Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday, April 28, 2015

Upload: rosalind-norris

Post on 22-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Contract Claims–Analysis and Avoidance

Sudhir DamlePrincipal – DHS Consulting, Inc.

and

John UnbewustDirector – Trauner Consulting Services

Tuesday, April 28, 2015

Page 2: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Meet Your Instructors – Sudhir Damle

Sudhir Damle• Civil Engineer, P.E.• 35 years of construction industry

experience, claims avoidance and resolution

• President of DHS Consulting, Inc.• DHS Consulting Program and Construction

Management firm

CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 1 April 28, 2015

Page 3: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Meet Your Instructors – John Unbewust

John Unbewust, P.E.• Director, Trauner Consulting Services• 40 years of construction experience• Former DOT Chief Engineer• Expert in forensic analysis of construction

phase contract claims• Significant experience revising/rewriting

DOT Standard Specifications• Significant experience implementing

alternative delivery methods• Significant experience creating and

implementing management controls

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 3

Page 4: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Introduction

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 4

The typical successful construction project benefits from two key components:• Quality contract documents, and• Quality construction management.

Seminar goal:• How to avoid/mitigate claims on projects;• Review project development processes;• Review construction phase management;• Resolve disputes fairly and timely; and• Identify tools for managing claims.

Page 5: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Introduction

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 5

ORIGIN OF CLAIMS

• Claims are generated by actions taken from Project Conception, Planning, Design and Construction• Seeds that Owners/AE Design firms plant that

germinate and become potential disputes/claims

Page 6: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Project Pre Bid

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 6

Page 7: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

KEY AREAS TO ADDRESS IN CONTRACT DOCUMENTS• Scope Definition & Realistic Timeline• Existing Site conditions• Design Errors and Omissions• Specifications • Drawings• Contract Language • Bid Documents & Q/A

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 7

Page 8: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

SCOPE DEFINITION & REALISTIC TIMELINE• Completeness of Scope Definition • Adjoining work added after NTP• Additional work added during the job• Developing Realistic Timeline/durations

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 8

Page 9: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

EXISTING SITE CONDITIONS• Reluctance by owners to identify all unknown

site conditions• Verifying As-Built Conditions• Inconsistent/Generic Geotechnical Reports• Incomplete Site Surveys

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 9

Page 10: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Example of Claim Dispute – DUCTBANK LOCATION

• Duct Bank Location conflicting with Existing Building Foundation• “Blame Game”• Six Weeks Lost in Schedule• Claim - $150 ThousandSOLUTION: 1) Agency to provide As-Builts to GC Pre-Bid; and

2) Designer to job walk before routing the duct bank.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 10

Page 11: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Example of Claim Dispute – SEWER LINE CONVEYANCE

• Bore Hole Data showed No Rock Conflict• Generic Comment stated “Expect Rock in Area”• 80% rock found along route • Major Claim - $4 Million SOLUTION: Add Bid Item for Rock with a Cost/CY and a reasonable quantity.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 11

Page 12: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

DESIGN ERRORS & OMISSIONS• Completion of Design• Design criteria in conflict with Local agencies• Deferred Approvals – Fire Sprinkler • Over-Design versus Under-Design• Omissions• Delegated Design

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 12

Page 13: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Example of Claim Dispute – PIPE SUPPORTS

• Specifications outline Spacing Requirements for Pipe Supports• Drawings only show a few Pipe Supports • Drawing Note specifies that “No Attempt Made to Show All Pipe

Supports”• Major Claim - $10 Million SOLUTION: 1) Drawing Note should have been on

the same page where pipe supportswere shown.

2) Additional note that contractor shallcalculate the loading and determinenumber of supports required.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 13

Page 14: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

SPECIFICATIONS• Conflicting Standards/sections• Unclear Hierarchy • Specifications referenced to drawings • Specifications in conflict with local codes• Specifications not updated• Specifications that state “and or equal” material,

equipment etc.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 14

Page 15: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

DRAWINGS• Not to Scale – Misleading• Lacking Specification Notations• Incorrect Revision• Conflict with Specs• Scope omitted• Detailing errors

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 15

Page 16: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

CONTRACT LANGUAGE• Lacking clarity• Conflicting sections• Overly onerous specs• Vague conflict resolution

language

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 16

Page 17: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS

BID DOCUMENTS & Q/A• No involvement by third party stakeholders

(private companies, public utilities, city planners)• Schedule of values to reflect the entire scope in

the drawings• Escrow of Bid Documents

Proposed manpower Was the complete scope bid?

