SPD

    18/58

    System Process DocumentCreating a Bill of Material

    Step Action

    24. Click in the Quantity field.

    Step Action

    25. Enter the desired information into the Quantity field. Enter "100".

    Page 18 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    19/58

    System Process DocumentCreating a Bill of Material

    Step Action

    26. Click in the Inverse Usage field.

    Last changed on: 1/18/2010 09:36:00 AM Page 19

  • 8/14/2019 Creating a Bill of Material_SPD

    20/58

    System Process DocumentCreating a Bill of Material

    Step Action

    27. Click in the Item Seq field.

    Step Action

    28. Click in the Component field.

    Page 20 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    21/58

    System Process DocumentCreating a Bill of Material

    Step Action

    29. Enter the desired information into the Component field. Enter "CM00043".

    Last changed on: 1/18/2010 09:36:00 AM Page 21

  • 8/14/2019 Creating a Bill of Material_SPD

    22/58

    System Process DocumentCreating a Bill of Material

    Step Action

    30. Click the horizontal scrollbar.

    Step Action

    31. Click in the Item Description field.

    Page 22 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    23/58

    System Process DocumentCreating a Bill of Material

    Step Action

    32. Click the horizontal scrollbar.

    Last changed on: 1/18/2010 09:36:00 AM Page 23

  • 8/14/2019 Creating a Bill of Material_SPD

    24/58

    System Process DocumentCreating a Bill of Material

    Step Action

    33. Click in the Quantity field.

    Step Action

    34. Enter the desired information into the Quantity field. Enter "100".

    Page 24 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    25/58

    System Process DocumentCreating a Bill of Material

    Step Action

    35. Click in the Inverse Usage field.

    Last changed on: 1/18/2010 09:36:00 AM Page 25

  • 8/14/2019 Creating a Bill of Material_SPD

    26/58

    System Process DocumentCreating a Bill of Material

    Step Action

    36. Click in the Item Seq field.

    Step Action

    37. Click in the Component field.

    Page 26 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    27/58

    System Process DocumentCreating a Bill of Material

    Step Action

    38. Enter the desired information into the Component field. Enter "CM67433".

    Last changed on: 1/18/2010 09:36:00 AM Page 27

  • 8/14/2019 Creating a Bill of Material_SPD

    28/58

    System Process DocumentCreating a Bill of Material

    Step Action

    39. Click the horizontal scrollbar.

    Step Action

    40. Click in the Item Description field.

    Page 28 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    29/58

    System Process DocumentCreating a Bill of Material

    Step Action

    41. Click the horizontal scrollbar.

    Last changed on: 1/18/2010 09:36:00 AM Page 29

  • 8/14/2019 Creating a Bill of Material_SPD

    30/58

    System Process DocumentCreating a Bill of Material

    Step Action

    42. Click in the Quantity field.

    Step Action

    43. Enter the desired information into the Quantity field. Enter "100".

    Page 30 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    31/58

    System Process DocumentCreating a Bill of Material

    Step Action

    44. Click in the Inverse Usage field.

    Last changed on: 1/18/2010 09:36:00 AM Page 31

  • 8/14/2019 Creating a Bill of Material_SPD

    32/58

    System Process DocumentCreating a Bill of Material

    Step Action

    45. Click the horizontal scrollbar.

    Step Action

    46. Click the Date Effectivity tab.

    Page 32 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    33/58

    System Process DocumentCreating a Bill of Material

    Step Action

    47. Click in the To field.

    Last changed on: 1/18/2010 09:36:00 AM Page 33

  • 8/14/2019 Creating a Bill of Material_SPD

    34/58

    System Process DocumentCreating a Bill of Material

    Step Action

    48. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".

    Step Action

    49. Click in the To field.

    Page 34 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    35/58

    System Process DocumentCreating a Bill of Material

    Step Action

    50. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".

    Last changed on: 1/18/2010 09:36:00 AM Page 35

  • 8/14/2019 Creating a Bill of Material_SPD

    36/58

    System Process DocumentCreating a Bill of Material

    Step Action

    51. Click in the To field.

    Step Action

    52. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".

    Page 36 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    37/58

    System Process DocumentCreating a Bill of Material

    Step Action

    53. Click in the To field.

    Last changed on: 1/18/2010 09:36:00 AM Page 37

  • 8/14/2019 Creating a Bill of Material_SPD

    38/58

    System Process DocumentCreating a Bill of Material

    Step Action

    54. Enter the desired information into the To field. Enter "05-NOV-2009 00:00:00".

    Step Action

    55. You can use the ECO tab to enable the Implemented check box to indicate

    whether the component is implemented.

    Unchecked: Component is on a pending Engineering Change Order (ECO).

    Checked: Component is on an implemented ECO or was added directly to the bill.

    If the component is part of a pending or implemented ECO, the ECO field displays

    this ECO.

