8/10/2019 Consulting IRR ( 23 June 2008)-Revised
1/43
CONSULTANT
May be Filipino or foreigner
Has the appropriate education, training
and relevant experience
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
2/43
HIRING OF CONSULTANTS
Filipino consultants shall be hired if
required expertise and capability areavailable. (EO 278)
If not available locally, foreign consultantsmay be hired.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
3/43
PROVISIONS OF THE IRR OF RA 9184RELATING TO
PROCUREMENT OF
CONSULTING SERVICES
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
4/43
Standard Bidding Procedures for
Consulting Services
Pre-Procurement
Conf.Advertisement
Submission and Opening ofEligibility Envelopes(Eligibility Check)
ShortlistingPre-Bid
Conference
Submissionof
Bids
Opening ofTechnical Envelopes& Preliminary Exam.
Bid Evaluation&
RankingNegotiation
Post-Qualification
Award ofContract
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
5/43
CONSULTING SERVICES
Specialized expertise provided for a
client in the performance of a specifiedtaskover a specified period of timeExample:
Design of a facility
Economic and Financial Analysis
Management Advisory Services
Construction Supervision
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
6/43
PRE-PROCUREMENT
CONFERENCE
To ensure that the procurement is in
accordance with the project and
agency procurement plan
To determine the readiness ofprocurement at hand (availability of
funds, clarity of TOR)
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
7/43
PRE-PROCUREMENT
CONFERENCE
Review/agree on the criteria for
eligibility screening/short listingDetermine numberof shortlist of firms
Review/agree on the criteria for
evaluation of proposalsDetermine evaluation procedure (Quality-based or
Quality-cost based)
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
8/43
ADVERTISEMENT
At least once in one(1) newspaper of general
nationwide circulation which has been regularly
published for at least two (2) years
Posted in the website of the agency and the EPS
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
9/43
Posted in a conspicuous placein the agency
concerned
For contracts costing P1,000,000 and belowor
those with duration of 4 months or less, posting in
the website, G-EPS and conspicuous place in the
agency concerned would suffice
ADVERTISEMENT
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
10/43
LETTER OF INTENT
Must be received by the BAC not later than7 daysfrom last date of posting of theIAEB
Upon receipt, the list of eligibility /shortlisting requirementsshall be providedby the BAC Secretariat
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
11/43
ELIGIBILITY DOCUMENTS
Class A Documents
Legal
SEC or DTI Registration Certificate
Valid and current municipallicense/Mayors permit
Tax Identification Number Statement that Consultant is not
blacklistedby any government agency
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
12/43
ELIGIBILITY DOCUMENTS
Tax Clearance/ Tax Returns per BIR EO398
Certificate of GEPS Registration
Technical
Statement of completed, ongoing and
contracts awarded but not yet started(government and private contracts) withinthe period specifiedin the IAEB
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
13/43
ELIGIBILITY DOCUMENTS
Types of equipment owned, under leaseand/or under purchase agreement
Key staffs,partners or principal officers of theconsulting firm and their respectivecurriculum vitae
Financial
Audited financial statements, stampedreceivedby the BIR or its duly authorizedinstitution
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
14/43
ELIGIBILITY DOCUMENTS
Class B Documents
Valid joint venture agreement, if any.(each memberof the JV shall submit the
eligibility documents)
Letter authorizing agency to verify allsubmitted documents
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
15/43
Eligibility Check
EligibilityRequirements Firm 1 Firm 2 Firm 3 Firm 4 Firm 5
DTI/SECRegistration
Mayors Permit
TIN
List of Projects
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
16/43
SHORT-LISTING
To determine the most qualified firms toundertake the project
Shortlist of consultants to be drawn fromthose eligible
Shortlist shall consist of 3 to 7consultants,with 5 as preferable number
If less than the required number pass theminimum score, BAC shall consider thesame
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
17/43
SHORT-LISTING
Applicable experience of Consultants 30%
Qualification of personnel to be assigned 50%
to the job (education,work experience,number of years in firm, etc.)
Current work load relative to capacity 20 %
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
18/43
BID DOCUMENTS
Technical Envelope
Bid Security Authority of the Signatory
Organizational Chart
List of completed and on-goingprojects
Approach, work plan, and schedule
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
19/43
BID DOCUMENTS
List of key personnel to be assigned
Certificate under oath of compliance with
Labor Laws Disclosure Affidavit
Statement attesting compliance withresponsibilities of bidder
Financial Envelope
Financial Proposal
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
20/43
PRE-BID CONFERENCE
For contracts P1.0M and above, at least one(1)
pre-bid conference
For contracts below P1.0M, discretion of BAC
Attendance of the bidders not required
Shall be held at least 12 daysbefore deadline for
the submission and receipt of bids
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
21/43
SUPPLEMENTAL BULLETIN
Requests for clarification must be in writing
and submitted at least 10 daysbefore deadline
for submission and receipt of bids
Supplemental bulletins shall be issued 7 days
before deadline for the submission and
opening of bids
Supplemental bulletin shall also be postedon
the agency website
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
22/43
SUBMISSION AND OPENING OF
BIDS
Bids shall be submitted/opened at the place,
date and timespecified in the IAEB
Bids may be modified beforethe deadline for the
submission and receipt of bids. Bids may be withdrawn beforethe deadline for
the receipt of bids. Withdrawal after deadline
shall be subject to sanctions.
