construction projects 2014 - university of alaska fairbanks · pdf filefrom geist road to...

1
Ash Dump Site Manager: EHS&RM Coal ash dump from Power Plant to Taku Parking Lot area and Eco Dump. Scheduled 2013 - 2018 Sewerline Replacement on Yukon Dr, Chandalar Dr, near Wood Center and the Fire Station (UTWH) Manager: Mike Schuetz Sewer line reconstruction. Construction scheduled May - October 1 2014 Roof Drain Modifications at Constitution Hall and Wickersham Hall (UTWBD) Manager: Mike Schuetz Removing roof drains from sanitary sewer. Construction scheduled May - October 1 2014 Gruening Building Roof Replacement (CWGRR) Manager: Reed Morisky This project will replace the existing 40 year old roof system with a new built-up roof system. Construction scheduled May - August 2014 Utilities Wood Center Vault Manager: Jenny Campbell Completion of UTWCV. Summer work includes realigning the South Chandalar Fire Lane west of Wood Center. Construction Scheduled April 2013 - Aug 2014 Campus Wide Housing and Dining, Phase 1A Manager: Jenny Campbell Construct 585 seat dining facility adjacent to existing Wood Center. Construction scheduled April 2013 - August 2014 Sewer Line Relining West Ridge Arctic Health (UTWBR) Manager: Mike Schuetz Relining through selected manholes on West Ridge. Construction scheduled May - October 1, 2014 Butrovich Exterior Civil Engineering Project (BUECE) Manager: Mary Pagel Demolition of the widened sidewalk and failing retaining wall on the South side of Yukon Drive. Construction scheduled Summer 2014 Prepare and repaint Butrovich Building Canopy Manager: Mary Pagel Prepare and repaint the building canopy. Construction scheduled Summer 2014 Elvey Deferred Maintenance (ELDM) Manager: Reed Morisky This project will establish critical utilities connections between the Elvey Annex (ASF) and the WRRB server room. Construction scheduled Summer & Fall 2014 Arctic Health East Passenger Elevator Modernization Manager: Mike Schuetz Modernize elevator 36 and include seismic improvements. Construction scheduled Apr - Sept 2014 West Ridge Deferred Renewal Temporary Labs Manager: Cameron Wohlford Relocate two donated lab modules from Geist Road to Arctic Health. Construction scheduled Summer 2014 Yankovich/Miller Hill Multi-Use Path Manager: Mary Pagel Construct a multi-use pedestrian path adjacent to West Tanana Dr, Sheep Creek, Miller Hill and Yankovich Roads. Construction scheduled mid-September 2014 Campus Wide Gruening Switchgear Replacement (CWGSR) Manager: Milton Ludington This project will replace the switchgear in the basement. Major power outages in between summer sessions. Construction scheduled May - September 2014 BUTROVICH MURIE MUSEUM REICHARDT MBS SRC LOLA TILLY Campus Wide ADA Restrooms (GR5RR) Manager: Milton Ludington This project will construct two new ADA restrooms on the sixth floor of Gruening. Construction scheduled May - August 2014 Akasofu Restoration (AKR) Manager: Bob Crenshaw Restore and renovate office spaces on the fourth floor and restorations throughout entire building. Construction scheduled May 2014 - February 2015 2 2 3 4 3 4 5 5 7 8 9 10 15 16 17 20 25 26 7 8 9 10 20 17 16 15 27 19 21 29 25 26 27 19 21 29 22 22 1 1 13 14 13 Patty Center Bleacher Installation (PCBI) Manager: Mary Pagel Install new bleachers. Construction scheduled May - September 2014 14 Patty Ice ADA Restroom and Seating (PIARS) Manager: Mary Pagel Construct ADA restrooms and new seating. Construction scheduled September 2014 Temporary Access Route SEE PAGE 2 24 18 