Slide Show of Construction Progress at TechTown - Detroit TechTown 1st Floor Renovation Aug. 1 - Aug. 31 Construction 2013 CentricdesignStudio | www.centricdesignstudio.com

Upload: damon-thomas

Post on 11-Nov-2014

247 views

Category:

Business


0 download

DESCRIPTION

Please check out the latest slideshare of the 1st floor renovation project at TechTown - Detroit. This slideshare marks month no. 4 of the construction progress on this project designed by Centric Design Studio. You can view the previous three slide share months of progress (starting in May 2013) to see how far we have come. Come back next month and see the progress. Thanks for viewing.

TRANSCRIPT

Page 1: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Slide Show of Construction Progress at TechTown - DetroitTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 2: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Rear Accent Wall At Conference Room 4TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 3: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Painted Entry Wall At Conference Room 4TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 4: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Ceiling Cloud Framing At Future Copy CenterTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Ceiling Cloud Framing At Future Copy Center

Page 5: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Ceiling Cloud Grid + Lighting At Conference Room 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 6: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Exterior View Of Conference Room 2 ProgressTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 7: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Retrofitting Of Existing Light Fixtures (Recycling)TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 8: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Installation Of Retrofitted Light Fixtures (Reuse)TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 9: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Aluminum Storefront System Ready For InstallationTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 10: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Storefront System Installed At Future Video Conf. RoomTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 11: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Storefront System Installed At Conf. Rooms 1 + 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 12: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Storefront Glazing Ready For InstallationTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 13: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Storefront Glazing Installed At Conf. Rooms 1 + 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 14: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Storefront Glazing Installed Inside Conf. Room 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 15: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Construction Progress At Corridor 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 16: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Ceiling + Lighting Installation At Future Video Conf. RoomTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 17: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Construction Progress At Event Spaces 1 + 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Construction Progress At Event Spaces 1 + 2

Page 18: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Construction Progress At Event Spaces 1 + 2TechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Construction Progress At Event Spaces 1 + 2

Page 19: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Wall Panel Finish Mock-Up Outside Of Event + Conf. Room AreaTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 20: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Co-Working Kitchen Construction ProgressTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 21: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Co-Working Kitchen Construction ProgressTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 22: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Co-Working Kitchen Construction ProgressTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 23: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Construction Progress At TechTown Management SuiteTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 24: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

Construction Progress At TechTown Management SuiteTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013

CentricdesignStudio | www.centricdesignstudio.com

Page 25: Construction Progress for TechTown 1st Floor Renovation | Aug 1 - Aug 31

More Construction Progress Photos Will Be Posted Next MonthTechTown 1st Floor Renovation

Aug. 1 - Aug. 31 Construction 2013