contoh lap. kemajuan pekerjaan jalan
DESCRIPTION
SipilTRANSCRIPT
![Page 1: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/1.jpg)
REKAPITULASI PROGRESSKEGIATAN : REHABILITASI/PEMELIHARAAN JALAN
PEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYU
KONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANT
RUAS JALAN : BETONISASI JALAN SADANG
VOLUME : 186m x 6m
KONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN PEKERJAAN
0% 0%
1 2 3 4
I PEKERJAAN PERSIAPAN 0.70 0.70
II PEKERJAAN TANAH 0.04 0.04
III PEKERJAAN PERKERASAN BERBUTIR 1.03 1.03
IV PERKERASAN ASPAL 0.83 0.83
V PEKERJAAN STRUKTUR 97.39 97.39
TOTAL 100.00 100.00
BOBOT PRESTASI s/d BULAN INI 100.00 BOBOT RENCANA PRESTASI BULAN INI 100.00 DEVIASI -
BOBOT PEKERJAAN
BOBOT KEMAJUAN PEKERJAAN
![Page 2: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/2.jpg)
LAPORAN PROGRESS BULANANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 - - 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 - DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 - PPN 10 %TOTAL JUMLAHDIBULATKAN
Disetujui Oleh Diperiksa OlehPEJABAT PELAKSANA TEKNIS KEGIATAN PELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG DINAS BINA MARGA KABUPATEN BANDUNG
CECEP MULYANA, ST. MT ERI HERNAWAN, STNIP. 19690311 199803 1 006 NIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL BULAN LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 3: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/3.jpg)
LAPORAN PROGRESS BULANAN09 Juli 2015 BULAN KE
s/d 105 Agustus 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.17 0.08 - - - -
0.08 0.08
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - 0.08 0.08
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
DENY WIGANDI, STSite Engineer
VOL BULAN INI
VOL s/d BULAN INI
![Page 4: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/4.jpg)
LAPORAN PROGRESS BULANANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.17 0.08 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 0.08 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 0.08 PPN 10 %TOTAL JUMLAHDIBULATKAN
Disetujui Oleh Diperiksa OlehPEJABAT PELAKSANA TEKNIS KEGIATAN PELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG DINAS BINA MARGA KABUPATEN BANDUNG
CECEP MULYANA, ST. MT ERI HERNAWAN, STNIP. 19690311 199803 1 006 NIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL BULAN LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 5: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/5.jpg)
LAPORAN PROGRESS BULANAN06 Agustus 2015 BULAN KE
s/d 202 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.51 0.14 0.68 0.31 0.25 0.06 0.25 0.06
0.20 0.37
7.20 - 7.20 0.04 - 0.04
- - - - - -
- - - - - - - -
- -
- - - - 18.00 - 18.00 3.81 - - - - 91.00 - 91.00 27.91
- 31.72 0.20 32.14
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
DENY WIGANDI, STSite Engineer
VOL BULAN INI
VOL s/d BULAN INI
![Page 6: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/6.jpg)
LAPORAN PROGRESS BULANANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.68 0.31 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.25 0.06
JUMLAH DIVISI 1 0.70 0.37 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 18.00 3.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 91.00 27.91
JUMLAH DIVISI 7 97.39 31.72 JUMLAH 100.00 32.14 PPN 10 %TOTAL JUMLAHDIBULATKAN
Disetujui Oleh Diperiksa OlehPEJABAT PELAKSANA TEKNIS KEGIATAN PELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG DINAS BINA MARGA KABUPATEN BANDUNG
CECEP MULYANA, ST. MT ERI HERNAWAN, STNIP. 19690311 199803 1 006 NIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL BULAN LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 7: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/7.jpg)
LAPORAN PROGRESS BULANAN03 September 2015 BULAN KE
s/d 330 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.85 0.38 0.25 0.06 0.50 0.13
0.14 0.51
- - 7.20 0.04 - 0.04
15.00 0.62 15.00 0.62 0.62 0.62
- - - - - - - -
- -
- - - - 18.00 3.81 36.00 7.62 - - - - 91.00 27.91 182.00 55.83
31.72 63.45 32.48 64.61
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
DENY WIGANDI, STSite Engineer
VOL BULAN INI
VOL s/d BULAN INI
![Page 8: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/8.jpg)
LAPORAN PROGRESS BULANANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.85 0.38 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.50 0.13
JUMLAH DIVISI 1 0.70 0.51 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 36.00 7.62 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 182.00 55.83
JUMLAH DIVISI 7 97.39 63.45 JUMLAH 100.00 64.61 PPN 10 %TOTAL JUMLAHDIBULATKAN
Disetujui Oleh Diperiksa OlehPEJABAT PELAKSANA TEKNIS KEGIATAN PELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG DINAS BINA MARGA KABUPATEN BANDUNG