28 11 12 6 Irving I Rm 210 & 211 Renovation Manager: Bob Crenshaw Remove walls between rooms 210 & 211. Construction scheduled July 2014 6 West Ridge Animal Resources Facility Relocation (WRARF) Manager: Cameron Wohlford This project will complete approximately 6000 SF of previously shelled space to support animal care and housing. Construction scheduled Summer 2014 11 12 Eielson ADA Restroom Renovation Manager: Jonathan Shambare Renovate ADA restroom. Construction scheduled June - September 2014 18 Eielson Entry Door Renovation Manager: Milton Ludington Replace north and south entry vestibule doors. Construction scheduled June - August 2014 24 28 UAF Engineering Building Manager: Cameron Wohlford Laydown area for ENNF Contractor. Construction scheduled April 2013 - June 2015 Taku Stairs (PLTMS) Manager: Cameron Wohlford Replace the sidewalk along Taku Drive with metal stairs. Construction scheduled May - August 2014 UAF Engineering Building Manager: Cameron Wohlford Construct new engineering facility to meet the needs of the College of Engineering and Mines. Construction scheduled April 2013-June 2015 Museum Renovate Rm 101 Manager: Bob Crenshaw Remove walls enclosing office area to expand gift shop. Construction scheduled May 2014 MBS Drinking Fountains Manager: Bob Crenshaw Replace drinking fountains in Bartlett Hall on 1st to 4th floor. Construction scheduled July 2014 Brooks Building Flood Repairs Manager: Bob Crenshaw Repair damage caused by water on 3rd and 4th floor. Construction scheduled July - September 2014 23 Gruening 8th Floor Ceiling Replacement Manager: Milton Ludington Remove and replace existing ceiling and lights. Construction scheduled June - July 2014 23 FOR FURTHER INFORMATION: Division of Design and Construction P.O. Box 758160 Fairbanks, Ak 99775-8160 (907) 474-5299 1" = 500' @ 11x17 University of Alaska Fairbanks CONSTRUCTION PROJECTS 2014 April 02, 2014 www.uaf.edu/fs/departments/design-construction/ AERIAL DATED: JUNE 2013 TM Community & Technical College Barnette Parking Rehabilitation Manager: Mike Schuetz Improve parking and landscape for CTC Barnette building. Construction scheduled May - 1 October 2014 Community & Technical College Aviation Entry Canopy Manager: Mike Schuetz Design and install canopies over building entrances. Construction scheduled July - August 2014 Antenna Base Construction (AIAS2) Manager: Cameron Wohlford Install antenna base on Richardson Hwy. Construction scheduled May - July 2014 Northwest Campus Science Building Remodel (NWSBR) Manager: Milton Ludington Exterior and interior improvements to the existing campus facilities located in Nome, Alaska. Construction scheduled May-August 2014 Sewerline Demolition AFES Farm Manager: Mike Schuetz Close abandoned sewerline South of farm including eleven manholes. Construction scheduled June - July 2014 Road Improvements FMATS Street Light Conversion Stage III (RISLC) Manager: Mary Pagel Street light conversion and select pole replacement, trenching and associated electrical work will occur all over campus. Construction scheduled August 2014 Utilities Campus Wide (UTER) Manager: Mike Ruckhaus Convert buildings to new system - multiple power outages. Construction scheduled Summer 2014 Utilities Construction / Renovation Staging Areas / Parking Impacts Critical Electrical Distribution Renewal Construction Scheduled Summer 2014 Grading, Topsoil and Seeding Temporary Fire Lane 1 Dining Facility related Staging Areas Street Lights Affected by Street Light Conversion Project (RISLC)