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 17

Page 18: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

POTENTIAL DISPUTES / CLAIMS – Conclusion

WHAT CAN THE OWNER DO TO AVOID/MITIGATE CLAIMS?1. Third Party Constructability Reviews2. Clarity and Completeness of Contract Docs3. Develop a Risk Mitigation Register4. Comprehensive Sign Off by Stakeholders5. Have a Risk Mitigation Manager in place early

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 18

Page 19: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

RISK MITIGATION

RISK MITIGATION MANAGER ROLE• Pro active risk management before and after bid• Front line in recognizing potential

disputes/claims• Assist in mitigating and resolving disputes during

the job• Responsible for all contemporaneous

documentation on all disputed issues and claims

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 19

Page 20: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Project Pre Bid

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 20

Page 21: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Contract Claims–Analysis and Avoidance

BREAK

BREAK

BREAK

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 21

Page 22: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Quality Construction Management

Quality construction management; attributes that help avoid/mitigate construction claims:• Understanding the role of the Construction Manager;• Understanding of the contract/owner’s intent;• Industry experience (technical);• Working knowledge of the general provisions;• Close coordination/working relationship with the contractor;• Good documentation practices;• Proactive issue identification, analysis, and resolution;• Responsiveness to requests; and• Open communication.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 22

Page 23: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Construction Manager

Understanding the role of the Construction Manager:• Scope of services in CM Agreement• Role of the Construction Manager• Relationship with the owner• Role of the architect• Relationship with the architect• Duration of services• Location of services• Agreement budget (time and cost)

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 23

Page 24: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Contract Documents

Understanding the Contract Documents:• Bid document;

Including GCs, GPs, and Specs Including Drawing list and dates Including the Estimated Quantities and Prices

• Bid Addenda;• Notice of Award;• Executed Contract;• Notice to Proceed;• Notice, Submission, and Response times;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 24

Page 25: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – General Provisions

Understanding the General Provisions/General Conditions:• General Information, Definitions, and Terms

Definitions are very important• Bidding Requirements and Conditions• Contract Award and Execution• Scope of Work• Controlling Work• Controlling Material• Legal Relations and Responsibility to the Public• Prosecution and Progress• Measurement and Payment

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 25

Page 26: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Owner’s Intent

Understanding the project scope of work and the owner’s intent:• Project Scope of Work• Project Budget• Project Schedule• Owner’s expectations

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 26

Page 27: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Industry Experience

Recognizing issues that may create impacts as early as possible:• Focus on minor issues that may lead to bigger problems;• Categorize types of issues;• Collect data on recurring issues;• Start documenting the consequences in the field of issues that

cause impacts;• Review issues regularly with the contractor;• Identify and implement mitigation measures as appropriate.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 27

Page 28: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – General Provisions

A working knowledge of the general provisions includes understanding the changes clause and related clauses:• Changes Clause• Spearin Doctrine• Coordination Clause (Order of Precedence)• Latent changes• Patent changes

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 28

Page 29: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes

Construction contracts are the only contracts that allow for the possibility of changes and address how to modify the contract to implement contract changes.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 29

Page 30: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes Clause

Attributes of a Changes Clause:• Right to modify the contract• Functional system to implement changes• Provides for the continuation of work

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 30

Page 31: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes Clause

Example of a changes clause from AIA, Article 7.1.1:• Changes in the Work may be accomplished after execution of the

Contract, and without invalidating the Contract, by Change Order, Construction Change Directive, or order for a minor change in the Work, subject to the limitations stated in . . . .the Contract Documents.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 31

Page 32: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes Clause

Right to modify language in the contract from AIA, Article 7.1.1:• Changes in the Work may be accomplished after execution of the