CECEP MULYANA, ST. MT ERI HERNAWAN, STNIP. 19690311 199803 1 006 NIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL BULAN LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 9: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/9.jpg)
LAPORAN PROGRESS BULANAN01 Oktober 2015 BULAN KE
s/d 405 November 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.15 0.07 1.00 0.45 0.50 0.13 1.00 0.25
0.19 0.70
- - 7.20 0.04 - 0.04
10.20 0.42 25.20 1.03 0.42 1.03
24.00 0.07 24.00 0.07 2.16 0.76 2.16 0.76
0.83 0.83
- - - - 19.80 4.19 55.80 11.81 - - - - 97.00 29.75 279.00 85.58
33.95 97.39 35.39 100.00
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
DENY WIGANDI, STSite Engineer
VOL BULAN INI
VOL s/d BULAN INI
![Page 10: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/10.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 - - 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 - DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 - PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 11: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/11.jpg)
LAPORAN PROGRESS MINGGUAN09 Juli 2015 MINGGU KE
s/d 115 Juli 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - - - - - - -
- -
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - - -
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 12: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/12.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 - - 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 - DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 - PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 13: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/13.jpg)
LAPORAN PROGRESS MINGGUAN16 Juli 2015 MINGGU KE
s/d 222 Juli 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - - - - - - -
- -
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - - -
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 14: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/14.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 - - 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 - DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 - PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 15: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/15.jpg)
LAPORAN PROGRESS MINGGUAN23 Juli 2015 MINGGU KE
s/d 329 Juli 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - - - - - - -
- -
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - - -
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 16: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/16.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 - - 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 - DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 - PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 17: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/17.jpg)
LAPORAN PROGRESS MINGGUAN30 Juli 2015 MINGGU KE
s/d 405 Agustus 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.17 0.08 - - - -
0.08 0.08
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - 0.08 0.08
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 18: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/18.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.17 0.08 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 - -
JUMLAH DIVISI 1 0.70 0.08 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 0.08 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 19: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/19.jpg)
LAPORAN PROGRESS MINGGUAN06 Agustus 2015 MINGGU KE
s/d 512 Agustus 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 0.17 0.08 0.25 0.06 0.25 0.06
0.06 0.14
- - - - - -
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - 0.06 0.14
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 20: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/20.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.17 0.08 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.25 0.06
JUMLAH DIVISI 1 0.70 0.14 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 - - JUMLAH DIVISI 3 0.04 -
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 0.14 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 21: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/21.jpg)
LAPORAN PROGRESS MINGGUAN13 Agustus 2015 MINGGU KE
s/d 619 Agustus 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.34 0.15 - - 0.25 0.06
0.08 0.22
7.20 0.04 7.20 0.04 0.04 0.04
- - - - - -
- - - - - - - -
- -
- - - - - - - - - - - - - - - -
- - 0.12 0.26
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 22: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/22.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.34 0.15 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.25 0.06