Upload: phamdan

Post on 16-Feb-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CONSTRUCTION PROJECTS 2014 - University of Alaska Fairbanks · PDF filefrom Geist Road to Arctic Health. Construction ... Bartlett Hall on 1st to 4th floor. Construction ... Construction

Ash Dump Site

Manager: EHS&RM

Coal ash dump from Power Plant to

Taku Parking Lot area and Eco Dump.

Scheduled 2013 - 2018

Sewerline Replacement on Yukon Dr,

Chandalar Dr, near Wood Center and the

Fire Station (UTWH)

Manager: Mike Schuetz

Sewer line reconstruction.

Construction scheduled May - October 1 2014

Roof Drain Modifications at Constitution Hall

and Wickersham Hall (UTWBD)

Manager: Mike Schuetz

Removing roof drains from sanitary sewer.

Construction scheduled May - October 1 2014

Gruening Building Roof Replacement (CWGRR)

Manager: Reed Morisky

This project will replace the existing 40 year old

roof system with a new built-up roof system.

Construction scheduled May - August 2014

Utilities Wood Center Vault

Manager: Jenny Campbell

Completion of UTWCV. Summer work includes

realigning the South Chandalar Fire Lane west

of Wood Center.

Construction Scheduled April 2013 - Aug 2014

Campus Wide Housing and Dining, Phase 1A

Manager: Jenny Campbell

Construct 585 seat dining facility adjacent to

existing Wood Center.

Construction scheduled April 2013 - August 2014

Sewer Line Relining West

Ridge Arctic Health (UTWBR)

Manager: Mike Schuetz

Relining through selected

manholes on West Ridge.

Construction scheduled

May - October 1, 2014

Butrovich Exterior Civil

Engineering Project (BUECE)

Manager: Mary Pagel

Demolition of the widened sidewalk

and failing retaining wall on the

South side of Yukon Drive.

Construction scheduled

Summer 2014

Prepare and repaint Butrovich

Building Canopy

Manager: Mary Pagel

Prepare and repaint the building

canopy.

Construction scheduled

Summer 2014

Elvey Deferred Maintenance (ELDM)

Manager: Reed Morisky

This project will establish critical utilities

connections between the Elvey Annex (ASF)

and the WRRB server room.

Construction scheduled Summer & Fall 2014

Arctic Health East Passenger Elevator

Modernization

Manager: Mike Schuetz

Modernize elevator 36 and include

seismic improvements.

Construction scheduled Apr - Sept 2014

West Ridge Deferred Renewal

Temporary Labs

Manager: Cameron Wohlford

Relocate two donated lab modules

from Geist Road to Arctic Health.

Construction scheduled Summer 2014

Yankovich/Miller Hill Multi-Use Path

Manager: Mary Pagel

Construct a multi-use pedestrian path

adjacent to West Tanana Dr, Sheep Creek,

Miller Hill and Yankovich Roads.

Construction scheduled mid-September 2014

Campus Wide Gruening Switchgear

Replacement (CWGSR)

Manager: Milton Ludington

This project will replace the switchgear in the

basement. Major power outages in between

summer sessions.

Construction scheduled May - September 2014

BUTROVICH

MURIE

MUSEUM

REICHARDT

MBS

SRC

LOLA

TILLY

Campus Wide ADA Restrooms (GR5RR)

Manager: Milton Ludington

This project will construct two new ADA

restrooms on the sixth floor of Gruening.

Construction scheduled May - August 2014

Akasofu Restoration (AKR)

Manager: Bob Crenshaw

Restore and renovate office spaces

on the fourth floor and restorations

throughout entire building.

Construction scheduled

May 2014 - February 2015

2

2

3

4

3

4

5

5

7

8

9

10

15

16

17

20

25

26

7

8

9

10

20

17

16

15

27

19

21

29

25

26

27

19

21

29

22

22

1

1

13 14

13

Patty Center Bleacher Installation (PCBI)

Manager: Mary Pagel

Install new bleachers.

Construction scheduled May - September 2014

14

Patty Ice ADA Restroom and

Seating (PIARS)

Manager: Mary Pagel

Construct ADA restrooms and new seating.

