contractor track: need for speed - project acceleration, tech trends, logistics - part 3

31

Upload: energy-construction-forum

Post on 17-Jan-2017

496 views

Category:

Business


2 download

TRANSCRIPT

•    Vice  President  of  PK  Industrial    

•    PKI  is  one  of  the  Largest  Intumescent  Shop  Applicators          in  North  America    

•    Developed  Proven  Techniques  and  Cost  Comparisons  to          help  establish  the  Intumescent    Fireproofing    Industry    

•    Provides  services  to  Fortune  500  Oil  and  Gas  companies            around  the  world.  

Landon  Riggs  Background  in  Intumescent  Fire  ProtecMon  

 

Need  for  Speed  Project  AcceleraMon:  

 Passive  Fire  ProtecMon    

     

Presenta/on  Agenda  

•    Types  of  Passive  Fire  Protec/on    •    ApplicaMon  in  the  Shop      •    Total  Installed  Cost  (TIC)    •    QuesMons  

 Typically  1  of  3  Types  

 

•  High  Density  Concrete  •  Light  Weight  CemenMMous  •  Epoxy  Intumescent  

       

Types  of  Passive  Fire  ProtecMon  Materials  

     “  A  coaMng  which  reacts  to  heat  by  swelling  in    a  controlled  manner  to  many  Mmes  its  original  thickness  to  produce  a  carbonaceous  char,    which  acts  as  an  insulaMng  layer  to  protect    the  steel  substrate.”  

-­‐How  Does  it  work?  

Epoxy  Intumescent      

•    Intumesce  is  an  expansion  or  foaming  process  whereby                an  insulaMng  char  is  formed  at  the  fire  surface.  

Epoxy  Based  materials  “intumesce”  

Epoxy  Intumescent      

Box  and  Contour        

Contour        

Presenta/on  Agenda  

•    Types  of  Passive  Fire  ProtecMon    •    Applica/on  in  the  Shop      •    Total  Installed  Cost  (TIC)    •    QuesMons  

       

Receive  Carbon  Steel  Sandblasted  Shop  Primed  Steel  

DAY  1      

IdenMfy  Block-­‐Out  ConnecMons  

       

Receive  Carbon  Steel  Sandblasted  Shop  Primed  Steel  1st  Intumescent  ApplicaMon  Mesh  ApplicaMon  (if  necessary)  

DAY  2      

       

Receive  Carbon  Steel  Sandblasted  Shop  Primed  Steel  1st  Intumescent  ApplicaMon  

2nd  Intumescent  ApplicaMon  

DAY  3      

Mesh  ApplicaMon  (if  necessary)  

       

DAY  4      

Receive  Carbon  Steel  Sandblasted  Shop  Primed  Steel  1st  Intumescent  ApplicaMon  

Finishing  Top  Coat  2nd  Intumescent  ApplicaMon  Mesh  ApplicaMon  (if  necessary)  

       

Ready  for  Shipment  Day  5  

DAY  5      

Modular  Assembly      

Presenta/on  Agenda  

•    Types  of  Passive  Fire  ProtecMon    •    ApplicaMon  in  the  Shop      •    Total  Installed  Cost  (TIC)    •    QuesMons  

 

•  No  Galvanizing  Required  •  50%  Savings  on  TransportaMon  •  No  Scaffolding  in  the  Field  •  SubstanMal  Durability          Less  Damage  During  Shipment    •  Intangibles    

     

Total  Installed  Cost      

Light  Weight  Concrete:    Trailer  Load  

Intumescent  Fire  Proofing:    Trailer  Load  

50%  Cost  Savings  in  Shipping      

Presenta/on  Agenda  

•    Types  of  Passive  Fire  ProtecMon    •    ApplicaMon  in  the  Shop      •    Total  Installed  Cost  (TIC)    •    Ques/ons  

QuesMons?