JUMLAH DIVISI 1 0.70 0.22 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 - - 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 - -
JUMLAH DIVISI 7 97.39 - JUMLAH 100.00 0.26 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 23: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/23.jpg)
LAPORAN PROGRESS MINGGUAN20 Agustus 2015 MINGGU KE
s/d 726 Agustus 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.51 0.23 - - 0.25 0.06
0.08 0.29
- - 7.20 0.04 - 0.04
- - - - - -
- - - - - - - -
- -
- - - - 18.00 3.81 18.00 3.81 - - - - 91.00 27.91 91.00 27.91
31.72 31.72 31.80 32.06
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 24: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/24.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.51 0.23 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.25 0.06
JUMLAH DIVISI 1 0.70 0.29 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 18.00 3.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 91.00 27.91
JUMLAH DIVISI 7 97.39 31.72 JUMLAH 100.00 32.06 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 25: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/25.jpg)
LAPORAN PROGRESS MINGGUAN27 Agustus 2015 MINGGU KE
s/d 802 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.68 0.31 - - 0.25 0.06
0.08 0.37
- - 7.20 0.04 - 0.04
- - - - - -
- - - - - - - -
- -
- - - - - - 18.00 3.81 - - - - - - 91.00 27.91
- 31.72 0.08 32.14
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 26: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/26.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.68 0.31 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.25 0.06
JUMLAH DIVISI 1 0.70 0.37 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 - -
JUMLAH DIVISI 5 1.03 - DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 18.00 3.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 91.00 27.91
JUMLAH DIVISI 7 97.39 31.72 JUMLAH 100.00 32.14 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 27: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/27.jpg)
LAPORAN PROGRESS MINGGUAN03 September 2015 MINGGU KE
s/d 909 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 0.68 0.31 0.25 0.06 0.50 0.13
0.06 0.43
- - 7.20 0.04 - 0.04
15.00 0.62 15.00 0.62 0.62 0.62
- - - - - - - -
- -
- - - - - - 18.00 3.81 - - - - - - 91.00 27.91
- 31.72 0.68 32.81
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 28: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/28.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.68 0.31 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.50 0.13
JUMLAH DIVISI 1 0.70 0.43 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 18.00 3.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 91.00 27.91
JUMLAH DIVISI 7 97.39 31.72 JUMLAH 100.00 32.81 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 29: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/29.jpg)
LAPORAN PROGRESS MINGGUAN10 September 2015 MINGGU KE
s/d 1016 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.17 0.08 0.85 0.38 - - 0.50 0.13
0.08 0.51
- - 7.20 0.04 - 0.04
- - 15.00 0.62 - 0.62
- - - - - - - -
- -
- - - - 18.00 3.81 36.00 7.62 - - - - 91.00 27.91 182.00 55.83
31.72 63.45 31.80 64.61
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 30: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/30.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.85 0.38 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.50 0.13
JUMLAH DIVISI 1 0.70 0.51 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 36.00 7.62 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 182.00 55.83
JUMLAH DIVISI 7 97.39 63.45 JUMLAH 100.00 64.61 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 31: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/31.jpg)
LAPORAN PROGRESS MINGGUAN17 September 2015 MINGGU KE
s/d 1123 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 0.85 0.38 - - 0.50 0.13
- 0.51
- - 7.20 0.04 - 0.04
- - 15.00 0.62 - 0.62
- - - - - - - -
- -
- - - - - - 36.00 7.62 - - - - - - 182.00 55.83
- 63.45 - 64.61
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 32: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/32.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.85 0.38 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.50 0.13
JUMLAH DIVISI 1 0.70 0.51 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 36.00 7.62 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 182.00 55.83
JUMLAH DIVISI 7 97.39 63.45 JUMLAH 100.00 64.61 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 33: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/33.jpg)
