construction project management
DESCRIPTION
Construction Project Management. Prepared By: Abd Ul-Rahman Jamal Barqawi Rana Omar Abu- Tayyoun Supervisor: Eng. Baraq Jum’aa. Graduation Project consist of two part: Part 1) includes preparing a theoretical research - PowerPoint PPT PresentationTRANSCRIPT
Construction Project Management
Prepared By:Abd Ul-Rahman Jamal Barqawi
Rana Omar Abu-TayyounSupervisor: Eng. Baraq Jum’aa
Graduation Project consist of two part:
• Part 1) includes preparing a theoretical research• Part 2) includes the application of the principles
in construction project management
Introduction to Project Management
What Is a project?
• A project is a sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to specification.
The Scope Triangle
What is Project Management?
• Project management is the application of Knowledge, skills, tools and techniques to project activities to meet project requirements. Project management is accomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring and controlling, and closing.
Project Lifecycle
Project ManagementBody Of Knowledge
The PMI has identified nine topic areas to define the scope of project management knowledge as follows:
• Project Integration Management• Project Scope Management• Project Time Management
• Project Cost Management• Project Quality Management• Project Human Resource Management• Project Communication Management• Project Risk Management• Project Procurement Management
Deir Al-Ghusun Basic Girls School
Technical Description of the School Building
Location Deir Al-Ghusun Tulkarem
Area of Building(m2) 2240
Area of Land (m2) 2635
Classrooms 14
Science Laboratories 1
Libraries 1
Computer Room 1
Arts & Crafts Room 1
Administration Unit 1
Other Rooms (Teachers Room) 1
Stores 2
No. of Toilets 10
Analysis of the Project using Primavera
Primavera results show that the expected time frame for the implementation of the project is 232 working days, while the total budgeted cost will be equal 1,004,903 $.
Work Break Down Structure
Problem Case
If the assumption that the period of completion of the project according to the contract agreement is 250 working days, and required the contractor to 280 days of work to accomplish the works.
Earned Value Analysis
• Earned Value Reporting – CostsCot variance = BCWP – ACWP = 1004903 – 1135870 = - 130967Cost Performance Index = BCWP/ACWP = 1004903/1135870 = 0.88 < 1 over budget
• Earned Value Reporting – Schedule Schedule Variance = BCWP – BCWS = 1004903 – 1100000 = - 95097Schedule Performance Index = BCWP / BCWS = 1004903/1100000 = 0.91 < 1 behind schedule