cornell tech campus plans presentation andrew winters

44
Campus Plan Roosevelt Island campus > Laboratory of innovation > Open and inviting to the public > Sustainable and energy- efficient

Upload: rooseveltislander

Post on 06-Dec-2015

2.154 views

Category:

Documents


0 download

DESCRIPTION

October 1 Cornell Tech Roosevelt Island Town Hall Community Update Presentation.Cornell Tech Director Of Capital Planning Andrew Winters describes construction status and plans for the campus.

TRANSCRIPT

Page 1: Cornell Tech Campus Plans Presentation Andrew Winters

Campus Plan

Roosevelt Island campus> Laboratory of innovation> Open and inviting to the public> Sustainable and energy-efficient

Page 2: Cornell Tech Campus Plans Presentation Andrew Winters

BLOOMBERG CENTER

Page 3: Cornell Tech Campus Plans Presentation Andrew Winters
Page 4: Cornell Tech Campus Plans Presentation Andrew Winters

Public Open Space> More than 20% of the Site> No Gates, Walls or Barriers> Public Programming

Page 5: Cornell Tech Campus Plans Presentation Andrew Winters

Public Open Space> Laboratory of innovation> State of the art technologies> Sustainable and energy-efficient

Bloomberg Center> Collaborative Work Environment> Net-Zero Goal> Public Café, Art and Programming

Page 6: Cornell Tech Campus Plans Presentation Andrew Winters

The Bridge> Co-Location Space for Companies> Cornell Tech Studio Space> Common Spaces for Programming

Page 7: Cornell Tech Campus Plans Presentation Andrew Winters

Residential Building> First High Rise Passive House in the World> Housing for Students, Faculty & Staff

Page 8: Cornell Tech Campus Plans Presentation Andrew Winters

2017Phase One

Page 9: Cornell Tech Campus Plans Presentation Andrew Winters

Project Schedule

Start of Demolition January 2013End of Demolition June 2015

Start of Sitework December 2014Start of Bloomberg Ctr. March 2015Start of The Bridge May 2015Start of Residential June 2015

Phase I Opening Summer 2017

Page 10: Cornell Tech Campus Plans Presentation Andrew Winters

December 2014

Page 11: Cornell Tech Campus Plans Presentation Andrew Winters

January 2015

Page 12: Cornell Tech Campus Plans Presentation Andrew Winters

February 2015

Page 13: Cornell Tech Campus Plans Presentation Andrew Winters

March 2015

Page 14: Cornell Tech Campus Plans Presentation Andrew Winters

April 2015

Page 15: Cornell Tech Campus Plans Presentation Andrew Winters

May 2015

Page 16: Cornell Tech Campus Plans Presentation Andrew Winters

June 2015

Page 17: Cornell Tech Campus Plans Presentation Andrew Winters

July 2015

Page 18: Cornell Tech Campus Plans Presentation Andrew Winters

August 2015

Page 19: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Page 20: Cornell Tech Campus Plans Presentation Andrew Winters

October 1, 2015

Page 21: Cornell Tech Campus Plans Presentation Andrew Winters

October 1, 2015

Bloomberg Center

Page 22: Cornell Tech Campus Plans Presentation Andrew Winters

October 1, 2015

Bloomberg Center

The Bridge (Co-Location)

Page 23: Cornell Tech Campus Plans Presentation Andrew Winters

October 1, 2015

Bloomberg Center

The Bridge (Co-Location)

Residential Building

Page 24: Cornell Tech Campus Plans Presentation Andrew Winters

October 1, 2015

Page 25: Cornell Tech Campus Plans Presentation Andrew Winters

Current & Upcoming Work

Sitework• Utility installation on East and West roads (closed to public)• Utility installation on campus• Completion of CUP structure & start of equipment installation

• North Road to re-open by the week of October 12

Bloomberg Center• Steel structure started September• Façade/enclosure to start in January 2016

The Bridge (Co-Location)• Steel structure to start in early October• Façade/enclosure to start in Winter 2016

Residential• Superstructure to start in mid October• Façade/enclosure to start in Winter 2016

Page 26: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Utilities & Roadways

Page 27: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Utilities & Roadways

Page 28: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Bloomberg Center

Page 29: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Bloomberg Center

Page 30: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Bridge (Co-Location)

Page 31: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Bridge (Co-Location)

Page 32: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Residential

Page 33: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Residential

Page 34: Cornell Tech Campus Plans Presentation Andrew Winters

Construction Commitments Reduce truck traffic through largest voluntary

barging effort in NYC history

Minimum 17% MWBE participation in construction

Union labor on all construction projects

On-site air monitoring for duration of the project

Extensive roadway & utility improvements

Close communication with Roosevelt Island stakeholders

Page 35: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Demolition

Reduction of more than 12,000 truck trips on Main Street

Page 36: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Barging for Demolition

Page 37: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Construction

Page 38: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Construction

Page 39: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Construction

Page 40: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Construction

Page 41: Cornell Tech Campus Plans Presentation Andrew Winters

Barging for Construction

Page 42: Cornell Tech Campus Plans Presentation Andrew Winters

September 2015

Barging for Construction

1

3

2

4

Page 43: Cornell Tech Campus Plans Presentation Andrew Winters

Upcoming Milestones

• Reopening of North Loop Road

• Relocation of West Road fence to facilitate road reconstruction

• Steel construction at Bloomberg Center & The Bridge

• Concrete superstructure at Residential Building

• Start of geothermal wellfield

Page 44: Cornell Tech Campus Plans Presentation Andrew Winters

2017