Contract, and without invalidating the Contract, by Change Order, Construction Change Directive, or order for a minor change in the Work, subject to the limitations stated in . . . .the Contract Documents.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 32

Page 33: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes Clause

Change implementation language in the contract from AIA, Article 7.1.1:• Changes in the Work may be accomplished after execution of the

Contract, and without invalidating the Contract, by Change Order, Construction Change Directive, or order for a minor change in the Work, subject to the limitations stated in . . . .the Contract Documents.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 33

Page 34: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Changes Clause

Continuation of work language in the contract from the Engineers Joint Contract Documents Committee (EJCDC), Article 10.01.A:• . . . .Owner may, at any time or from time to time, order

additions, deletions, or revisions in the Work by a Change Order, or a Work Change Directive.

• Upon receipt of any such document, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 34

Page 35: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Spearin Doctrine

The Spearin Doctrine:• In every construction contract, the owner impliedly warrants that

the plans and specifications are accurate and sufficient to build the project.

• The contractor can recover the cost of delays, disruption, and additional work associated with defective plans and specifications from the party who provides the inadequate plans and specifications.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 35

Page 36: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Coordination Clause

Understanding the coordination clause and order of precedence:• Special Provisions• Technical specifications• Plan notes• Plans• Standard Plans• Supplemental Specifications• Standard Specifications• General Provisions

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 36

Page 37: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Latent Conditions

Understanding latent physical conditions:• Latent conditions are those that cannot be identified during site

inspection and reasonable investigation.• How a latent condition will be addressed will depend on the

terms of the contract.• Allocation of the risk for latent conditions on a project depends

on which party is best able to address that risk.• Consideration of physical site conditions, available information,

technical investigations and results, and expertise of investigator.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 37

Page 38: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Patent Conditions

Understanding patent conditions:• Patent defect is anything that renders the work unfit for the use

it was intended for, when used in a reasonable way and with reasonable care.

• In the context of a construction contract, work may be defective if it is not carried out in accordance with the contract.

• A patent defect could be discovered by competent professional inspection.

• A patent defect is obvious, observable, but may not be observed.• A defect is patent if it is reasonably discoverable with the benefit

of skilled third party advice, such as from an architect or engineer.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 38

Page 39: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Types of Changes

Types of changes include:• Significant Changes in Character of Work• Differing Site Conditions • Suspension of Work• Extra Work• Eliminated Work

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 39

Page 40: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Significant Changes

Significant Changes in the Character of the Work:• If alterations or changes in quantities significantly change the

character of the work under the contract, an adjustment will be made to the contract.

• The owner will adjust a contract price based on the difference between the cost to perform the work as planned and the cost to perform the work as changed.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 40

Page 41: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Significant Changes

Example of a Significant Changes in the Character of the Work Clause from Caltrans, Section 4-1.05B:• An ordered plan or specification change materially changes the

character of a work item from that on which the bid price was based;

• The unit cost of the changed item differs when compared to the unit cost of that item under the original plans and specifications; or

• No approved Change Order addresses the payment.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 41

Page 42: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Differing Site Conditions

Differing Site Conditions:• Type 1: Subsurface or latent physical conditions at the site which

differ materially from those indicated in this contract.• Type 2: Unknown physical conditions at the site of an unusual

and unpredictable nature.• CA Type 3: Unanticipated hazardous waste at the site, unless the

hazardous material is material brought on site by the contractor.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 42

Page 43: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Suspension of Work

Example of a Suspension of Work clause from Engineers Joint Contract Documents Committee (EJCDC), Article 15.01:• At any time and without cause, Owner may suspend the Work or

any portion thereof for a period of not more than 90 consecutive days and fix the date on which Work will be resumed.

• Contractor shall resume the Work on the date so fixed.• Contractor shall be granted an adjustment in the Contract Price

or an extension of the Contract Times, or both.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 43

Page 44: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Extra Work

Example of an Extra Work clause from the Colorado DOT, Subsection 104.03:• Contractor shall perform unforeseen work, for which there is no

price included in the Contract, whenever the extra work is necessary or desirable for contract completion;

• This work shall be performed in accordance with the Contract and as directed; and

• Work will be paid for as provided in Subsection 109.04, Compensation for Changes and Force Account Work.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 44

Page 45: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Eliminated Work

Example of an Eliminated Work clause from the Colorado DOT, Subsection 104.03:• Should any items contained in the Contract be found unnecessary

for the proper completion of the work, the Engineer will notify the Contractor in writing, to eliminate the item;

• Such action will not invalidate the Contract;• The Contractor will be reimbursed for actual work done and all

costs incurred . . . . . .