LAPORAN PROGRESS MINGGUAN24 September 2015 MINGGU KE
s/d 1230 September 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 0.85 0.38 - - 0.50 0.13
- 0.51
- - 7.20 0.04 - 0.04
- - 15.00 0.62 - 0.62
- - - - - - - -
- -
- - - - - - 36.00 7.62 - - - - - - 182.00 55.83
- 63.45 - 64.61
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 34: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/34.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.85 0.38 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.50 0.13
JUMLAH DIVISI 1 0.70 0.51 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 36.00 7.62 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 182.00 55.83
JUMLAH DIVISI 7 97.39 63.45 JUMLAH 100.00 64.61 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 35: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/35.jpg)
LAPORAN PROGRESS MINGGUAN01 Oktober 2015 MINGGU KE
s/d 1307 Oktober 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 0.85 0.38 0.25 0.06 0.75 0.19
0.06 0.57
- - 7.20 0.04 - 0.04
- - 15.00 0.62 - 0.62
- - - - - - - -
- -
- - - - 19.80 4.19 55.80 11.81 - - - - 97.00 29.75 279.00 85.58
33.95 97.39 34.01 98.62
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 36: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/36.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 0.85 0.38 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.75 0.19
JUMLAH DIVISI 1 0.70 0.57 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 15.00 0.62
JUMLAH DIVISI 5 1.03 0.62 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 55.80 11.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 279.00 85.58
JUMLAH DIVISI 7 97.39 97.39 JUMLAH 100.00 98.62 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 37: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/37.jpg)
LAPORAN PROGRESS MINGGUAN08 Oktober 2015 MINGGU KE
s/d 1414 Oktober 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
0.15 0.07 1.00 0.45 - - 0.75 0.19
0.07 0.64
- - 7.20 0.04 - 0.04
10.20 0.42 25.20 1.03 0.42 1.03
- - - - - - - -
- -
- - - - - - 55.80 11.81 - - - - - - 279.00 85.58
- 97.39 0.49 99.11
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 38: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/38.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 1.00 0.45 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.75 0.19
JUMLAH DIVISI 1 0.70 0.64 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 25.20 1.03
JUMLAH DIVISI 5 1.03 1.03 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 - - 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 - -
JUMLAH DIVISI 6 0.83 - DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 55.80 11.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 279.00 85.58
JUMLAH DIVISI 7 97.39 97.39 JUMLAH 100.00 99.11 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 39: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/39.jpg)
LAPORAN PROGRESS MINGGUAN15 Oktober 2015 MINGGU KE
s/d 1521 Oktober 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 1.00 0.45 - - 0.75 0.19
- 0.64
- - 7.20 0.04 - 0.04
- - 25.20 1.03 - 1.03
24.00 0.07 24.00 0.07 2.16 0.76 2.16 0.76
0.83 0.83
- - - - - - 55.80 11.81 - - - - - - 279.00 85.58
- 97.39 0.83 99.94
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 40: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/40.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 1.00 0.45 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 0.75 0.19
JUMLAH DIVISI 1 0.70 0.64 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 25.20 1.03
JUMLAH DIVISI 5 1.03 1.03 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 24.00 0.07 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 2.16 0.76
JUMLAH DIVISI 6 0.83 0.83 DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 55.80 11.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 279.00 85.58
JUMLAH DIVISI 7 97.39 97.39 JUMLAH 100.00 99.94 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 41: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/41.jpg)
LAPORAN PROGRESS MINGGUAN22 Oktober 2015 MINGGU KE
s/d 1628 Oktober 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 1.00 0.45 0.25 0.06 1.00 0.25
0.06 0.70
- - 7.20 0.04 - 0.04
- - 25.20 1.03 - 1.03
- - 24.00 0.07 - - 2.16 0.76
- 0.83
- - - - - - 55.80 11.81 - - - - - - 279.00 85.58
- 97.39 0.06 100.00
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 42: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/42.jpg)
LAPORAN PROGRESS MINGGUANKEGIATAN : REHABILITASI/PEMELIHARAAN JALANPEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYUKONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANTRUAS JALAN : BETONISASI JALAN SADANGVOLUME : 186m x 6mKONTRAKTOR PELAKSANA : CV. KOMALA
NO. URAIAN SAT.
