cornell tech campus plans presentation andrew winters
DESCRIPTION
October 1 Cornell Tech Roosevelt Island Town Hall Community Update Presentation.Cornell Tech Director Of Capital Planning Andrew Winters describes construction status and plans for the campus.TRANSCRIPT
Campus Plan
Roosevelt Island campus> Laboratory of innovation> Open and inviting to the public> Sustainable and energy-efficient
BLOOMBERG CENTER
Public Open Space> More than 20% of the Site> No Gates, Walls or Barriers> Public Programming
Public Open Space> Laboratory of innovation> State of the art technologies> Sustainable and energy-efficient
Bloomberg Center> Collaborative Work Environment> Net-Zero Goal> Public Café, Art and Programming
The Bridge> Co-Location Space for Companies> Cornell Tech Studio Space> Common Spaces for Programming
Residential Building> First High Rise Passive House in the World> Housing for Students, Faculty & Staff
2017Phase One
Project Schedule
Start of Demolition January 2013End of Demolition June 2015
Start of Sitework December 2014Start of Bloomberg Ctr. March 2015Start of The Bridge May 2015Start of Residential June 2015
Phase I Opening Summer 2017
December 2014
January 2015
February 2015
March 2015
April 2015
May 2015
June 2015
July 2015
August 2015
September 2015
October 1, 2015
October 1, 2015
Bloomberg Center
October 1, 2015
Bloomberg Center
The Bridge (Co-Location)
October 1, 2015
Bloomberg Center
The Bridge (Co-Location)
Residential Building
October 1, 2015
Current & Upcoming Work
Sitework• Utility installation on East and West roads (closed to public)• Utility installation on campus• Completion of CUP structure & start of equipment installation
• North Road to re-open by the week of October 12
Bloomberg Center• Steel structure started September• Façade/enclosure to start in January 2016
The Bridge (Co-Location)• Steel structure to start in early October• Façade/enclosure to start in Winter 2016
Residential• Superstructure to start in mid October• Façade/enclosure to start in Winter 2016
September 2015
Utilities & Roadways
September 2015
Utilities & Roadways
September 2015
Bloomberg Center
September 2015
Bloomberg Center
September 2015
Bridge (Co-Location)
September 2015
Bridge (Co-Location)
September 2015
Residential
September 2015
Residential
Construction Commitments Reduce truck traffic through largest voluntary
barging effort in NYC history
Minimum 17% MWBE participation in construction
Union labor on all construction projects
On-site air monitoring for duration of the project
Extensive roadway & utility improvements
Close communication with Roosevelt Island stakeholders
Barging for Demolition
Reduction of more than 12,000 truck trips on Main Street
September 2015
Barging for Demolition
Barging for Construction
Barging for Construction
Barging for Construction
Barging for Construction
Barging for Construction
September 2015
Barging for Construction
1
3
2
4
Upcoming Milestones
• Reopening of North Loop Road
• Relocation of West Road fence to facilitate road reconstruction
• Steel construction at Bloomberg Center & The Bridge
• Concrete superstructure at Residential Building
• Start of geothermal wellfield
2017