  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    1/43

    CONSULTANT

    May be Filipino or foreigner

    Has the appropriate education, training

    and relevant experience

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    2/43

    HIRING OF CONSULTANTS

    Filipino consultants shall be hired if

    required expertise and capability areavailable. (EO 278)

    If not available locally, foreign consultantsmay be hired.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    3/43

    PROVISIONS OF THE IRR OF RA 9184RELATING TO

    PROCUREMENT OF

    CONSULTING SERVICES

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    4/43

    Standard Bidding Procedures for

    Consulting Services

    Pre-Procurement

    Conf.Advertisement

    Submission and Opening ofEligibility Envelopes(Eligibility Check)

    ShortlistingPre-Bid

    Conference

    Submissionof

    Bids

    Opening ofTechnical Envelopes& Preliminary Exam.

    Bid Evaluation&

    RankingNegotiation

    Post-Qualification

    Award ofContract

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    5/43

    CONSULTING SERVICES

    Specialized expertise provided for a

    client in the performance of a specifiedtaskover a specified period of timeExample:

    Design of a facility

    Economic and Financial Analysis

    Management Advisory Services

    Construction Supervision

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    6/43

    PRE-PROCUREMENT

    CONFERENCE

    To ensure that the procurement is in

    accordance with the project and

    agency procurement plan

    To determine the readiness ofprocurement at hand (availability of

    funds, clarity of TOR)

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    7/43

    PRE-PROCUREMENT

    CONFERENCE

    Review/agree on the criteria for

    eligibility screening/short listingDetermine numberof shortlist of firms

    Review/agree on the criteria for

    evaluation of proposalsDetermine evaluation procedure (Quality-based or

    Quality-cost based)

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    8/43

    ADVERTISEMENT

    At least once in one(1) newspaper of general

    nationwide circulation which has been regularly

    published for at least two (2) years

    Posted in the website of the agency and the EPS

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    9/43

    Posted in a conspicuous placein the agency

    concerned

    For contracts costing P1,000,000 and belowor

    those with duration of 4 months or less, posting in

    the website, G-EPS and conspicuous place in the

    agency concerned would suffice

    ADVERTISEMENT

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    10/43

    LETTER OF INTENT

    Must be received by the BAC not later than7 daysfrom last date of posting of theIAEB

    Upon receipt, the list of eligibility /shortlisting requirementsshall be providedby the BAC Secretariat

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    11/43

    ELIGIBILITY DOCUMENTS

    Class A Documents

    Legal

    SEC or DTI Registration Certificate

    Valid and current municipallicense/Mayors permit

    Tax Identification Number Statement that Consultant is not

    blacklistedby any government agency

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    12/43

    ELIGIBILITY DOCUMENTS

    Tax Clearance/ Tax Returns per BIR EO398

    Certificate of GEPS Registration

    Technical

    Statement of completed, ongoing and

    contracts awarded but not yet started(government and private contracts) withinthe period specifiedin the IAEB

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    13/43

    ELIGIBILITY DOCUMENTS

    Types of equipment owned, under leaseand/or under purchase agreement

    Key staffs,partners or principal officers of theconsulting firm and their respectivecurriculum vitae

    Financial

    Audited financial statements, stampedreceivedby the BIR or its duly authorizedinstitution

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    14/43

    ELIGIBILITY DOCUMENTS

    Class B Documents

    Valid joint venture agreement, if any.(each memberof the JV shall submit the

    eligibility documents)

    Letter authorizing agency to verify allsubmitted documents

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    15/43

    Eligibility Check

    EligibilityRequirements Firm 1 Firm 2 Firm 3 Firm 4 Firm 5

    DTI/SECRegistration

    Mayors Permit

    TIN

    List of Projects

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    16/43

    SHORT-LISTING

    To determine the most qualified firms toundertake the project

    Shortlist of consultants to be drawn fromthose eligible

    Shortlist shall consist of 3 to 7consultants,with 5 as preferable number

    If less than the required number pass theminimum score, BAC shall consider thesame

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    17/43

    SHORT-LISTING

    Applicable experience of Consultants 30%

    Qualification of personnel to be assigned 50%

    to the job (education,work experience,number of years in firm, etc.)