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 45

Page 46: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Change

Definition of a Change:• A change is the difference between the contract requirements at

the time of bid and the actual requirements imposed during construction.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 46

Page 47: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Addressing Change

How to address Change:• Proactive issue identification, analysis, and resolution;• Good documentation practices;• Close coordination/working relationship with the contractor;• Responsiveness to requests; and• Open communication.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 47

Page 48: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Addressing Change

Proactive issue identification, analysis, and resolution:• During the design phase (constructability issues);• Between bid opening and Notice to Proceed (pricing issues);• During the initial construction phase (work plan); • Throughout the project duration (progress).

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 48

Page 49: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Documentation

Documentation Practices – Tools for Analyzing Time and Cost Impacts:• Schedules (delays)• Job cost reports (labor hours)• Force account records (cost justification)• Daily diaries (issue description)• Pictures/video of impacted work (issue verification)• Schedule of values/monthly estimates (production)• Time count charges (project status)

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 49

Page 50: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Documentation

The value of good documentation:• Consider as an insurance policy;• Contemporaneous analysis, not forensic;• Document while issue is fresh, recall is vivid, and staff is present;• Facilitates issue resolution;• Potential for reduced time and cost impacts after project

completion;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 50

Page 51: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Addressing Change

Close coordination/working relationship with the Contractor:• Reviewing baseline and monthly update schedules;• Facilitating weekly meetings;• Reviewing rolling look-ahead schedules;• Planning/scheduling reviews and inspections;• Responding timely to RFIs;• Coordinating/scheduling resources needed;• Resolving issues;• Executing contract change orders.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 51

Page 52: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Responding to Change

Responsiveness to requests:• Timely response to RFIs;• Timely review of contractor submissions;• Timely review of pay applications;• Planning/scheduling reviews and inspections;

Responsiveness to issues:• Proactive issue identification, analysis, and resolution;• Frequent coordination with contractor;• Timely consideration of options and decision-making;• Focus on mitigation of impacts (cost and time)

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 52

Page 53: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Communication

Open communication:• Discussing work progress;• Discussing issues encountered or anticipated;• Sharing information, issue analyses, findings;• Discussing potential impacts and mitigation measures;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 53

Page 54: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Construction Management

What is the primary benefit of quality construction management?

“You can – pay me now, or pay me later”

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 54

Page 55: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Construction Management

Why is Construction Management so important?• Addressing issues before they create impacts;• Identifying alternatives that mitigate impacts;• Minimizing the cost of change;• Timely bringing a project on line.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 55

Page 56: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Claims

What is a claim?• A claim is an unresolved change.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 56

Page 57: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Components of a Claim

What are the key components of a claim?• Entitlement or merit;• Impact and who was responsible for the impact; and• Costs or damages.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 57

Page 58: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Entitlement

Entitlement or Merit:• Contractual basis for the claim;• Specification references;• Interpretation of specifications; and• Reasonableness of references supporting the claim.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 58

Page 59: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Impacts

Impact and who was responsible for the impact:• Which party caused the impact;• What caused the impact?• How was project impacted?• Did impact delay the project; did it affect critical activities?• Could the impact been avoided or mitigated?• Did the Contractor perform mitigation measures?