PRESTASI HASIL PEKERJAAN
BOBOTVOLUME
BOBOT(%) ( % )
DIVISI 1. UMUM1.2 Mobilisasi dan Demobilisasi Ls 1.00 0.45 1.00 0.45 1.3 Kantor Lapangan dan Fasilitas (termasuk papan proyek) Ls 1.00 0.25 1.00 0.25
JUMLAH DIVISI 1 0.70 0.70 DIVISI 3. PEKERJAAN TANAH
3.1(2) Galian Tanah Berbatu Menggunakan Buruh (Bongkaran Beton) M³ 7.20 0.04 7.20 0.04 JUMLAH DIVISI 3 0.04 0.04
DIVISI 5. PERKERASAN BERBUTIR5.1(2) Lapis Pondasi Agregat Kelas B, menggunakan Buruh M³ 25.20 1.03 25.20 1.03
JUMLAH DIVISI 5 1.03 1.03 DIVISI 6. PERKERASAN ASPAL
6.1(1) Lapis Resap Pengikat Liter 24.00 0.07 24.00 0.07 6.3(5c) Laston Lapis aus ( AC-WC ) Leveling Ton 2.16 0.76 2.16 0.76
JUMLAH DIVISI 6 0.83 0.83 DIVISI 7. STRUKTUR
7.1(8)a Beton K-125 (Ready Mix) M³ 55.80 - - - 7.1(8)a M³ 55.80 11.81 55.80 11.81 7.16(1) Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar) M³ 279.00 - - - 7.16(1) M³ 279.00 85.58 279.00 85.58
JUMLAH DIVISI 7 97.39 97.39 JUMLAH 100.00 100.00 PPN 10 %JUMLAH TOTALDIBULATKAN
Diperiksa OlehPELAKSANA TEKNIS KEGIATAN
DINAS BINA MARGA KABUPATEN BANDUNG
ERI HERNAWAN, STNIP . 19741220 200901 1 001
KONTRAK ADDENDUM
VOL MINGGU LALU
Beton K-125 (Ready Mix)-(harga nego)
Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
![Page 43: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/43.jpg)
LAPORAN PROGRESS MINGGUAN29 Oktober 2015 MINGGU KE
s/d 1705 November 2015
PRESTASI HASIL PEKERJAAN
BOBOT BOBOTKETERANGAN
( % ) ( % )
- - 1.00 0.45 - - 1.00 0.25
- 0.70
- - 7.20 0.04 - 0.04
- - 25.20 1.03 - 1.03
- - 24.00 0.07 - - 2.16 0.76
- 0.83
- - - - - - 55.80 11.81 - - - - - - 279.00 85.58
- 97.39 - 100.00
Dibuat OlehKONSULTAN PENGAWAS
CV. DUTA GRAHA CONSULTANT
BANYU NUGRAHA, STInspector
VOL MINGGU INI
VOL s/d MINGGU INI
![Page 44: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/44.jpg)
KEGIATAN : REHABILITASI/PEMELIHARAAN JALAN
PEKERJAAN : PENGAWASAN PEMELIHARAAN JALAN KECAMATAN MARGAHAYU
KONSULTAN PENGAWAS : CV. DUTA GRAHA CONSULTANT
RUAS JALAN : BETONISASI JALAN SADANG
VOLUME : 186m x 6m
KONTRAKTOR PELAKSANA : CV. KOMALA
TIME SCHEDULE
URAIAN PEKERJAAN
SA
TU
ANRAB ADDENDUM 09 Juli 2015 08 Agustus 2015
BOBOT s/d s/d
07 Agustus 2015 06 September 2015 ( % ) BULAN KE-1 BULAN KE-2
### ### ### ### ### ### ###
I PEKERJAAN PERSIAPAN1.2 Mobilisasi dan Demobilisasi Ls ### ### ############1.3 Kantor Lapangan dan Fasilitasnya (termasuk P Ls ### ### ### ###
JUMLAH I ###II PEKERJAAN TANAH
3.1(2)Galian Tanah Berbatu Menggunakan Buruh (Bo M³ ### ###JUMLAH II ###
III PEKERJAAN PERKERASAN BERBUTIR5.1(2)Lapis Pondasi Agregat Kelas B, menggunakan M³ ### ### ############
JUMLAH III ###IV PERKERASAN ASPAL
6.1(1)Lapis Resap Pengikat Liter ### ###6.3(5c) Laston Lapis Aus ( AC - WC ) Leveling Ton ### ###
JUMLAH IV ###V PEKERJAAN STRUKTUR
7.1(8)aBeton K-125 (Ready mix) M³ - - 7.1(8)a M³ ### ###7.16( M³ - - 7.16( M³ ### ###
JUMLAH V ###JUMLAH (I + II + III + IV+V) ###
Rencana Bobot per hari : 5.88 - 0.01 0.03 0.88 0.88 0.87 31.93
: 100.00 - 0.01 0.04 0.92 1.80 2.67 34.60
Realisasi Bobot per hari : 7.14 - - - 0.40 0.38 0.40 0.38
: 100.00 - - - 0.40 0.78 1.18 1.56
Deviasi : 0.00 - 0.01 0.04 0.52 1.02 1.49 33.04
No.