Bid security now requiredfor Consulting
Services.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
23/43
BID EVALUATION
QUALITY-BASED
Simultaneoussubmission of both Technical andFinancial proposals in separatesealed envelopes
Technical proposals shall be evaluated firstand
the consultants ranked
First-in-rankconsultant shall be invited for
contract and financial negotiations
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
24/43
QUALITY-COST BASED
Ranking is based both on the Technicaland Financial Proposals
Technical and Financial proposals shall be
given corresponding weights
Financial proposal shall be given weightsof 15%up to maximum of 40%
BID EVALUATION
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
25/43
For QCBE
Evaluation
Firms whose TPs did not meet the minimum
qualifying score will have their financialproposals (FPs) returned unopened
Opening of financial proposals
Only firms whose TPs meet the qualifying score
shall be invited to the opening of FPs on a
separate date/time set by the BAC
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
26/43
FIRM
TECHNICALSCORE
(75%)
FINANCIALSCORE
(25%)
FINALSCORE RANK
1 84 100 88.00 1
2 86 91 87.25 2
3 85 83 84.50 3
4 80 77 79.25 5
5 83 71 80.00 4
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
27/43
For QCBE
Lowest financial proposal is given 100 points
Other financial proposals are scored as follows:
Fplowest x 100FPn
Example
P 1.0 million P 1.0 million
P 1.0 million P 1.2 million
P 1.0 million P 1.0 million
P 1.1 million P 1.3 million
100 points
90 points
83 points
77 points
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
28/43
For QCBE
To eliminate biased scoring of technical
proposals, it is recommended that the highest
and lowest scoresfor each criterion shall not be
considered in determining the average scores
Observe the Confidentiality Rule
Evaluation process shall be completed in 21
days
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
29/43
EVALUATOR FIRM 1 FIRM 2 FIRM 3 FIRM 4 FIRM 5
A 95 75 84 83 84
B 84 88 86 81 82
C 84 86 85 79 84
D 83 85 84 79 82
E 84 87 86 80 83
AVERAGE
(5E) 86.0 84.2 85.0 80.4 83.0
RANK 1 3 2 5 4
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
30/43
EVALUATOR FIRM 1 FIRM 2 FIRM 3 FIRM 4 FIRM 5
A 95 75 84 83 84
B 84 88 86 81 82
C 84 86 85 79 84
D 83 85 84 79 82E 84 87 86 80 83
AVERAGE
(5E) 86.0 84.2 85.0 80.4 83.0
RANK 1 3 2 5 4AVERAGE
(3E) 84 86 85 80 83
RANK 3 1 2 5 4
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
31/43
EVALUATION OF TECHNICAL
PROPOSALS
Experience and Capability of Firm 10%
Plan of Approach and Methodology 30% Quality of personnel to be assigned 60%
Project Manager
Other Key Staff
For unique or complexundertaking, short-listed consultants
may be required to make an oral presentationwithin 15 days
after the deadline for the submission of Technical proposals
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
32/43
NEGOTIATION
with Highest Rated Bidder
Finalization of methodology and workprogram
Personnel to be assigned (compensationvs.qualification, number of man months)
Facilities and data to be provided by theagency
Financial proposal submitted by Consultant(not included under quality-cost based)
Provisions of the contract
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
33/43
POSTQUALIFICATION
Legal Requirements.To verify andvalidate licenses/permits.
Technical Requirements. To verify andvalidate experience of firm and keypersonnel to be assigned to the project.
Financial Requirements. To verify andvalidate the bid priceproposal.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
34/43
FAILURE OF BIDDING
No LOI or no bid is received;
All prospective bidders are declared ineligibleorall eligible bidders fail to meet the shortlistingcriteria;
Shortlisted bidders fail to complywith all bidrequirements or there is no successfulnegotiations or fail postqualification;
Bidder with Highest Rated Responsive Bidrefuses without justifiable causeto accept awardof contract, and no award is made
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
35/43
AWARD OF CONTRACT
Award of contract shall be made to the
bidder with the highest rated and
responsive bid.
Decision to award or not to award shall be
made within 7 daysfrom the date the BAC
determines the highest rated andresponsive bid. For GOCCs and GFIs, the
period shall be 15 days.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
36/43
CONTRACT SIGNING
Contract shall be signed by the winning
bidder and head of the agency within 10days from receiptby the winning bidder of
the notice of award
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
37/43
CONTRACT APPROVAL/
NOTICE TO PROCEED
Contract shall be approved not later than 10daysfrom date the winning bidder and theagency concerned have signedthe contract
NTP shall be issued to the successful bidder 3daysfrom date of approval of the contract
Performance Security now requiredfor
Consulting Services All bids are fixed pricesand not subject to price
adjustments
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
38/43
WARRANTY
Consultants are liable for structural
defects/failures due to faulty/ inadequate
design and specificationsas well as
construction supervision.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
39/43
ALTERNATIVE METHODS OF
PROCUREMENT
Limited Source Bidding
Highly specialized type of consulting
services where only few consultantshave
the expertise
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
40/43
Negotiated Procurement
Where there has been failure of public bidding
for the second time
In case of imminent danger or when time is of
the essence
Take-over of consultancy contracts which havebeen rescinded or terminated
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
41/43
Special project is adjacentor contiguous to an
ongoing similar project
Procurement of Consulting Services from
another government agency Individual consultants hired to do work that is
highly technical or proprietary
primarily confidential or policy determining
Where amount involved is P50T and below
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
42/43
CONTRACT IMPLEMENTATION
Advance payment not to exceed 15%ofcontract amount.
Any extension of contract time shall notinvolve any additional cost.
No incentive bonusis allowed.
-
8/10/2019 Consulting IRR ( 23 June 2008)-Revised
43/43