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 59

Page 60: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Damages

Costs or Damages:• Quantification of the impact (dollars and time);• Basis for calculating cost;• Verification of costs;• Analysis of delay;• Determination of time (delay) caused by claim;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 60

Page 61: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Critical Path

Only delays to the project’s critical path can delay the project completion date.The Critical Path:• Determines the project’s completion date;• Is the longest continuous sequence of work;• Exists on every project; and• Is dynamic and can change throughout the course of the project.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 61

Page 62: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Critical Delays

Critical delays include the following categories:

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 62

Excusable Delays Non-Excusable Delays

Compensable Non-Compensable

Time & money Time, no money No time, no money

Page 63: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Inefficiency

Efficiency measurements determine if there is a difference in productivity – efficiency is relative to the base you are measuring against.• Productivity is a rate that equals:

Work PerformedResources Expended

• Efficiency is a rate that equals: Actual ProductivityExpected Productivity

• Inefficiency is based on a comparison of productivities.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 63

Page 64: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Measuring Inefficiency

Methods of measuring inefficiency include the following:• Measured mile;• Comparison with other projects;• Comparison with bid, estimate, or plan;• Use of experts; and• Use of published standards.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 64

Page 65: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Acceleration

Acceleration includes the following circumstances:• Action taken to improve completion date; and• Entails a change in sequence, a change in resources, or both.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 65

Page 66: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Avoiding Acceleration Claims

How to avoid acceleration claims:• Consider side effects of acceleration;• Change orders should address cost and time, when applicable;• Accelerate critical work only;• Determine cost-effective solution;• Give time extensions when due;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 66

Page 67: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Claims Avoidance/Mitigation

Contract Claims – Analysis and Avoidance• The importance of clear contract documents;

Including a specification for the management of claims.• Tools to support resolving disputes;• Timely resolving disputes and preventing claims;• Effectively managing claims; • Identifying the latest theory and practice in handling claims;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 67

Page 68: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Claims Specification

Example Claims Specification from the Engineers Joint Contract Documents Committee (EJCDC), Article 10.05:• Engineer’s Decision Required: A decision by Engineer shall be

required as a condition precedent to exercise of any rights or remedies.

• Notice: Written notice stating the general nature of each Claim shall be delivered by the claimant to Engineer and the other party to the Contract.

• Engineer’s Action: Engineer will review each Claim and deny, approve, or determine unable to resolve. If no action on a Claim within 30 days, the Claim shall be deemed denied.

• Engineer’s written action will be final and binding.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 68

Page 69: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Claims Specification

Claims Specification Attributes:• Request for Equitable Adjustment;• Notice;• Dedicated time limits for each step;• Identified presence of decision makers; and• Sequential issue escalation.

Optional Specification Requirements:• Escrowed bid documents; and• CPM schedules.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 69

Page 70: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Tools

Tools for Resolving Disputes/Claims:• General Provisions

Changes Claims Schedules (initial, baseline, update, rolling look ahead)

• Contemporaneous Project Records Schedules Job cost reports Force account records Daily diaries Pictures/videos Schedule of values/monthly estimates Time count charges

• Good documentation practices

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 70

Page 71: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Timely Claim Resolution

Timely Resolution of Disputes/Claims:• Proactive issue identification, analysis, and resolution;• Close coordination with the contractor;• Decision makers at the table;• Adherence to the issue escalation process.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 71

Page 72: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Claims Management

Effective Claims Management Techniques:• Communication;• Transparent document production;• Sharing information;• Joint issue discussion and resolution; and • Timely decision making.

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 72

Page 73: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – Alternative Dispute Resolution

Alternative Dispute Resolution• Dispute Resolution Boards• Mediation• Arbitration

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 73

Page 74: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Construction Contracts – The Best Alternative

Quality Construction Management – the Best Alternative: • Contemporary issue resolution;

CM and Contractor know project best; Issues and memories are current; Contemporary project records; Issues resolved as work progresses;

• Mitigation of costs; Alternative solutions may be available at the time; Alternative solutions implemented timely;

• Costs associated with ADR not necessary; Cost of claim preparation by CM and others; Time away from new work; Experts needed to support claim positions;

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 74

Page 75: Contract Claims–Analysis and Avoidance Sudhir Damle Principal – DHS Consulting, Inc. and John Unbewust Director – Trauner Consulting Services Tuesday,

Questions and Answers

For more information, please contact:• Sudhir Damle• [email protected]• 213-400-8430

• John Unbewust• [email protected]• 619-640-8500

April 28, 2015 CMAA San Diego Chapter: Contract Claims - Analysis and Avoidance 75