construction red flags - freese and nichols, inc. · concrete “construction red flags” •...

24
Construction Red Flags April 17, 2018 William (Clay) Herndon, P.E. 1

Upload: others

Post on 07-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Construction Red Flags

April 17, 2018William (Clay) Herndon, P.E.

1

Page 2: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

General Site Management & Safety

• Site Safety– Site Specific PPE

• Hard Hat, Safety Glass, Vest– What does the Contractor provide?

• Safe working environment for inspection

• Training to consider– Site Safety– Trench Safety– Confined Space– Fall Protection– Concrete– Nuclear Gauge– Coatings

11

Page 3: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

General Site Management & Safety

• Site Management– Clean Site– Safe Site– Construction Materials and Debris– Positive Drainage– Labels on bags – Recyclables in Trash (LEED)

12

Page 4: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Who’s Responsible?

• What is Quality Assurance?– Also know as verification testing– Also known as acceptance testing– Paid for by Owner (or under Engineer’s

Contract)

• What is Quality Control?– Testing done by contractor for their own

process control – Paid for by contractor

13

Page 5: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Earth Work “Construction Red Flags”

• Is the Proper Equipment in Use?– Large Equipment in Tight Areas

• Thickness of Lifts Being Placed• Use the “Heel” Test• Material Type in Use

– Sand– Clay– Stabilized

• Soil Moisture• Color Changes• Organics Debris

14

Page 6: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Formwork & Rebar “Construction Red Flags”

• Concrete Reinforcing– Size of Bar– Spacing– Lap

• Projection from Foundation– Corner Bars– Clearance– Tie Pattern– Cleanliness– Accessories

• Chairs• Bolsters

17

Page 7: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Formwork & Rebar “Construction Red Flags”

• Concrete Reinforcing– Confirm Spacing at Doors– Verify Proper Adhesive is Being Used– Verify Rebar is not Torch Cut

18

Page 8: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Formwork & Rebar “Construction Red Flags”

19

Page 9: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Formwork & Rebar “Construction Red Flags”

20

Page 10: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Concrete “Construction Red Flags”

• Pre-Placement– Pre-Placement QC Inspection Complete?– Does the Contractor Have the Appropriate Equipment?– Is there a Contingency Plan in Place?– Is Water Stop Installed Properly?– Is Curing Compound/Blankets Onsite?– Are Construction Joints Installed

Properly?– Is the Desired Finish Approved?

• Placement– Is the Contractor…..

• Monitoring Time to Placement?• Monitoring Batch Times?• Monitoring Vibration Cycles?• Monitoring Consistency of Mix?• Monitoring Placement Method?

21

Page 11: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Concrete “Construction Red Flags”

• Placement– What to Look For…..

• Batch Tickets for Batch Time and Mix Design Number• Batch Tickets for Added Water• Contractor is Using an Approved Method of Placement• Formwork and Rebar is Secure During Placement• Time to Placement and Time to Placement Between Lifts• Hanging forms are Removed in a

Timely Manner

• Post-Placement– Curing Methods are Being Followed– Once Formwork is Removed….

• Look for Signs of Cold Joints• Honey Combs• Desired Finish is Achieved

22

Page 12: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Concrete “Construction Red Flags”

25

Page 13: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Coatings “Construction Red Flags”

• Quality Control Program– Does your Contractor Have a QC Program?– QC Program Should Include

• Procedures• Follow SP Guidelines• Testing Procedures

• Pre-Application– Confirm QC Procedures in Place– Confirm Appropriate Equipment is Onsite– Confirm QC Plan will Accommodate for

Instances of Inclement Weather orEquipment Failure

26

Page 14: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Coatings “Construction Red Flags”

• Surface Prep– Verify Approved Material is Being Used

• Application– Verify QC Program is Followed– Verify Applicator is Using QC Equipment

• Wet Mil Gauge– Application is Even and There are

No “Runs” Present– Stripe Coat Applied to Edges– Verify Coating is Applied Adequately

• Post-Application– Test Coating

• Dry Mil Gauge• Spark Test/Holiday Testing

– Lessons Learned – Revisit Coatings Prior to Completing a Work Activity

27

Page 15: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Coatings “Construction Red Flags”

29

Page 16: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Stored Materials “Construction Red Flags”

• Handling of Materials– Per Spec and Manufactures Recommendations– Use Proper Equipment with Proper Means of Transporting Material– Limit Number of Time the Material is Handled

30

Page 17: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Stored Materials “Construction Red Flags”

31

Page 18: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

• Trench– Trench widths: Minimum and maximum– Trench height: Minimum and maximum

• Embedment/Backfill– Place between pipe and trench, not on top– Improper material used – “Placing” vs. “Dumping “– Compaction of embedment

• Handling – Non-abrasive slings or belts – No forklifts or rolling off trailer– Crane vs other equipment

32

Page 19: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

• Compactors– Right equipment for the space– Dual wheel mounted on a track hoe– Jumping Jack (9-12 inch wide space)– Flat plate vibrating compactors– Pneumatic Compactors

• Fine graded aggregate max lift ~12inches, can achieve 95% density

• Good in tight spaces, especially the haunches

• Compaction– Max lift (Spec and material type)– Testing Frequency– Moisture

33

Page 20: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

• Nuclear Gauge– Typical of testing the lifts of

embedment material between the sidewall of the pipe and the trench wall

– For tight areas, the Troxler gauge must be adjusted with a trench off-set or sidewall correction factor

– The technician must be trained to enter this correction factor before starting measurements

– The trench wall acts as a rebounding surface and returns more electrons to the gauge than normal causing readings to be skewed and show higher density than actual

34

Page 21: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

35

Page 22: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

36

Page 23: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline“Construction Red Flags”

37

Page 24: Construction Red Flags - Freese and Nichols, Inc. · Concrete “Construction Red Flags” • Placement – What to Look For….. • Batch Tickets for Batch Time and Mix Design

Pipeline “Construction Red Flags”

38