Page 1: Construction  Project  Management

Construction Project Management

Prepared By:Abd Ul-Rahman Jamal Barqawi

Rana Omar Abu-TayyounSupervisor: Eng. Baraq Jum’aa

Page 2: Construction  Project  Management

Graduation Project consist of two part:

• Part 1) includes preparing a theoretical research• Part 2) includes the application of the principles

in construction project management

Page 3: Construction  Project  Management

Introduction to Project Management

What Is a project?

• A project is a sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to specification.

Page 4: Construction  Project  Management

The Scope Triangle

Page 5: Construction  Project  Management

What is Project Management?

• Project management is the application of Knowledge, skills, tools and techniques to project activities to meet project requirements. Project management is accomplished through the application and integration of the project management processes of initiating, planning, executing, monitoring and controlling, and closing.

Page 6: Construction  Project  Management

Project Lifecycle

Page 7: Construction  Project  Management

Project ManagementBody Of Knowledge

The PMI has identified nine topic areas to define the scope of project management knowledge as follows:

• Project Integration Management• Project Scope Management• Project Time Management

Page 8: Construction  Project  Management

• Project Cost Management• Project Quality Management• Project Human Resource Management• Project Communication Management• Project Risk Management• Project Procurement Management

Page 9: Construction  Project  Management

Deir Al-Ghusun Basic Girls School

Page 10: Construction  Project  Management

Technical Description of the School Building

Location Deir Al-Ghusun Tulkarem

Area of Building(m2) 2240

Area of Land (m2) 2635

Classrooms 14

Science Laboratories 1

Libraries 1

Computer Room 1

Arts & Crafts Room 1

Administration Unit 1

Other Rooms (Teachers Room) 1

Stores 2

No. of Toilets 10

Page 11: Construction  Project  Management

Analysis of the Project using Primavera

Primavera results show that the expected time frame for the implementation of the project is 232 working days, while the total budgeted cost will be equal 1,004,903 $.

Page 12: Construction  Project  Management
Page 13: Construction  Project  Management

Work Break Down Structure

Page 14: Construction  Project  Management

Problem Case

If the assumption that the period of completion of the project according to the contract agreement is 250 working days, and required the contractor to 280 days of work to accomplish the works.

Page 15: Construction  Project  Management

Earned Value Analysis

• Earned Value Reporting – CostsCot variance = BCWP – ACWP = 1004903 – 1135870 = - 130967Cost Performance Index = BCWP/ACWP = 1004903/1135870 = 0.88 < 1 over budget

Page 16: Construction  Project  Management

• Earned Value Reporting – Schedule Schedule Variance = BCWP – BCWS = 1004903 – 1100000 = - 95097Schedule Performance Index = BCWP / BCWS = 1004903/1100000 = 0.91 < 1 behind schedule