Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011

Upload: others

Post on 21-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University

Unknown Data Center Somewhere, USA

4.12.2011

Page 2: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University

Unknown Data Center Somewhere, USA

4.12.2011

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Electrical Breadth

Tablet PC’s for Commissioning

Acknowledgements

Questions

Presentation Outline:

Page 3: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline: PROJECT OVERVIEW

o Owner – Anonymous

o Occupancy Type - Business

o Size - 17,445 SF South Expansion

o Cost - $ 50 Million (Design+Construction)

o Construction Duration - December 2008 – August 2010

o Delivery Method - Design-Bid-Build

oProject Team

CM – Turner Construction Architect/Engineers – Sigma 7 Design Group Civil – Birdsall Services Group Structural – Goldstein Associates

3

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Conclusions

Acknowledgements

Questions

Page 4: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline: PROJECT OVERVIEW

4

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Conclusions

Acknowledgements

Questions

o Building Enclosure

• Architectural Precast Panels

• Total of 33 Panels to enclose the building

• Penthouse enclosed with EIFS

o Existing Roof Structure:

• Primary Roof - Composite, EPDM w/ Concrete Pavers

• Penthouse Roof – Composite, Standing Seam Metal Roof

Page 5: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o Opportunity

• Redesigning the 20’ Parapet Wall

• Tilt-up vs. Precast

o Objective

• Lower Material/Labor Cost

• Accelerate Schedule

5

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 6: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o Conceptual Design:

o Deduction of 10’

o Design Criteria:

o Line of Sight

o Penthouse vs. Building Enclosure

6

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 7: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o Sequence

o Follow the same sequence as Precast (33)

o Panels are formed and stacked onsite

o Site Layout

o Need to Revise Site Layout Plan

o Tilt-up Increases Site Congestion

7

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 8: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o RS Means:

o $41.5/ SF – Precast

o $15/ SF – Tilt-up

o Total Savings

o $160,000 – Includes design

o $327,000 – Includes design and method

8

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 9: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o Schedule Impact:

o Precast – 3.3 panels / day

o Tilt-up – 4 panels / hour

o 33 panels in a nine hour work day

o 9 days cut off cut from the critical path

9

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 10: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Façade Redesign/Tilt-Up Construction

o Conclusion:

o Total Savings of 327,000

o 9 Days off the Critical Path

o Recommendations:

o The owner should pursue Tilt-up Method, but take note on the

safety issues and quality concerns.

o Highly recommended for the Redesign – Savings of $160,000

o Money could pay for PV system

10

Project Overview

Façade Redesign/Tilt-Up Construction

• Area of Potential Improvement

• Proposed Design

• Tilt-Up Sequence

• Cost Analysis

• Schedule Impact

• Conclusion

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 11: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o Opportunity

o Building is Oriented South

o Opportunity to utilize the Penthouse roof for design

o Objective

o Design a Preliminary Photovoltaic System

o Perform a Financial Feasibility Study

o Reduce Energy Cost of the Building

11

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 12: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o What will the power from the panels essentially replace?

o Conclusion:

o The design will be able to power all of the lighting fixtures in the

building.

o 125 panels required – Design consist of 129 panels

o 105 panels located on west penthouse

o 24 panels located on east penthouse

12

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 13: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o Calculate Optimal Tilt in Panels

o West Penthouse – 40°

o East Penthouse - 32°

o Determine Most Efficient Panel:

o Sanyo Electric, HIP-200BA19/20

13

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 14: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o PV Watts Calculations:

o System Produces 31,000 kWh / Year

o Yearly Savings of $3900

14

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 15: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o Energy Distribution:

o DC – Inverter – AC – Grid system

o Inverter:

o Sunny Tower ST 36

o Easy mount

o Includes all DC/AC connections

o Voltage Drop:

o DC - Use #8 AWG Wire 15

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 16: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o Total System Cost:

o $250,000

o W/ Rebates and Incentives: = $160,000

o Potential Buy back – 17-18 years 16

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

o Schedule Impact:

o Once the penthouses are constructed, the PV contractor can start

o Main Concern is Crane Usage

o Should not affect the critical path

Page 17: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Alternate Roof Type – Photovoltaic System

o Conclusion :

o Up front cost - $160,000

o Potential Buyback of 17-18 years

o Does not affect schedule’s critical path

o Recommendation:

o Highly recommended for the owner to consider this preliminary

design.

o Owner has potential to pay for the whole up front cost of this

system 17

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

• Area of Improvement

• Proposed PV System

• Electrical Breadth

• Cost Analysis/Schedule Impact

• Conclusion

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 18: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Tablet PCs for Commissioning

o Tablet PC Use:

o Quality Control

o Punch List Management

o Production Tracking

o Materials Management

o Safety

o Commissioning

o BIM in the Field

o Visual Reporting

18

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

• Introduction

• Potential Benefits/Challenges

• Case Study

• Conclusion

Acknowledgements

Questions

Page 19: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Tablet PCs for Commissioning

o Potential Benefits:

o Store PDF and paper forms of the budget, schedule, and specs.

o Easier to organize and manage while onsite

o Record performance of mechanical equipment

o Record issues during the commissioning process

o Reference the data on future projects

19

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

• Introduction

• Potential Benefits/ Challenges

• Case Study

• Conclusion

Acknowledgements

Questions

o Challenges:

o Tablet are exposed to hazards on the construction jobsites

o Weather may affect the life of the tablet

o Lack of knowledge in this industry

oUsing the tablets to it’s full advantage

Page 20: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Tablet PCs for Commissioning

o Case Study (Maryland General Hospital)

o Barton Malow – CM

o $57 Million renovation

o Includes an array of indoor AHU

o 650 –ton electric chillers/cooling towers

o Tablets for commissioning

o Collected data and documents as one integrated unit with their 3D

model.

o Eliminated all data re-entry

o Commissioning and their BIM Model totally in synched

20

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

• Introduction

• Potential Benefits/Challenges

• Case Study

• Conclusion

Acknowledgements

Questions

“The same tasks that used to take us days to manage and track,

now take just hours”

Page 21: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Tablet PCs for Commissioning

o Recommendations:

o All CM firms to use tablet PCs for the whole construction process

o For commissioning – highly recommended for complex MEP

projects (hospitals, data centers)

o Conclusion:

o Hard to determine actual value in cost and schedule acceleration.

21

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

• Introduction

• Potential Benefits/Challenges

• Case Study

• Conclusion

Acknowledgements

Questions

Page 22: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Acknowledgements

o Academic Acknowledgments

o Penn State AE Faculty

o Dr. Rob Leicht

o Industry Acknowledgements:

o Turner Construction

o Sigma 7 Design Group

o Special Thanks to:

o Frank Forcino @ Turner Construction

o Tom Atrens @ Turner Construction

o Family and Friends

22

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions

Page 23: Coppin State University Presentation.pdfThe Pennsylvania State University Unknown Data Center Somewhere, USA 4.12.2011 Project Overview Façade Redesign/Tilt-Up Construction Alternate

Presentation Outline:

Daniel Suter | Construction Management | 4.12.2011

Unknown Data Center Somewhere, USA Questions

23

Project Overview

Façade Redesign/Tilt-Up Construction

Alternate Roof Type – Photovoltaic System

Tablet PC’s for Commissioning

Acknowledgements

Questions