Mata
Pem
bayara
n
VO
LUM
E
Beton K-125 (Ready mix)-(harga nego)Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
Akumulasi Recana Bobot per hariAkumulasi Realisasi Bobot per hari
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 -
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
REALISASI
![Page 45: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/45.jpg)
TIME SCHEDULE08 Agustus 2015 07 September 2015 07 Oktober 2015
s/d s/d s/d06 September 2015 06 Oktober 2015 05 November 2015
BULAN KE-2 BULAN KE-3 BULAN KE-4
### ### ### ### ### ### ### ### ###
############################## ### ###
###
### - ######
######### - ######
### ###### ###
###
### ### ###
### ### ###
###
###
0.01 31.91 0.01 31.93 0.01 0.03 - - 1.50
34.61 66.52 66.53 98.46 98.47 98.50 98.50 98.50 100.00
0.40 0.38 48.26 0.01 47.85 0.01 1.51 0.01 -
1.97 2.35 50.61 50.61 98.47 98.48 99.99 100.00 100.00
32.64 64.18 15.93 47.85 0.01 0.03 (1.48) (1.50) 0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 -
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
REALISASI
![Page 46: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/46.jpg)
TIME SCHEDULE BETONISASI JL. SADANG
URAIAN PEKERJAAN
SA
TU
ANRAB ADDENDUM 09 Juli 2015 08 Agustus 2015
BOBOT s/d s/d
07 Agustus 2015 06 September 2015 ( % ) BULAN KE-1 BULAN KE-2
### ### ### ### ### ###
I PEKERJAAN PERSIAPAN1.2 Mobilisasi dan Demobilisasi Ls ### ### #########1.3 Kantor Lapangan dan Fasilitasnya (termasuk Pa Ls ### ### ### ###
JUMLAH I ###II PEKERJAAN TANAH
3.1(2)Galian Tanah Berbatu Menggunakan Buruh (BonM³ ### ###JUMLAH II ###
III PEKERJAAN PERKERASAN BERBUTIR5.1(2)Lapis Pondasi Agregat Kelas B, menggunakan B M³ ### ### #########
JUMLAH III ###IV PEKERJAAN PERKERASAN ASPAL
6.1(1)Lapis Resap Pengikat Liter ### ###6.3(5c) Laston Lapis Aus ( AC - WC ) Leveling Ton ### ###
JUMLAH IV ###V PEKERJAAN STRUKTUR
7.1(8)aBeton K-125 (Ready mix) M³ - - 7.1(8)a M³ ### ###7.16( M³ - - 7.16( M³ ### ###
JUMLAH V ###JUMLAH (I + II + III + IV+V) ###
No.
Mata
Pem
bayara
n
VO
LUM
EBeton K-125 (Ready mix)-(harga nego)Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)Perkerasan Jalan Beton K-350 (dengan sambungan Tie Bar)-(harga nego)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 -
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
REALISASI
![Page 47: Contoh Lap. Kemajuan Pekerjaan Jalan](https://reader036.vdocuments.mx/reader036/viewer/2022081415/5695d3651a28ab9b029dc789/html5/thumbnails/47.jpg)
TIME SCHEDULE BETONISASI JL. SADANG08 Agustus 2015 07 September 2015 07 Oktober 2015
s/d s/d s/d06 September 2015 06 Oktober 2015 05 November 2015
BULAN KE-2 BULAN KE-3 BULAN KE-4
### ### ### ### ### ### ### ### ### ###
############################## ###
### -
############ -
######
### ###
### ###
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 -
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
REALISASI