Construction scheduled September 2014

Temporary Access Route

SEE PAGE 2

24

18

28

11

12

6

Irving I Rm 210 & 211 Renovation

Manager: Bob Crenshaw

Remove walls between rooms 210 & 211.

Construction scheduled July 2014

6

West Ridge Animal Resources Facility

Relocation (WRARF)

Manager: Cameron Wohlford

This project will complete approximately

6000 SF of previously shelled space to

support animal care and housing.

Construction scheduled Summer 2014

11

12

Eielson ADA Restroom Renovation

Manager: Jonathan Shambare

Renovate ADA restroom.

Construction scheduled June - September 2014

18

Eielson Entry Door Renovation

Manager: Milton Ludington

Replace north and south entry vestibule doors.

Construction scheduled June - August 2014

24

28

UAF Engineering Building

Manager: Cameron Wohlford

Laydown area for ENNF Contractor.

Construction scheduled

April 2013 - June 2015

Taku Stairs (PLTMS)

Manager: Cameron Wohlford

Replace the sidewalk along Taku

Drive with metal stairs.

Construction scheduled

May - August 2014

UAF Engineering Building

Manager: Cameron Wohlford

Construct new engineering

facility to meet the needs of the

College of Engineering and Mines.

Construction scheduled

April 2013-June 2015

Museum Renovate Rm 101

Manager: Bob Crenshaw

Remove walls enclosing office

area to expand gift shop.

Construction scheduled May 2014

MBS Drinking Fountains

Manager: Bob Crenshaw

Replace drinking fountains in

Bartlett Hall on 1st to 4th floor.

Construction scheduled July 2014

Brooks Building Flood Repairs

Manager: Bob Crenshaw

Repair damage caused by water

on 3rd and 4th floor.

Construction scheduled

July - September 2014

23

Gruening 8th Floor Ceiling Replacement

Manager: Milton Ludington

Remove and replace existing ceiling and lights.

Construction scheduled June - July 2014

23

FOR FURTHER INFORMATION:

Division of Design and Construction

P.O. Box 758160

Fairbanks, Ak 99775-8160

(907) 474-5299

1" = 500' @ 11x17

University of Alaska Fairbanks

CONSTRUCTION PROJECTS 2014

April 02, 2014

www.uaf.edu/fs/departments/design-construction/

AERIAL DATED: JUNE 2013

TM

Community & Technical College Barnette Parking Rehabilitation

Manager: Mike Schuetz

Improve parking and landscape for CTC Barnette building.

Construction scheduled May - 1 October 2014

Community & Technical College Aviation Entry Canopy

Manager: Mike Schuetz

Design and install canopies over building entrances.

Construction scheduled July - August 2014

Antenna Base Construction (AIAS2)

Manager: Cameron Wohlford

Install antenna base on Richardson Hwy.

Construction scheduled May - July 2014

Northwest Campus Science Building Remodel (NWSBR)

Manager: Milton Ludington

Exterior and interior improvements to the existing campus facilities

located in Nome, Alaska.

Construction scheduled May-August 2014

Sewerline Demolition AFES Farm

Manager: Mike Schuetz

Close abandoned sewerline South of farm including eleven manholes.

Construction scheduled June - July 2014

Road Improvements FMATS Street Light Conversion Stage III (RISLC)

Manager: Mary Pagel

Street light conversion and select pole replacement, trenching and

associated electrical work will occur all over campus.

Construction scheduled August 2014

Utilities Campus Wide (UTER)

Manager: Mike Ruckhaus

Convert buildings to new system - multiple power outages.

Construction scheduled Summer 2014

Utilities

Construction / Renovation

Staging Areas / Parking Impacts

Critical Electrical Distribution Renewal

Construction Scheduled Summer 2014

Grading, Topsoil and Seeding

Temporary Fire Lane

1

Dining Facility related Staging Areas

Street Lights Affected by Street Light

Conversion Project (RISLC)