    Current work load relative to capacity 20 %

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    18/43

    BID DOCUMENTS

    Technical Envelope

    Bid Security Authority of the Signatory

    Organizational Chart

    List of completed and on-goingprojects

    Approach, work plan, and schedule

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    19/43

    BID DOCUMENTS

    List of key personnel to be assigned

    Certificate under oath of compliance with

    Labor Laws Disclosure Affidavit

    Statement attesting compliance withresponsibilities of bidder

    Financial Envelope

    Financial Proposal

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    20/43

    PRE-BID CONFERENCE

    For contracts P1.0M and above, at least one(1)

    pre-bid conference

    For contracts below P1.0M, discretion of BAC

    Attendance of the bidders not required

    Shall be held at least 12 daysbefore deadline for

    the submission and receipt of bids

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    21/43

    SUPPLEMENTAL BULLETIN

    Requests for clarification must be in writing

    and submitted at least 10 daysbefore deadline

    for submission and receipt of bids

    Supplemental bulletins shall be issued 7 days

    before deadline for the submission and

    opening of bids

    Supplemental bulletin shall also be postedon

    the agency website

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    22/43

    SUBMISSION AND OPENING OF

    BIDS

    Bids shall be submitted/opened at the place,

    date and timespecified in the IAEB

    Bids may be modified beforethe deadline for the

    submission and receipt of bids. Bids may be withdrawn beforethe deadline for

    the receipt of bids. Withdrawal after deadline

    shall be subject to sanctions.

    Bid security now requiredfor Consulting

    Services.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    23/43

    BID EVALUATION

    QUALITY-BASED

    Simultaneoussubmission of both Technical andFinancial proposals in separatesealed envelopes

    Technical proposals shall be evaluated firstand

    the consultants ranked

    First-in-rankconsultant shall be invited for

    contract and financial negotiations

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    24/43

    QUALITY-COST BASED

    Ranking is based both on the Technicaland Financial Proposals

    Technical and Financial proposals shall be

    given corresponding weights

    Financial proposal shall be given weightsof 15%up to maximum of 40%

    BID EVALUATION

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    25/43

    For QCBE

    Evaluation

    Firms whose TPs did not meet the minimum

    qualifying score will have their financialproposals (FPs) returned unopened

    Opening of financial proposals

    Only firms whose TPs meet the qualifying score

    shall be invited to the opening of FPs on a

    separate date/time set by the BAC

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    26/43

    FIRM

    TECHNICALSCORE

    (75%)

    FINANCIALSCORE

    (25%)

    FINALSCORE RANK

    1 84 100 88.00 1

    2 86 91 87.25 2

    3 85 83 84.50 3

    4 80 77 79.25 5

    5 83 71 80.00 4

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    27/43

    For QCBE

    Lowest financial proposal is given 100 points

    Other financial proposals are scored as follows:

    Fplowest x 100FPn

    Example

    P 1.0 million P 1.0 million

    P 1.0 million P 1.2 million

    P 1.0 million P 1.0 million

    P 1.1 million P 1.3 million

    100 points

    90 points

    83 points

    77 points

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    28/43

    For QCBE

    To eliminate biased scoring of technical

    proposals, it is recommended that the highest

    and lowest scoresfor each criterion shall not be

    considered in determining the average scores

    Observe the Confidentiality Rule

    Evaluation process shall be completed in 21

    days

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    29/43

    EVALUATOR FIRM 1 FIRM 2 FIRM 3 FIRM 4 FIRM 5

    A 95 75 84 83 84

    B 84 88 86 81 82

    C 84 86 85 79 84

    D 83 85 84 79 82

    E 84 87 86 80 83

    AVERAGE

    (5E) 86.0 84.2 85.0 80.4 83.0

    RANK 1 3 2 5 4

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    30/43

    EVALUATOR FIRM 1 FIRM 2 FIRM 3 FIRM 4 FIRM 5

    A 95 75 84 83 84

    B 84 88 86 81 82

    C 84 86 85 79 84

    D 83 85 84 79 82E 84 87 86 80 83

    AVERAGE

    (5E) 86.0 84.2 85.0 80.4 83.0

    RANK 1 3 2 5 4AVERAGE

    (3E) 84 86 85 80 83

    RANK 3 1 2 5 4

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    31/43

    EVALUATION OF TECHNICAL

    PROPOSALS

    Experience and Capability of Firm 10%

    Plan of Approach and Methodology 30% Quality of personnel to be assigned 60%

    Project Manager

    Other Key Staff

    For unique or complexundertaking, short-listed consultants

    may be required to make an oral presentationwithin 15 days

    after the deadline for the submission of Technical proposals

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    32/43

    NEGOTIATION

    with Highest Rated Bidder

    Finalization of methodology and workprogram

    Personnel to be assigned (compensationvs.qualification, number of man months)

    Facilities and data to be provided by theagency

    Financial proposal submitted by Consultant(not included under quality-cost based)

    Provisions of the contract

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    33/43

    POSTQUALIFICATION

    Legal Requirements.To verify andvalidate licenses/permits.

    Technical Requirements. To verify andvalidate experience of firm and keypersonnel to be assigned to the project.

    Financial Requirements. To verify andvalidate the bid priceproposal.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    34/43

    FAILURE OF BIDDING

    No LOI or no bid is received;

    All prospective bidders are declared ineligibleorall eligible bidders fail to meet the shortlistingcriteria;

    Shortlisted bidders fail to complywith all bidrequirements or there is no successfulnegotiations or fail postqualification;

    Bidder with Highest Rated Responsive Bidrefuses without justifiable causeto accept awardof contract, and no award is made

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    35/43

    AWARD OF CONTRACT

    Award of contract shall be made to the

    bidder with the highest rated and

    responsive bid.

    Decision to award or not to award shall be

    made within 7 daysfrom the date the BAC

    determines the highest rated andresponsive bid. For GOCCs and GFIs, the

    period shall be 15 days.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    36/43

    CONTRACT SIGNING

    Contract shall be signed by the winning

    bidder and head of the agency within 10days from receiptby the winning bidder of

    the notice of award

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    37/43

    CONTRACT APPROVAL/

    NOTICE TO PROCEED

    Contract shall be approved not later than 10daysfrom date the winning bidder and theagency concerned have signedthe contract

    NTP shall be issued to the successful bidder 3daysfrom date of approval of the contract

    Performance Security now requiredfor

    Consulting Services All bids are fixed pricesand not subject to price

    adjustments

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    38/43

    WARRANTY

    Consultants are liable for structural

    defects/failures due to faulty/ inadequate

    design and specificationsas well as

    construction supervision.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    39/43

    ALTERNATIVE METHODS OF

    PROCUREMENT

    Limited Source Bidding

    Highly specialized type of consulting

    services where only few consultantshave

    the expertise

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    40/43

    Negotiated Procurement

    Where there has been failure of public bidding

    for the second time

    In case of imminent danger or when time is of

    the essence

    Take-over of consultancy contracts which havebeen rescinded or terminated

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    41/43

    Special project is adjacentor contiguous to an

    ongoing similar project

    Procurement of Consulting Services from

    another government agency Individual consultants hired to do work that is

    highly technical or proprietary

    primarily confidential or policy determining

    Where amount involved is P50T and below

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised

    42/43

    CONTRACT IMPLEMENTATION

    Advance payment not to exceed 15%ofcontract amount.

    Any extension of contract time shall notinvolve any additional cost.

    No incentive bonusis allowed.

  • 8/10/2019 Consulting IRR ( 23 June 2008)-Revised