    Page 38 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    39/58

    System Process DocumentCreating a Bill of Material

    Step Action

    56. Click the Component Details tab.

    Last changed on: 1/18/2010 09:36:00 AM Page 39

  • 8/14/2019 Creating a Bill of Material_SPD

    40/58

    System Process DocumentCreating a Bill of Material

    Step Action

    57. Use the Components Details tab to enter the planning percent, the yield, and the

    Enforce Integer Requirement.

    You can also indicate whether the component should be included in cost rollups. If

    enabled, the material cost of this component, but not the routing cost, is included inthe cost of the parent item.

    Step Action

    58. Use the Material Control tab to enter the supply type.

    Click the Material Control tab.

    Page 40 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    41/58

    System Process DocumentCreating a Bill of Material

    Step Action

    59. Click in the Subinventory field.

    Last changed on: 1/18/2010 09:36:00 AM Page 41

  • 8/14/2019 Creating a Bill of Material_SPD

    42/58

    System Process DocumentCreating a Bill of Material

    Step Action

    60. Enter the desired information into the Subinventory field. Enter "Stores".

    Step Action

    61. Click in the Subinventory field.

    Page 42 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    43/58

    System Process DocumentCreating a Bill of Material

    Step Action

    62. Enter the desired information into the Subinventory field. Enter "Stores".

    Last changed on: 1/18/2010 09:36:00 AM Page 43

  • 8/14/2019 Creating a Bill of Material_SPD

    44/58

    System Process DocumentCreating a Bill of Material

    Step Action

    63. Click in the Subinventory field.

    Step Action

    64. Enter the desired information into the Subinventory field. Enter "Stores".

    Page 44 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    45/58

    System Process DocumentCreating a Bill of Material

    Step Action

    65. Click in the Subinventory field.

    Last changed on: 1/18/2010 09:36:00 AM Page 45

  • 8/14/2019 Creating a Bill of Material_SPD

    46/58

    System Process DocumentCreating a Bill of Material

    Step Action

    66. Enter the desired information into the Subinventory field. Enter "Stores".

    Step Action

    67. Use the Order Management tab to enter the minimum and maximum sales order

    quantities.

    Click the Order Management tab.

    Page 46 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    47/58

    System Process DocumentCreating a Bill of Material

    Step Action

    68. Click in the Minimum field.

    Last changed on: 1/18/2010 09:36:00 AM Page 47

  • 8/14/2019 Creating a Bill of Material_SPD

    48/58

    System Process DocumentCreating a Bill of Material

    Step Action

    69. Enter the desired information into the Minimum field. Enter "1".

    Step Action

    70. Click in the Maximum field.

    Page 48 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    49/58

    System Process DocumentCreating a Bill of Material

    Step Action

    71. Click the Check ATP option.

    Last changed on: 1/18/2010 09:36:00 AM Page 49

  • 8/14/2019 Creating a Bill of Material_SPD

    50/58

    System Process DocumentCreating a Bill of Material

    Step Action

    72. Click in the Minimum field.

    Step Action

    73. Enter the desired information into the Minimum field. Enter "1".

    Page 50 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    51/58

    System Process DocumentCreating a Bill of Material

    Step Action

    74. Click in the Maximum field.

    Last changed on: 1/18/2010 09:36:00 AM Page 51

  • 8/14/2019 Creating a Bill of Material_SPD

    52/58

    System Process DocumentCreating a Bill of Material

    Step Action

    75. Click the horizontal scrollbar.

    Step Action

    76. Use the Check ATP check box to indicate whether the component is Available to

    Promise.

    Click the Check ATP option.

    Page 52 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    53/58

    System Process DocumentCreating a Bill of Material

    Step Action

    77. Click in the Minimum field.

    Last changed on: 1/18/2010 09:36:00 AM Page 53

  • 8/14/2019 Creating a Bill of Material_SPD

    54/58

    System Process DocumentCreating a Bill of Material

    Step Action

    78. Enter the desired information into the Minimum field. Enter "10".

    Step Action

    79. Click in the Maximum field.

    Page 54 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    55/58

    System Process DocumentCreating a Bill of Material

    Step Action

    80. Click the horizontal scrollbar.

    Last changed on: 1/18/2010 09:36:00 AM Page 55

  • 8/14/2019 Creating a Bill of Material_SPD

    56/58

    System Process DocumentCreating a Bill of Material

    Step Action

    81. Click in the Minimum field.

    Step Action

    82. Enter the desired information into the Minimum field. Enter "10".

    Page 56 Last changed on: 1/18/2010 09:36:00 AM

  • 8/14/2019 Creating a Bill of Material_SPD

    57/58

    System Process DocumentCreating a Bill of Material

    Step Action

    83. Click in the Maximum field.

    Last changed on: 1/18/2010 09:36:00 AM Page 57

  • 8/14/2019 Creating a Bill of Material_SPD

    58/58

    System Process DocumentCreating a Bill of Material

    Step Action

    84. Click the Save button.

    Step Action

    85. You have completed the Creating a Bill of Material procedure.